Eastern States Construction Service, Inc. v. Darleycap, LLC

CourtListener 10745973DelsuperctDec 2, 2025

Full text

IN THE SUPERIOR COURT OF THE STATE OF DELAWARE
EASTERN STATES CONSTRUCTION )
SERVICE, INC., )
)
PLAINTIFF, )
)
v. ) C.A. No. N21C-07-188 SPL
)
DARLEYCAP, LLC, SPRINGCAP II, LLC )
WILLOWCAP, LLC, AND ST. ANNES )
DEVELOPMENT ASSOCIATES, LLC )
)
DEFENDANTS. )
____________________________________)
DARLEYCAP, LLC, SPRINGCAP II, LLC )
WILLOWCAP, LLC, AND ST. ANNES )
DEVELOPMENT ASSOCIATES, LLC )
)
COUNTERCLAIM PLAINTIFFS, )
)
v. )
)
EASTERN STATES CONSTRUCTION )
SERVICE, INC., )
)
COUNTERCLAIM DEFENDANT. )
Submitted: May 30, 2025
Decided: September 29, 2025
Withdrawn and Corrected: December 2, 2025
CORRECTED POST-TRIAL DECISION
David E. Wilks, Esquire, Charles D. Vavala, Esquire, WILKS LAW, Wilmington,
Delaware, for Plaintiff-Counterclaim Defendant Eastern States Construction
Service, Inc.
Sean A. Meluney, Esquire, Matthew D. Beebe, Esquire, MELUNEY, ALLEMAN &
SPENCE, Lewes, Delaware, for Defendants-Counterclaim Plaintiffs Darleycap, LLC,
Springcap II, LLC, Willowcap, LLC, and St. Annes Development Associates, LLC

LUGG, Judge
I. INTRODUCTION

This case involves a contract dispute between two established Delaware

companies—Eastern States Construction Service, Inc. (“Eastern States”) and the

Capano Management Company. The parties agree that contracts defined their

relationship; they quibble over their performance under the contracts. Each asserts

the other breached and owes some measure of damages. Over the course of a six-

day bench trial, the parties endeavored to unwind their relationship and prove their

respective claims.

These two longstanding businesses worked together for years. While

contracts defined their relationship, they routinely worked outside the contracts to

accommodate each other. Deadlines passed, payments were missed, and projects

were delayed. Over time, the relationship degraded. Leaders of the companies met

to resolve their differences, but the conflict steadily grew. In late 2020, the

relationship ended with a terse voicemail message. Each business believes the

other’s shortcomings excused their own failure to perform and packaged these

failures as breaches of the underlying contracts. The Court must determine whether

one, the other, or both, broke the deal. The answer is not simple.

Darleycap, LLC (“Darleycap”), Springcap II, LLC (“Springcap”), Willowcap,

LLC (“Willowcap”), and St. Anne’s Development Associates, LLC (“St. Anne’s”)

(collectively “Developers”) are the management entities for properties then under

1
development by the Capano Management Company. Developers hired Eastern

States to perform heavy civil site development on undeveloped land managed by

Darleycap, Springcap, Willowcap, and St. Anne’s. Developers sought to prepare the

land for vertical construction—buildings and residences. Preparing undeveloped

land for vertical construction is no easy task; ground must be broken, cleared,

smoothed, and readied to support the various utilities required for 21st Century

homes and businesses. Of course, unforeseen and unanticipated challenges are

inherent in the process.

Developers expected Eastern States to perform under their contracts. After

all, unimproved land does not attract bids for further development. In exchange for

its work, Eastern States, of course, expected to be paid. These expectations led to

persistent disputes. When Eastern States failed to adhere to the contracts,

Developers would not pay, and when Developers would not pay, Eastern States

would “demobilize.” Demobilizations ranged from pulling resources off

Developers’ projects to a complete cessation of work. This volley continued until

December 16, 2020, when Louis J. Capano, III (“Capano”), Developers’ owner, left

a voicemail with Eastern States’ Vice President, Terence Gleason (“Gleason”),

terminating the parties’ contractual relationship. Capano ordered Eastern States off

all of Developers’ projects. Eastern States collected its equipment and materials, and

this litigation commenced.

2
Eastern States filed suit for breach of contract and unjust enrichment.

Developers counterclaimed, asserting similar claims to recover the sums they spent

to fix and finish Eastern States’ work. The Court finds that both parties breached the

contracts and owe damages to one another. In the end, offsetting the damages, the

Court awards judgment to Developers in the amount of $50,189.25. The Court

declines to award attorneys’ fees to either party.1

1
Developers shall receive credit in the final form of order for payments made to
Springcap and Darleycap. See infra notes 281 and 283; JX 294, JX 454.

3
II. FACTS AND PROCEDURAL HISTORY

A. The Parties

Eastern States is a family-owned civil site development and underground

utility contractor incorporated under Delaware law.2 Eastern States transforms

undeveloped land into property prepared for vertical construction.3 At all times

relevant to this dispute, Stephen Julian (“Julian”) served as Eastern States’

President,4 Gleason, a decades-long employee of Eastern States, served as Vice

President,5 and Matt Green (“Green”), served as Eastern States’ general

superintendent.6 While Julian and Gleason often visited job sites, Green acted as

Eastern States’ “boots on the ground” and oversaw the day-to-day operations.7

Developers—Darleycap, Springcap, Willowcap, and St. Anne’s—are the

quasi-eponymous business entities associated with the properties under development

by the Capano Management Company owned by Capano.8 Developers contracted

with Eastern States to prepare undeveloped properties for vertical construction

2
Trial Tr. Day 1 at 18:5-23.
3
Trial Tr. Day 1 at 20, 25.
4
Trial Tr. Day 1 at 24.
5
Trial Tr. Day 1 at 263-264.
6
Trial Tr. Day 2 at 214.
7
Trial Tr. Day 6 at 246.
8
Trial Tr. Day 6 at 8–9.

4
projects.9 Capano’s second-in-command, Justin Hensley (“Hensley”), served as

Developers’ Director of Land Development,10 and operated as Developers’ primary

contact throughout their relationship with Eastern States. William Krapf (“Krapf”),

after years overseeing site development work for Developers, served in this role

prior to Hensley.11

B. The Projects

Eastern States worked on several projects for Developers; four are the subject

of this dispute. Darleycap served as the business entity overseeing the development

of Darley Green, a residential for-sale neighborhood in New Castle County.12 The

Darleycap project sought to develop about 800 “mixed use” units and required

approximately eleven “phases” of construction.13 St. Anne’s oversaw the

development of the Estate of St. Anne’s, a neighborhood located in New Castle

County comprised of about 600 home units.14 Willowcap oversaw the development

of Willowwood, a 500 lot neighborhood located off Brenford Road in Kent County.15

9
JX 663 (Darleycap Contract), JX 664 (Willowcap Contract), JX 081 (Springcap
Contract), JX 665 (St. Anne’s Contract) (“Contracts”).
10
Trial Tr. Day 3 at 85.
11
Trial Tr. Day 4 at 42.
12
Trial Tr. Day 3 at 89.
13
Id.
14
Id.
15
Trial Tr. Day 3 at 90.

5
Like Darleycap, the Willowcap project involved phased construction.16 Springcap

oversaw the development of a neighborhood situated “off Conleys Chapel Road in

Lewes, Delaware.”17 The Springcap project called for Eastern States to work on the

internal roadway of Burtons Pond, and Conleys Chapel Road.18

C. The Parties’ History

Eastern States and Developers began working together in 2012, when Capano

initiated the Darley Green project.19 The parties’ relationship expanded from there.20

Satisfied with their work, Capano invited Eastern States to bid on additional

projects.21 By 2018, Eastern States became Developers’ site developer on all

projects relevant to this litigation.

Developers tasked Eastern States with complex work. Transforming an

untouched parcel into land prepared for development is a challenging endeavor. For

Eastern States to prepare Developers’ land, it must clear the ground, install sewer

systems and water lines, construct facilities, and install roads and curbs.22 The

16
Trial Tr. Day 3 at 90.
17
Id.
18
D.I. 112 (“Def. Op. Br.”) 4.
19
Trial Tr. Day 1 at 266.
20
Trial Tr. Day 1 at 94.
21
Trial Tr. Day 1 at 94.
22
Trial Tr. Day 1 at 37.

6
projects often spanned several years, and while the contracts captured the general

contours of the work, they did not capture the minutiae and the unforeseen, day-to-

day hurdles that arise during heavy civil site development. Neither Eastern States

nor Developers dispute that the contracts are valid and enforceable.

D. The Parties’ Contractual Relationship

Between 2012 and 2018, Eastern States and Developers entered into the four

contracts—the Darleycap Project, St. Anne’s Project, Willowcap Project, and

Springcap Project—(“Contracts”) relevant to this case. Julian explained that

throughout the process, Eastern States never “had to call a lawyer in a negotiation of

a contract” because “[t]he Capano organization always provided [the] contract[s].”23

It became apparent at trial that Eastern States and Developers did not heavily

negotiate their business relationship.24 From project to project, some contractual

provisions were edited or removed, but the terms germane to the parties claims

remained the same; most variations involved descriptions of land and the amount

Developers were required to pay Eastern States for each job.25

While the general terms set forth in each of the contracts governing the four

projects were virtually identical, rarely were the contracts terms strictly followed by

23
Trial Tr. Day 1 at 40.
24
Trial Tr. Day 1 at 39-40.
25
Trial Tr. Day 1 at 99.

7
either party. As Gleason put it, “[w]hen you open up the ground, things can be

different” than what the parties assumed at the time they signed the Contracts.26 And

things often were different. For larger unforeseen circumstances arising during a

project, Eastern States submitted change orders to Developers.27 These change

orders included additional work, additional payment,28 and often necessitated

schedule changes. According to Julian, those in the construction industry “deal with

[change orders] all the time.”29

Smaller adjustments or fixes, often referred to as “punch list” items, also arise

“all the time” and are an unavoidable component of site development.30 While not

reduced to change orders, the parties generally agreed that punch list items would be

remedied prior to project completion. As the projects progressed, the Authority

Having Jurisdiction (“AHJ”)—in this case, DelDOT—would flag correctable issues

and bring them to Eastern States’ and Developers’ attention through these punch

lists.31 Punch list items varied in severity; some were quick fixes, others required

26
Trial Tr. Day 1 at 45.
27
Id.
28
Trial Tr. Day 1 at 45-47.
29
Trial Tr. Day 1 at 46.
30
Trial Tr. Day 1 at 87.
31
Trial Tr. Day 3 at 11-12.

