NYU Hospital Center et al v. HRH Construction LLC

7:10-ap-08242NysbAug 3, 2011

Full text

1
UNITED STATES BANKRUPTCY COURT
SOUTHERN DISTRICT OF NEW YORK
---------------------------------------------------------------X
In re: 	Chapter 11
HRH CONSTRUCTION LLC, et al., 	Case No. 09-23665 (RDD)
Debtors. 	Jointly Administered
---------------------------------------------------------------X
NYU HOSPITALS CENTER,
Plaintiff,
v.
HRH CONSTRUCTION LLC,
Defendant.
Adv. Pro. No. 10-8242 (SHL)
CURTIS PARTITION CORPORATION,
Plaintiff,
v.
HRH CONSTRUCTION LLC,
NYU HOSPITALS CENTER, et al.,
Defendants.
---------------------------------------------------------------X
MEMORANDUM DECISION AND ORDER
A P P E A R A N C E S:
HOLLAND & KNIGHT LLP
Attorneys for NYU Hospitals Center
31 West 52nd Street
New York, New York 10019
Frederick R. Rohn, Esq.
Henry A. H. Rosenzweig, Esq.
HERRICK, FEINSTEIN LLP
Attorneys for HRH Construction LLC
2 Park Avenue
New York, New York 10016
William R. Fried, Esq.
Kerry K. Jardine, Esq.
10-08242-rdd Doc 40 Filed 08/03/11 Entered 08/03/11 10:37:37 Main Document
Pg 1 of 32
2
KIRSCH GARTENBERG HOWARD LLP
Attorneys for Curtis Partition Corporation
11 Penn Plaza, Fifth Floor
New York, New York 10001
Jesse C. Klaproth, Esq.
SEAN H. LANE
United States Bankruptcy Judge:
This action arises out of a construction contract dispute among debtor HRH Construction
LLC (“HRH”), facilities owner NYU Hospitals Center (“NYU”), and sub-contractor Curtis
Partition Corporation (“Curtis”).1 NYU claims that HRH breached their contract by failing to
proceed with phase 2 of a multi-phased construction project. HRH counters that it was neither
required nor able to move forward with phase 2 because NYU failed to meet with HRH, as
contractually mandated, to negotiate and resolve outstanding issues, including a plan for the
remaining work. HRH also claims that NYU breached the contract by failing to make required
payments on approved requisitions. A trial was held on January 5, 6, 7, and 10 before this Court.
For the reasons set forth more fully below, the Court finds in favor of debtor HRH and awards
damages for three unpaid requisitions.
BACKGROUND
A. 	Findings of Fact
Pursuant to an agreement dated October 21, 2003, HRH was hired to renovate NYU’s
existing radiology center in Manhattan (the “Construction Agreement”). Trial Ex. 1. Because
NYU wanted the radiology department to remain operational during the renovation, the
construction project was to be accomplished in a sequence of phases, with the first phase
1 Additional parties are mentioned in the pleadings, but only HRH, NYU, and Curtis have appeared before the
Court.
10-08242-rdd Doc 40 Filed 08/03/11 Entered 08/03/11 10:37:37 Main Document
Pg 2 of 32
3
designated as phase 0. Berger Aff. ¶ 8 (Dec. 13, 2010);2 Trial Tr. 13:17-21 (Jan. 5, 2011). HRH
agreed to complete the work for a guaranteed maximum price of $8,520,000, subject to equitable
adjustment by submission of proposed change orders by the contractor for unforeseen conditions
arising during the work. Trial Ex. 1, Construction Agreement § 3.6. Over the course of the
project, NYU approved change orders in the aggregate amount of $907,447, thereby increasing
the guaranteed maximum price to $9,427,447. Trial Exs. 9-13; Berger Aff. ¶ 54; Ross Aff. ¶ 8
(Dec. 13, 2010). As contemplated by the Construction Agreement, HRH entered into several
subcontracts, including one with Curtis for work on drywall, carpentry, and acoustical ceilings.3
Trial Ex. 1, Construction Agreement § 3.3; Trial Ex. 4; Berger Aff. ¶ 7.
For periodic reimbursement of its costs and expenses, HRH was required to submit
requisitions to NYU on a monthly basis. Trial Ex. 1, Construction Agreement § 10.1.1. Each
requisition was subject to written approval by NYU before NYU would pay HRH on the
requisition. See Trial Ex. 1, Construction Agreement § 10.1.7. NYU was permitted to withhold
approval of any requisitions that reflected disputed work. Id. Importantly, NYU was required to
approve or disapprove requisitions within twelve business days of receipt. Id.; Trial Tr. 122:25-
123:3 (Jan. 5, 2011). If NYU disapproved a requisition or a portion thereof, NYU was required
to “prepare and promptly issue” to HRH a written statement describing those items in the
requisition that were not approved. Trial Ex. 1, Construction Agreement § 10.1.7. Within thirty
days of approving a requisition, NYU was to pay the requisition regardless of whether HRH
continued working in the future. Id. at § 10.2; Trial Tr. 122:20-24 (Jan. 5, 2011). See also Trial
Ex. 1, Construction Agreement § 13.1; Trial Ex. 3, Completion Agreement ¶ 2(d). Within ninety
2 Direct testimony by all parties for the trial was presented by affidavit.
3 The subcontract was dated November 12, 2003 and was signed by Curtis on January 28, 2004. Trial Ex. 4.
10-08242-rdd Doc 40 Filed 08/03/11 Entered 08/03/11 10:37:37 Main Document
Pg 3 of 32
4
days of approval, HRH was to pay any relevant subcontractors like Curtis.4 Trial Ex. 4,
Subcontract § 10.1(a). According to article 13.1 of the Construction Agreement, “[HRH] shall
have no right to suspend all or any part of the Work or to refuse to comply with any written
instruction, direction or order of [NYU] pending resolution of any dispute or for any other
reason, provided that [NYU] continues to make payments of undisputed amounts as provided in
this Agreement.” Trial Ex. 1, Construction Agreement § 13.1 (emphasis added).
The construction project encountered delays in 2004 and early 2005. See Berger Aff.
¶ 21; DeCesare Aff. ¶ 19 (Dec. 10, 2010). HRH contends that these delays were due to
unanticipated difficulties. For example, while the contract contemplated raising the ceilings in
the facility, the ceilings were lowered during construction to increase the area needed for new
installations. Fox Aff. ¶ 15 (Dec. 13, 2010). In addition, it is undisputed that NYU failed to
make timely payments, which led unpaid subcontractors to neglect their duties. Trial Tr. 111:22-
112:5 (Jan. 5, 2011); Fox Aff. ¶¶ 21-23; Trial Exs. 216, 217, 220. See also Trial Ex. 221, units
73.1, 73.3; Egeberg Dep. 158:24-159:25 (May 14, 2007). 5 NYU counters that the project delays
were a result of HRH’s inadequate management and supervision of the work. Berger Aff. ¶¶ 23-
31; DeCesare Aff. ¶¶ 22-31.
HRH and NYU attempted to resolve their differences by entering into a Completion
Agreement dated May 11, 2005.6 Trial Ex. 3; Berger Aff. ¶ 32; Ross Aff. ¶ 28. NYU’s
4 The subcontract is vague about when the 90 day periods begin, using the verb “furnished” somewhat
ambiguously: “[HRH] shall pay . . . on or about the 90th day after such requisition was furnished, a sum equal to
the amount shown in such requisition . . . .” Trial Ex. 4, Subcontract § 10.1(a).
5 Mr. Egeberg did not appear at trial, but the parties stipulated to use of his deposition in lieu of live testimony.
6 On December 22, 2010, HRH filed a motion in limine to preclude evidence relating to the period prior to the
execution of the Completion Agreement. This motion was denied at trial. See Order Granting and Denying
Certain Pre-Trial Motions filed on January 10, 2011 at docket entry 26. HRH renewed its motion in its post-trial
briefing. As events prior to the Completion Agreement provide the background necessary to understand the
present dispute between the parties, the Court once again denies the motion.
10-08242-rdd Doc 40 Filed 08/03/11 Entered 08/03/11 10:37:37 Main Document
Pg 4 of 32
5
attorneys drafted the Completion Agreement at the request of NYU’s facilities manager, Mr.
Kenneth Egeberg. Egeberg Dep. 163:22-164:2. See also Trial Tr. 123:8-10 (Jan. 5, 2011). Mr.
Egeberg understood that the Completion Agreement was intended, at least in part, to give HRH’s
subcontractors more confidence that NYU would make timely payments going forward.
