Pennsylvania Act 2004-40 — CAPITAL BUDGET PROJECT ITEMIZATION ACT OF 2003-2004 - ENACTMENT

act-2004-0-402004 Pa. Act 40Law

Act text
CAPITAL BUDGET PROJECT ITEMIZATION ACT OF 2003-2004 - ENACTMENT
Act of Jun. 22, 2004, P.L. 257, No. 40Cl. 86

AN ACT

Providing for the capital budget for the fiscal year 2003-2004, itemizing public improvement projects, furniture and equipment projects, transportation assistance projects, redevelopment assistance capital projects, flood control projects, Keystone Recreation, Park and Conservation Fund projects, Environmental Stewardship Fund projects, Pennsylvania Fish and Boat Commission projects, The State Stores Fund current revenue projects, public highway projects, Motor License Fund projects, Manufacturer's Fund projects and State forestry bridge projects to be constructed or acquired or assisted by the Department of General Services, the Department of Community and Economic Development, the Department of Conservation and Natural Resources, the Department of Environmental Protection, the Pennsylvania Fish and Boat Commission, Pennsylvania Game Commission and the Department of Transportation, together with their estimated financial costs; authorizing the incurring of debt without the approval of the electors for the purpose of financing the projects to be constructed or acquired or assisted by the Department of General Services, the Department of Community and Economic Development, the Department of Conservation and Natural Resources, the Department of Environmental Protection, the Department of Transportation, the Pennsylvania Fish and Boat Commission or the Pennsylvania Game Commission; stating the estimated useful life of the projects; making appropriations; and making related repeals.

The General Assembly of the Commonwealth of Pennsylvania hereby enacts as follows:

Section 1. Short title.

This act shall be known and may be cited as the Capital Budget Project Itemization Act of 2003-2004.

Section 2. Total authorizations.

(a) Public improvements.--The total authorization for the additional capital projects in the category of public improvement projects itemized in section 3 and to be acquired or constructed by the Department of General Services, its successors or assigns and to be financed by the incurring of debt shall be $3,951,146,000.

(b) Furniture and equipment.--The total authorization for the additional capital projects in the category of public improvement projects consisting of the acquisition of original movable furniture and equipment to complete public improvement projects itemized in section 4 and to be acquired by the Department of General Services, its successors or assigns and to be financed by the incurring of debt shall be $135,024,000.

(c) Transportation assistance.--The total authorization for the capital projects in the category of transportation assistance projects itemized in section 5 with respect to which an interest is to be acquired in or constructed by the Department of Transportation, its successors or assigns and to be financed by the incurring of debt shall be $1,772,370,000.

(d) Redevelopment assistance.--The total authorization for the additional capital projects in the category of redevelopment assistance and redevelopment assistance capital projects itemized in section 6 for capital grants by the Department of Community and Economic Development, its successors or assigns and to be financed by the incurring of debt shall be $6,861,226,000.

(e) Flood control.--The total authorization for the capital projects in the category of flood control projects itemized in section 7 and to be constructed by the Department of Environmental Protection, its successors or assigns and to be financed by the incurring of debt shall be $42,944,000.

(f) Keystone Recreation, Park and Conservation Fund projects.--The total authorization for the capital projects in the category of public improvement projects itemized in section 8 and to be constructed by the Department of Conservation and Natural Resources, its successors or assigns and to be financed from current revenues in the Keystone Recreation, Park and Conservation Fund shall be $40,887,000.

(g) Environmental Stewardship Fund projects.--The total authorization for the capital projects in the category of public improvement projects itemized in section 9 and to be constructed by the Department of Conservation and Natural Resources, its successors or assigns and to be financed from current revenues in the Environmental Stewardship Fund shall be $80,555,000.

(h) Fish and Boat Fund projects.--The total authorization for the capital projects in the category of public improvement projects itemized in section 10 to be acquired or developed by the Pennsylvania Fish and Boat Commission and to be financed by the incurring of debt or by current revenues of the Fish Fund and the Boat Fund pursuant to executive authorization shall be $44,675,000.

(i) Game Commission Fund projects.--The total authorization for the capital projects in the category of public improvement projects itemized in section 11 and to be acquired or developed by the Pennsylvania Game Commission and to be financed from current revenues of the Game Fund pursuant to executive authorization shall be $0,000,000.

(j) General Fund current revenue projects.--The total authorization for the capital projects in the category of public improvement projects itemized in section 12 and to be developed or constructed by the Department of General Services, its successors or assigns and to be financed from current revenues in the General Fund shall be $4,950,000.

(k) Motor License Fund current revenue projects.--The total authorization for the capital projects in the category of public improvement projects itemized in section 13 and to be constructed by the Department of General Services, its successors or assigns and to be financed from current revenues in the Motor License Fund shall be $21,070,000.

(l) Manufacturing Fund current revenue projects.--The total authorization for the capital projects in the category of public improvement projects itemized in section 14 and to be constructed by the Department of General Services, its successors or assigns and to be financed from current revenues in the Manufacturing Fund shall be $0,000,000.

(m) State Stores Fund current revenue projects.--The total authorization for the capital projects in the category of public improvement projects itemized in section 15 and to be developed by the Department of General Services, its successors or assigns for the Pennsylvania Liquor Control Board and to be financed from the current revenues of the State Stores Fund shall be $00,000,000.

(n) Public highway projects.--The total authorization for the capital projects in the category of public highway projects itemized in section 16 and to be constructed by the Department of Transportation, its successors or assigns and to be financed from current revenues of the Motor License Fund shall be $209,425,000.

(o) State forestry bridge projects.--The total authorization for the capital projects itemized in section 16.1 to be constructed by the Department of Conservation and Natural Resources, its successors or assigns and to be financed by oil company franchise tax revenues pursuant to 75 Pa.C.S. § 9502(a)(2)(iv) (relating to imposition of tax) shall be $10,166,000.

Section 3. Itemization of public improvement projects.

