Claim for ongoing monthly maintenance from December 2005.
The defendant must pay the claimant €573.41 per month beginning in December 2005.
42 F 706/04•Claim for Ongoing and Arrears Maintenance
42 F 706/04Gericht erster Instanz02.11.2005FamilienrechtTeilweise gutgeheissen
Von Omnilex extrahiert
In this first-instance family-law judgment, the Bonn Local Court ordered the defendant to pay the claimant ongoing maintenance of €573.41 per month from December 2005. It also awarded €7,661.39 in maintenance arrears for July 2004 through November 2005, with interest at 5% above the base rate on specified amounts from the stated dates. The court dismissed the remainder of the claim and allocated litigation costs equally between the parties. The judgment is provisionally enforceable, subject to security of 110% of the amount to be enforced.
Entscheidungsdatum: 2005-11-02
Aktenzeichen: 42 F 706/04
ECLI: ECLI:DE:AGBN:2005:1102.42F706.04.00
Dokumenttyp: Urteil
Spruchkörper: 42. Familienabteilung
Claim for ongoing monthly maintenance from December 2005.
The defendant must pay the claimant €573.41 per month beginning in December 2005.
Claim for maintenance arrears for July 2004 through November 2005, with interest.
The defendant must pay €7,661.39 in arrears, with the specified interest at 5% above the base rate on the listed amounts from their respective dates.
Remaining portion of the maintenance claim.
The remainder of the claim is dismissed.
Allocation of litigation costs.
Each party bears half of the litigation costs.
Kostenlose und unverbindliche Beratung
Schildern Sie uns Ihre Situation. Unser Team meldet sich per E-Mail bei Ihnen für Ihre Beratung.
Verbinden Sie Omnilex, um den Rechtskorpus über Ihren KI-Assistenten zu durchsuchen.