In re: Brawner Builders

CourtListener 10866397MdctspecappMay 29, 2026

Full text

In the Matter of Brawner Builders, Inc., No. 1451, September Term, 2024, filed May 29,
2026. Opinion by Friedman, J.
HEADNOTES:
PUBLIC CONTRACTS — COMPENSATION
In an underrun scenario, a Variations in Estimated Quantities (VEQ) clause allows the
contractor to demand that the government equitably adjust the contract price if the
government procures so much less than the parties had expected that it increases the
contractor’s actual costs per unit.
PUBLIC CONTRACTS — EXTRA COSTS OR EXPENSES IN GENERAL
A contractor must satisfy a four-prong test to prove its entitlement to an equitable
adjustment under a VEQ clause in an underrun situation: (1) the government purchased
less than 75% of the estimated quantity of a contract item; (2) the actual cost per unit of
the item that the government purchased exceeds the contract cost per unit; (3) the actual
cost per unit of the item that the government purchased is greater than the per unit cost
would have been for units purchased absent the underrun; and (4) the underrun is the sole
reason that the actual cost per unit increased. Satisfaction of the first prong establishes the
underrun. The remaining three prongs together establish that the contractor’s actual costs
per unit increased as a result of the underrun.
PUBLIC CONTRACTS — EXTRA COSTS OR EXPENSES IN GENERAL
Where contractor’s calculation failed to mention contract costs per unit or the cost of units
purchased absent an underrun, contractor could not satisfy prongs (2) and (3) of the
four-prong test to establish entitlement to an equitable adjustment under the VEQ clause:
that its actual costs per unit exceeded these amounts.
PUBLIC CONTRACTS — EXTRA COSTS OR EXPENSES IN GENERAL
Contractor failed to satisfy prong (4) of the four-prong test to establish an equitable
adjustment under the VEQ clause, that the increased actual costs per unit were caused by
the underrun, because its increased actual costs were caused by its decision to buy things
that were excluded from payment under the contract.
Circuit Court for Baltimore County
Case No. C-03-CV-23-000136
REPORTED

IN THE APPELLATE COURT

OF MARYLAND

No. 1451

September Term, 2024

______________________________________

IN THE MATTER OF BRAWNER
BUILDERS, INC.

______________________________________
Friedman,
Shaw,
Kehoe, Christopher B.
(Senior Judge, Specially Assigned),

JJ.
______________________________________
Opinion by Friedman, J.
______________________________________

Filed: May 29, 2026

Pursuant to the Maryland Uniform Electronic Legal
Materials Act (§§ 10-1601 et seq. of the State
Government Article) this document is authentic.

2026.05.29
'00'04- 15:01:33
Gregory Hilton, Clerk
When the State government enters into a procurement contract, it may provide

estimates of the items that it will purchase from the contractor. If it does, it is required by

law to insert a Variations in Estimated Quantities (VEQ) clause into the contract. The VEQ

clause provides a narrow remedy to a narrow problem: if the government purchases so

much less of an item that the cost per unit increases, the VEQ clause allows the contractor

to demand an equitable adjustment to the contract price for its increased actual costs. This

clause is intended to provide some security for the contractor, not a mechanism to get more

money for a bid that, in hindsight, turns out to have been unwise.

FACTS

Appellee, Brawner Builders, Inc. (Brawner), entered into a procurement contract

with appellant, the State Highway Administration (SHA), to provide labor and equipment,

such as traffic signs and vehicles, for highway maintenance. The contract provided

estimated total quantities and payment for the labor and equipment that SHA expected to

purchase from Brawner throughout the contract’s two-year term. SHA agreed to pay

Brawner only for those quantities that it ultimately purchased from Brawner. SHA would

not pay Brawner for things that Brawner bought and let sit idle.

The contract also included a VEQ clause:

Where the quantity of a pay item in this Contract is an
estimated quantity and where the actual quantity of such pay
item varies more than 25 percent above or below the estimated
quantity stated in this Contract, an equitable adjustment in the
Contract price shall be made upon demand of either party. The
equitable adjustment shall be based upon any increase or
decrease in costs due solely to the variation above 125 percent
or below 75 percent of the estimated quantity.1

This VEQ clause allows the contractor to demand an equitable adjustment to the contract

price if the government purchases less than 75% of the estimated contract quantity (an

underrun), thereby increasing the contractor’s actual costs per unit. The same analysis

applies to the government’s demand for an equitable adjustment when it purchases more

than 125% of the estimated contract quantity (an overrun), thereby decreasing the

contractor’s actual costs per unit.

At the end of the two-year term, Brawner invoked the VEQ clause to demand an

equitable adjustment from SHA. Brawner claimed that SHA had purchased less than 75%

of the estimated quantities of various contract items, and that these underruns had increased

Brawner’s actual costs per unit. SHA denied Brawner’s demand. It asserted that Brawner

had not established its claim that its actual costs per unit had increased.

