Key legal question
Whether the architect was liable under the architecture contract for failing to warn about the water line during later garden works
Extracted holding
Any duty arising from the building permit condition concerned only the construction of the garden hall, not the later, uncontracted garden works.
Extracted reasoning
The permit condition protected the water line in relation to the garden hall project. Its protective purpose did not extend to later landscaping works outside the original contract.