Additional capital projects in the category of public improvement projects to be constructed or acquired by the Department of General Services, its successors or assigns and to be financed by the incurring of debt are hereby itemized, together with their respective estimated financial costs, as follows:

ProjectTotal Project Allocation
(1) Department of Agriculture
(i) Pennsylvania Animal Diagnostic Laboratory System
(A) Renovation and/or addition of existing facility in Harrisburg to provide for biosecurity level 3 capabilities4,333,000

(Base Project Allocation - $3,500,000)

(Design and Contingencies - $833,000)

(B) Renovation and/or addition of existing facility in New Bolton to provide for biosecurity level 3 capabilities4,333,000

(Base Project Allocation - $3,500,000)

(Design and Contingencies - $833,000)

(C) Renovation and/or addition of existing facility at The Pennsylvania State University to provide for biosecurity level 3 capabilities4,333,000

(Base Project Allocation - $3,500,000)

(Design and Contingencies - $833,000)

(ii) New Bolton Center
(A) Design and construction of new barns and clinical facilities, renovation and rehabilitation of existing clinic and consolidation of laboratory facilities30,000,000
(B) Veterinary hospital improvements and renovations necessary for infection control and to prevent facility contamination1,500,000
(iii) Department Headquarters
(A) Electrical and HVAC renovations3,000,000

(Base Project Allocation - $2,700,000)

(Design and Contingencies - $300,000)

(B) Upgrade to elevators500,000

(Base Project Allocation - $450,000)

(Design and Contingencies - $50,000)

(iv) Produce Distribution Center
(A) Construction of a Pennsylvania Produce Co-op Distribution Center5,510,000

(Base Project Allocation - $4,283,000)

(Land Allocation - $125,000)

(Design and Contingencies - $1,102,000)

(v) Laboratory
(A) Construction of a new plant industry laboratory10,000,000

(Base Project Allocation - $9,000,000)

(Design and Contingencies - $1,000,000)

(2) Department of Community and Economic Development
(i) Philadelphia County
(A) New sidewalks, benches and other pedestrian and landscape amenities for the entire length of the Benjamin Franklin Parkway between 16th Street and Eakins Oval3,000,000
(B) Streetscape and landscape enhancements for outer park areas in Logan Square1,000,000
(C) Streetscape improvements along the Benjamin Franklin Parkway from Logan Square to Eakins Oval to relocate curb lanes providing additional bicycle and pedestrian paths2,000,000
(D) Reconstruct Eakins Oval to improve traffic flow, create safer pedestrian crossings to Art Museum and to the new Schuylkill River Park and provide new recreational and athletic facilities for adjacent communities20,000,000
(E) Improvements to Pennsylvania Avenue that will reduce traffic accidents, provide safer pedestrian crossings to recreational and cultural facilities and add new roadway lighting4,500,000
(F) Spring Garden District, for streetscaping and lighting10,000,000
(3) Department of Conservation and Natural Resources
(i) Bald Eagle State Park
(A) Construct environmental interpretive complex2,000,000

(Base Project Allocation - $1,660,000)

(Design and Contingencies - $340,000)

(B) Construct family campground2,000,000
(ii) Benjamin Rush State Park
(A) Develop park2,170,000

(Base Project Allocation - $1,953,000)

(Design and Contingencies - $217,000)

(B) Additional funds for DGS 160-1, Phase II, park development2,000,000
(iii) Blue Knob State Park
(A) Rehabilitation of facilities1,008,000

(Base Project Allocation - $907,000)

(Design and Contingencies - $101,000)

(iv) Cook Forest State Park
(A) Develop park1,142,000

(Base Project Allocation - $1,028,000)

(Design and Contingencies - $114,000)

(v) Delaware Canal State Park
(A) Canal dredging2,000,000

(Base Project Allocation - $1,800,000)

(Design and Contingencies - $200,000)

(vi) Forest District 10
(A) Refurbish Hyner View Road, Phases 1 and 22,000,000

(Base Project Allocation - $1,800,000)

(Design and Contingencies - $200,000)

(vii) Lackawanna State Park
(A) Lake dredging and removal of silt1,250,000
(viii) Little Buffalo State Park
(A) Lake dredging and removal of silt750,000
(ix) Lehigh Gorge State Park
(A) Construct trail and interpretive facilities3,500,000

(Base Project Allocation - $3,150,000)

(Design and Contingencies - $350,000)

(x) Nockamixon State Park
(A) Construct campground4,000,000
(xi) Norristown Farm Park
(A) Rehabilitate farm park building1,000,000

(Base Project Allocation - $830,000)

(Design and Contingencies - $170,000)

(xii) Pine Grove Furnace State Park
(A) Lake dredging and removal of silt750,000
(xiii) Poe Valley/Poe Paddy State Park
(A) Campground rehabilitation922,000

(Base Project Allocation - $830,000)

(Design and Contingencies - $92,000)

(xiv) Point State Park
(A) Phase I of park capital development, including design, engineering and construction for trail and park improvements, riverfront connections to the Eliza Furnace Trail and to the David L. Lawrence Convention Center, which may include a visitors center and land acquisition for park expansion35,000,000
(xv) Presque Isle State Park
(A) Beach nourishment and rehabilitation8,000,000
(xvi) Ridley Creek State Park
(A) Restoration and rehabilitation of historically significant Environmental Living Demonstration Center and associated outbuildings, including, but not limited to, window and door replacement, HVAC and electrical system upgrades, installation of ADA facilities and reconstruction of pond and wetlands504,000

(Base Project Allocation - $420,000)

(Design and Contingencies - $84,000)

(xvii) Ryerson Station State Park
(A) Lake dredging1,000,000
(B) Repair and rehabilitation of dam and spillway750,000
(C) Rehabilitation of park maintenance facility and equipment storage facility650,000
(xviii) Sinnemahoning State Park
(A) Development of visitors facility3,500,000
(xix) Whipple Dam State Park
(A) Lake dredging and removal of silt2,250,000
(xx) Allegheny County
(A) Alle-Kiski Rails-to-Trails Project to expand existing rail trails along unused right-of-way on both sides of Allegheny and Kiskiminetas Rivers so that a continuous trail is established from Pittsburgh through the Alle-Kiski Region15,000,000
(xxi) Bucks County
(A) Restoration of Delaware Canal in Tullytown Borough500,000
(xxii) Cameron County
(A) Forest District 9, demolition of existing structures and site restoration at Quehanna Reactor Building Site4,000,000