Brawner appealed from SHA’s denial of its demand to the Maryland State Board of

Contract Appeals (MSBCA). Brawner revised the specific amount that it claimed multiple

times, but settled on a claim for $1,806,493.63.2 The MSBCA denied Brawner’s appeal. It

1
Md. Code, State Fin. & Procurement § 13-218(a)(3) requires that procurement
contracts include a clause “covering … variations that occur between estimated and actual
quantities of work in a procurement contract.” The implementing COMAR regulation
provides the required language for the VEQ clause in all “construction contracts that
contain estimated quantity items.” COMAR 21.07.02.03. The required language was
inserted into the parties’ contract.
2
Brawner also asserted a second and third claim, which are discussed below.
The second claim was for $1,784,300.93, which was based on a formula set forth in
TPH Indus., Inc., MSBCA No. 2311 (2003). The MSBCA rejected Brawner’s second claim
because TPH does not apply to contracts with a VEQ clause. The circuit court affirmed

2
determined that, although Brawner had established that there was an underrun, Brawner

had failed to establish that its actual costs per unit increased as the VEQ clause requires.

Brawner filed a petition for review of the MSBCA’s decision in the Circuit Court

for Baltimore County. The circuit court determined that Brawner established that the

underrun caused its actual costs per unit to increase. The circuit court reversed the decision

of the MSBCA and remanded the case to the MSBCA with instructions to award Brawner

an equitable adjustment. SHA noted this timely appeal.

that part of the MSBCA’s decision. Brawner did not appeal from that ruling, so it is not
before us.
Brawner asserted yet a third claim after the MSBCA held a hearing on Brawner’s
claims. Brawner claimed that because SHA had “self-performed” the contract, the VEQ
clause is “set aside” and Brawner is entitled to the unpaid balance of the contract:
$2,696,571.65. The MSBCA found that Brawner had failed to establish that SHA
“self-performed” Brawner’s obligations. The circuit court reversed that part of the
MSBCA’s decision. We reverse the circuit court and reinstate the MSBCA’s determination
that Brawner cannot recover under this claim. Brawner never asserted it to SHA, so
Brawner failed to preserve this claim. See COMAR 21.10.04.04 (claim must be filed with
the MSBCA within 30 days of the denial of a claim by an agency such as SHA). We cannot
reverse the MSBCA for failing to award relief based on an unpreserved claim. Even if we
did, this claim is not recognized under Maryland law and relies on a misinterpretation of
federal law. See Appeal of Maya Transit Co., ASBCA No. 20186, 75 BCA ⁋ 11552 (1975)
(holding that, if the government performs the contractor’s obligations, the contractor is
only entitled to compensation to the extent of the government’s performance). Moreover,
as the MSBCA found, the record does not support Brawner’s assertion that SHA
“self‑performed.” All that the record reveals is vague testimony that SHA, at some
unknown time, completed some unknown amount of the work that Brawner promised to
perform. That is insufficient to substantiate Brawner’s sweeping claim.

3
ANALYSIS

In its appeal, SHA contends that the MSBCA was correct in concluding that

Brawner failed to prove its entitlement to an equitable adjustment under the VEQ clause.

We agree.

When we review a decision of the MSBCA, we look past the decision of the circuit

court to evaluate the MSBCA’s decision directly. People’s Counsel for Balt. Cnty. v.

Surina, 400 Md. 662, 681 (2007). We review the MSBCA’s legal conclusions without

deference and will affirm its decision when supported by substantial evidence. Md.

Aviation Admin. v. Noland, 386 Md. 556, 571 (2005).

The VEQ clause provides a specific remedy for a specific problem. In an underrun

scenario, it allows the contractor to demand that the government equitably adjust the

contract price if the government procures so much less than the parties had expected that

it increases the contractor’s actual costs per unit.3 Genstar Stone Paving Prods. Co. v. State

Highway Admin., 94 Md. App. 594, 612-13 (1993) (explaining that a VEQ clause entitles

the contractor to “an adjustment to the contract unit price for the [underrun] in an amount

equal to the difference in actual unit costs due solely to the variation”). It must be

understood exclusively in this narrow context. The VEQ clause does not apply simply

because the government procures less than the contractor expected. The underrun must

cause the actual costs per unit to increase. When the VEQ clause does apply, the equitable

adjustment is limited to the increased actual costs. See id. The VEQ clause does not allow

3
See infra note 4.

4
the contractor to obtain a windfall, such as the unpaid balance of the contract price. Id. at

612.