Egeberg Dep. 162:15-163:17. According to Mr. Egeberg, the subcontractors were reducing
manpower and/or refusing to work because of NYU’s failure to make timely payments as early
as May 4, 2005. Id. at 159:16-21. “It was not a new development,” Mr. Egeberg explained. Id.
at 159:21. Mr. Egeberg testified regarding the purpose of the Completion Agreement:
It was my opinion that the performance of HRH over a sustained
period of time was miserable. 	Equally as miserable was [NYU’s]
lousy pattern of payment. . . . if we wanted to do anything, to give
us any opportunity to get the work done, that we would have to do
something to improve the payments dramatically to HRH and that
would give us the ability to either keep HRH or consider what the
next step should be in dealing with the HRH problem.
Id. at 161:7-162:4.
Under the terms of the Completion Agreement, NYU promised to make payments, on
dates certain, of four outstanding requisitions, and HRH promised to achieve “Substantial
Completion” of phases 0 and 1 of the construction project by June 15, 2005, which was
approximately fifteen months later than originally provided for in the Construction Agreement.
Trial Ex. 3, Completion Agreement ¶ 1; Berger Aff. ¶ 20; Trial Ex. 1, Construction Agreement,
Ex. C. Substantial Completion is a term defined by the underlying Construction Agreement to
reflect NYU’s ability to use and occupy an area for its intended purposes. Trial Ex. 1,
Construction Agreement § 5.2; Trial Ex. 3, Completion Agreement ¶ 4. The Completion
Agreement clarified that Substantial Completion would include “all [w]ork necessary to obtain
10-08242-rdd Doc 40 Filed 08/03/11 Entered 08/03/11 10:37:37 Main Document
Pg 5 of 32
6
New York State Department of Health (‘DOH’) approval for full use and occupancy of the Phase
0 and Phase 1 areas . . . .” Trial Ex. 3, Completion Agreement ¶ 1.
NYU issued payments to HRH for the four requisitions listed in the Completion
Agreement. Trial Exs. 222, 225, 228. While HRH did not achieve Substantial Completion by
June 15, 2005, both NYU and HRH agree that Substantial Completion of phases 0 and 1 was
reached before the premises were inspected and approved by the Department of Health on June
21, 2005. Trial Tr. 125:9-10 (Jan. 5, 2011); DeCesare Aff. ¶ 36; Trial Exs. 226, 227. While the
June 15, 2005 Substantial Completion date was originally scheduled so as to permit an
inspection by the Department of Health, the date for such an inspection ultimately proved to be
June 21, 2005, a date scheduled at least thirty days prior. See Trial Tr. 91:4-92:3 (Jan. 5, 2011).
There is evidence that NYU used some of its own employees to prepare the premises for the
inspection. Trial Tr. 125:11-15, 168:18-23 (Jan. 5, 2011); DeCesare Aff. ¶ 35.
Pursuant to the Completion Agreement, following Substantial Completion of phases 0
and 1, NYU and HRH were to “meet (prior to the start of the next phase of the Work) to
negotiate and resolve remaining issues between them, including the schedule for completion of
the remaining Work.” Trial Ex. 3, Completion Agreement ¶ 3. The parties seem to agree that,
after Substantial Completion of phases 0 and 1 was reached in June of 2005, little construction
work followed. NYU argues that HRH’s failure to proceed with the next phase of work—phase
2—constituted the breach of contract that is central to its case. HRH counters by highlighting
the language in the Completion Agreement requiring that HRH and NYU first meet to negotiate
and resolve remaining issues between them before HRH was to proceed with the work. HRH
argues that, despite HRH’s good faith efforts to schedule such a meeting, NYU refused to meet,
preventing HRH from continuing its work.
10-08242-rdd Doc 40 Filed 08/03/11 Entered 08/03/11 10:37:37 Main Document
Pg 6 of 32
7
On this disagreement, Mr. Egeberg’s testimony is particularly useful. He understood that
the Completion Agreement required a meeting after Substantial Completion of phases 0 and 1
before HRH could continue with phase 2. He testified: “My view of what was in that payment
agreement was that the parties needed to sit down and figure this out. There was no time frame
other than as soon as possible for both of us to figure out what we were going to do to continue.”
Egeberg Dep. 227:10-14 (May 15, 2007).
The parties’ respective positions are reflected in their correspondence during the summer
of 2005. On July 11, 2005, HRH wrote to NYU explaining that HRH “would like to proceed
with Phase 2.” Trial Exs. 132, 236. The July 11, 2005 letter also identified certain issues that
“need[ed] to be addressed” “in order to proceed” including a request that NYU “turn over all of
the rooms designated under phase 2.” Id. NYU did not respond to this letter. Trial Tr. 172:13-
173:13 (Jan. 5, 2011). In fact, the meeting identified in the Completion Agreement as a
prerequisite to proceeding with phase 2 never occurred.7 In any case, it is difficult to imagine
that HRH was capable of commencing with phase 2 through July of 2005 because, by July 27,
2005, it is undisputed that the plan for phase 2 had not been finalized by NYU. 8 Trial Ex. 237,
item 80.4.
Around this time, Mr. Egeberg “suggested” to HRH that it needed to “submit something .
. . to the hospital which identifies what the issues are.” Egeberg Dep. 212:3-16. See also
Egeberg Dep. 240:15-241:11. Subsequently, HRH submitted a proposed change order dated
7 Mr. Egeberg was not aware of any such meeting occurring. Egeberg Dep. 228:10- 229:7, 269:17-270:3. Nor
were other senior managers at NYU aware of any such meeting. Trial Tr. 147:12-15, 163:2-165:23, 172:3-173:3
(Jan. 5, 2011). At trial, NYU’s counsel conceded, “I don’t think they held a meeting in a formal sense. There
were conversations, instead.” Trial Tr. 26:8-11 (Jan. 5, 2011).
8 While NYU’s senior project manager, John DeCesare, testified at one point that this plan was not necessary to
start phase 2, Trial Tr. 187:7-9 (Jan. 5, 2011), Mr. DeCesare conceded on cross-examination that it would be
“pretty tough” to start phase 2 without it. Trial Tr. 180:2-13 (Jan. 5, 2011).
10-08242-rdd Doc 40 Filed 08/03/11 Entered 08/03/11 10:37:37 Main Document
Pg 7 of 32
8
August 2, 2005 requesting that the guaranteed maximum price for the project be increased by
approximately $4.1 million. Trial Ex. 238. This proposed change order included cost
adjustments as requested by three subcontractors, plus cost adjustments exclusive to HRH, to
fund the remainder of the project. Id. “We look forward to meeting with you to review this
request,” HRH wrote. Id.
NYU refused HRH’s offer to meet.9 Instead, NYU responded by letter dated August 5,
2005, stating that HRH’s submissions did not “provide a basis for discussion or negotiations.”
Trial Ex. 34. NYU’s letter also “hereby directed [HRH] to proceed with the Work immediately.”
Id. In a letter dated August 9, 2005, NYU reiterated its view that HRH’s claim submissions from
HRH’s subcontractors “do not provide a basis for further discussion and are rejected.” Trial Ex.
35. Similar language was employed by NYU in a letter to HRH dated August 23, 2005: “Your
request does not provide a basis for negotiation and is denied . . . .” Trial Ex. 38.
On August 3, 2005, one day after HRH submitted its change order request of around $4.1
million, NYU wrote to another general contractor, Bovis Lend Lease LMB, Inc. (“Bovis”), in an
apparent attempt to have Bovis replace HRH. Trial Ex. 134. Mr. Egeberg of NYU admitted that
he gave Bovis permission to contact HRH’s subcontractors on this project while the various
subcontracts with HRH remained pending. Egeberg Dep. 278:10-17. The evidence strongly
suggests that communications between Bovis and the subcontractors had a negative impact on
HRH’s ability to proceed with the project. See Trial Ex. 244, units 82.2, 83.3, 84.4, 85.3, 87.2,
88.2 (revealing that six separate subcontractors were delaying or refusing to return because of
contact by a new general contractor). See also Ross Aff. ¶¶ 54-57; Behrouzian Aff. ¶¶ 14, 15,
18, 19 (Dec. 23, 2010); Egeberg Dep. 299:20-300:9. The construction meeting minutes of
9 See supra note 6 and accompanying text.
10-08242-rdd Doc 40 Filed 08/03/11 Entered 08/03/11 10:37:37 Main Document
Pg 8 of 32
9
August 24, 2005 further confirm that the parties were aware that the involvement of Bovis as a
potential replacement contractor was interfering with HRH’s ability to work with its own
subcontractors.10 See Trial Ex. 244, units 82.2, 83.3, 84.4, 85.3, 87.2, 88.2. See also Trial Tr.