(Base Project Allocation - $3,200,000)

(Design and Contingencies - $800,000)

(xxiii) Clearfield County
(A) Acquisition and construction of Visitors Gateway Center proximate to Interstate 805,000,000
(xxiv) Elk and Clearfield Counties
(A) Construction of a regional visitor center as portal to the Lumber Heritage Region4,000,000
(xxv) Elk County
(A) Acquisition, construction and rehabilitation of the Elk Viewing Center in Benezette Township2,500,000
(xxvi) McKean County
(A) Kinzua Bridge State Park, construction of a new office/visitor center, maintenance center, roads, trails, parking lots, water and sewage systems, clearing and grubbing of debris field, fencing of debris field, rehabilitation of remaining bridge towers and related site work7,000,000

(Base Project Allocation - $6,300,000)

(Design and Contingencies - $700,000)

(xxvii) Forest District 12
(A) Replacement of two bridges and relocation of two miles of forestry road located in McHenry Township, Lycoming County1,000,000
(xxviii) Archbald Regional Park
(A) Site development, infrastructure improvements and new construction1,470,000
(4) Department of Corrections
(i) State Correctional Institution at Cambridge Springs
(A) Construct new warehouse4,430,000

(Base Project Allocation - $3,544,000)

(Design and Contingencies - $886,000)

(ii) State Correctional Institution at Camp Hill
(A) Replacement of water main450,000

(Base Project Allocation - $375,000)

(Design and Contingencies - $75,000)

(B) Renovate kitchen and staff dining area5,880,000

(Base Project Allocation - $5,292,000)

(Design and Contingencies - $588,000)

(iii) State Correctional Institution at Chester
(A) Renovate control center1,210,000

(Base Project Allocation - $1,089,000)

(Design and Contingencies - $121,000)

(iv) State Correctional Institution at Coal Township
(A) Replacement of hot/chilled water loop system8,836,000

(Base Project Allocation - $7,072,000)

(Design and Contingencies - $1,764,000)

(v) State Correctional Institution at Cresson
(A) Install new and upgrade existing fire alarms4,200,000

(Base Project Allocation - $3,500,000)

(Design and Contingencies - $700,000)

(vi) State Correctional Institution at Dallas
(A) Life safety code4,104,000

(Base Project Allocation - $3,420,000)

(Design and Contingencies - $684,000)

(vii) State Correctional Institution at Laurel Highlands
(A) Construction of a medium/close security housing unit988,000

(Base Project Allocation - $823,000)

(Design and Contingencies - $165,000)

(B) Construction of new restricted housing unit702,000

(Base Project Allocation - $632,000)

(Design and Contingencies - $70,000)

(C) Boiler plant renovations and upgrades3,500,000
(viii) State Correctional Institution at Smithfield
(A) Construction of a new restricted housing unit660,000
(B) Renovation of boiler plant1,925,000

(Base Project Allocation - $1,540,000)

(Design and Contingencies - $385,000)

(ix) State Correctional Institution at Somerset
(A) Construction of a security tower1,214,000

(Base Project Allocation - $971,000)

(Design and Contingencies - $243,000)

(x) State Correctional Institution at Rockview
(A) Institution electrical upgrade including replacing existing service with new generators, new cables, switch gear and transformers7,540,000
(B) Upgrade reservoir to meet dam safety regulations482,000

(Base Project Allocation - $434,000)

(Design and Contingencies - $48,000)

(5) Department of Education
(i) Clearfield County
(A) Design and construction of a new health sciences building to include laboratories, classrooms, clinical facilities and multipurpose rooms15,000,000
(B) Design and construction of classrooms and laboratories for programs in engineering technologies and computers and for multipurpose rooms15,000,000
(C) Acquisition and improvements of existing building or buildings for classrooms and small business incubator3,000,000
(ii) Lincoln University
(A) Renovation of Wright Hall classroom and laboratories6,000,000

(Base Project Allocation - $5,000,000)

(Design and Contingencies - $1,000,000)

(B) Renovations, which include fire/life safety system installations, to the Lincoln University Center for Graduate and Continuing Education Building6,000,000
(C) Renovations, which include ADA accessibility upgrades, to the Student Union and Services Building8,000,000
(D) Major renovations to the Langston Hughes Memorial Library6,000,000
(E) Repairs and renovations of Thurgood Marshall Living-Learning Center8,000,000
(F) Repairs and renovations of John Miller Dickey Hall2,500,000
(G) Repairs and renovations of Lincoln Hall2,900,000
(H) Repairs and renovations of Vail Building2,700,000
(I) Repairs and renovations of Amos Hall2,500,000
(J) Repairs and renovations of President's House1,200,000
(K) Repairs and renovations of Azikiwe-Nkrumah Hall1,000,000
(L) Repairs and renovations of Lincoln House600,000
(M) Repairs and renovations of Cresson Hall2,500,000
(N) Repairs and renovations of maintenance storage facility1,500,000
(O) Repairs and renovations of residence facility1,000,000
(P) Repairs and renovations of Guest House Facility100,000
(Q) Construction of new International Cultural Center19,000,000
(R) Construction of new 125,000-square-foot Science and General Classroom High Technology Building31,000,000
(S) Renovation of University Hall3,000,000
(T) Construction of international cultural center20,000,000

(Base Project Allocation - $16,667,000)

(Design and Contingencies - $3,333,000)

(iii) The Pennsylvania State University
(A) Renovation of Swift Hall at DuBois Campus4,250,000

(Base Project Allocation - $3,542,000)

(Design and Contingencies - $708,000)

