Key legal question
Whether the quarry access road and tire-washing facility had already been covered by the 15 December 2009 building permit, so that no later permit process was required.
Extracted holding
Yes. The plans, technical report, and permit conditions sufficiently showed that both installations were included in the original permit.
Extracted reasoning
The Federal Court accepted that the location, approximate width, slope, and specific permit conditions referred to both installations. A later separate permit procedure was neither envisaged nor permissible.