Kernrechtsfrage
Whether the boat harbor project required an environmental impact report
Extrahierter Entscheid
No. The project fell below the UVP threshold for boat harbors and was therefore not subject to an EIA report.
Extrahierte Begründung
The project provided only about 70 fixed and 5 guest berths, far below the threshold of more than 100 berths. The lack of an explicit numerical cap in the concession did not change this, because the approved berth plan had to match the concession file.