public-law-119-90•Public Law 119–90: To require the Federal Energy Regulatory Commission to extend the time period during which licensees are required to commence construction of certain hydropower projects.
Public Law 119–90: To require the Federal Energy Regulatory Commission to extend the time period during which licensees are required to commence construction of certain hydropower projects.
public-law-119-90Public Law 119-90Statute
As enacted: this collection preserves GovInfo's listed Beta USLM public-law XML, including printed amendment instructions and legislative history. Later amendments are not consolidated here; availability in this XML inventory does not establish completeness of all laws enacted by Congress.
[S. 1020]
16 USC 806 note.
EXTENSION OF TIME TO COMMENCE CONSTRUCTION OF CERTAIN HYDROPOWER PROJECTS.
Definition of Covered Project.—
Authorization of Extension.—
Period of Extension.—
Reinstatement of Expired License.—
LEGISLATIVE HISTORY—S. 1020 (H.R. 2072):
CONGRESSIONAL RECORD:
July 29, considered and passed Senate.
Apr. 21, considered and passed House.
Was bedeutet dieser Text für Ihre Situation?
Kostenlose und unverbindliche Beratung
Schildern Sie uns Ihre Situation. Unser Team meldet sich per E-Mail bei Ihnen für Ihre Beratung.
Setzen Sie Ihre Recherche in ChatGPT oder Claude fort
Verbinden Sie Omnilex, um den Rechtskorpus über Ihren KI-Assistenten zu durchsuchen.