8
Eastern States to spend more significant time.32 Until DelDOT approved Eastern

States’ punch list corrections, the work was deemed incomplete.33 Green testified

that prior to December 16, 2020, Capano had never terminated Eastern States for

failing to meet DelDOT’s approval.34

The Contracts’ Terms

The relevant Contracts stood as separate agreements, but key provisions were

consistent across the documents.35

Monthly Invoices. Section 5.1 required Developers to “make payments to

[Eastern States] on the basis of applications for payment submitted by [Eastern

States] to [Developers] as the Work progresse[d].”36 The Contracts limited Eastern

States’ payment applications to “one (1) time in any calendar month,” and, “[t]he

billing period [was] monthly.”37 Eastern States, by the fifth of each month, was

required to submit its invoices through an American Institute of Architects (“AIA”)

payment form, which assigned industry standard percentages to different tasks

32
Trial Tr. Day 1 at 87-88.
33
Trial Tr. Day 2 at 231.
34
Trial Tr. Day 2 at 230.
35
See generally, Contracts.
36
Contracts § 5.1.
37
Id.

9
within an entire project.38 Then, within one calendar month of Eastern States’ AIA

submission, Developers were to pay Eastern States.39 For each invoice, Eastern

States billed Developers for the percentage of the work completed in a given month

with the sum determined by applying that percentage to the total cost of the project.40

Pay-When-Paid Provision. Section 5.5, the “pay-when-paid” provision,

required Developers to pay Eastern States for its “satisfactory performance . . .

within thirty (30) days of receipt of [Eastern States’] application for payment out of

such amounts as have been paid to [Developers] for the Work performed by [Eastern

States] to which such application for payment applies.”41 The pay-when-paid

provision allowed Developers to pay Eastern States using money supplied by a third-

party (e.g., by a bank draw) within thirty days of Eastern States’ applications for

payment. While Eastern States “never knew where a payment was coming from”42

and rejected the idea that the pay-when-paid provision applied to Eastern States’ and

Developers’ relationship at all,43 Hensley insisted that pay-when-paid provisions are

38
Contracts at 1.
39
Id.
40
Trial Tr. Day 1 at 105-107.
41
Contracts § 5.5.
42
Trial Tr. Day 1 at 111.
43
Trial Tr. Day 2 at 19.

10
necessary in “any job that has financing,” including the relevant projects. 44 And,

Hensley explained, if Developers “didn’t receive that money, [Developers] didn’t

pay it.”45

Holdback Provision. Section 5.3 allowed Developers to withhold payments

“in [their] sole discretion and without further notice to [Eastern States] if [Eastern

States] defaults in performance . . . or fails to perform the Work in accordance with

the provisions [of the contract] or if [Developers] dispute such payments.” 46 To

Developers, the Holdback Provision provided them “some recourse” had Eastern

States not corrected its work.47 But, it was not until December 2020 that Capano

“ended up holding payments.”48

Notice Provision. Under Section 5.7, the “Notice Provision,” Developers

could “dispute any application by [Eastern States] or other claim for payment by

notice (which may be by telephone, fax or e-mail) to [Eastern States] given within

seven (7) calendar days after receipt of the duly submitted application for payment

44
Trial Tr. Day 3 at 108.
45
Id.
46
Contracts § 5.3.
47
Trial Tr. Day 3 at 107.
48
Id.

11
or other claim for payment.”49 Developers never provided notice that Eastern States

had failed to comply with any of the Contracts’ terms.50

E. Tensions Grow

Eastern States and Developers held biweekly progress meetings; Julian,

Gleason, and Green attended for Eastern States, and Hensley participated for

Developers.51 Capano did not attend the progress meetings.52 These meetings were

held to address, among other things, project delays and payment issues.53

Developers’ failure to pay invoices “was a topic that was always present” at these

meetings and throughout the parties’ relationship.54 Of course, both parties had

issues with the other’s contractual compliance. While Eastern States pressed

Developers for payment, Developers implored Eastern States to stay on schedule.55

Throughout 2018 and 2019, in response to unpaid invoices, Eastern States

demobilized on Developers’ projects.56 This included “removing resources,

49
Contracts § 5.7.
50
Trial Tr. Day 1 at 256; Trial Tr. Day 2 at 195.
51
Trial Tr. Day 1 at 119.
52
Id.
53
Trial Tr. Day 1 at 119-121.
54
Trial Tr. Day 1 at 121.
55
Trial Tr. Day 3 at 113-114.
56
Trial Tr. Day 2 at 20.

12
equipment, tools, [and] materials from [the] project.”57 Eastern States engaged in

demobilization as a last resort, and only when Developers had “large sums of money

that [were] significantly delinquent.”58

Developers financed the projects from various sources.59 For some projects,

Developers would enter into an agreement with DelDOT under which DelDOT

would contribute funding.60 For other projects, Developers’ received bank draws

after the bank’s inspector verified Eastern States’ work.61 Understandably, Eastern

States was not concerned with the source of Developer’s funding, “as long as

[Eastern States] got paid in the end.”62

In July of 2019, Capano, believing that “every job was significantly behind

schedule and really affecting [Developers’] ability to do business,” requested a

meeting with Eastern States.63 Both parties were well-represented at this meeting—

Julian, Gleason, and Green appeared for Eastern States, and Capano, Hensley, and

Krapf represented Developers.64 Capano wanted the projects to “move faster,” and

57
Trial Tr. Day 1 at 78.
58
Trial Tr. Day 1 at 80.
59
Trial Tr. Day 1 at 114-115.
60
Id.
61
Trial Tr. Day 6 at 13-14.
62
Trial Tr. Day 2 at 21.
63
Trial Tr. Day 1 at 138-139; Trial Tr. Day 6 at 14–15.
64
Trial Tr. Day 1 at 139.

13
Eastern States wanted to be paid for its work.65 Eastern States affirmed its ability to

complete the work and left the meeting with the understanding that its “end of the

bargain was getting the work done. [Developers’] end of the bargain was paying

[Eastern States] in 60 days.”66

In the months following the meeting, Eastern States performed a large amount

of site work on Developers’ projects and invoiced Developers accordingly.67 Sixty

days came and went, and Eastern States was not paid. On October 2, 2019, a member

of Eastern States’ accounting department emailed Hensley and asked for a “payment

status” regarding a $250,800 invoice more than sixty days old, and a $124,454.50

invoice more than ninety days old.68 Hensley told Julian that Developers were

moving money around; they expected to “be funded early next week” and were

“pressing on closing the loan this week to receive funding.”69 Julian informed

Hensley that Eastern States was “becoming increasingly frustrated with the hollow

statements and lack of progress [toward] being paid in a timely manner,” and in the

65
Trial Tr. Day 6 at 15.
66
Trial Tr. Day 1 at 140–141.
67
Trial Tr. Day 1 at 145.
68
JX 138.
69
Id.

14
event payments were not received, Eastern States would again be forced to

demobilize.70

It was not until summer 2020 that Eastern States, in response to “significant”

nonpayment, demobilized again.71 By September 24, 2020, Developers were 117

days overdue on a $200,000.00 payment for St. Anne’s, sixty-one days overdue on

a $257,260.00 payment for Willowcap, and approaching sixty days overdue on a

$301,279.50 payment for Springcap.72 In response to Eastern States’ summer

demobilization, Developers brought some, but not all, outstanding accounts up to

date. On December 2, 2020, Developers were ninety-six days late on a $153,150.00

payment for Springcap, 126 days late on an additional $160,000.00 payment for

Springcap, and sixty-three days late on a $108,800.00 payment for Willowcap.73

Throughout 2019 and 2020, DelDOT representatives brought to Developers’

attention several instances of Eastern States’ defective work. David Scott (“Scott”),

DelDOT’s Central District Subdivision Manager who oversaw the Willowcap

project, found that significant portions of Brenford Road needed to “be removed and

replaced” to satisfy DelDOT’s rideability specifications.74 Richard Larkin

70
Id.
71
Trial Tr. Day 1 at 146-147.
72
JX 188.
73
JX 207.
74
JX 118.

15
(“Larkin”), a DelDOT Utility Coordinator, testified that Eastern States’ work on

Springcap did not meet DelDOT’s standards—such as “a hump in the road.”75

On December 3, 2020, Scott emailed Hensley and informed him of corrections

needed on Brenford Road in the Willowcap project.76 Hensley, including Eastern

States on his email, responded to Scott to schedule an on-site meeting to “review all

the Brenford Road issues.”77 Hensley assumed, based on Scott’s email, that DelDOT

would refuse to perform a formal inspection on Developers’ projects until Eastern

States corrected its work because a project was not considered complete until these

DelDot punch list items were addressed.78 The parties met on site to review

DelDOT’s concerns, and Brandon Bunting—an Eastern States site supervisor—

recorded the various issues and planned corrective measures.79

F. Capano Terminates the Contracts

On December 8, 2020, five days after the parties met with DelDOT, Hensley

emailed Gleason and asked him to “send good schedules [for fixing the DelDOT

issues] over for Darley Green, willowwood, and burtons pond” because Developers

75
D.I. 112, 37.
76
JX 211.
77
Id.
78
Trial Tr. Day 1 at 137.
79
Trial Tr. Day 3 at 146–147.

16
were “thinking of ways to keep both parties satisfied moving forward.”80 Despite

myriad issues, Hensley remained optimistic that Developers and Eastern States

could continue to work together. On December 15, 2020, Gleason replied with the

requested proposed schedules.81 The next day, Capano called Gleason and left a

voicemail:

Terry, hey, it’s uh Louis Capano. I just received your schedule for
Burton’s Pond, and it looks as though you don’t want to work for us.
So, um, I just want to catch up with you and figure out how we, um,
separate here. Um, we have your checks, um, but you know obviously,
this is a substantial cost to us, so we have to figure out how to separate.
You know, giving us a schedule for April on a job where you have to
run water and pave is, obviously you just don’t care about doing the
job. So, we’re just gonna move on. Um, based on your schedule and
uh I guess we figure out the money however you want to. Give me a
call.82

Gleason, unsure of Capano’s intent, emailed Krapf and Hensley and asked

them to “clarify in writing” what Capano meant by his voicemail.83 Neither Hensley

nor Krapf responded to Gleason’s email. On December 18, 2020, Gleason called

Capano, again requesting clarification.84 Capano told Gleason that he had

terminated Eastern States from all jobs that Developers had contracted them to

80
JX 222.
81
Id.
82
D.I. 9 (“Am. Compl.”) ¶ 12.
83
JX 227.
84
Trial Tr. Day 2 at 82-83.

17
complete.85 Gleason, to no avail, advised Capano that the schedules were

reasonable; the call ended with a complete termination of all the Contracts.86 Lest

any doubt remain, Capano testified at trial that he intended to completely terminate

Eastern States’ from all of Developers projects, that it was solely his decision, and

that he did not confer with any of his employees before leaving the voicemail.87

Capano never contacted Julian to discuss the termination; in fact, they had not

spoken since the summer 2019 meeting where Eastern States confirmed its ability to

complete the work on the Developers open projects.88

Gleason emailed Krapf and Hensley to inform them that “based on [Capano’s]

verbal direction, no further work will be performed on any sites,” and that

“[d]emobilization will proceed and be completed by 12/31/20.”89 Green testified

that he spoke with Hensley “to try to work things out” after Capano’s voicemail, but

Eastern States received no further response or direction from Developers.90 On

January 6, 2021, Gleason emailed Krapf and Hensley to inform them that “Eastern

85
Trial Tr. Day 2 at 82-83.
86
Id.
87
Trial Tr. Day 6 at 53-54.
88
Trial Tr. Day 1 at 152-153.
89
JX 227.
90
Trial Tr. Day 3 at 9-11.

18
States proceeded with demobilization last week.”91 By mid-January 2021, Eastern

States had completely extricated its materials and equipment from Developers’ work

sites and ceased performance under the Contracts.92

G. The Aftermath of Capano’s Termination

On several occasions throughout the first half of 2021, Developers contacted

Eastern States to discuss completing the projects Capano had terminated.93 On

January 11, 2021, Hensley asked Green and Gleason to attend a meeting with

DelDOT and told them he did “not have any intention o[f] performing corrective

work on Conleys chapel rd until . . . we both agree on a path forward.”94 On

February 6, 2021, Hensley again emailed Gleason, this time telling him that it was

Developers’ goal to “work [issues] out with [Eastern States] and bring it to a closure

asap because [he] would rather not fix [Eastern States’] work when [Eastern States]

can do it for a fraction of the cost [than] it would cost [him]—then we are in a

payment dispute.”95 On April 2, 2021, Developers repeatedly “demand[ed]” that

Eastern States provide a remediation plan aimed at fixing the defects in its work.96

91
JX 227.
92
Trial Tr. Day 2 at 83.
93
JX 229; JX 254; JX 297.
94
JX 229.
95
JX 254.
96
JX 297.

19
Developers’ post-termination requests went unanswered. As Gleason

testified, “at that point we were terminated and we didn’t feel like we had a

relationship with [Developers] . . . to go back and work on their sites because we

were told to vacate the sites.”97 Developers turned to another site developer to

remediate identified issues and complete the projects. Harmony Construction met

Developers’ needs and worked to continue—and in some instances fix—Eastern

States’ work.98

Eastern States contends that Developers owed $1,194,121.7599 at the time of

termination. And Gleason estimated that Eastern States suffered $963,976.96 in lost

profits as a result of Developers’ termination of the Contracts.100 Developers, left to

bring the projects to AHJ approval, assert that they were forced to pay $4,274,368

across the four projects to repair Eastern States’ defective work and to complete the

land development.101

97
Trial Tr. Day 2 165-66.
98
Trial Tr. Day 5 at 181-182.
99
JX 331.
100
Trial Tr. Day 2 at 96.
101
Trial Tr. Day 6 at 79.

20
H. The Litigation

Eastern States sued Developers.102 In its Amended Complaint, Eastern States

asserted breach of contract and unjust enrichment claims against Developers—

Darleycap, Springcap, Willowcap, and St. Anne’s.103 Developers answered, and

collectively as “Counterclaim Plaintiffs,” asserted claims for declaratory judgment,

breach of contract, breach of express warranties, and breach of implied warranties.104

Developers moved to dismiss Eastern States’ complaint;105 the Court denied

the motion.106 Developers then endeavored to dismiss portions of Eastern States’

Complaint through summary judgment.107 The Court denied that motion as well.108

The case proceeded to trial. Over six days, from July 15, 2024, through July 22,

2024, the parties presented evidence in support of their claims and defenses.109

Thereafter, the Court received written briefing and oral argument from the parties.110

102
D.I. 1.
103
See Am. Compl.
104
See D.I. 50 (“Am. Countercl.”).
105
D.I. 4.
106
D.I. 8.
107
D.I. 59.
108
D.I 97.
109
D.I. 101.
110
D.I. 112, 113, 117, 118, 121, 122, 125.

21
1. Eastern States’ Claims

Eastern States contends Developers materially breached the Contracts in two

ways. First, Eastern States argues that Developers’ failed to pay for work

performed.111 Eastern States alleges Developers never invoked the Notice Provision

or otherwise disputed its applications for payment, running afoul of the Contracts’

requirements.112 And, when unchallenged, Eastern States maintains that those

payment applications became binding contractual obligations that Developers’

breached by failing to pay.113 Second, Eastern States asserts Capano’s termination

acted as a material breach that “relieved Eastern States of further performance.”114

Eastern States’ proposed damages are two-pronged. Eastern States contends

it is entitled to $1,194,121.75115 for the unpaid invoices and $963,976.96 for the

profits it lost as a result of Capano’s termination.116 Eastern States’ total claimed

damages, therefore, are $2,158,098.71. The basis for the amount owed on unpaid

invoices is straightforward: Eastern States worked on Developers’ projects, and

111
Pl. Op. Br. 41-46.
112
Pl. Op. Br. 42-43.
113
Pl. Op. Br. 43.
114
Pl. Op. Br. 46-49.
115
JX 331.
116
Pl. Op. Br. 49-53.

22
Developers did not pay for that work.117 As to lost profits, Eastern States posits that

its trial evidence proved these damages with “reasonable certainty.”118

Eastern States’ unjust enrichment claims serve as a backstop to its contract

claims; asserting that “if the Court determined that a legal remedy is not available,”

then Developers must pay because their retention of the money was “without

justification.”119

2. Developers’ Counterclaims

Developers answered and counterclaimed for breach of contract.120

Developers contend Eastern States materially breached the Contracts in three ways:

“it did bad work; it missed critical deadlines; and it refused to fix errors.”121 On the

Willowcap and Springcap projects, Developers allege Eastern States’ work failed to

pass DelDOT inspection on several occasions and that, as a result, neither schedule

was maintained.122 Additionally, Developers maintain that Eastern States’ failure to

remediate its defects constitutes a material breach of the Contracts.123

117
Pl. Op. Br. 49-50.
118
Pl. Op. Br. 50-52.
119
Pl. Op. Br. 59.
120
See Am. Countercl.
121
Def. Op. Br. 31.
122
Def. Op. Br. 33-35, 37-38.
123
Def. Op. Br. 36.

23
Developers calculate their damages to total $4,274,368.124 This sum

encompasses the costs Developers incurred to fix Eastern States’ defective work, and

the costs Developers incurred to complete the projects.125 Developers assert these

damages need not be offset by any damages Eastern States alleges because, in

Developers’ view, “Eastern States is not entitled to any damages.”126

Developers assert they “have proven their declaratory judgment claim based

on the same facts proven to support their breach of contract claims.”127 Similarly,

Developers support their breach of warranty claims with the same factual allegations

as they do their breach of contract and declaratory judgment claims.128

Presented with the parties’ evidence at trial and having considered their

posttrial briefing and argument, the resolution of this case turns on the parties’

performance under the contracts. The Court will address the various claims

presented, but, in the end, this case is, at its core, a contract dispute.

124
Def. Op. Br. 51.
125
Id.
126
Def. Op. Br. 56.
127
Def. Op. Br. 42.
128
Def. Op. Br. 41.

24
III. GENERAL LEGAL PRINCIPLES

In a civil trial, “[e]ach party bears the burden of proving their respective

claims and defenses by a preponderance of the evidence.”129 “Proof by a

preponderance of the evidence means proof that something is more likely than

not.”130 “This means that certain evidence, when compared to the evidence opposed

to it, has the more convincing force and makes the Court believe that something is

more likely true than not.”131 If the evidence presented by the parties “is

inconsistent, and the opposing weight of the evidence is evenly balanced, then ‘the

party seeking to present a preponderance of the evidence has failed to meet its

burden.’”132 To determine which party has met its burden, the Court “may consider

the testimony of all witnesses regardless of who called them, and all exhibits

received into evidence regardless of who produced them.”133

129
Navient Sols., LLC v. BPG Office Partners XIII Iron Hill LLC, 2023 WL 3120644,
at *10 (Del. Super. Ct. Apr. 27, 2023).
Feenix Payment Sys., LLC v. Blum, 2024 WL 2768386, at *10 (Del. Super. Ct.
130

May 29, 2024).
131
Id.
132
Interim Healthcare, Inc. v. Spherion Corp., 884 A.2d 513, 545 (Del. Super. Ct.
2005) (quoting Eskridge v. Voshell, 593 A.2d 589 (TABLE), 1991 WL 78471, at *3
(Del. 1991)).
133
Feenix Payment Sys., LLC, 2024 WL 2768386, at *10.