(B) Renovation of McAllister Building at University Park Campus12,000,000
(C) Infrastructure improvements at University Park Campus40,000,000
(D) Renovation of the Ferguson Building at University Park Campus8,000,000
(E) Library Depository at University Park Campus10,000,000
(F) Delaware Administration and Classroom Building at Delaware Campus6,000,000
(G) Infrastructure improvements at Erie Campus2,000,000
(H) Addition and renovation to Henderson Building at University Park Campus25,000,000
(I) Renovation of Borland Laboratory at University Park15,000,000
(J) Renovation of Chandlee Laboratory at University Park21,000,000
(K) Land acquisition and reconstruction of 1912 Building at Schuylkill Campus4,000,000
(L) Development and construction of a hydrogen fueling station2,110,000

(Base Project Allocation - $110,000)

(Design and Contingencies - $2,000,000)

(M) Upgrade telecommunications and data infrastructure10,000,000

(Base Project Allocation - $10,000,000)

(iv) University of Pittsburgh
(A) Chevron Science Center ventilation upgrade12,900,000
(B) Additional funds for DGS 1103-67, Hillman Library renovation17,600,000
(C) Benedum Hall addition30,000,000
(D) Construction of upper campus boiler plant25,000,000
(E) Upgrade and deferred maintenance, Phase III (campuswide)20,000,000
(F) Upgrade and deferred maintenance, Phase IV (campuswide)20,000,000
(G) Campuswide programmatic renovations9,000,000
(H) Construction of a Bio-Sciences Medical Tower at the University of Pittsburgh Medical Center10,000,000
(I) Acquisition, design, planning, renovations and construction of a new Transplant Center of Excellence20,000,000
(J) Additional funds for DGS 1103-69, ventilation fume hood upgrade, Chevron Science Center2,500,000
(K) University of Pittsburgh Medical Center - Braddock, construction and renovations for hospital expansion project2,975,000
(v) Scranton School for the Deaf
(A) Cabling infrastructure improvement132,000

(Base Project Allocation - $115,000)

(Design and Contingencies - $17,000)

(B) Campus safety improvements121,000

(Base Project Allocation - $105,000)

(Design and Contingencies - $16,000)

(C) Campus paving project302,000

(Base Project Allocation - $263,000)

(Design and Contingencies - $39,000)

(D) Cabling infrastructure improvement137,000

(Base Project Allocation - $123,000)

(Design and Contingencies - $14,000)

(E) Campus safety improvements5,100,000

(Base Project Allocation - $4,250,000)

(Design and Contingencies - $850,000)

(vi) Thaddeus Stevens College of Technology
(A) Renovate Mellor Building7,000,000

(Base Project Allocation - $5,800,000)

(Design and Contingencies - $1,200,000)

(B) Asbestos removal723,000

(Base Project Allocation - $651,000)

(Design and Contingencies - $72,000)

(C) Expand dining hall and kitchen5,750,000

(Base Project Allocation - $5,000,000)

(Design and Contingencies - $750,000)

(D) Construct second floor to the Hartzell Building3,200,000

(Base Project Allocation - $2,000,000)

(Design and Contingencies - $1,200,000)

(E) Expand Vocational Education Building750,000

(Base Project Allocation - $675,000)

(Design and Contingencies - $75,000)

(vii) Temple University
(A) Fire safety project, Phase III sprinkler installation5,048,000
(B) Paley Library renovation and expansion60,000,000
(C) Renovation of existing facilities to consolidate instructional spaces for Tyler Main Campus programs3,492,000
(D) Exterior improvements on Mini-Arts Campus to create an Arts Walk6,600,000
(E) Construct state-of-art computer lab in Bell Building16,200,000
(F) Liacouras Walk reconstruction, including underground water main replacement3,960,000
(G) Various buildings at Main, HSC and Ambler, major and interior systems rehabilitation65,000,000
(H) Addition to Presser Hall for School of Music5,688,000
(I) Construction of welcome center/admissions office6,300,000
(J) Design and construction of Mini-Arts Campus primarily for the arts at the Main Campus. This project shall be construed as a supplement to the project authorized in section 3(5)(vi)(B) of the act of October 30, 2002 (P.L.891, No.131), known as the Capital Budget Project Itemization Act of 2001-2002.15,000,000
(K) Design and construction for restoration of the Historic Baptist Temple on Main Campus. This project shall be construed as a supplement to the project authorized in section 3(5)(vi)(N) of the act of October 30, 2002 (P.L.891, No.131), known as the Capital Budget Project Itemization Act of 2001-2002.2,011,000
(viii) Community College of Allegheny County
(A) Science facility upgrades15,700,000

(Base Project Allocation - $14,130,000)

(Design and Contingencies - $1,570,000)

(B) Acquisition and renovation of Siemens property5,300,000

(Base Project Allocation - $4,770,000)

(Design and Contingencies - $530,000)

(C) North Campus, renovation and replacement of classrooms, including computer and technology upgrades, improvement of restroom facilities, repair of elevator controls, repair and renovation of the health center and repaving of main driveway400,000
(D) North Campus, facility upgrades and improvements581,000
(E) Science Building, Allegheny Campus, renovation and construction of new building24,500,000
(F) Siemens Building, Airport West Corridor, renovation and rehabilitation of old Siemens Building for classroom and workforce purposes8,000,000
(G) Information technology upgrades, all campuses7,000,000
(H) Acquisition of building for the replacement of three leased facilities4,000,000
(I) Construction of new building for the purpose of consolidating the allied health programs8,250,000
(J) Life safety code improvements, all campuses6,800,000
(K) Upgrade of telecommunications infrastructure, server clusters and high-speed fiber network408,000
(L) Upgrade to campus cabling and wiring, electronics and associated hardware to deploy high-speed network to the desktop3,144,000
(ix) Community College of Beaver County
(A) Campus improvements5,000,000

(Base Project Allocation - $4,500,000)

(Design and Contingencies - $500,000)

(B) Replacement of radar lab simulator153,000
(C) Replacement of radar tower simulator425,000
(D) Upgrade classroom instructional hardware and software for the Jenzabar nontraditional module and the installation of a parking gate for the allied health facility205,000
(x) Reading Area Community College
(A) Design and construction of advanced technology and police center23,600,000

(Base Project Allocation - $21,240,000)

(Design and Contingencies - $2,360,000)

