UNITED STATES DISTRICT COURT DISTRICT OF ALASKA United States of America for the ) use of J & L Paving LLC, ) ) Plaintiff, ) 3:18-cv-156 JWS ) vs. ) ORDER AND OPINION ) Rockford Corporation and ) [Re: Motion at docket 22] Liberty Mutual Insurance Co., ) ) Defendants. ) ) I. MOTION PRESENTED At docket 22, Plaintiff moves to strike defendant Rockford’s counterclaim. Rockford responds at docket 23. Plaintiff replies at docket 25. Oral argument was not requested and would not aid the court. II. DISCUSSION Plaintiff alleges in its Complaint that the U.S. Army Corps of Engineers awarded the prime contract to construct a replacement fueling station at Tinker Air Force Base to Rockford. Rockford purchased a Miller Act payment bond from Liberty Mutual Insurance Co. Rockford subcontracted the pavement work on the project to J&L Paving LLC. (“J&L”). Plaintiff further alleges that J&L completed the pavement work, but when Case 3:18-cv-00156-JWS Document 28 Filed 10/16/18 Page 1 of 3
it submitted its final application to be paid, Rockford did not pay all of what was owed.1 Plaintiff seeks to recover the money it alleges should be paid. Count One of the Complaint alleges a breach of contract by Rockford. Count Two seeks recovery based on the theory of quantum meruit. Count Three seeks to recover on the payment bond. Rockford’s Answer denies that J&L performed its subcontract obligations and asserts that “J&L breached the subcontract on numerous occasions . . . . 2 Rockford’s Counterclaim seeks a declaration that J&L materially breached the subcontract so that Rockford owes nothing to J&L. The Counterclaim mirrors Rockford’s defense to Plaintiff’s breach-of-contract claim that it was J&L which breached the subcontract. The Counterclaim raises no issue not raised in the Answer. It merely recasts the defense that J&L breached the subcontract in the form of a counterclaim. In sum, the Counterclaim is redundant and unnecessary. Plaintiff’s briefing demonstrates that allowing the Counterclaim to go forward would unnecessarily complicate the proceedings in this case. Mindful of the admonition in Fed. R. Civ. P. 1 to construe and apply the civil rules “to secure the just, speedy, and inexpensive determination of every action and proceeding,” the court concludes that the Counterclaim should be stricken. 1Doc. 1. 2Doc. 14 at ¶¶ 12 and 17. 2 Case 3:18-cv-00156-JWS Document 28 Filed 10/16/18 Page 2 of 3
III. CONCLUSION AND ORDER TO FILE AMENDED ANSWER For the reasons above, the motion at docket 22 is granted. IT IS FURTHER ORDERED that defendant Rockford shall file an Amended Answer which does not include a counterclaim within 7 days. DATED October 16, 2018. /s/ JOHN W. SEDWICK SENIOR JUDGE, UNITED STATES DISTRICT COURT 3 Case 3:18-cv-00156-JWS Document 28 Filed 10/16/18 Page 3 of 3
Wondering how this text applies to your situation?
Free consultation, no commitment
Describe your situation. Our team will contact you by email about your consultation.
Continue your research in ChatGPT or Claude
Connect Omnilex to search the legal corpus from your AI assistant.