182:2-183:21 (Jan. 5, 2011).
In a letter dated August 17, 2005, NYU notified HRH that its “continuing lack of
progress constitutes a default” under the Construction Agreement. Trial Ex. 36. On August 22,
2005, HRH reminded NYU that NYU was in default of the payment terms of the Construction
Agreement. Trial Ex. 37. On October 27, 2005, NYU sent a letter terminating the Construction
Agreement. Trial Ex. 39. Bovis ultimately took over the project from HRH and hired many of
the subcontractors who had been working for HRH. Trial Tr. 27:12-28:1 (Jan. 5, 2011); Trial
Exs. 49-53.
HRH remains unpaid for requisitions 14, 15, 16, and 17 submitted for work on the project
through July of 2005. Trial Tr. 114:10-14, 115:25-117:25 (Jan. 5, 2011). These are the only
requisitions being claimed by HRH in this litigation. See Trial Tr. 34:2-5 (Jan. 7, 2011). NYU
approved requisition 14 by May 19, 2005 in the amount of $684,889, making this amount due by
June 18, 2005. Trial Ex. 252; Trial Tr. 115:3-116:2 (Jan. 5, 2011). See also Trial Ex. 225
(“NYU Hospital remains seriously delinquent in its payments.”). NYU approved requisition 15
by June 30, 2005 in the amount of $800,874, rendering this amount due by July 30, 2005. Trial
Ex. 252; Trial Tr. 116:6-14 (Jan. 5, 2011). Requisition 16, in the amount of $486,194, appears to
have been received by NYU as of August 3, 2005. Trial Ex. 252; Trial Tr. 116:15-117:20 (Jan.
5, 2011). Based on the weight of evidence at trial, the Court concludes that requisition 16 was
10 Despite the failure of HRH and NYU to sit down for the meeting contemplated by the Completion Agreement,
HRH and NYU did meet to discuss current construction issues. See Trial Tr. 178:7-12 (Jan. 5, 2011) (discussing
meeting minutes issued on a regular basis on this project). Neither party has argued, however, that these meetings
constituted the meeting contemplated by the Completion Agreement.
10-08242-rdd Doc 40 Filed 08/03/11 Entered 08/03/11 10:37:37 Main Document
Pg 9 of 32
10
also approved and notes that there is no evidence to suggest that NYU was unsatisfied with the
work reflected in requisition 16. Trial Ex. 235; Trial Ex. 252; Trial Tr. 116:15-117:20, 123:4-7,
177:1-3 (Jan. 5, 2011); Egeberg Dep. 291:22-292:7. But see Berger Aff. ¶ 65 (“HRH’s payment
application 16R was never approved internally at NYU after its receipt from the architect, and
payment was likewise withheld on account of HRH’s failure to progress the work.”). Allowing
for NYU’s twelve day period to accept or deny a requisition, HRH was due to receive $486,194
on account of requisition 16 by September 14, 2005. See Trial Ex. 1, Construction Agreement §
10.1.7.
As for requisition 17, dated July 31, 2005, it is unclear whether or when NYU received
this requisition. See Trial Ex. 250; Trial Tr. 4:17-21, 7:15-11:6 (Jan. 10, 2011). Requisition 17
purports to claim reimbursement for work accomplished during the month of July in 2005 after
Substantial Completion of phases 0 and 1 but before work commenced on phase 2. Trial Ex.
250.
The evidence indicates that HRH made NYU aware of its failure to timely pay
requisitions on many occasions, including a letter dated June 20, 2005. See Trial Exs. 216, 217,
220, 225. Eventually, HRH sent NYU a letter of default on August 22, 2005, informing NYU
that failure to pay the outstanding requisitions constituted a breach of contract permitting HRH to
suspend performance if NYU did not cure the default within ten days. Trial Ex. 243.
B. 	Litigation in New York State Court
On November 10, 2005, NYU filed a complaint against HRH in the Supreme Court of the
State of New York. In its complaint, NYU asserted only one cause of action against HRH for its
failure to progress with work after Substantial Completion was achieved in June of 2005. In
subsequent briefing, NYU has explained that its breach of contract claim is based on theories of
10-08242-rdd Doc 40 Filed 08/03/11 Entered 08/03/11 10:37:37 Main Document
Pg 10 of 32
11
constructive abandonment and work stoppage. HRH responded to NYU’s complaint with
counterclaims for breach of contract, quantum meruit, and unjust enrichment.
Subcontractor Curtis filed its own complaint in state court against HRH and NYU to
seek, under a variety of legal theories, Curtis’s share of the unpaid contract requisitions and to
foreclose upon a mechanic’s lien against NYU for that unpaid amount plus other damages. On
February 19, 2009, the state court issued a decision dismissing Curtis’s claims arising in
quantum meruit and New York General Business Law § 756, leaving only two causes of action:
(1) a mechanic’s lien claim against both NYU and HRH, and (2) a “hardship” or tortious
interference claim against HRH. Curtis Partition Corp. v. HRH Constr., LLC, 2009 N.Y. Misc.
LEXIS 329, 2009 WL 415550, 2009 N.Y. Slip Op. 50272U, at *7-11 (N.Y. Sup. Ct. Feb. 19,
2009). 	NYU responded to Curtis’s complaint by filing various counterclaims against Curtis,
including willful exaggeration of the Curtis mechanic’s lien and a third-party beneficiary claim
seeking damages for Curtis’s breaches of the subcontract between HRH and Curtis. NYU also
sought indemnification against HRH for any damages NYU might owe to Curtis.
C. 	Removal from State Court
After HRH filed for bankruptcy protection on September 6, 2009, HRH removed the state
court action to the United States District Court for the Southern District of New York,
whereupon this matter was referred to the bankruptcy court pursuant to the standing order of
referral dated July 10, 1984 (Ward, Acting C.J.). Pursuant to letters filed on the docket in July of
2011, the parties consented to the entry of this decision as a final judgment. See docket entries
37-39; 28 U.S.C. § 157(c)(2); Stern v. Marshall, 131 S. Ct. 2594 (U.S. 2011). This decision
constitutes the Court’s findings of fact and conclusions of law.
10-08242-rdd Doc 40 Filed 08/03/11 Entered 08/03/11 10:37:37 Main Document
Pg 11 of 32
12
DISCUSSION
A. 	The Parties and Applicable Law
NYU is a New York not-for-profit corporation and HRH is a New York limited liability
corporation. Trial Ex. 1, Construction Agreement at 1; NYU Complaint ¶ 1; HRH Answer and
Counterclaims ¶ 31. Curtis is a New Jersey corporation having its principal place of business in
New York. Curtis Complaint ¶ 1. Both the Construction Agreement and the subcontract
between HRH and Curtis are governed by the laws of New York. Trial Ex. 1, Construction
Agreement §§ 22.2, 22.4; Trial Ex. 4, Subcontract § 18.5. Not surprisingly then, the parties
agree that New York law applies to the instant dispute.
B. 	New York Law on Contracts
The elements of a cause of action to recover damages for breach of contract are (1) the
existence of a contact, (2) the plaintiff’s performance under the contract, (3) the defendant’s
breach of the contract, and (4) resulting damages. Palmetto Partners, L.P. v. AJW Qualified
Partners, LLC, 921 N.Y.S.2d 260, 264 (N.Y. App. Div. 2d Dep’t 2011) (citations omitted). A
party’s failure to perform results in the suspension of the complying party’s obligation to
perform. P.A. Bldg. Co. v. City of New York, 10 N.Y.3d 430, 437 (N.Y. 2008) (citations
omitted). See also 17A AM J UR 2D CONTRACTS § 606 (“As a rule, a party first guilty of a
substantial or material breach of contract cannot complain if the other party subsequently refuses
to perform. That party can neither insist on performance by the other party nor maintain an
action against the other party for a subsequent failure to perform. This is because a material
breach relieves the other party of the obligation to perform.”). Where one party demands strict
performance as to time by another party, he must perform on his part all the conditions which are
requisite in order to enable the other party to perform his part, and a failure on the part of the
10-08242-rdd Doc 40 Filed 08/03/11 Entered 08/03/11 10:37:37 Main Document
Pg 12 of 32
13
party demanding performance operates as a waiver of the time provision in the contract. Walter
Sign Corp. v. State, 31 A.D.2d 729, 729-30 (N.Y. App. Div. 4th Dep’t 1968) (citations omitted).
Accord Mosler Safe Co. v. Maiden Lane Safe Deposit Co., 199 N.Y. 479, 489 (N.Y. 1910).