(B) Construction of a new training and technology center11,800,000
(C) Acquisition, renovation and improvement of two buildings for use as a testing center, classroom and office space1,500,000
(D) Building and site improvements associated with the 2004-2005 Capital Plan215,000
(E) Technology and Oritzky projects826,000
(xi) Bucks County Community College
(A) Acquisition, rehabilitation and construction of facilities at the Bristol Center7,200,000

(Base Project Allocation - $6,480,000)

(Design and Contingencies - $720,000)

(B) Campuswide renovations for ADA compliance533,000
(C) Parking improvements for 100 additional spaces, Upper County site500,000
(D) Construction of an addition to Hicks Arts Center525,000
(E) Relocation and centralization of student services300,000
(F) Acquisition and construction of a new facility to replace leased facility in Lower Bucks County7,052,000
(G) New construction and renovation of existing facilities based on facilities construction study11,000,000
(xii) Butler County Community College
(A) Capital improvements, including a public safety training center2,000,000

(Base Project Allocation - $1,800,000)

(Design and Contingencies - $200,000)

(B) Capital improvements, including building renovation and restoration, roadway improvements and parking expansion8,304,000
(C) Construction of a 25,500-square-foot comprehensive student services building and associated traffic and parking improvements6,000,000
(D) Construction of a 145-space parking lot253,000
(E) Renovation and renewal of library, including furnishings175,000
(F) Campus improvements related to student and visitor circulation, accessibility and safety, including signage2,000,000
(xiii) Cambria County Area Community College
(A) Acquisition and rehabilitation of facilities6,000,000

(Base Project Allocation - $5,400,000)

(Design and Contingencies - $600,000)

(B) Acquisition and rehabilitation of structures related to the Cambria County Area Community College and Greater Johnstown Career and Technology Center Partnership10,000,000
(C) Cambria County Area Community College North Side Campus renovation project460,000
(D) Johnstown consolidation, consolidation of four leased sites into one centralized campus14,000,000
(E) Consolidation of student services at centralized location, including improvement of telecommunications infrastructure208,000
(xiv) Harrisburg Area Community College
(A) Renovation and upgrades of technology and telecommunications infrastructure and upgrades to mechanical systems11,000,000

(Base Project Allocation - $9,900,000)

(Design and Contingencies - $1,100,000)

(B) Expansion of the Lancaster Campus24,400,000

(Base Project Allocation - $21,960,000)

(Design and Contingencies - $2,440,000)

(C) Energy enhancement, Phase II, technology infrastructure upgrades and expansion of Gettysburg Campus3,900,000
(D) Construction of a building for the allied health programs4,900,000
(E) Construction of an early care/early childhood education center1,100,000
(F) Lancaster Campus improvements, Phase II1,750,000
(xv) Delaware County Community College
(A) Campus improvements5,000,000

(Base Project Allocation - $4,500,000)

(Design and Contingencies - $500,000)

(B) Renovation and upgrade of science laboratories875,000
(C) Renovation of board room, HVAC improvement and exterior improvements, including lighting and security improvements357,000
(D) Upgrade and renovation of nursing simulation laboratory175,000
(E) Construction of a 250-space structured parking facility1,250,000
(F) Replacement of interior fluorescent lighting with T-8 technology300,000
(G) Upgrade and renovation of the library/learning center325,000
(xvi) Lehigh-Carbon County Community College
(A) Campus improvements5,000,000

(Base Project Allocation - $4,500,000)

(Design and Contingencies - $500,000)

(B) Purchase of a classroom building located on the college's campus7,150,000
(C) Acquisition and rehabilitation of classroom and administrative office building adjacent to main campus7,150,000

(Base Project Allocation - $6,500,000)

(Design and Contingencies - $650,000)

(D) Design and construction of a new allied health sciences laboratory and classroom building on main campus8,800,000

(Base Project Allocation - $8,000,000)

(Design and Contingencies - $800,000)

(E) Acquisition and rehabilitation of an existing building located in Tremont, Schuylkill County, for use as a regional education center5,500,000

(Base Project Allocation - $5,000,000)

(Design and Contingencies - $500,000)

(F) Renovation and expansion of the Carbon and Donley Center sites2,750,000

(Base Project Allocation - $2,500,000)

(Design and Contingencies - $250,000)

(G) Capital improvements related to the creation of the National Institute for Teaching Excellence2,200,000

(Base Project Allocation - $2,000,000)

(Design and Contingencies - $200,000)

(H) Capital improvements to the Learning Resource Center located on the main campus3,300,000

(Base Project Allocation - $3,000,000)

(Design and Contingencies - $300,000)

(I) Design and construction of a new classroom building, including an auditorium/conference center8,800,000

(Base Project Allocation - $8,000,000)

(Design and Contingencies - $800,000)

(J) Acquisition and renovation of the Carbon Lehigh Intermediate Unit for offices, conference and student services facilities3,500,000
(K) Renovation of the Donley Center250,000
(L) Renovation and retrofitting of classrooms in Science Hall and improvements to the Technology Center475,000
(M) Renovation of Science Hall, including parking improvements275,000
(N) Upgrade radio station and multimedia production studio225,000
(xvii) Luzerne County Community College
(A) Campus improvements5,000,000

(Base Project Allocation - $4,500,000)

(Design and Contingencies - $500,000)

(B) Construction and renovations to day care center250,000
(C) Construction of regional athletic facility10,000,000
(D) Replacement of HVAC equipment and roof replacements for various buildings and improvement of deteriorating parking lot450,000
(E) Construction or acquisition of a public safety building250,000
(xviii) Montgomery County Community College
(A) Renovation of the advanced technology and science center14,200,000

(Base Project Allocation - $12,780,000)

(Design and Contingencies - $1,420,000)

(B) Pottstown-West Campus improvements20,700,000

(Base Project Allocation - $18,630,000)

(Design and Contingencies - $2,070,000)

(C) Design of a multiuse facility292,000
(D) Renovation and expansion of Art Barn Complex and both Central and West Campuses for development of art compound1,738,000
(E) Development of a facilities master plan618,000
(xix) Northampton County Area Community College
(A) Acquisition and rehabilitation of the East Annex Building, Bethlehem Works10,000,000