25
In a bench trial, the Court sits as the factfinder.134 The Court must “assess the

credibility of the witnesses and then . . . weigh all of the evidence presented.”135 The

Court is “free to accept or reject any or all of the sworn testimony, as long as it

consider[s] all of the evidence presented,” just as a jury does.136 Where the Court

cannot reconcile conflicting evidence, it retains discretion to determine which

evidence deserves more weight.137

In reaching its verdict, the Court has examined all exhibits and considered the

testimony of all of the witnesses. The fact that some particular point or concept may

be mentioned should not be read as any indication that the Court did not consider all

evidence and legal principles applicable to this case and to the parties’ claims,

counterclaims, and defenses. It is difficult at times to completely segregate findings

of fact from conclusions of law; to the extent any one of the Court’s factual findings

might be more appropriately viewed as a conclusion of law, that finding of fact may

be considered the Court's conclusion of law on that point. The Court has considered

Delaware caselaw defining the legal precepts applicable to the claims and defenses

134
See, e.g., Torres v. Bishop, 2021 WL 6053870, at *4 (Del. Super. Ct. Dec. 21,
2021) (citing Pencander Associated, LLC v. Synergy Direct Mortg. Inc., 2010 WL
2681862, at *2 (Del. Super. Ct. June 30, 2010)).
135
Mundy v. Devon, 906 A.2d 750, 755 (Del. 2006).
136
Pardo v. State, 160 A.3d 1136, 1150 (Del. 2017).
137
Torres, 2021 WL 6053870, at *4.

26
offered by the parties. The Court applied the Delaware Rules of Evidence to the

testimony and exhibits and, in its deliberation, has relied only upon that which would

be admissible under those rules. And the Court has considered each party’s

arguments on their respective theory of the case and any weight to be assigned to

testimony or evidence.

27
IV. ANALYSIS

The parties do not dispute that their relationship is defined by contracts.

Rather, they dispute their respective performance. Their arguments in support of

their claims are quite similar: both insist their performance was excused because the

other party breached. The trial revealed that both parties failed to fully perform, and

the Court must determine which party, if either, was justified in their actions based

on the other’s failure.138 The Court finds that before Capano left the December 16,

2021, voicemail, neither Eastern States nor Developers adhered to the terms of the

Contracts, but also finds that both parties elected to work within the relationship they

had cultivated for a decade. And, despite Eastern States’ defective work, any

damages must account for Developer’s conclusive election to discontinue the

parties’ contractual relationship.

A. The Parties’ Breach of Contract Claims

The threshold question is whether Eastern States established that Developers

must pay the outstanding invoices. To answer that question, the Court must

determine: first, whether Developers had a contractual duty to pay the invoices; and

second, whether Developers’ failure to pay is excused by any breaches of Eastern

States. The Court finds that Eastern States proved the Contracts required Developers

to pay the submitted invoices. And Eastern States also proved that Developer’s

138
See Restatement (Second) of Contracts § 227.

28
failure to pay is not excused. Developers’ election to have Eastern States continue

its performance until Capano terminated the Contracts does not preclude Developers

from recovering damages for Eastern States’ breaches. The Court’s reasoning

follows.

1. Eastern States’ Breach of Contract Claim.

To prevail on its claim that Developers breached the contracts, Eastern States

must establish, by a preponderance of the evidence: “(1) the existence of a

contractual obligation; (2) a breach of that obligation; and (3) damages resulting

from the breach.”139 Under Delaware law, contracts are construed as they would be

understood by an “objective, reasonable third party.”140 “The true test is not what

the parties to the contract intended it to mean, but what a reasonable person in the

position of the parties would have thought it meant.”141 Consequently, “Delaware

law requires courts to enforce the plain and unambiguous terms of a contract as the

binding expression of the parties’ intent.”142

139
Active Day OH, Inc. v. Wehr, 2024 WL 3201167, at *3 (Del. Super. Ct. June 27,
2024) (internal citations omitted).
140
Id. (quoting Zenith Energy Terminals Joliet Holdings LLC v. CenterPoint
Properties Trust, 2023 WL 615997, at *9 (Del. Super. Ct. Jan. 23, 2023)).
141
Lorillard Tobacco Co. v. Am. Legacy Foundation, 903 A.2d 728, 739 (Del. 2006)
(citing Rhone-Poulenc Co., 616 A.2d 1192, 1196 (Del. 1992)).
New Castle County v. Hersha Hospitality Mgmt., L.P., 2025 WL 1203501, at *7
142

(Del. Super. Ct. Apr. 25, 2025).

29
As site development continued, Eastern States, to receive payment for its

work, submitted pay applications pursuant to the parties’ Contracts. Eastern States

contends it “timely submitted its invoices for work that it appropriately performed

pursuant to the terms of the Contracts and that Developers failed to meet their

payment obligations.”143 Eastern States’ breach of contract claims, therefore, center

on Developers’ failure to pay for work performed.144 The parties rely on different

provisions of the same Contracts to support their respective positions; while Eastern

States contends Developers failure to pay their debts constitutes a breach of contract,

Developers assert the Contracts—and Eastern States’ defective performance—

justify their failure to pay.

i. The Pay-When-Paid Provision Does Not Justify Developers’ Failure to
Pay Eastern States.

Developers turn to two provisions of the Contracts—Sections 5.3 and 5.5—to

justify their nonpayment. Section 5.5, the “Pay-When-Paid” provision, allowed

Developers to pay Eastern States using money supplied by a third-party (e.g., by a

bank draw) within thirty days of Eastern States’ applications for payment.145 While

Eastern States insists the pay-when-paid provision “does not align with the parties’

143
Pl. Op. Br. at 40.
144
Pl. Reply Br. at 4; See generally, Pl. Op. Br.
145
Contracts § 5.5.

30
relationship,”146 Developers maintain the pay-when-paid provision allowed them to

withhold payments until they receive funding, and, in effect, granted them

permission to ignore Eastern States’ invoices—and the thirty-day schedule for

payment—until Developers were funded by a third-party.147 In Developers’ view,

its obligation to pay Eastern States did not arise until it received funding from the

third-party, and, when Developers were not paid by the third-party, they argue that

Eastern States’ right to receive payment had not yet accrued. Eastern States argues

that even if the Pay-When-Paid provision applies, it did not shift to Eastern States

“the risk of nonpayment if Developers failed to obtain payment from another

source.”148

Developers contend that the pay-when-paid provision created a condition

precedent to Developers’ obligation to pay Eastern States.149 A condition precedent

is an “act or event, other than a lapse of time, that must exist or occur before a duty

to perform something promised arises.”150 Generally, Delaware law disfavors

conditions precedent “because of their tendency to work a forfeiture.”151 As such,

146
Pl. Op. Br. at 25.
147
D.I. 118 (“Def. Ans. Br.”) 42.
148
Pl. Op. Br. at 26.
149
Def. Op. Br. at 16.
150
Thomas v. Headlands Tech Principal Holdings, L.P., 2020 WL 5946962, at *5
(Del. Super. Ct. Sept. 22, 2020).
151
Id.

31
“[p]arties to a contract must use unambiguous, express language to create a condition

precedent capable of producing a forfeiture.”152 Where that unambiguous language

is absent, the Restatement (Second) of Contracts compels the Court to interpret the

parties’ contract in a way “that will reduce the obligee’s risk of forfeiture, unless the

event is within the obligee’s control or the circumstances indicate that he has

assumed the risk.”153

Matters regarding pay-when-paid provisions are a question of contract

interpretation.154 Under Delaware law, where there exists no “unambiguous intent

to make receipt of payment by [Developers] a condition precedent of its obligation

to pay [Eastern States], a pay-when-paid clause must be interpreted as providing the

time for payment rather than a condition precedent.”155 Where, as here, an owner

fails to pay their contractor, this Court has adopted the majority view that the

contractor must be paid in a “reasonable” time.156

Despite the differing interpretations of the provision offered by the parties, the

pay-when-paid provision in their contracts “does not evince an intent to impose a

152
Id.
153
Restatement (Second) of Contracts § 227.
154
Casey Emp. Services, Inc. v. Dali, 1993 WL 478088, at *4 (Del. Nov. 18, 1993).
155
McAnulla Elect. Const., Inc. v. Radius Technologies, LLC, 2010 WL 3792129, at
*7 (Del. Super. Ct. Sept. 24, 2010) (cleaned up).
156
Id.

32
condition precedent upon [Developers’] payment obligation.”157 As in McAnulla,

the pay-when-paid provision “does not explicitly reference a condition precedent or

employ other language shifting the risk of a default” by the third-party to Eastern

States.158 Instead, the language providing that Eastern States’ “application for

payment” would be paid “out of such amounts as have been paid to” Developers sets

a time for payment. And, because Eastern States was not timely paid, the pay-when-

paid provision would require Eastern States to be paid within a reasonable time. That

did not occur.

ii. The Holdback Provision Does Not Justify Developers’ Failure to Pay
Eastern States.

Section 5.3, the “Holdback Provision,” allowed Developers to withhold

payments “in [their] sole discretion and without further notice to [Eastern States] if

[Eastern States] defaults in performance. . . or fails to perform the Work in

accordance with the provisions [of the contract] or if [Developers] dispute such

payments.”159 Developers argue that Section 5.3 trumps Section 5.7, rendering

unnecessary any notice of dispute to Eastern States.160

157
Id.
158
Id.
159
Contracts § 5.3.
160
Def. Ans. Br. 30-31.

33
The Holdback Provision specifically allowed Developers to withhold

payments in their sole discretion if Eastern States failed to complete its site work in

accordance with the Contracts. And for more than a year, Developers did what they

were allowed to do—they withheld payments to Eastern States in their “sole

discretion.” But Developers’ decision not to pay does not mean that Eastern States

must suffer at the hands of Developers’ “sole discretion” forever.

iii. Time Was Not of the Essence.