Failure to make periodic payments due under a contract can constitute a breach entitling
the counterparty to regard the contract as terminated. See Paterno & Sons, Inc. v. New Windsor,
43 A.D.2d 863, 864 (N.Y. App. Div. 2d Dep’t 1974) (citations omitted). Section 276 of the
Restatement of the Law of Contracts explains that an owner who fails to make timely payments
excuses a contractor from further work until payments are made current. See Tri-Mar
Contractors, Inc. v. Itco Dry-Wall, Inc., 74 A.D.2d 601, 602 (N.Y. App. Div. 2d Dep’t 1980).
Unless a payment is delayed an unreasonably long time, the contractor must resume work when
the payment is made. See id.
The unambiguous language of uncontested, valid contracts must be enforced. Weiser v.
Exeter Capital Partners LLC, 890 N.Y.S.2d 371, 2009 N.Y. Slip Op. 51406U, at *6 (N.Y. Sup.
Ct. June 11, 2009) (citations omitted). If an agreement on its face is reasonably susceptible of
only one meaning, a court is not free to alter the contract to reflect its personal notions of fairness
and equity. Krystal Investigations & Sec. Bur., Inc. v. United Parcel Serv., Inc., 35 A.D.3d 817,
818 (N.Y. App. Div. 2d Dep’t 2006) (citations omitted).
C. 	Unpaid Requisitions Sought by HRH
Given the chronology of events, the Court will first address HRH’s claim that NYU
breached the contract by failing to timely pay requisitions approved in the late spring and
summer of 2005.
Each of these requisitions had a different submission date and thus triggered different
deadlines for payment. By May 19, 2005, NYU had approved requisition 14, which HRH had
10-08242-rdd Doc 40 Filed 08/03/11 Entered 08/03/11 10:37:37 Main Document
Pg 13 of 32
14
submitted for its work on the construction project during the month of April 2005. Pursuant to
section 10.2 of the Construction Agreement, NYU was required to pay HRH within thirty days
of its approval, making payment for requisition 14 due by June 18, 2005. Trial Ex. 1,
Construction Agreement §§ 10.2, 13.1. See also Trial Ex. 3, Completion Agreement ¶ 2(d); Trial
Tr. 122:20-24 (Jan. 5, 2011). Adding the Construction Agreement’s ten-day cure period, NYU
was in breach by June 28, 2005 for failure to pay. It is undisputed that NYU never paid HRH for
requisition 14. Trial Tr. 114:10-14 (Jan. 5, 2011). By letter dated June 20, 2005, HRH notified
NYU that NYU “remains seriously delinquent in its payments.” Trial Ex. 225. It is similarly
undisputed that NYU never paid HRH for requisitions 15 and 16, despite NYU’s approval of
these requisitions. Trial Tr. 115:25-117:25 (Jan. 5, 2011).
Unlike requisitions 14 through 16, requisition 17 is disputed as NYU claims to not have
received it. Trial Tr. 4:4-25 (Jan. 10, 2011). While there is documentation proving that NYU
received requisitions 14 through 16, with signatures and dates affixed by NYU, there is no such
documentary evidence for requisition 17. See Trial Exs. 129, 130, 131, 141, 250A. Instead,
HRH provided only limited testimony on the subject, none of which established that requisition
17 was received and approved by NYU. Given the deficiencies in documentary support and the
timing of requisition 17—purportedly submitted on or after July 31, 2005, at which point the
relationship among the parties had deteriorated significantly and a requisition approval was
unlikely—the Court will not consider requisition 17 as having been submitted to and approved
by NYU.
Under the terms of the Construction Agreement, HRH is entitled to payment on approved
requisitions 14, 15 and 16 unless NYU somehow was relieved of its obligation to pay such
requisitions. NYU offers four theories to support its failure to pay the approved requisitions:
10-08242-rdd Doc 40 Filed 08/03/11 Entered 08/03/11 10:37:37 Main Document
Pg 14 of 32
15
(1) HRH’s failure to proceed with phase 2, (2) HRH’s unsatisfactory or disputed job progress,
(3) HRH’s breach prior to Substantial Completion, and (4) HRH’s failure to provide formal
notice to NYU of an intended suspension of work.
1. 	Alleged Failure to Proceed with Phase 2
NYU contends that HRH abandoned the construction project in June of 2005 by failing to
proceed with phase 2. Berger Aff. ¶ 63; NYU Post-Trial Brief ¶ 130. NYU argues, therefore,
that it was under no obligation to pay requisitions that became due at or after that time.
To recover on the ground of abandonment, an owner must establish that the contractor is
responsible for delays which are so unreasonable that they connote a relinquishment of the
contract by the contractor with the intention of never resuming it. Corinno Civetta Constr. Corp.
v. New York, 67 N.Y.2d 297, 312-13 (N.Y. 1986) (citations omitted). “To establish
abandonment of a contract by conduct, it must be shown that the conduct is mutual, positive,
unequivocal, and inconsistent with the intent to be bound. Generally, a finding of . . .
abandonment will be based upon clear, affirmative conduct by at least one of the parties that is
entirely at odds with the contract.” EMF Gen. Contr. Corp. v. Bisbee, 6 A.D.3d 45, 49-50 (N.Y.
App. Div. 1st Dep’t 2004) (citations omitted). The party who asserts abandonment has the
burden of establishing it since the termination of a contract is not presumed. Rosiny v. Schmidt,
185 A.D.2d 727, 732 (N.Y. App. Div. 1st Dep’t 1992). See also Armour & Co. v. Celic, 294
F.2d 432, 435-36 (2d Cir. 1961) (setting forth the law in New York for abandonment of
contracts); Benson v. RMJ Sec. Corp., 683 F. Supp. 359, 373 (S.D.N.Y. 1988) (same).
NYU has not provided sufficient evidence to meet its burden to establish abandonment
by HRH for failure to proceed with phase 2. It is undisputed that the Completion Agreement was
designed to help the parties overcome the problems previously plaguing this project by reaching
10-08242-rdd Doc 40 Filed 08/03/11 Entered 08/03/11 10:37:37 Main Document
Pg 15 of 32
16
an understanding on a variety of important matters going forward, including the scheduling of
payments, the scope and timing of work on phase 2, and a new deadline for Substantial
Completion of phases 0 and 1. Of particular relevance here, the Completion Agreement—
drafted by NYU—specifically provided that the parties were to “meet (prior to the start of [phase
2]) to negotiate and resolve remaining issues between them, including the schedule for
completion of the remaining Work.” The evidence at trial established that no such meeting
occurred. Without such a meeting, NYU cannot prevail on its claim that HRH abandoned the job
by failing to move forward with phase 2.
In fact, the evidence suggests that HRH attempted to move forward with the project
several times during the summer of 2005. In letters from June through August of 2005, HRH
repeatedly requested meetings and clearance to proceed with phase 2. See Perlman v. M. Israel
& Sons Co., 306 N.Y. 254, 257 (N.Y. 1954) (refusal to accept tender of performance is a breach
of contract that excuses further performance). The evidence reveals that HRH, on multiple
occasions, conveyed its intent to finish the project. Indeed, the change order request of August 2,
2005, was provided to NYU in contemplation of continued performance.
NYU argues that the meeting referenced in the Completion Agreement was not a
condition precedent because the relevant contractual language lacked the unmistakable language
of “if” or “unless and until.” NYU Post-Trial Brief ¶ 136. However, the meaning of the
Completion Agreement is unmistakable from its plan language: “Following Substantial
Completion of Phase 0 and Phase 1 of the Work, the Owner and Contractor will meet (prior to
the start of the next phase of the Work) to negotiate and resolve remaining issues between them,
including the schedule for completion of the remaining Work.” Trial Ex. 3, Completion
Agreement ¶ 3 (emphasis added); Weiser, 2009 N.Y. Slip Op. 51406U, at *6 (the unambiguous
10-08242-rdd Doc 40 Filed 08/03/11 Entered 08/03/11 10:37:37 Main Document
Pg 16 of 32
17
language of uncontested, valid contracts controls). This Court’s ruling is consistent with the
state court’s understanding, prior to removal, of the parties’ obligations under the Completion
Agreement. See Curtis Partition, 2009 N.Y. Slip Op. 50272U, at *2 (“The parties also agreed
that once Phases 0 and 1 were substantially complete, they would negotiate a plan for the
commencement of work on Phase 2 of the project.”).
Given the language of the Completion Agreement, there is no doubt of the parties’ intent,
and NYU has not presented any evidence that would dictate a contrary result. 11 See
Oppenheimer & Co. v. Oppenheim, 86 N.Y.2d 685, 691 (N.Y. 1995) (“Though the court may
regret the harshness of such a condition, as it may regret the harshness of a promise, it must,
nevertheless, generally enforce the will of the parties unless to do so will violate public policy.”).