(Base Project Allocation - $9,000,000)

(Design and Contingencies - $1,000,000)

(B) Construction of student activity center11,900,000

(Base Project Allocation - $10,710,000)

(Design and Contingencies - $1,190,000)

(C) Acquisition and rehabilitation of the East Annex Building in the Bethlehem Works site for classrooms, laboratories and studios5,000,000
(D) Construction of a 43,000-square-foot student activity center and renovation/conversion of existing student activity facilities for classroom and office spaces7,500,000
(E) Acquisition and renovation of former Bethlehem Steel Corporate office in South Bethlehem for classroom and office space5,000,000
(xx) Community College of Philadelphia
(A) Parking expansion2,200,000

(Base Project Allocation - $1,980,000)

(Design and Contingencies - $220,000)

(B) Laboratory upgrades at main campus2,200,000

(Base Project Allocation - $1,980,000)

(Design and Contingencies - $220,000)

(C) Renovations to Winnet/Gymnasium Complex, main campus1,000,000

(Base Project Allocation - $900,000)

(Design and Contingencies - $100,000)

(D) Renovations to Mint Building, main campus1,400,000

(Base Project Allocation - $1,260,000)

(Design and Contingencies - $140,000)

(E) Infrastructure upgrades1,700,000

(Base Project Allocation - $1,530,000)

(Design and Contingencies - $170,000)

(F) Construction of new building at 1809 Spring Garden Street2,400,000

(Base Project Allocation - $2,160,000)

(Design and Contingencies - $240,000)

(G) Renovations to Bonnell Building4,800,000

(Base Project Allocation - $4,320,000)

(Design and Contingencies - $480,000)

(H) Construction and renovation to develop the third floor of Building B at the Northwest Regional Center2,500,000

(Base Project Allocation - $2,250,000)

(Design and Contingencies - $250,000)

(I) Expansion of the Winnet Building9,100,000

(Base Project Allocation - $8,190,000)

(Design and Contingencies - $910,000)

(J) Construction of new student dining facility6,300,000

(Base Project Allocation - $5,670,000)

(Design and Contingencies - $630,000)

(K) Construction of new building at Northeast Regional Center13,200,000

(Base Project Allocation - $11,880,000)

(Design and Contingencies - $1,320,000)

(L) Renovation and reconstruction of 600-car parking garage1,200,000

(Base Project Allocation - $1,080,000)

(Design and Contingencies - $120,000)

(M) Technology system upgrades7,200,000

(Base Project Allocation - $6,480,000)

(Design and Contingencies - $720,000)

(N) Acquisition and installation of new administrative system3,600,000
(O) Roofing repairs, Bonnell, Winnet and gymnasium210,000
(P) Upgrade of science and allied health laboratories500,000
(Q) Replacement or renewal of key building systems as part of building life cycle program of repairs, all campuses1,000,000
(xxi) Westmoreland County Community College
(A) Design and construction of various physical fitness facilities, including a fitness trail and a combination auditorium and gymnasium3,250,000
(B) Design and construction of a railroad hazards training facility1,750,000
(C) Design and construction of an equipment maintenance and storage building1,750,000
(D) Design and construction of an indoor firing range1,750,000
(E) Design and construction of a trucking transportation hazards training facility1,250,000
(F) Design and construction of a public safety response station2,250,000
(G) Public safety training center expansion, including additional classrooms, lab facilities and administrative offices5,850,000
(H) Design and construction of the Hogan's Alley Outdoor Firing Range2,200,000
(I) Design and construction of a structural collapse training facility2,250,000
(J) Design and construction of an Emergency Vehicle Operator Course5,335,000
(K) Campus improvements5,000,000

(Base Project Allocation - $4,500,000)

(Design and Contingencies - $500,000)

(L) Construction of a new 12,000-square-foot education center and parking lot, including demolition of an existing structure1,000,000
(M) Renovation of an existing structure for the Indiana Education Center180,000
(N) Conversion of a portion of Founders Hall for a student center300,000
(O) Founders Hall roof replacement and installation of rooftop HVAC units500,000
(6) Pennsylvania Emergency Management Agency
(i) Building security at PEMA headquarters
(A) Install and construct new interior/exterior security system for headquarters building2,174,000
(ii) Commonwealth Emergency Operating Center Colocation
(A) Construct alternate site for core operations in the event of a disaster7,000,000
(iii) Eastern Regional Office
(A) Construction of office and operations center space935,000
(iv) Western Regional Office
(A) Demolition of western regional office375,000
(v) Dauphin County
(A) Purchase and renovation of currently leased headquarters building10,500,000

(Base Project Allocation - $10,500,000)

(vi) National Emergency Alert System
(A) Acquisition and installation of power equipment for the Pennsylvania Public Television Network to support the National Emergency Alert System and PEMA's delivery of data to secondary and tertiary emergency services4,000,000
(7) Department of Environmental Protection
(i) Allegheny County
(A) Additional funds for DGS project 183-15, McKeesport flood protection1,200,000

(Base Project Allocation - $1,000,000)

(Design and Contingencies - $200,000)

(B) Logan Run Creek flood mitigation, storm water retention and flood control measures associated with the tributary of Piney Fork adjacent to Logan Road in Bethel Park Borough1,700,000

(Base Project Allocation - $1,000,000)

(Land Allocation - $500,000)

(Design and Contingencies - $200,000)

(C) Harmony Road tributary, flood control project including stream bank stabilization and storm water management measures in association with the Ohio River tributary in Ohio and Killbuck Townships800,000

(Base Project Allocation - $650,000)

(Design and Contingencies - $150,000)

(D) Flood control and storm water management project associated with the tributary of Painters Run along Cedar Road at intersection of Greenhurst Road in Mt. Lebanon Township300,000

(Base Project Allocation - $200,000)

(Land Allocation - $65,000)

(Design and Contingencies - $35,000)

(E) Flood control, stream bank stabilization and storm water management project associated with the tributary of Bear Run along Crawford Road in Ohio Township500,000