Trial testimony was devoted to explaining why projects were delayed, which

party was responsible for the delays, and how that responsibility impacts the

outcome of this case. Developers assert that because construction deadlines are

“critically important,” time was of the essence, and Eastern States’ delays constituted

material breaches of the contracts.161 Developers allege Eastern States failed to

complete Block K in Darley Green by December 2019, Phase 5 of Burtons Pond by

July 2019, Conleys Chapel Road by June 2020, Phase 1 of Brenford Road in 2018,

and all of Brenford Road by July 2020.162 Developers concede that none of the

Contracts expressly contained a “time is of the essence” clause, and, in effect, ask

this Court to inject and enforce an unwritten term. The Court will not do so.

161
Def. Ans. Br. 14-25.
162
Def. Ans. Br. 17.

34
Delaware “law presumes contracting parties are familiar with time of the

essence clauses and that they know how to make time of the essence if they so desire,

especially in contracts between sophisticated business[es].”163 While Developers

argue the delays prevented them from “being able to sell lots to homebuilders,”164

Developers (and Eastern States) have decades of experience working in the

construction industry. Both parties are experienced and sophisticated in construction

contracting, and if they wanted time to be of the essence, they would have

memorialized it in their written agreements. This Court’s insertion of a “time is of

the essence” clause “would be inconsistent with fundamental rules of contract

interpretation, which require strict adherence to the language of the contract when

its terms are clear.”165

iv. Developers Never Invoked the Notice Provision

Section 5.7 of the Contracts instructed Developers to “dispute any application

by [Eastern States] or other claim for payment by notice (which may be by telephone,

fax or e-mail) to [Eastern States] given within seven (7) calendar days after receipt

of the duly submitted application for payment or other claim for payment.”166

163
HIFN, Inc. v. Intel Corp., 2007 WL 1309376, at *10 (Del. Ch. May 2, 2007).
164
Def. Ans. Br. 16.
165
HIFN, Inc., 2007 WL 1309376, at *11.
166
Contracts § 5.7.

35
Eastern States asserts its payment applications “became binding contractual

obligations once the 5.7 notice period elapsed.”167 And, as a result, Eastern States

asks this Court to find that Defendants breached the Contracts by failing to pay the

duly submitted invoices.

Eastern States asserts it was not until this litigation that Developers actually

disputed Eastern States’ invoices.168 In Eastern States’ view, Developers never

premised non-payment on disputed invoices, rather, “the invoices were simply past

due.”169 Developers had direct and daily contact with Eastern States during the

projects, but no evidence in the record reveals that Developers ever provided notice

of a dispute of Eastern States’ billing.

Relying on an email sent by Henlsey to Julian, Developers contend they “put

Eastern States on notice that it breached the Contracts no later than September 24,

2020.”170 In this email, Hensley expressed concern with Eastern States’ progress,

telling Julian that “Darley Green [was] a disaster,” Burtons Pond remained

incomplete, and Brenford Road’s sidewalks were only half complete.171 But,

167
Pl. Op. Br. 43.
168
Pl. Op. Br. 27-28.
169
Pl. Op. Br. 28.
170
Def. Ans. Br. 45-46.
171
JX 188.

36
“[v]oicing displeasure and asking for accountability is not the same as challenging

[the] right to payment.”172

Hensley’s email identified parts of the outstanding projects in need of

remediation. But Hensley did not—as the Notice Provision required—dispute

Eastern States’ payment applications. In fact, his communications conveyed the

opposite. Despite the “fixes” identified in his e-mail, Hensley concluded his

correspondence to Julian by stating: “I am not complaining so please don’t interpret

this the wrong way or as an excuse for the late payments as two wrongs don’t make

a right.”173 Developers did not invoke the Notice Provision.

v. Developers’ Breached Their Obligation to Pay Eastern States.

The parties agree that the Contracts are valid and enforceable.174 The Court

must determine whether Developers breached an obligation they owed Eastern

States under the Contracts. Developers maintained one obligation: to “make

payments to [Eastern States] on the basis of applications for payment submitted by

[Eastern States] to [Developers] as the Work progresses.”175 Developers’ payments

were to be made “within thirty (30) days of receipt of [Eastern States’] application

172
Outbox Sys., Inc. v. Trimble, Inc., 2024 WL 1886089, at *9 (Del. Super. Ct. Apr.
30, 2024).
173
JX 188.
174
Pl. Op. Br. 40; Def. Op. Br. 31.
175
Contracts § 5.1.

37
for payment.”176 Eastern States contends Developers’ materially breached their

obligation to pay Eastern States under the Contracts.

“Whether a breach is material is a fact-sensitive analysis.”177 Under Delaware

law, materiality is a question for the trier of fact; it “is one of degree” and is

determined by “weighing the consequences in light of the actual custom of men in

the performance of contracts similar to the one that is involved in the specific

case.”178 A material breach is “a failure to do something that is so fundamental to a

contract that the failure to perform that obligation defeats the essential purpose of

the contract or makes it impossible for the other party to perform under the

contract.”179

This Court looks to the Restatement (Second) of Contracts to determine

whether a breach is material, and in doing so, weighs the following factors:

(a) the extent to which the injured party will be deprived of a reasonably
expected benefit; (b) the extent to which the injured party can be
adequately compensated for the part of that benefit of which he will be
deprived; (c) the extent to which the party failing to perform or to offer
to perform will suffer forfeiture; (d) the likelihood that the party failing
to perform or to offer to perform will cure his failure, taking into

176
Contracts § 5.5.
177
Current Solutions, Inc. v. Appoquinimink Sch. Dist., 2024 WL 5103281, at *3
(Del. Super. Ct. Dec. 13, 2024).
Foraker v. Voshell, 2022 WL 2452396, at *8 (Del. Super. Ct. July 1, 2022) (citing
178

Carey v. Estate of Myers, 2015 WL 4087056, at *20 (Del. Super. Ct. July 1, 2015)).
Shore Inv., Inc. v. Bhole, Inc., 2011 WL 5967253, at *5 (Del. Super. Ct. Nov. 28,
179

2011) (quoting 23 Williston on Contracts § 63:3 (4th ed.)).

38
account of all the circumstances including any reasonable assurances;
and (e) the extent to which the behavior of the party failing to perform
or to offer to perform comports with the standards of good faith and fair
dealing.180

The Court finds Developers materially breached the Contracts. Perhaps nothing is

more fundamental to a contract for services than the concomitant obligation to pay

for work performed. From Contract formation, through years of work, until Capano

abruptly terminated the Contracts, Developers continually promised to pay Eastern

States its outstanding invoices but never did. Developers, relying at trial on the “pay-

when-paid” provision, now seek to excuse their nonpayment. But it was not until

Eastern States sued for payment that Developers, for the first time, asserted Eastern

States’ deficient performance as justification for their nonpayment. And while the

Contracts allowed Developers to “terminate t[he] Agreement[s] at any time,” it did

not grant them the right to avoid compensating Eastern States for its work.

vi. Eastern States Damages

Eastern States must prove damages stemming from Developers’ breach.181

Here, Eastern States presents several unpaid invoices it directed to Developers under

180
See Restatement (Second) of Contracts § 241.
181
Connelly v. State Farm Mut. Auto. Ins. Co., 135 A.3d 1271, 1279 (Del. 2016)
(“[I]n Delaware, a cause of action for breach of contract includes damages as an
element.”).

39
the terms of the Contracts. Eastern States claims it is owed $1,194,121.75—the

remaining balance on unpaid invoices at the cessation of the parties’ relationship.182

Developers may not simply ignore the invoices for the work performed at the

time Capano terminated the Contracts.183 And, the Court disagrees with Developers

calculations of invoiced work related to work performed. For example, Developers

argue that Eastern States’ last invoice billed Springcap for 95% of the work when

only half the work had been done.184 Not so. The “Contract Sum” on Springcap was

$9 million.185 The final Springcap invoice, dated December 31, 2020, stated that

$3,857,350 in work had been completed, with a $5,142,650 “Balance to Finish.”186

Dividing the value of the completed work, $3,857,350, by the value of the Springcap

contract, $9,000,000, it is clear that Eastern States invoiced Developers—just as the

payment application indicates—for roughly 43% of the work, not, as Developers

maintain, for 95% of the work.

182
Pl. Op. Br. at 49-50.
183
See Outbox Sys., Inc., 2024 WL 1886089, at *1.
184
Def. Ans. Br. 51-56.
185
JX 667.
186
Id.

40
2. Developers May Recover for Eastern States’ Breaches.

Developers responded to Eastern States’ Complaint by asserting their own

counterclaims for breach of contract.187 Developers contend Eastern States failed

to: perform adequate work, meet deadlines, and remediate shoddy work. Developers

allege these failures constituted material breaches of the contracts. Eastern States

asserts that even if Developers’ breach of contract counterclaim had merit, its own

shortcomings were not so significant that they justified working for Developers for

free.188

To prevail on their claim, Developers must prove: “(1) the existence of a

contractual obligation; (2) a breach of that obligation; and (3) damages resulting

from the breach.”189 Developers focus on Eastern States’ poor work, failure to meet

deadlines, and refusal to fix errors.190 Generally, where “one party to a contract is

confronted with its counterparty’s material breach, the non-breaching party can

either cancel the contract and sue for total breach or continue the contract and sue

for partial breach.”191 As this Court has explained,

187
See Am. Countercl.
188
Pl. Ans. Br. 53.
189
Active Day OH, Inc. v. Wehr, 2024 WL 3201167, at *3 (Del. Super. Ct. June 27,
2024) (internal citations omitted).
190
Def. Op. Br. 31.
191
Outbox Sys., Inc., 2024 WL 1886089, at *8.

