Kernrechtsfrage
Whether the Linth canal project unlawfully reduced the existing flood-protection capacity contrary to Art. 4 WBG.
Extrahierter Entscheid
The project does not reduce the canal's flood-protection capacity; the complaint under Art. 4 WBG fails.
Extrahierte Begründung
The relevant capacity is determined by the entire built stretch and by its lowest dam sections, not by the highest sections or an assumed original ideal configuration. The appellants did not disprove the cantonal findings that the project improves stability and achieves the required discharge capacities.