FILED 5/16/2023 DOCUMENT NO. 03215-2023 FPSC - COMMISSION CLERK BEFORE THE FLORIDA PUBLIC SERVICE COMMISSION In re: Petition for approval of revised underground residential distribution tariff, by Tam a Electric Com an . DOCKET NO. 20230042-EI --~----~~~-------~ ORDER NO. PSC-2023-0160-PCO-EI ISSUED: May 16, 2023 The following Commissioners participated in the disposition of this matter: ANDREW GILES FAY, Chairman ARTGRAHAM GARY F. CLARK MIKE LAROSA GABRIELLA P ASSIDOMO ORDER SUSPENDING TAMPA ELECTRIC COMPANY' S UNDERGROUND RESIDENTIAL DISTRIBUTION TARIFFS BY THE COMMISSION: Background On March 31, 2023, Tampa Electric Company (TECO) filed a petition for approval of revisions to its underground residential distribution (URD) tariffs and associated charges. These tariffs represent the additional costs, if any, TECO incurs to provide underground service in place of overhead service in new residential subdivisions. The petition was filed pursuant to Rule 25-6.078(3), Florida Administrative Code (F .A.C.), which states, in part, " If the cost differential as calculated in Form PSC 1031 (08/20) varies from the Commission-approved differential by plus or minus 10 percent or more, the utility sha ll file a written policy and supporting data and analyses as prescribed in subsections (1), (4) and (5) of this rule on or before April 1 of the following year." In this petition, TECO is proposing revised URD charges to reflect changes in cost differentials between overhead and underground service. For example, TECO proposes to decrease the per service lateral underground charge for low density subdivisions. TECO is also proposing to increase the cost to underground new service laterals, as well as to increase the cost to convert existing overhead service laterals to underground. Finally, TECO is proposing to increase the non-refundable deposit to convert existing overhead distribution facilities to underground facilities. This order is to suspend the proposed tariffs. We have jurisdiction over this matter pursuant to Sections 366.03, 366.04, 366.05, and 366.06, Florida Statutes (F.S.).
ORDER NO.PSC -20 23 -0 160-PCO-El DO CKET NO. 20230042-El PAGE2 Decision Pursuant to Section 366.06(3), F.S., we may wi thho ld conse nt to the operat ion of a ll or any portion o f a new rate schedul e, de li ve ring to the util ity requesti ng such a change a reason or written statement of good cause fo r do in g so within 60 da ys. We find th at th e reason stated above is a good cause consiste nt w ith th e requ ir eme nt of Se ction 366.06(3), F.S. Based on the fo regoi ng , it is ORD ERED by th e Flor id a Public Service Co mmi ss ion that Tampa Elec tri c Com pany's proposed underground res id ential distribution tari ffs shall be suspe nd ed. It is further ORDERED that this docket sha ll rema in open pending o ur decision on the proposed tariffs. DD By ORDER of the Florida Pub li c Serv ice Commission th is 16th day of May, 2023. Flor id a Public Service Commission 2540 Shumard Oak Boulevard Ta ll ahassee, Florida 32399 (850) 4 13-6770 www.floridapsc.com Co pi es furni shed: A copy of thi s document is prov ided to the parties of record at the t im e of iss uance and, if app li cable, interested pe rsons. NOTICE OF FURTHER PRO CEEDINGS OR JUDICIAL REVIEW The Florida Public Serv ice Co mmi ss ion is requ ired by Section 120.569( I ), Florida Statutes, to notify parties of any ad mini strative hea ring or judicial re view of Comm iss ion orders that is ava il able under Sections 120.57 or 120 .6 8, Fl orida Statutes, as we ll as the procedu re s and t im e limits that app ly. This notice should not be const ru ed to mean all requests fo r an ad ministrati ve hearing or judicial rev iew w ill be granted or res ul t in the rel ief soug ht.
ORDER NO. PSC-2023-0160-PCO-EI DOCKET NO. 20230042-EI PAGE 3 Mediation may be available on a case-by-case basis. If mediation is conducted, it does not affect a substantially interested person's right to a hearing. Any party adversely affected by this order, which is preliminary, procedural or intermediate in nature, may request: (1) reconsideration within 10 days pursuant to Rule 25- 22.0376, Florida Administrative Code; or (2) judicial review by the Florida Supreme Court, in the case of an electric, gas or telephone utility, or the First District Court of Appeal, in the case of a water or wastewater utility. A motion for reconsideration shall be filed with the Office of Commission Clerk, in the form prescribed by Rule 25-22.0376, Florida Administrative Code. Judicial review of a preliminary, procedural or intermediate ruling or order is available if review of the final action will not provide an adequate remedy. Such review may be requested from the appropriate court, as described above, pursuant to Rule 9.100, Florida Rules of Appellate Procedure.
Wondering how this text applies to your situation?
Free consultation, no commitment
Describe your situation. Our team will contact you by email about your consultation.
Continue your research in ChatGPT or Claude
Connect Omnilex to search the legal corpus from your AI assistant.