41
A material breach acts as a termination of the contract going forward,
abrogating any further obligations to perform by the non-breaching
party. Conversely, a slight breach of one party, while giving rise to an
action for damages, does not terminate the obligations of the injured
party under the contract. Failure to perform by the injured party after a
non-material breach constitutes breach of contract by the injured
party.192

The general rule is that Eastern States’ material breach would operate to

release Developers of their obligation to pay, and subsequent nonperformance by

Developers, no matter the reasons articulated, would be justified.193 But the

converse of this rule is that Eastern States’ non-material breaches would not

terminate Developers’ obligation to pay; under those circumstances, Developers’

non-performance is a breach of contract.194

Developers argue, as the general rule instructs, that “Eastern States’ prior

breaches excuse all [of] Developers’ payments.”195 Not so. Developers cannot

absolve their past debts under the contracts and reap the benefits of Eastern States’

work simply because Eastern States failed to complete the contract. In fact, “[a]n

exception to the general rule that a material breach excuses the nonbreaching party’s

192
Foraker, 2022 WL 2452396, at *7 (cleaned up).
See Eastern Elec. and Heating, Inc. v. Pike Creek Professional Center, 1987 WL
193

9610, at *4 (Del. Super. Ct. Apr. 7, 1987).
194
Id. (citing 11 Williston on Contracts § 1292, at 8 (3d ed. 1968)).
195
Def. Ans. Br. 49.

42
performance exists where the nonbreaching party chooses to maintain its benefits

under the contract.”196 This Court has held:

Where there has been a material failure of performance by one party to
a contract, so that a condition precedent to the duty of the other party’s
performance has not occurred, the latter party has the choice to continue
to perform under the contract or to cease to perform, and conduct
indicating an intention to continue the contract in effect will constitute
a conclusive election, in effect waiving the right to assert that the
breach discharged any obligation to perform. In other words, the
general rule that one party’s uncured, material failure of performance
will suspend or discharge the other party’s duty to perform does not
apply where the latter party, with knowledge of the facts, either
performs or indicates a willingness to do so, despite the breach, or
insists that the defaulting party continue to render future
performance.197

Developers kept Eastern States working despite its present claim that Eastern States’

work was defective or untimely. Developers, having waived Eastern States breaches

at the time of their occurrence as a matter of course, cannot retrospectively avoid the

obligation to pay for that work.198

i. Developers Elected to Continue the Contracts.

Developers—with knowledge of Eastern States’ deficient performance—

continued the Contracts. Their decision to abruptly terminate the contracts once

thousands of dollars in unpaid bills accrued “does not mean the balance is any less

196
Outbox Sys., Inc., 2024 WL 1886089, at *11.
197
Id. (emphasis in original) (internal citations omitted).
198
See Outbox Sys., Inc., 2024 WL 1886089, at *11.

43
due.”199 Throughout 2019 and 2020, Developers repeatedly indicated their intent

and willingness to continue the Contracts. Developers may not disregard the unpaid

invoices.

Developers’ focus on the Willowcap and Springcap projects as evidence of

Eastern States’ poor work.200 As to Willowcap, Developers knew of Eastern States

defective work for more than a year before Capano terminated the Contracts. On

April 30, 2019, Scott, the DelDOT employee overseeing progress on Willowcap,

emailed Hensley to inform Developers that DelDOT identified areas of Brenford

Road that needed to be replaced to comply with DelDOT’s rideability standards.201

Nonetheless, Developers reaffirmed their belief in Eastern States’ capability and

committed to a sixty-day payment schedule.202 As for Burtons Pond, Developers

knew of defects as early as September 2020, when Hensley emailed Julian and

detailed the deficient work.203

Nonetheless, Developers focus on three “critical deadlines” that Eastern

States failed to meet.204 Under the Contracts, Eastern States agreed to complete: (1)

199
See Balooshi v. GVP Global Corp., 2022 WL 576819, at *8 (Del. Super. Ct. Feb.
25, 2022).
200
Def. Op. Br. 1-5.
201
Trial Tr. Day 4 at 147-48; JX 118.
202
Trial Tr. Day 1 at 140.
203
JX 186.
204
Def. Op. Br. 19-21.

44
Block K in Darley Green by December 2019,205 Conleys Chapel Road by June

2020,206 and Brenford Road Phase 2 by July 2020.207 Developers assert myriad

factors for Eastern States’ inability to meet these deadlines: demobilizations, poor

work, and lack of manpower.208 Eastern States, for its part, generally asserts that

Developers own conduct caused the delays.209 Who or what caused the delays, in

the end, is immaterial to the Court’s analysis. After the deadline lapsed, Developers

had two choices: continue to perform under the contract or to cease to perform and

sue for breach of contract.210 They chose to continue.

Despite the various delays and knowledge of defective work, Developers, on

several occasions, indicated their willingness to continue performance under the

Contracts. On September 24, 2020, months after each deadline had lapsed, and with

knowledge of Eastern States’ defective work, Hensley, on behalf of Developers,

emailed Julian to inform him that, despite the issues, Developers “would like to

continue [the parties’] great relationship and get through everything.”211 Hensley

205
JX 123.
206
JX 114.
207
JX 147.
208
Def. Ans. Br. 1, 24, 26.
209
Pl. Ans Br. 41-43.
210
See Outbox Sys., Inc., 2024 WL 1886089, at *11.
211
JX 186.

45
did not convey that Eastern States should stop work or that Developers intended to

terminate the Contracts. In fact, Hensley began his email with a proposal that would

“keep things moving and . . . get back on track.”212 Eastern States kept working.

The next morning, Julian responded that it was Eastern States’ intent to

“perform items we owe to [Developers].”213 Two weeks later, on October 2, 2020,

Julian followed up and informed Hensley that Eastern States “ha[d] performed all of

the work items committed to in the email below,” the Springcap work was scheduled

for the following week, and a third-party contractor was currently scheduling the

Willowcap repaving.214 Again, despite now-alleged breaches, Developers

compelled Eastern States to press on. Developers never conveyed an intent to cancel

the Contracts.

Developers continued to induce Eastern States’ performance under the

Contracts. On November 10, 2020, Hensley emailed Green and Gleason, asking

them to “order the pipe if [they] ha[d] not done so,” because Hensley heard there

was a “pipe shortage” on the Darley Green project.215 On December 1, 2020,

Hensley promised to “[p]ay Burtons 160k before the end of [that] week.”216 On

212
JX 186.
213
JX 188.
214
Id.
215
JX 199.
216
JX 207.

46
December 8, 2020—eight days before Capano terminated the Contracts—Hensley

emailed Gleason and asked Eastern States to “send good schedules over for Darley

Green, willowwood, and burtons pond for us to review . . . [We] are thinking of

ways to keep both parties satisfied moving forward.”217

Until Capano’s fateful call, Developers engaged in conduct indicating an

intention to continue the contract.218 Developers induced Eastern States to continue

its work even though Developers were aware of the defects it now claims constitute

material breaches. As a result, their obligation to pay Eastern States under the

Contracts was not discharged.

ii. Developers May Recover for Eastern States’ Defective Work

Eastern States’ defective work constitutes a breach for which Developers may

recover. Under the Contracts, Eastern States was obligated to perform its work: (i)

in compliance with local regulations; and (ii) in a “workmanlike manner.”219 Eastern

States breached these obligations.

DelDOT, the agency responsible for ensuring Eastern States’ work complied

with local regulations, specifically rejected Eastern States’ work on several

occasions. All four DelDOT witnesses—the “ultimate decider[s] of whether or not

217
JX 222.
218
Id.
219
Contracts § 2.1.

47
a roadway meets specifications in Delaware”—were consistent in concluding that

Eastern States performed defective work.220 In January 2019, Eastern States’ work

on Brenford Road failed to pass DelDOT inspection; DelDOT, based on a

profilograph test, concluded there were a significant number of areas where Brenford

Road needed to “be removed and replaced.”221 Over a year later, on September 10,

2020, DelDOT’s conclusion remained the same: “[t]he first phase of Brenford Rd.

that was completed by Eastern States . . . requires removal and replacement.”222

Eastern States spent the next two months attempting to correct its

noncompliant work. It failed. On December 3, 2020, DelDOT found “non-

compliant work that require[d] correction” on Brenford Road.223 According to Scott,

the Brenford Road issues were not “punch list” items.224

Kevin Gorman testified in detail regarding Eastern States’ failure to meet

DelDOT’s rideability specifications on Willowcap, the “longevity issue[s]”225

associated with Eastern States’ high asphalt paving, and Developers’ “costly and

220
Trial Tr. Day 5 at 16.
221
Trial Tr. Day 4 at 159; JX 118.
222
JX 184.
223
JX 211.
224
Trial Tr. Day 4 at 168.
225
Trial Tr. Day 5 at 88.

48
time-consuming” remediation efforts.226 Gorman, a civil engineer, explained that

DelDOT required roads to contain zero quarter-inch deflections, and concluded,

based on several accepted tests, that Eastern States’ paving of Brenford Road

suffered from ninety-eight quarter-inch deflections. The road ran afoul of DelDOT’s

requirements.227

Similar failures existed in Eastern States’ work at Springcap, specifically

Burtons Pond and Conleys Chapel Road. There, according to DelDOT, Eastern

States’ construction resulted in “rideability issues in front of both entrances where

against [our] recommendation [Eastern States] pulled the entrances and the

deceleration lane before they pulled the mainline.”228 In other words, Eastern States’

failure to comply with DelDOT’s recommendation resulted in noncompliant work

and ultimately, a breach of the Contract.

Under Delaware law, where a company holds themselves out as a competent

contractor to perform certain labor, the law presumes that the company “possesses

the requisite skill to perform such labor in a proper manner, and implies as a part of

[the] contract that the work shall be done in a skillful and workmanlike manner.”229

226
Trial Tr. Day 5 at 28.
227
Trial Tr. Day 5 at 45.
228
JX 158.
229
August v. Hernandez, 2020 WL 95658, at *2 (Del. Super. Ct. Jan. 6, 2020)
(cleaned up).