In Genstar, this Court established a four-prong test for an underrun situation that a

contractor must satisfy to prove their entitlement to an equitable adjustment under a VEQ

clause: (1) the government purchased less than 75% of the estimated quantity of a contract

item; (2) the actual cost per unit of the item that the government purchased exceeds the

contract cost per unit; (3) the actual cost per unit of the item that the government purchased

is greater than the per unit cost would have been for units purchased absent the underrun;

and (4) the underrun is the sole reason that the actual cost per unit increased.4 See id. at

613. Satisfaction of the first prong establishes the underrun. The remaining three prongs

together establish that the contractor’s actual costs per unit increased as a result of the

underrun. Id. at 612-13.

The MSBCA determined that, based on Brawner’s calculations, SHA had purchased

less than 75% of the estimated contract quantities of 13 items. This evidence satisfied the

first prong of Genstar: the existence of an underrun. SHA concedes that this determination

was correct.

Brawner also claimed to the MSBCA that its calculations satisfied the remaining

three prongs of Genstar, and that, as a result, the underrun caused its actual costs per unit

to increase. It described its calculation as follows:

4
The same test applies in an overrun situation. The only differences are that the
numbers change and that the government proves that costs decreased, rather than increased.
See Genstar, 94 Md. App. at 613.

5
[1] Brawner calculated its original unit cost for each pay item.

[2] Brawner multiplied its original unit cost for each pay item by the
Contract Quantity to obtain its total cost to perform each Contract pay
item.

[3] Brawner divided the total cost of each contract pay item by the actual
quantity used by SHA to determine the adjusted unit cost for each pay
item.

[4] Brawner subtracted the original unit cost for each pay item from the
adjusted unit cost of each pay item to obtain the increase in unit cost
to Brawner.

[5] Brawner multiplied [the] increase in unit cost by the actual pay item
quantities used by SHA to establish the increase[d] cost to perform.

The MSBCA concluded that Brawner failed to satisfy the remaining three prongs of

Genstar, and thus failed to prove that its costs increased because of the underrun.

The MSBCA determined that this calculation failed to satisfy prong (2), that the

actual costs per unit exceed the contract costs per unit, and prong (3), that the actual costs

per unit exceed the costs of units purchased absent an underrun. We agree with the

MSBCA’s conclusion. Brawner’s calculation does not mention contract costs per unit or

the cost of units purchased absent an underrun. Without these amounts, Brawner’s

calculation cannot satisfy prongs (2) and (3) and show that its actual costs per unit exceeded

these amounts. See id. at 613.

Furthermore, the MSBCA determined that Brawner failed to satisfy prong (4), that

the underrun was the sole reason that the actual costs per unit increased. The MSBCA

concluded that Brawner’s claimed “increased actual costs per unit” were caused not by the

underrun, but by Brawner’s decision to buy more items than SHA purchased and to let

6
them sit idle. We agree with the MSBCA. Brawner’s complex calculation obscures the fact

that its “increased actual costs” were not caused by the underrun. A simplified version of

Brawner’s calculation makes this clear:

(1) Brawner calculated what it cost to buy every item in the contract,
including those that SHA never purchased and thus sat idle. Brawner
calls this amount its “total cost to perform,” or its actual costs in the
language of the VEQ clause.

(2) Brawner reduced these “actual costs” by SHA’s payment to Brawner
for the units that it purchased. This leaves only its idle costs. Brawner
calls its idle costs its “increased cost to perform,” or its increased
actual costs in the language of the VEQ clause, and claims entitlement
to the idle costs as an equitable adjustment.

This simplified calculation demonstrates that Brawner’s purported increased actual costs

were its costs to buy more items than SHA purchased and to let them sit idle. The contract

provided that SHA would not pay Brawner for idle time. These costs are therefore not

caused by an underrun in estimated contract quantities, but by Brawner’s decision to buy

things that were excluded from payment under the contract. Brawner failed to satisfy prong

(4) of Genstar, that the increased actual costs per unit were caused by the underrun. See id.

By failing to satisfy the last three prongs of Genstar, Brawner failed to establish the

only basis for an equitable adjustment under the VEQ clause—that its actual costs per unit

increased as a result of the underrun. Instead, Brawner demands payment for a bid that

proved unwise in hindsight. That isn’t the function of the VEQ clause. We conclude that

the MSBCA’s decision that Brawner failed to establish entitlement to an equitable

adjustment under the VEQ clause was legally correct and was supported by substantial

7
evidence. We reverse the decision of the circuit court and remand with instructions to

reinstate the decision of the MSBCA.

JUDGMENT OF THE CIRCUIT COURT
FOR BALTIMORE COUNTY IS
REVERSED. CASE REMANDED TO THE
CIRCUIT COURT WITH INSTRUCTIONS
TO REINSTATE THE DECISION OF THE
BOARD OF CONTRACT APPEALS.
COSTS TO BE PAID BY APPELLEE.

8

Continue your research in ChatGPT or Claude

Connect Omnilex to search the legal corpus from your AI assistant.