(Base Project Allocation - $400,000)

(Design and Contingencies - $100,000)

(F) Flood control and storm water retention project associated with tributary of Brush Run adjacent to Hays and Underwood in Upper St. Clair Township200,000

(Base Project Allocation - $150,000)

(Land Allocation - $25,000)

(Design and Contingencies - $25,000)

(G) Flood control and storm water management project associated with Weyman Run adjacent to Route 51 in Whitehall Borough460,000

(Base Project Allocation - $400,000)

(Land Allocation - $40,000)

(Design and Contingencies - $20,000)

(ii) Bedford County
(A) Additional funds for DGS project 183-8, Hyndman flood protection600,000

(Base Project Allocation - $500,000)

(Design and Contingencies - $100,000)

(iii) Berks County
(A) Furnace Creek rehabilitation and storm water management project1,000,000
(B) Installation of an inflatable dam and fish ladders at the Felix Dam site3,900,000
(C) City of Reading, rehabilitation of the Antietam Lake Dam2,000,000
(D) Heidelberg Township flood protection project1,560,000

(Base Project Allocation - $1,404,000)

(Design and Contingencies - $156,000)

(iv) Bradford County
(A) Borough of Monroe flood protection project4,800,000

(Base Project Allocation - $4,320,000)

(Design and Contingencies - $480,000)

(v) Butler County
(A) Sullivan Run stream improvements500,000
(B) Evans City Borough, improvements to the sanitary sewer collection system to address inflow of storm water4,000,000
(vi) Cambria County
(A) Borough of Northern Cambria flood protection project3,000,000

(Base Project Allocation - $2,700,000)

(Design and Contingencies - $300,000)

(B) Rehabilitation of Borough of Patton flood protection project5,040,000

(Base Project Allocation - $4,536,000)

(Design and Contingencies - $504,000)

(C) Borough of Wilmore flood protection project840,000

(Base Project Allocation - $756,000)

(Design and Contingencies - $84,000)

(D) Dalton Run Dam Spillway Project875,000

(Base Project Allocation - $745,000)

(Design and Contingencies - $130,000)

(E) North Fork Dam Spillway Project4,200,000

(Base Project Allocation - $3,530,000)

(Design and Contingencies - $670,000)

(F) Conemaugh/Stoneycreek River collapsible dam project5,000,000
(vii) Carbon County
(A) Borough of Weissport flood protection project840,000

(Base Project Allocation - $756,000)

(Design and Contingencies - $84,000)

(viii) Chester County
(A) Borough of Downingtown and East Caln Township flood protection project4,800,000

(Base Project Allocation - $4,320,000)

(Design and Contingencies - $480,000)

(B) Borough of Downingtown and East Caln Township flood protection diversion project5,400,000

(Base Project Allocation - $4,860,000)

(Design and Contingencies - $540,000)

(ix) Clearfield County
(A) Additional funds for DGS project 182-14, Coalport flood protection820,000

(Base Project Allocation - $700,000)

(Design and Contingencies - $120,000)

(B) Stinky Run flood protection1,560,000

(Base Project Allocation - $1,300,000)

(Design and Contingencies - $260,000)

(C) Construction of flood protection along Orrs Run3,600,000

(Base Project Allocation - $3,000,000)

(Design and Contingencies - $600,000)

(D) River and stream rehabilitation project in Clearfield, Centre and Cambria Counties15,000,000
(x) Crawford County
(A) City of Meadville, storm sewer infrastructure improvements3,000,000
(xi) Dauphin County
(A) Renovation of laboratory, including design and construction of a PEM fuel cell demonstration unit16,500,000

(Base Project Allocation - $14,000,000)

(Design and Contingencies - $2,500,000)

(xii) Delaware County
(A) Flood abatement along Chester Creek in the City of Chester and Upland Borough800,000
(xiii) Elk County
(A) Borough of Ridgway flood protection project10,200,000

(Base Project Allocation - $9,180,000)

(Design and Contingencies - $1,020,000)

(xiv) Erie County
(A) Union City, property acquisition and construction for the Union City Dam Project15,000,000
(xv) Lackawanna County
(A) Rehabilitation of City of Scranton flood protection project4,800,000

(Base Project Allocation - $4,320,000)

(Design and Contingencies - $480,000)

(xvi) Lehigh County
(A) Sewer infrastructure improvements in municipalities of Slatington, Emerald, Coopersburg, Upper Saucon, Ormond and North Whitehall7,000,000
(xvii) Luzerne County
(A) Borough of West Pittston, flood control project from North and Fifth Streets to the Susquehanna River, including Tunkhannock Avenue2,476,000
(B) Borough of West Pittston, flood control project from North and Fifth Streets to the Susquehanna River and route pipe along North Street2,152,000
(xviii) (Reserved)
(xix) Montgomery County
(A) Upper Merion Township and Bridgeport Borough, flood control project from Crooked Lane to the intersection of DeKalb and Ford Streets2,000,000
(B) Additional funds for DGS 181-7, Plymouth Creek improvements, Conshohocken Borough840,000

(Base Project Allocation - $700,000)

(Design and Contingencies - $140,000)

(xx) Northampton County
(A) Raubsville Creek, flood control improvements, Williams Township250,000
(xxi) Northumberland County
(A) Delaware Township, stream bank stabilization flood control250,000
(B) Construction, reconstruction and improvements to the Sunbury Flood Project1,500,000
(C) Plum Creek Flood Protection Project400,000
(xxii) Philadelphia County
(A) Flat Rock Dam canal wall stabilization/flood protection, stabilization and rehabilitation of concrete retention at Manayunk Canal300,000

(Base Project Allocation - $250,000)

(Design and Contingencies - $50,000)

(B) Manayunk Canal Wall, rehabilitation of Flat Rock Dam along Schuylkill River900,000

(Base Project Allocation - $810,000)

(Design and Contingencies - $90,000)

(xxiii) Potter County
(A) Rehabilitation of Borough of Coudersport flood protection project1,200,000

(Base Project Allocation - $1,080,000)

(Design and Contingencies - $120,000)