Indeed, even if there were some ambiguities in the language of contract on this issue, such
ambiguities would be construed against NYU as the drafter of the agreement. See Matter of
Liberty Mut. Fire Ins. Co. v Malatino, 75 A.D.3d 967, 969-70 n.4 (N.Y. App. Div. 3d Dep’t
2010) (citing Guardian Life Ins. Co. of Am. v Schaefer, 70 N.Y.2d 888, 890 (1987)); State of
New York v. Industrial Site Servs., Inc., 862 N.Y.S.2d 118, 124 (N.Y. App. Div. 3d Dep’t 2008)
(citations omitted); Burgos v. Metro-North Commuter R. R., 836 N.Y.S.2d 76, 77 (N.Y. App.
Div. 1st Dep’t 2007) (citing Jacobson v. Sassower, 66 N.Y.2d 991, 993 (1985)). Thus, as NYU
cannot establish that the contract required HRH to proceed with phase 2, NYU’s abandonment
claim must fail.
NYU offers an alternative theory by arguing that HRH’s change order request of August
2, 2005 was an anticipatory breach, or a condition precedent to continued performance. See
11 The testimony of NYU’s most senior official on the project, Mr. Egeberg, strongly confirms the parties’ intent to
meet before moving forward with phase 2. See Egeberg Dep. 227:10-14 (“[T]he parties needed to sit down and
figure this out. There was no time frame other than as soon as possible for both of us to figure out what we were
going to do to continue.”).
10-08242-rdd Doc 40 Filed 08/03/11 Entered 08/03/11 10:37:37 Main Document
Pg 17 of 32
18
DeCesare Aff. ¶ 48; Trial Tr. 104:10-14, 106:1-17 (Jan. 5, 2011). More simply, NYU contends
that HRH refused to proceed with phase 2 unless NYU agreed to the change order request of
August 2, 2005. But NYU’s theory is inconsistent with its own claim that “HRH was in breach
of the Construction Agreement by failing to give NYU an unequivocal demand for timely
payment prior to its work stoppage.” NYU Post-Trial Brief ¶ 133. NYU cannot have it both
ways.
Moreover, the evidence strongly suggests that the change order request was not seriously
considered by NYU. One of NYU’s witnesses testified that she did not read the proposed
change order of August 2, 2005 until four years later, and another witness explained that he did
not read it “in depth.” Trial Tr. 99:6-100:20 (Jan. 5, 2011); Egeberg Dep. 243:12-244:7. NYU
also argues that the change order request demand for an additional $4,153,566 to complete the
project was patently unreasonable and not a basis for further negotiation. NYU’s position is,
however, difficult to reconcile with NYU’s assertion that its reasonable costs to complete the
project were $3,678,830, or some 13% less than HRH’s demand. 12 Wright Aff. ¶ 23 (Dec. 10,
2010); NYU Post-Trial Brief ¶ 141. Given all these circumstances, the Court rejects NYU’s
theory of anticipatory breach as inconsistent with the events of the summer 2005 and the
contractual burdens imposed on each party pursuant to the Completion Agreement.
NYU also maintains that the Court should reject HRH’s claim for unpaid requisitions
because HRH failed to provide the ten days’ written notice required when a party threatened to
suspend work for nonpayment. NYU Post-Trial Brief ¶¶ 80-82; Berger Aff. ¶ 68 (citing Trial
Ex. 1, Construction Agreement § 10.3). But NYU’s argument misses the point. HRH did not
unilaterally suspend work on the project. The next work contemplated by the project was
12 After including NYU’s termination fees and expenses through February of 2010 in the amount of $350,931, this
percentage shrinks to a modest 3%. See Wright Aff. ¶ 25; NYU Post-Trial Brief ¶ 141.
10-08242-rdd Doc 40 Filed 08/03/11 Entered 08/03/11 10:37:37 Main Document
Pg 18 of 32
19
phase 2, and HRH was not obligated to begin work on phase 2 until the parties had met pursuant
to the Completion Agreement. As no such meeting occurred, NYU cannot successfully argue
that HRH suspended work on the job. The contract having been terminated, however, HRH is
now entitled to seek payment of these requisitions pursuant to the contract’s termination
provision. Trial Ex. 1, Construction Agreement, Article 17.
Separate and apart from the parties’ contractually mandated meeting, HRH persuasively
presents an alternative theory for recovery of its unpaid requisitions: NYU’s interference with
HRH’s ability to perform its ongoing contractual obligations. Each party to a construction
contract impliedly agrees not to hinder or obstruct the other’s performance. Wolff & Munier,
Inc. v. Whiting-Turner Contracting Co., 946 F.2d 1003, 1007 (2d Cir. 1991) (citations omitted).
See also Young v. Whitney, 111 A.D.2d 1013, 1014 (N.Y. App. Div. 3d Dep’t 1985) (citations
omitted) (“[T]he law implies in every contract that one party will not prevent the other party’s
performance.”). The credible evidence at trial establishes that NYU impeded HRH’s ability to
perform in three fundamental ways. First, HRH contacted general contractor Bovis about
replacing HRH on the job and gave Bovis permission to communicate directly with HRH’s
subcontractors, thereby frustrating HRH’s ability to work with subcontractors who expected that
HRH had been or likely would be replaced. Second, NYU failed to timely pay outstanding
requisitions, especially requisitions 14 and 15 due in June and July respectively, further
frustrating HRH’s ability to obtain cooperation from these same unpaid subcontractors. Third,
NYU failed to finalize drawings for phase 2 as of July 27, 2005, which made it difficult to
proceed with work on phase 2.
All of these actions collectively obstructed HRH’s ability to perform, even if
performance was required to proceed with phase 2. Savin Bros., Inc. v. State, 62 A.D.2d 511,
10-08242-rdd Doc 40 Filed 08/03/11 Entered 08/03/11 10:37:37 Main Document
Pg 19 of 32
20
516 (N.Y. App. Div. 4th Dep’t 1978) (“In every express contract for the performance of
construction work there exists an implied term that the owner or the party for whom the work is
to be performed will not obstruct but, on the contrary, will facilitate performance.”), affirmed, 47
N.Y.2d 934 (N.Y. 1979); Bialo v. Walter Lawlor, Inc., 160 A.D.2d 559, 560 (N.Y. App. Div. 1st
Dep’t 1990) (“A duty is imposed upon an employer not to interfere with the prosecution of the
work of his contractor.”). Accord Lower v. Vill. of Watkins Glen, 17 A.D.3d 829, 831 (N.Y.
App. Div. 3d Dep’t 2005) (“A plaintiff seeking to maintain action for breach or nonperformance
of contract must demonstrate that tender of his or her own performance was made, unless tender
was waived or the necessity for such tender was obviated by acts of the other party amounting to
an anticipatory breach of the contract or establishing that such party would be unable to
perform.”) (citations omitted).
The facts of this case are quite similar to those recently addressed in Plainview S. & S.
Concrete Co. v. NVNG Dev. Corp., 151 A.D.2d 654 (N.Y. App. Div. 2d Dep’t 1989). In
Plainview, the plaintiff was contracted to do construction work on a building owned by the
defendant. Id. at 655. The owner failed to complete certain preparatory work that it was
responsible for doing, thereby frustrating the plaintiff’s ability to continue the work. Id. The
owner then hired other contractors to perform the work which the plaintiff had been obligated to
perform under their contract. Id. The Plainview court held that, under these circumstances, the
owner could not successfully assert that the plaintiff abandoned its obligations under the
contract. Id. Moreover, the Plainview court held that the owner, in hiring other contractors
before the plaintiff could complete its work, breached the contract by effectively preventing the
plaintiff from performing. Id. 	As in Plainview, owner NYU here frustrated HRH’s ability to
perform and, therefore, cannot successfully assert that HRH abandoned its contractual
10-08242-rdd Doc 40 Filed 08/03/11 Entered 08/03/11 10:37:37 Main Document
Pg 20 of 32
21
obligations. Id.; see Michael G. Buck & Son Constr. Corp. v. Poncell Constr. Co., 217 A.D.2d
925, 926 (N.Y. App. Div. 4th Dep’t 1995) (finding the defendant breached the contract by
wrongfully ordering plaintiff off the job at a time when plaintiff was in “substantial
compliance”).
2. 	Unsatisfactory or Disputed Job Progress
NYU contends that it was entitled to withhold payments on account of the approved
requisitions 14 through 16 because of “unsatisfactory or disputed job progress.” Berger Aff.
