Noise forecast required when DS II limits will be exceeded

ATA/359/1998Court of Justice / Administrative ChamberJun 9, 1998Modified

Extracted by Omnilex

Omnilex summary

The challenge concerned a building authorization on a parcel classified in noise sensitivity degree II. The court held that, because the relevant limit values for DS II would be exceeded, the authority had to require a noise forecast under environmental law. The permit was nonetheless confirmed, but only after a remediation plan is established in advance.

Omnilex headnote

Art. 25 al. 1 LPE; art. 36 OPB; noise forecast in case of exceedance of sensitivity-degree threshold values: where a parcel is assigned to sensitivity degree II and the applicable limit values are likely to be exceeded, the permit authority must require an acoustical forecast before deciding on the construction application. The permit may be maintained if the situation is addressed by prior remediation or assainissement measures; the authority must not dispense with the forecast merely because the project is otherwise admissible.

Full text

Descripteurs

CONSTRUCTION ET INSTALLATION; BRUIT; DEGRE DE SENSIBILITE; TPE

Normes

OPB.2 al.1

Résumé

Dès lors que la parcelle des recourants est soumise au degré de sensibilité II et que les valeurs correspondant au DS II seront dépassées, le département devait exiger un pronostic de bruit (art. 25 al. 1 LPE, art. 36 OPB). L'autorisation de construire doit être confirmée, moyennant l'établissement préalable d'un plan d'assainissement.

Keywords

construction permitnoise pollutionsensitivity degreenoise forecastremediation planenvironmental law

Extracted by Omnilex

Key legal question

Whether a noise forecast had to be required before granting the building permit.

Extracted holding

Yes. Because the parcel was subject to sensitivity degree II and the corresponding values would be exceeded, the authority had to require a noise forecast under the applicable environmental rules.

Extracted reasoning

When a property is classified in sensitivity degree II and the threshold values applicable to that degree will be exceeded, the permit authority must obtain a noise forecast before authorizing the project.

Key legal question

Whether the construction authorization could be confirmed despite the noise issue.

Extracted holding

Yes, the authorization was confirmed, but only on the condition that an adjustment or remediation plan be established beforehand.

Extracted reasoning

The court accepted the permit in principle, while requiring prior preparation of a remediation plan to address the exceedance.