Key legal question
Whether Y.'s building application had priority under Art. 7 KEG despite parallel quarter-plan proceedings
Extracted holding
The municipality and the cantonal court could treat Y.'s application as earlier and not 'obviously not approvable'; the quota priority for Y. was upheld.
Extracted reasoning
The decisive moment was not approval of the quarter plan but the expiry of the objection period, after which the project could be considered sufficiently approvable. Parallel quarter-plan and building-permit proceedings were permissible.