¶ 64. But see Trial Tr. 118:1-119:4, 122:20-24 (Jan. 5, 2011). NYU further argues that
requisitions 14 and 15 were approved “only in anticipation that HRH would continue working.”
Berger Aff. ¶ 65. These arguments represent a strained and unsupported reading of Construction
Agreement section 10.1.7, which allows NYU to withhold payment only on account of disputed
requisitions, and of the Completion Agreement. The evidence makes clear that requisitions 14
through 16 were never disputed by NYU, and requisitions 14 and 15 were, in fact, affirmatively
approved by NYU. The Court rejects NYU’s argument as inconsistent with the contract,
particularly given the provisions of the Completion Agreement—discussed above—setting forth
the parties obligation to meet before moving forward with phase 2.
3. 	Alleged Breach Prior to Phase 2
NYU has suggested that it should prevail because HRH breached the contract by virtue of
the six-day delay in reaching Substantial Completion and because NYU devoted some of its own
personnel to achieving Substantial Completion by June 21, 2005. The Court rejects NYU’s
argument.
As a threshold matter, this theory of breach was presented for the first time in this Court
at trial and is inconsistent with NYU’s long held view that HRH breached the contract by failing
10-08242-rdd Doc 40 Filed 08/03/11 Entered 08/03/11 10:37:37 Main Document
Pg 21 of 32
22
to move forward with phase 2 of the work. See NYU Complaint ¶ 10 (“Following substantial
completion of Phases 0 and 1 on or about June 15, 2005, construction progress ceased . . . .”);
NYU Post-Trial Brief ¶ 58 (claiming that NYU “was the first party to declare a breach of the
Construction Agreement, pursuant to written notice to HRH dated August 17, 2005”) (citing
Trial Ex. 36, which provides that HRH is in default for its “continuing lack of progress”). See
also Trial Tr. 58:9-20 (Jan. 5, 2011) (“It has no place in this case, Your Honor, because they’ve
never made a claim. . . . It’s not in their complaint.”) (statement of HRH’s counsel at opening of
trial regarding completion of phases 0 and 1). As such, this new theory of breach is not properly
before the Court. See S.E.C. v. Tambone, 597 F.3d 436, 450 (1st Cir. 2010) (“A party cannot
switch horses mid-stream, changing its theory of liability at a later stage of the litigation in hopes
of securing a swifter steed.”); Armstrong Cork Co. v. Lyons, 366 F.2d 206, 209 n.3 (8th Cir.
1966) (“The plaintiff in his proof must ordinarily be confined to the cause of action set forth in
his declaration or complaint, and must recover, if at all, on the case made therein.”); Auguste v.
Dep’t of Corrections, 424 F. Supp. 2d 363, 368 (D. Conn. 2006) (declining to consider claims
raised in memorandum response to motion for summary judgment, but not raised in original
complaint). See also Opals on Ice Lingerie v. Bodylines, Inc., No. 99 CV 3761, 2002 WL
718850, at *4, 2002 U.S. Dist. LEXIS 10738, at *13-14 (E.D.N.Y. Mar. 4, 2002); Beckman v.
U.S. Postal Service, 79 F. Supp. 2d 394, 408-10 (S.D.N.Y. 2000); Dir. Gen. of India Supply
Mission v. S.S. Janet Quinn, 335 F. Supp. 1329, 1338 (S.D.N.Y. 1971); In re Freeman, 30 B.R.
704, 706-07 (Bankr. W.D. La. 1983).
In any event, NYU’s new theory of breach is not supported by the evidence at trial.
According to the Completion Agreement, HRH was to reach Substantial Completion by June 15,
2005. Substantial Completion was to include all work necessary to obtain approval from the
10-08242-rdd Doc 40 Filed 08/03/11 Entered 08/03/11 10:37:37 Main Document
Pg 22 of 32
23
Department of Health. The parties were aware that the Department of Health was scheduled to
review the facilities on June 21, 2005. This inspection had been scheduled at least thirty days
prior. Trial Tr. 91:4-92:3 (Jan. 5, 2011). According to schedule, the Department of Health
visited the facilities on June 21, 2005, and NYU was given approval for full use and occupancy
of the facilities. Given the ten-day cure period found in section 17.3 of the Construction
Agreement, a six-day delay in reaching Substantial Completion does not constitute a default or
breach. Moreover, Substantial Completion was reached in time for a successful inspection by
the Department of Health in compliance with the purpose of the June 15, 2005 deadline
articulated in the Completion Agreement. As for NYU’s use of its own staff, the mere use of
such personnel does not, by itself, constitute a breach and is insufficient under these
circumstances establish abandonment by HRH. See Savin Bros., 62 A.D.2d at 516 (every
express construction contract contains an implied term that the owner will facilitate the
contractor’s performance). Not surprisingly, NYU did not allege a breach of the contract at the
time of these events—compare Trial Exs. 224, 242, 245—nor has NYU asserted damages in
connection with the completion of phases 0 and 1. See Wright Aff. ¶¶ 13-15, 22-23; NYU Post-
Trial Brief ¶¶ 109-120.
4. 	Alleged Lack of Formal Notice Prior to Suspension of Work
Finally, NYU complains that HRH failed to give NYU notice of its intent to suspend
work for non-payment. See NYU Post-Trial Brief ¶¶ 80-82; Berger Aff. ¶ 68. In support of this
position, NYU points to section 10.3 of the Construction Agreement, which reads: “[HRH] may
suspend the Work until payment of the amount owing has been received after providing [NYU]
written notice and an opportunity to cure at least ten (10) days before the intended suspension.
Such notice shall (a) inform [NYU] that payment of undisputed amounts has not been received,
10-08242-rdd Doc 40 Filed 08/03/11 Entered 08/03/11 10:37:37 Main Document
Pg 23 of 32
24
and (b) state the intent of [HRH] to suspend the Work for non-payment.” NYU Post-Trial Brief
¶ 81; Trial Ex. 1, Construction Agreement § 10.3.
While there is substantial evidence that HRH made NYU aware, on numerous occasions,
of NYU’s failure to timely pay requisitions, including a letter dated June 20, 2005, the Court is
not aware of a notice from HRH to NYU stating HRH’s intent to suspend performance for non-
payment until August 22, 2005. See Trial Ex. 37. For the reasons set forth above, however, the
lack of earlier notice does not undermine HRH’s claim for payment of requisitions 14, 15, and 16
because HRH did not have an obligation to move forward with phase 2 prior to the August 22,
2005 notice. Even accepting that HRH employees may have orally expressed some
unwillingness about moving forward with the job, the Construction Agreement is abundantly
clear about NYU’s obligation to timely pay requisitions for completed work where such
requisitions had been approved by NYU. 13
E. 	Quantum Meruit and Unjust Enrichment
HRH’s remaining causes of action against NYU arise in quantum meruit and unjust
enrichment. These causes of action apply only when a written, valid, and enforceable contract
does not exist. See Steven Strong, 303 A.D.2d at 882. HRH’s work for NYU was done pursuant
to their Construction Agreement and subsequent Completion Agreement, and neither party has
challenged the validity or enforceability of these contracts. Therefore, as the state court
previously recognized, HRH’s claims for quantum meruit and unjust enrichment must fail,
including its claim for payment of requisition 17. See Curtis Partition, 2009 N.Y. Slip Op.
13 Although HRH urges the Court to take a negative inference from Mr. Egeberg’s failure to appear at trial as a
witness, it would not appear necessary to do so, because Mr. Egeberg’s deposition testimony supports the decision
reached by the Court. See Revson v. Cinque & Cinque, 221 F.3d 71, 81 (2d Cir. 2000) (“It is well-settled that a
party’s failure to call a witness may permissibly support an inference that that witness’s testimony would have
been adverse.”).
10-08242-rdd Doc 40 Filed 08/03/11 Entered 08/03/11 10:37:37 Main Document
Pg 24 of 32
25
50272U, at *6 (“HRH’s admission that its work on the Project is governed by the Construction
Agreement with NYU precludes a claim for quantum meruit or unjust enrichment because, under
New York law, the existence of a written contract covering the particular subject matter of the
claims asserted precludes recovery in quasi contract.”) (citations omitted). See also Steven
Strong, 303 A.D.2d at 882.
F. 	Curtis’s Hardship Claim
Curtis brings a hardship claim against HRH in which it seeks damages for various delays
in the work and lack of an adequate storage area on site. See Trial Tr. 64:16-65:2 (Jan. 5, 2011);
Trial Tr. 89:4-18 (Jan. 7, 2011) (explaining that its hardship claim is essentially one for breach of
contract). 	See also Curtis Partition, 2009 N.Y. Slip Op. 50272U, at *7-8 (discussing Curtis’s
claims arising in breach of contract and quantum meruit).
