Key legal question
Whether the federal appeal was admissible despite the public procurement exception and whether the dispute raised a question of fundamental importance.
Extracted holding
The appeal was admissible because the contract value exceeded the threshold and two questions of fundamental importance were present.
Extracted reasoning
The award concerned the entire project, including later phases, so the threshold was exceeded; the appellant identified two unresolved procurement-law questions of principle.