49
Deciding whether Eastern States’ work was performed in a “workmanlike manner”

requires the Court to consider if it “displayed the degree of skill or knowledge

normally possessed by members of their profession or trade in good standing in

similar communities” in performing the work.230 While Developers were “not

entitled to excellence,” the standard requires Eastern States to have exhibited

“reasonableness and requires compliance with the building code.”231 Based on

DelDOT’s persistent issues with Eastern States’ work, the Court finds that Eastern

States breached its contractual obligation to perform “in a workmanlike manner.”

Developers’ claim for damages is supported by the Contracts, under which

Developers had the option to “remedy any defects and deficiencies” present in

Eastern States’ work.232 Once Developers exercised that option, the Contracts

explicitly required that “[Eastern States] shall correct at its expense.”233

iii. Developers May Not Recover for Eastern States’ Failure to Finish Its
Work

Developers argue they “are owed $4,351,703 for the costs to fix and finish

Eastern States’ defective work.”234 After Capano terminated the Contracts,

230
Foraker, 2022 WL 2452396, at *10 (quoting Shipman v. Hudson, 1993 WL
54469, at *3 (Del. Super. Ct. Feb. 5, 1993)).
231
Foraker, 2022 WL 2452396, at *10.
232
Contracts § 2.1.
233
Id.
234
Def. Op. Br. 58.

50
Developers hired third-party contractors to correct Eastern States’ defective work,

and Developers will be compensated for that. Awarding those costs makes sense;

Eastern States’ work was, on many occasions, defective and constituted a breach of

the Contracts. But Developers’ need for third-party remediation was also a

consequence of their own actions. In other words, they were tasked to finish Eastern

States’ work because Capano expressly ordered Eastern States not to return to all job

sites.

The Contracts permitted Developers, in the event Eastern States breached the

Contracts, to “five (5) days after written notice, (i) proceed to have the Work

performed by others, in which event any expenses for labor and materials incurred

to finish the Work will be treated as a back charge against this Agreement, and/or (ii)

terminate this Agreement at any time.”235 This provision, in effect, allowed

Developers to back charge Eastern States if Eastern States, in response to

Developers’ written notice, refused to fix its work. But the Court has not found—

nor have Developers proffered—any evidence that Developers gave Eastern States

written notice within five days of Capano’s voicemail. Instead, they were “thinking

of ways to keep both parties satisfied moving forward.”236 And, the Court cannot

interpret this provision to mean that Developers were allowed to terminate Eastern

235
Contracts at 2.
236
JX 222.

51
States on a whim and then back charge Eastern States for work Developers’ own

actions prevented Eastern States from completing.

When Julian was asked why Eastern States did not return to the projects to fix

certain issues, his answer was simple: “Because we were terminated . . . . [A]t the

end of the day [Developers] told us to get all our stuff and get off their jobs. It never

really. . . changed from that.”237 While certain issues persisted—Conleys Chapel

Road was half-paved—Capano’s termination was clear. Eastern States was to pack

its equipment, exit the job sites, and not return. Once Developers materially

breached the Contracts, they could no longer complain that Eastern States

subsequently refused to perform.238 In the end, Developers’ material breach relieved

Eastern States of its contractual obligations, and Eastern States’ subsequent

nonperformance was justified.

3. Eastern States’ Claim for Lost Profits Fails

Eastern States asserts it “incurred lost profits that it justifiably expected to

achieve” through completion of Developers’ projects.239 To support this claim,

Gleason testified—based on his own calculations—that Eastern States lost profits in

the amount of $963,976.96: for Darley Green Phase 3, $281,923.71, for Burton’s

237
Trial Tr. Day 1 at 171-72.
238
See, e.g., Frunzi v. Paoli Servs., Inc., 2012 WL 2691164, at *7 (Del. Super. Ct.
July 6, 2012).
239
Pl. Op. Br. 36.

52
Pond, $538,435.46, for Willowwood Phases 6 & 7, $19,766.04, and for Willowwood

Phases 8 & 9, $123,861.75.240 Gleason possessed no formal training on lost profit

calculations, lacked expertise on damages, and did not seek knowledge or guidance

from any other sources to guide his calculation of lost profits.241 Instead, Gleason,

on behalf of Eastern States, simply used profit margins he “thought [were] fair.”242

The Court, over Developers’ objection, allowed Gleason to testify in support

of Eastern States’ lost profits claim. Delaware law allows a court to hear evidence

in a bench trial that might otherwise be excluded from a jury “as jury confusion in

that context is not a concern.”243 And, the Court endeavored to confine Eastern

States’ lost profit testimony within the permissible parameters of a fact witness.244

Nevertheless, Eastern States failed to prove, by a preponderance of the evidence, its

entitlement to lost profit damages.

“It is axiomatic that a claim for lost profits requires evidence of lost revenues,

minus the costs associated with generating those revenues.”245 Under Delaware law,

240
Trial Tr. Day 2 at 92-96.
241
Trial Tr. Day 2 at 172-173.
242
Trial Tr. Day 2 at 175.
City of Wilmington v. Flamer, 2013 WL 4829585, at *6 (Del. Super. Ct. May 22,
243

2013).
244
Trial Tr. Day 2 at 98.
245
Empire Fin. Servs., Inc. v. Bank of New York (Delaware), 2007 WL 1991179, at
*4 (Del. Super. Ct. June 19, 2007).

53
“no recovery can be had for loss of profits which are determined to be uncertain,

contingent, conjectural, or speculative.”246 Gleason’s lost profits calculation was

conjectural and speculative as it was contingent upon Eastern States’ work

progressing precisely according to plan from beginning to end. His calculations

were based on the numbers Eastern States “expected when [it] started the

project[s].”247 Gleason compared Eastern States’ original budget to the original

contract amount, thereby eliminating the impact of change orders, amendments, or

any other variable that may have affected the numbers as the parties’ work

continued.248 Gleason acknowledged that “number[s] fluctuate[]” based on external

factors and agreed that throughout his calculations, he did not “consider any risk

factors whatsoever.”249 As Gleason put it, “sometimes the proposed or expected

[number] when we start a job is not exactly as it is when we finish the job.”250 These

variables can—and in this case did—affect profits, and Gleason failed to factor these

variables in his calculations.

246
Siga Tech., Inc. v. PharmAthene, Inc., 132 A.3d 1108, 1131 (Del. 2015) (quoting
Siga Tech., Inc. v. PharmAthene, Inc., 67 A.3d 330, 351 (Del. 2013)).
247
Trial Tr. Day 2 at 177.
248
Trial Tr. Day 2 at 175-177.
249
Trial Tr. Day 2 at 173.
250
Trial Tr. Day 2 at 176-177.

54
Gleason candidly revealed this variability. For example, Eastern States’

original estimates projected it would return a 9.02% profit margin on Brenford Road,

but Brenford Road’s “current profit margin” turned out to be negative 9.83%.251 And

these variations cut both ways—Eastern States’ original projections showed a

15.95% return on Willowwood 6 and 7; its current estimate increased to 22.09%.252

Regardless of the actual progression of the projects, Gleason’s basis remained the

same: Eastern States’ original projections.

Under certain circumstances, “[r]esponsible estimates that lack mathematical

certainty are permissible so long as the court has a basis to make a responsible

estimate of damages. Speculation is an insufficient basis, however.”253 On the

evidence offered here, an award of lost profits would be grounded in guesswork, and

the Court can make no responsible estimate. Eastern States’ claim for lost profits is

denied.

4. Eastern States’ Unjust Enrichment Claim

Unjust enrichment is “the unjust retention of a benefit to the loss of another,

or the retention of money or property of another against the fundamental principles

251
Trial Tr. Day 2 at 178.
252
Trial Tr. Day 2 at 184.
253
Delaware Exp. Shuttle, Inc. v. Older, 2002 WL 31458243, at *15 (Del. Ch. Oct.
23, 2002) (internal citations omitted).

55
of justice or equity and good conscience.”254 An unjust enrichment claim may be

brought “as a standalone claim or as a remedy for other claims.”255 To sustain a

claim for unjust enrichment, the plaintiff must establish: “(1) an enrichment, (2) an

impoverishment, (3) a relation between the enrichment and impoverishment, (4) the

absence of justification, and (5) the absence of a remedy provided by law.”256

An unjust enrichment claim cannot be made where the parties’ relationship is

“comprehensively governed by a contract.”257 The Superior Court may award

damages for unjust enrichment “when it cannot hold the parties to a formal

agreement but determines that the aggrieved party is entitled to relief for a benefit

conferred on the other party.”258

Here, the parties agree that the Contracts are valid and enforceable. Because

Eastern States and Developers’ relationship was “comprehensively governed by a

contract,”259 Eastern States’ unjust enrichment claim is dismissed.

254
Fleer Corp. v. Topps Chewing Gum, Inc., 539 A.2d 1060, 1062 (Del. 1988)
(quoting 66 Am. Jur. 2d, Restitution and Implied Contracts §3, p. 945 (1973)).
255
State ex rel. Jennings v. Monsanto Co., 299 A.3d 372, 390 (Del. 2023).
256
Nemec v. Shrader, 991 A.2d 1120, 1130 (Del. 2010).
257
Chumash Capital Investments, LLC v. Grand Mesa Partners, LLC, 2024 WL
1554184, at *14 (Del. Super. Ct. Apr. 10, 2024).
258
Crosse v. BCBSD, Inc., 836 A.2d 492, 497 (Del. 2003).
259
Chumash Capital Investments, LLC, 2024 WL 1554184, at *14.