Curtis’s claim is problematic because the relevant contracts contain provisions precluding
such damages. These include no-delay provisions and drawings that reflect the amount of space
available for the project.14 See Trial Ex. 1, Construction Agreement §§ 5.4-5.6, Ex. A; Trial Ex.
4, Subcontract §§ 7.2(c-e), 13.1(a). Curtis relies upon Abax Inc. v. N.Y. City Hous. Auth., 282
A.D.2d 372, 373 (N.Y. App. Div. 1st Dep’t 2001) for the proposition that the no-delay damages
clauses do not apply because the interference with Curtis’s performance was egregious, in bad
faith, willful, or grossly negligent. The evidence does not in any way support such a factual
finding, however, and the Court declines to award the “exemplary damages” requested by Curtis.
See Curtis Partition, 2009 N.Y. Slip Op. 50272U, at *6-7 (exemplary damages not authorized in
breach of contract action where only a private wrong and not a public right is involved) (citing
Cross v. Zyburo, 185 A.D.2d 967, 968 (N.Y. App. Div. 2d Dep’t 1992)).
14 Notably, HRH has not asserted a claim for inadequate storage against NYU.
10-08242-rdd Doc 40 Filed 08/03/11 Entered 08/03/11 10:37:37 Main Document
Pg 25 of 32
26
G. 	Claims of Subcontractor Curtis
On October 28, 2005, one day after NYU notified HRH of its termination, Curtis filed a
mechanic’s lien on NYU’s property. See Trial Ex. 45. Curtis now seeks to foreclose on its
mechanic’s lien to the extent that it is not otherwise made whole. Somewhat relatedly, Curtis
also claims that any money owed to Curtis as a subcontractor is held in trust for Curtis pursuant
to Article 3-A of New York’s Lien Law.
1. 	The Curtis Mechanic’s Lien
Mechanic’s liens “may be enforced against the property specified in the notice of lien and
which is subject thereto and against any person liable for the debt upon which the lien is
founded.” Martirano Constr. Corp. v. Briar Contracting Corp., 104 A.D.2d 1028, 1030 (N.Y.
App. Div. 2d Dep’t 1984) (quoting N.Y. Lien Law § 24). It is well established that a mechanic’s
lien of a subcontractor will attach only to funds due and owing to the general contractor at the
time of its filing, or which may thereafter become due and owing. Electric City Concrete Co. v.
Phillips, 100 A.D.2d 1, 4 (N.Y. App. Div. 3d Dep’t 1984); Curtis Partition, 2009 N.Y. Slip Op.
50272U, at *10. The rights of lienors are derivative of the general contractor and are restricted
to satisfaction out of the amount established to be due and owing from the owner to the general
contractor. Curtis Partition, 2009 N.Y. Slip Op. 50272U, at *10 (citing Electric City Concrete,
100 A.D.2d at 4; Timothy Coffey Nursery/Landscape, Inc. v. Gatz, 304 A.D.2d 652, 653-54
(N.Y. App. Div. 2d Dep’t 2003)).
A subcontractor bears the burden of demonstrating that there is money due and owing to
the general contractor from the owner based on the primary contract. Timothy Coffey
Nursery/Landscape, Inc. v. Gatz, 304 A.D.2d at 654 (citations omitted). “If labor is performed
for, or materials furnished to, a contractor or subcontractor for an improvement, the lien shall not
10-08242-rdd Doc 40 Filed 08/03/11 Entered 08/03/11 10:37:37 Main Document
Pg 26 of 32
27
be for a sum greater than the sum earned and unpaid on the contract at the time of filing the
notice of lien, and any sum subsequently earned thereon.” N.Y. Lien Law § 4(1).
A lien becomes vested upon filing and subsequent failure to perform does not preclude or
reduce recovery. 104 Constr., Inc. v. R.T. Golf Assocs., L.P., 270 A.D.2d 817, 819 (N.Y. App.
Div. 4th Dep’t 2000) (citations omitted). A mechanic’s lien will not be defeated by the
subsequent abandonment of the project by the general contractor even though payments to third
parties in excess of the original contract price may be required by the owner to complete the
construction. Albert J. Bunce, Ltd. v. Fahey, 73 A.D.2d 632, 632 (N.Y. App. Div. 2d Dep’t
1979) (citations omitted).
At trial, Curtis presented little evidence, relying predominately on the evidence presented
by general contractor HRH. For the reasons set forth above, the Court concludes that Curtis is
entitled to payment from requisitions 14, 15 and 16 for the monies owed to Curtis under those
requisitions received and approved by NYU but denies its claim for requisition 17 and its
hardship claim. Because no amount due and owing will remain for Curtis after judgment is
entered in connection with this decision, Curtis’s request to foreclose on its mechanic’s lien is
denied.15 See C.B. Strain & Son, Inc. v. J. Baranello & Sons, 90 A.D.2d 924, 925 (N.Y. App.
Div. 3d Dep’t 1982) (“The rights of lienors are derivative of those of the general contractor and
are restricted to satisfaction out of the amount established to be due and owing from the owner to
the general contractor.”) (citations omitted).
15 Relatedly, the Court rejects NYU’s claim against Curtis for willfully exaggerating its mechanic’s lien. To prevail
on such a claim requires proof that the lienor deliberately and intentionally exaggerated the lien amount. Barden
& Robeson Corp. v. Czyz, 245 A.D.2d 599, 601 (N.Y. App. Div. 3d Dep’t 1997) (citing Pratt General Contractors
v. Trappey, 177 A.D.2d 566, 568 (N.Y. App. Div. 2d Dep’t 1991)). While it is true that Curtis’s allegations of
damages have been inconsistent and that Curtis partially waived its liens for the period ending March 31, 2005,
see Trial Ex. 46, the Court concludes that the evidence falls short of establishing deliberate and intentional
exaggeration, particularly given the uncertainties of the project at the time the lien was created in October of
2005.
10-08242-rdd Doc 40 Filed 08/03/11 Entered 08/03/11 10:37:37 Main Document
Pg 27 of 32
28
2. 	Applicability of Article 3-A
The Court concludes that the monies owed to Curtis under requisitions 14 through 16
should be paid by NYU directly to Curtis, rather than through HRH, pursuant to Article 3-A of
New York’s Lien Law (N.Y. Lien Law §§ 70 – 79-a). Article 3-A “create[s] trust funds out of
certain construction payments or funds to assure payment of subcontractors, suppliers, architects,
engineers, laborers, as well as specified taxes and expenses of construction.” Canron Corp. v.
City of New York, 89 N.Y.2d 147 (N.Y. 1996) (citation omitted). The purpose of the trust is to
“safeguard the rights of those working on construction projects by providing for the payment of
obligations incurred in performing the contract.” Kemper Ins. Cos. v State of New York, 70
A.D.3d 192, 196 (N.Y. App. Div. 3d Dep’t 2009) (quoting AMG Indus. v. A.J. Eckert Co., 279
A.D.2d 717, 719 (N.Y. App. Div. 3d Dep’t 2001)). With respect to trusts for which a contractor
is trustee, “trust claims” means claims arising at any time for payments for which the trustee is
authorized to use trust funds as provided in the Lien Law. N.Y. Lien Law § 71(3)(b).
According to the Lien Law, “every trust claim shall be deemed to be in existence from
the time of the making of the contract or the occurrence of the transaction out of which the claim
arises.” N.Y. Lien Law § 71(5). The trust res consists not only of funds already received, but
also of the right to receive funds in the future, including prospective payments that are contingent
upon the trustee’s future performance of its contractual obligations. Kemper Ins., 892 N.Y.S.2d
at 600 (citing N.Y. Lien Law § 70(1)(a); Canron, 89 N.Y.2d at 156). See also RLI Ins. Co. v.
N.Y. State DOL, 97 N.Y.2d 256, 262 (N.Y. 2002) (“As a matter of statutory construction and
under our precedents, even before funds are ‘due or earned,’ they become assets of an article 3-A
trust.”)
10-08242-rdd Doc 40 Filed 08/03/11 Entered 08/03/11 10:37:37 Main Document
Pg 28 of 32
29
A contractor does not have a sufficient beneficial interest in the moneys, due or to
become due from the owner under the contract, to give him a property right in them, except
insofar as there is a balance remaining after all subcontractors and other statutory beneficiaries
have been paid. Aquilino v. United States, 10 N.Y.2d 271, 282 (N.Y. 1961). 	Once an Article 3-
A trust comes into existence, its funds may not be diverted for non-trust purposes, and the trust
continues until all trust claims have been paid or discharged, or all assets have been applied for
trust purposes. RLI Ins., 97 N.Y.2d at 262-63 (citations omitted).
Here, the Court finds that Curtis met its burden to demonstrate that Curtis performed
under its subcontract and pursuant to requisitions 14, 15, and 16 that were received and approved
by NYU. The operation of Article 3-A of the Lien Law creates a trust to ensure payment for the
services rendered by Curtis as a subcontractor on the construction project.16 There does not
appear to be any dispute among the parties that Article 3-A applies to the monies owed to
subcontractor Curtis and, therefore, the monies owed to Curtis for these requisitions should be
paid directly to Curtis by NYU. 17
H. 	Third-Party Beneficiary and Indemnification
The Court rejects the two remaining claims in this case, both of which are asserted
against Curtis by NYU. In the first, NYU argues that Curtis is liable to NYU under an
indemnification provision for any failure by Curtis to proceed with and complete its work on the
construction project. Verified Answer, Counterclaims and Cross-Claim of Defendant NYU
Hospitals Center ¶¶ 35-36. In addition, NYU seeks recovery against Curtis as a third-party
16 NYU will pay Curtis directly for any monies owed to Curtis on these three requisitions and pay the remaining
balance owed on these requisitions to HRH.
17 This conclusion is supported by the fact that NYU is holding ten percentage retainers otherwise payable to Curtis
under its subcontract at article 10(h). See Trial Ex. 4, Subcontract § 10.1(h).
10-08242-rdd Doc 40 Filed 08/03/11 Entered 08/03/11 10:37:37 Main Document
Pg 29 of 32
30
beneficiary for Curtis’s breach of the Curtis subcontract, despite the fact that there is no contract
between NYU and Curtis. 18 See Berger Aff. ¶ 7; Egeberg Dep. 279:9-11. NYU argues that
owners of construction projects are considered intended third-party beneficiaries of the general
contractor’s subcontracts even when the identity of the third-party beneficiary is not specifically
set forth in the subcontract. See NYU Pre-Trial Memorandum of NYU Hospitals Center and
New York University 6 (citing Finch, Pruyn & Co. v. M. Wilson Control Servs., 239 A.D.2d
814, 815 (N.Y. App. Div. 3d Dep’t 1997)). However, NYU has not met its burden of proof with
respect to its indemnification and third-party beneficiary claims against Curtis. Neither the
indemnification provisions in the contracts nor any theory of implied indemnification can be
maintained against Curtis because NYU neither proved that it suffered grave injuries nor
established “active negligence” or “active fault” on the part of Curtis. See Potter v. M.A.
Bongiovanni, Inc., 271 A.D.2d 918, 919 (N.Y. App. Div. 3d Dep’t 2000) (discussing contractual
indemnification and common-law indemnity); Finch, Pruyn, 239 A.D.2d at 815-18 (discussing
third-party beneficiaries and “active negligence”); Kozerski v. Deer Run Homeowners Ass’n,
217 A.D.2d 841, 843 (N.Y. App. Div. 3d Dep’t 1995) (discussing implied indemnification and
“active fault”). See also Westbank Contr., Inc. v. Rondout Val. Cent. School Dist., 46 A.D.3d
1187, 1189 (N.Y. App. Div. 3d Dep’t 2007) (“The right to indemnification ‘arises out of a
contract which may be express or may be implied in law to prevent a result which is regarded as
18 The only contract to which Curtis is a party in connection with this project is the subcontract between Curtis and
HRH. See Curtis Partition, 2009 N.Y. Slip Op. 50272U, at *7; Trial Ex. 4. Indeed, the state court has already
ruled that Curtis could not assert a breach of contract claim against NYU without a contract between Curtis and
NYU: “Because there is no contract between NYU and Curtis, as a matter of law, NYU may not be held liable for
breach of contract . . . .” Curtis Partition, 2009 N.Y. Slip Op. 50272U, at *7. See also id. at *8 (“Curtis’s
argument ignores the express language in the governing agreements stating that none of HRH’s subcontracts with
its subcontractors shall create any contractual relationship between NYU and those subcontractors, ignores the
fact that NYU was not a party to the subcontract between HRH and Curtis, and misrepresents that HRH acted as
nothing more than an advisor on the Project.”). The state court also concluded that there is no privity of contract
between NYU and Curtis. Id. at *8-9.
10-08242-rdd Doc 40 Filed 08/03/11 Entered 08/03/11 10:37:37 Main Document
Pg 30 of 32
31
unjust or unsatisfactory.’”) (quoting Rosado v. Proctor & Schwartz, Inc., 66 N.Y.2d 21, 24 (N.Y.
1985)); State Facilities Dev. Corp. v. Kallman & McKinnell, Russo & Sonder, 121 A.D.2d 805,
806 (N.Y. App. Div. 3d Dep’t 1986) (“Indemnity involves an attempt to shift the entire loss from
one who is compelled to pay for a loss, without regard to his own fault, to another person who
should more properly bear responsibility for that loss.”) (quoting County of Westchester v.
Welton Becket Associates, 102 A.D.2d 34, 47 (N.Y. App. Div. 2d Dep’t 1984), affirmed, 66
N.Y.2d 642 (N.Y. 1985)).
I. 	Damages
The Construction Agreement explains how damages are to be calculated if NYU
terminates for convenience or cause. “In the case of such termination or deletion, the Contractor
shall be entitled to be reimbursed by the Owner for [c]osts of the [w]ork properly due and owing
to the Contractor under the terms of this Agreement for Work performed up to and including the
date of such termination or deletion . . . .” Trial Ex. 1, Construction Agreement § 17.4. Based
on the analysis set forth above, the Court determines that NYU terminated for convenience, not
based upon cause such as abandonment.19 Accordingly, section 17.4 of the Construction
Agreement entitles HRH to be reimbursed by NYU for the work described in requisitions 14
through 16, and NYU is not entitled to damages of its own. See 400 15th St., LLC v Promo-Pro,
Ltd., 2010 WL 3529466, 2010 N.Y. Misc. LEXIS 4339, 2010 N.Y. Slip Op. 51580U, at *6 (N.Y.
Sup. Ct. Sept. 10, 2010) (citations omitted); Fruin-Colnon Corp. v. Niagara Frontier Transp.
Authority, 180 A.D.2d 222, 233-34 (N.Y. App. Div. 4th Dep’t 1992).20 The amounts sought by
19 The mere fact that there is a termination for convenience clause does not mean that a party cannot be found to
have breached the contract. Matter of RSG Caulking & Waterproofing Inc. v. J.P. Morgan Chase & Co., 13
Misc.3d 1218A, 2006 N.Y. Slip Op. 51902U, at *8 (N.Y. Sup. Ct. 2006).
20 In the alternative, the Court finds that NYU breached the contract for failure to make timely payments and that
HRH is entitled to damages for such a breach once HRH sent its default letter of August 22, 2005.
10-08242-rdd Doc 40 Filed 08/03/11 Entered 08/03/11 10:37:37 Main Document
Pg 31 of 32
32
HRH on these three requisitions are $684,889, $800,874, and $486,194, respectively. Trial Exs.
129-131. The amounts awarded to HRH must be reduced, however, by the amounts that must be
directly paid by NYU to Curtis as a subcontractor pursuant to Article 3-A, which appear to be
$77,867, $18,000, and $180,352, respectively.21 Trial Ex. 129 p. 2; Trial Ex. 130 p. 2; Trial Ex.
131 p. 2. The damages awarded to HRH must also be reduced by the amounts requested by
subcontractors who were subsequently paid for returning to the project pursuant to later
agreements with replacement contractor Bovis.
CONCLUSION
As set forth above, the Court rules in favor of HRH and grants Curtis’s trust fund claims
in connection with requisitions 14 through 16. All other causes of action are denied. The parties
should submit an agreed upon order and judgment consistent with this decision. 22
August 2, 2011
New York, New York 	/s/ Sean H. Lane
THE HONORABLE SEAN H. LANE
UNITED STATES BANKRUPTCY JUDGE
21 NYU should also release its retainer to Curtis.
22 Neither NYU nor HRH discussed the calculation of interest at trial or in briefing. Curtis proposed an interest rate
of 9% pursuant to New York CPLR § 5004, but the Court will not address this issue unless the parties are unable
to agree upon an interest calculation in the proposed order and judgment to be submitted.
10-08242-rdd Doc 40 Filed 08/03/11 Entered 08/03/11 10:37:37 Main Document
Pg 32 of 32