56
5. Developers’ Breach of Warranty Claims is Duplicative of Their
Breach of Contract Claims

Eastern States cannot, as Developers assert, be in breach of the Contracts and

also in breach of the express and implied warranties.260 Under Delaware law, “when

a party alleges a breach of contract and breach of warranty claim based on the same

contractual provisions and facts, one claim may be dismissed.”261

Here, Developers ground both their breach of contract claims and their breach

of warranty claims on Eastern States’ failure to perform its work in a “workmanlike

manner” and “to comply with DelDOT specifications.”262 On both claims,

Developers rely on the same facts and the same provisions of the Contracts. Notably,

Developers do not claim any separate and distinct damages on their breach of

warranty claims; instead, they rely solely on the damages they assert are necessary

to compensate them for Eastern States’ breaches of contract. The Court dismisses

Developers’ breach of warranty claims as duplicative of their breach of contract

claims.263

260
Def. Op. Br. 41.
RSM US LLP v. Cision US Inc., 2025 WL 819123, at *2 (Del. Super. Ct. Mar. 14,
261

2025) (citing Osram Sylvania Inc. v. Townsend Ventures, LLC, 2013 WL 6199554
(Del. Ch. Nov. 19, 2013).
262
Def. Op. Br. 41.
263
See Outbox Sys., 2022 WL 3696773, at *9.

57
6. Developers’ Declaratory Judgment Claim is Duplicative of Their
Breach of Contract Claims

Developers seek a declaration that they did not violate the Contracts and

properly used the Holdback Provision.264 But like their breach of warranty claims,

Developers’ claim of declaratory judgment fails because it is duplicative. And the

Court declines offer a declaration pertaining to the parties’ contractual relationship

beyond its verdict on the breach of contract claims.

A declaratory judgment “is a statutory action . . . meant to provide relief in

situations where a claim is ripe but would not support an action under common-

law.”265 While “[t]he existence of another adequate remedy does not preclude a

judgment for declaratory relief in cases where it is appropriate,”266 under Delaware

law, “there is no need for a declaratory judgment . . . where a claimant merely has

repackaged in the language of a declaration an adequately-pleaded affirmative

count[.]”267 A request for a declaratory judgment must be rejected where it “relates

264
Am. Countercl. ¶ 106.
265
Loeffler v. MNTN, Inc., 2025 WL 1256148, at *4 (Del. Super. Ct. Apr. 28, 2025)
(internal citation omitted).
266
Super. Ct. Civ. R. 57.
267
Blue Cube Spinco LLC v. Dow Chem. Co., 2021 WL 4453460, at *15 (Del. Super.
Ct. Sept. 29, 2021).

58
wholly and completely to the claim asserted in the complaint.”268 To survive

dismissal, a decision on the affirmative counts must not resolve the declaratory

count.269

Developers’ argument that it did not breach the Contracts mirrors their breach

of contract claims. Their declaratory judgment claim seeks a ruling on the same

legal issues addressed in their Answer, Counterclaims, and throughout this

Opinion—whether Developers violated the Contracts. The Court’s resolution of the

parties’ contract dispute resolves the declaratory judgment claim. Thus, the

declaratory judgment claim adds nothing new, is duplicative, and is dismissed. To

the extent Developers seek a declaration regarding their own future conduct,

including use of the Holdback Provision, such a claim is speculative and not ripe for

decision.270

DuPont De Nemours, Inc. v. Hemlock Semiconductor Operations LLC, 2024 WL
268

3161799, at *11 (Del. Super. Ct. June 10, 2024) (citing IP Network Sols., Inc. v.
Nutanix, Inc., 2022 WL 369951, at *7 (Del. Super. Ct. Feb. 8, 2022)).
269
Blue Club Spinco LLC, 2021 WL 4453460, at *15.
270
See Loeffler, 2025 WL 1256148, at *5.

59
V. DAMAGES

“Under Delaware law, the standard remedy for breach of contract is based on

the reasonable expectations of the parties that existed before or at the time of the

breach.”271 It is well-settled that breach of contract damages “are designed to place

the injured party in an action for breach of contract in the same place as he would

have been if the contract had been performed. Such damages should not act as a

windfall.”272

To assess the parties’ damages, the Court considers Eastern States’ submitted

invoices and the testimony of Paul Pocalyko (“Pocalyko”), a forensic accountant

Developers proffered at trial.273 Pocalyko’s testimony focused on two categories of

damages: the costs Developers incurred to repair Eastern States’ defective work, and

the costs Developers incurred to complete Eastern States’ work.274 In this case, both

parties are entitled to damages based on their breach of contract claims. The Court

addresses the damages associated with each project in turn.

271
Siga Tech., Inc. v. PharmAthene, Inc., 132 A.3d 1108, 1132-33 (Del. 2015)
(internal citation omitted).
Paul v. Deloitte & Touche, LLP, 974 A.2d 140, 146 (Del. 2009) (internal citations
272

omitted).
273
Trial Tr. Day 6 at 63-66.
274
Trial Tr. Day 6 at 74.

60
A. Willowcap

Eastern States met its burden of proving, by a preponderance of the evidence,

that Developers breached the Willowcap contract by failing to compensate Eastern

States for its work on the project and by abruptly terminating the Contract. To assess

Eastern States’ damages on Willowcap, the Court looks to its submitted pay

applications.275 The unpaid invoices on Willowcap totals $638,813.17.276 Eastern

States’ damages must be offset by $807,732—the total costs Developers incurred,

and will incur, to fix Eastern States’ deficient work.277 On this calculation, the Court

awards Developers $168,918.83 on the Willowcap claim.

B. Darleycap

Eastern States has met its burden of proving, by a preponderance of the

evidence, that Developers breached the Darleycap contract by failing to compensate

Eastern States for its work on the project. The outstanding amount reflected in its

invoices totals $106,913.19.278 Developers assert they are owed $796,247.00 for the

costs “to finish” Darleycap, but as explained, the Court intends only to award

damages to Developers for Eastern States’ defective work.279 And, according to

275
JX 668; JX 331.
276
JX 331.
277
Trial Tr. Day 6 at 85-86.
278
JX 331.
279
Def. Op. Br. 51.

61
Pocalyko, “the work [was] all incomplete work[,] there [was] no defective work”

included in his calculations.280 The Court, therefore, awards Eastern States

$106,913.19 on the Darleycap claim.281

C. Springcap

Eastern States has met its burden of proving, by a preponderance of the

evidence, that Developers breached the Springcap contract by failing to compensate

Eastern States for its work on the project. The outstanding amount reflected in its

invoices totals $444,659.39.282 These damages must be offset by the amount

Developers paid to fix Eastern States’ work on Springcap. That amount, according

to Pocalyko, was $432,843.00.283 Based on the damages reflected in the invoices,

less the costs Developers incurred to fix Eastern States’ defective work on Springcap,

Eastern States is awarded $11,816.39 for the Springcap claim.284

280
Trial Tr. Day 6 at 88.
281
Developers assert that a proper accounting must be made for payments made
toward the Darleycap balance after the parties severed their relationship. Def. Ans.
Br. at 51. These payments, documented in JX 394 and JX 454, shall be accounted
for in the final form of order to be prepared and submitted by the parties. For
Darleycap, Developers will be credited $106,410.97.
282
JX 331.
283
Trial Tr. Day 6 at 84.
284
As noted in note 280, supra, Developers shall be credited in the final accounting
for the $61,337.81 payment made on the Springcap account. JX 454.

62
D. St. Anne’s

There were no unpaid invoices on St. Anne’s.285 Eastern States sought only

lost profits for this project.286 The Court has found Eastern States failed to prove its

lost profits claims. On the St. Anne’s project, “there [was] no defective work items,

there [was] just incomplete work.”287 Accordingly, there are no damages associated

with the St. Anne’s claims.

E. Attorneys’ Fees

Both parties have requested attorneys’ fees from one another.288 “Delaware

law follows the American Rule, under which litigants are generally responsible for

paying their own litigation costs.”289 But this Court recognizes “limited exceptions”

to the American Rule, including where “there is a contractual provision regarding

entitlement to attorneys’ fees.”290 Developers assert the Contracts’ indemnity

provision entitles them to attorneys’ fees in this case.

Under the Contracts, Eastern States agreed to “defend, indemnify and save

harmless [Developers]. . . from any and all liability. . . including the cost of defense

285
Am. Compl. ¶ 45.
286
Am. Compl. ¶¶ 43-46.
287
Trial Tr. Day 6 at 90.
288
See Am. Compl.; See Am. Countercl.
289
DeMatteis v. RiseDelaware Inc., 315 A.3d 499, 508 (Del. 2024).
290
In re Delaware Public Sch. Litig., 312 A.3d 703, 716 (Del. 2024).

63
and attorneys’ fees, arising from [Eastern States’] performance under this

agreement.” Developers contend this provision requires Eastern States to pay the

cost of their attorneys’ fees.291 Not so. As this Court has explained,

Indemnity provisions covering first-party claims aren’t the norm in
Delaware. In fact, indemnity agreements are presumed not to require
reimbursement for attorneys’ fees incurred as a result of substantive
litigation between the parties to the agreement. If the provision is to
apply to first-party claims, that intent must be via a clear and
unequivocal articulation . . . . As a general matter, this Court has found
previously that the use of “indemnify” and “hold harmless” in an
indemnity provision demonstrate an intent to indemnify third-party
claims only.292

Here, there is no “clear and unequivocal articulation” that Eastern States and

Developers intended to allow indemnity of attorneys’ fees resulting from actions

between each other. And while there exist additional, limited exceptions to the

American Rule, none apply here.293 The Court, therefore, declines to award

attorneys’ fees in this case.

291
Def. Op. Br. 52-53.
Fortis Advisors LLC v. Boston Dynamics Inc., 2025 WL 1356521, at *5-6 (Del.
292

Super. Ct. Apr. 29, 2025) (cleaned up).
293
See In re Delaware Public Sch. Litig., 312 A.3d at 716.

64
VI. CONCLUSION

Judgment is entered in favor of Eastern States on its breach of contract claims,

and in favor of Developers on its counterclaims for breach of contracts. Offsetting

the damages awarded to each, the Court awards Developers $50,189.25 plus pre-

judgment interest. Eastern States shall reimburse Developers any overpayments

made after the breaches and before trial; however, these sums are not damages

subject to prejudgment interest. The parties shall, by December 31, 2025, prepare

and submit a form of final order of judgment consistent with this decision.

IT IS SO ORDERED

Sean P. Lugg, Judge

65

Continue your research in ChatGPT or Claude

Connect Omnilex to search the legal corpus from your AI assistant.