(xxiv) Somerset County
(A) Borough of New Baltimore flood protection project2,100,000

(Base Project Allocation - $1,890,000)

(Design and Contingencies - $210,000)

(xxv) Snyder County
(A) Stream bank stabilization along Weiser Run, including acquisition, design and construction, Selinsgrove Borough481,000
(xxvi) Tioga County
(A) Borough of Elkland flood protection project8,100,000

(Base Project Allocation - $7,290,000)

(Design and Contingencies - $810,000)

(B) Township of Middlebury flood protection project750,000

(Base Project Allocation - $675,000)

(Design and Contingencies - $75,000)

(xxvii) Warren County
(A) Rehabilitation of Glad Run Flood Protection, including repairs to existing concrete structures, drainage improvements and improvements to existing levees3,000,000

(Base Project Allocation - $2,500,000)

(Design and Contingencies - $500,000)

(B) Borough of Sheffield flood protection project6,480,000

(Base Project Allocation - $5,832,000)

(Design and Contingencies - $648,000)

(xxviii) Washington County
(A) East Bethlehem Township, Clyde Mine, refuse dump remediation and cleanup2,000,000
(xxix) Westmoreland County
(A) Additional funds for DGS project 182-7, Jeannette flood protection600,000

(Base Project Allocation - $500,000)

(Design and Contingencies - $100,000)

(8) Department of General Services
(i) Capitol Complex
(A) Restoration of the Finance Building, Forum Building, North Office Building and the Speaker K. Leroy Irvis Building, including the restoration of murals, bronze, sculptures and ornate spaces8,000,000
(B) Restoration of the Main Capitol Building, including the restoration of artwork, historic spaces, statuary and historic furnishings17,000,000
(C) Additional funds for DGS project 948-35.1, Phase 1, Part F - Basement Terazzo and Door Systems, Main Capitol Building, Capitol Complex - for finishes and systems for the Senate and House of Representatives500,000
(D) Additional funds for DGS project 948-35, Phase 1, Part L, Capitol Complex Security Upgrades, Main Capitol Building, for additional security enhancements for the Senate and House of Representatives3,600,000
(E) Renovation, restoration and rehabilitation of the Forum Building, including, but not limited to, life safety code, HVAC, security and telecommunication improvements and enhancements58,200,000

(Base Project Allocation - $48,500,000)

(Design and Contingencies - $9,700,000)

(F) Renovation, restoration and rehabilitation of the North Office Building, including, but not limited to, life safety code, HVAC, security and telecommunication improvements and enhancements35,368,000

(Base Project Allocation - $30,568,000)

(Design and Contingencies - $4,800,000)

(G) Renovation, restoration and rehabilitation of the Finance Building, including, but not limited to, life safety code, HVAC, security and telecommunication improvements and enhancements61,812,000

(Base Project Allocation - $52,610,000)

(Design and Contingencies - $9,202,000)

(H) Renovation, restoration and rehabilitation of the Speaker K. Leroy Irvis Building, including, but not limited to, life safety code, HVAC, security and telecommunication improvements and enhancements33,051,000

(Base Project Allocation - $28,642,000)

(Design and Contingencies - $4,409,000)

(ii) Philadelphia County
(A) DGS 522-2, Diagnostic and Rehabilitation Center, Philadelphia4,000,000
(B) Land acquisition, site preparation, related infrastructure improvements, including transportation access and new construction of terminal facilities for the operation of a fresh food distribution center in Philadelphia150,000,000
(C) Pennsylvania Convention Center expansion, including planning, land acquisition and construction400,000,000
(iii) Erie County Convention Center Authority
(A) Development and construction of an entertainment and cultural district in the City of Erie25,000,000
(iv) Allegheny County
(A) Completion of the David L. Lawrence Convention Center8,000,000
(8.1) Department of Health
(i) Washington and Greene Counties
(A) Centerville Clinic, improvements to radiology services facility1,000,000
(9) Pennsylvania Historical and Museum Commission
(i) Drake Well Museum
(A) Renovations to museum and collections storage3,600,000

(Base Project Allocation - $3,000,000)

(Design and Contingencies - $600,000)

(ii) Pennsylvania Military Museum
(A) Construction and installation of new permanent exhibits4,200,000

(Base Project Allocation - $3,500,000)

(Design and Contingencies - $700,000)

(iii) Washington Crossing Historic Park
(A) Additional funds for DGS project 996-15, rehabilitation of existing facility1,800,000

(Base Project Allocation - $1,500,000)

(Design and Contingencies - $300,000)

(B) Renovation of Bowman's Hill Wildflower Preserve2,500,000
(iv) Northumberland County
(A) Joseph Priestley House, installation of fire protection systems180,000
(v) Ephrata Cloister
(A) Design and construction of a new visitors center6,000,000
(vi) Daniel Boone Homestead
(A) Design and construction of a new visitors center3,000,000
(vii) Pennsylvania Lumber Museum
(A) Expansion of museum, including construction of a two-story addition1,200,000

(Base Project Allocation - $1,000,000)

(Design and Contingencies - $200,000)

(10) Pennsylvania Infrastructure Investment Authority (Reserved)
(11) Department of Military and Veterans Affairs
(i) Lebanon County
(A) Construction improvements to existing facility at Fort Indiantown Gap650,000
(B) Land acquisition and construction of a Veterans Home12,000,000

(Base Project Allocation - $10,000,000)

(Land Allocation - $2,000,000)

(ii) Hollidaysburg Veterans Home, Blair County
(A) Upgrades at Eisenhower Hall and dietary building2,916,000

(Base Project Allocation - $2,442,000)

(Design and Contingencies - $474,000)

(B) Upgrades at MacArthur Hall2,483,000

(Base Project Allocation - $2,075,000)

(Design and Contingencies - $408,000)

(C) Replace and upgrade sewer line1,008,000

(Base Project Allocation - $907,000)

(Design and Contingencies - $101,000)

(D) Erect steel storage building210,000

(Base Project Allocation - $189,000)

(Design and Contingencies - $21,000)

(E) Upgrades at old administration building630,000

(Base Project Allocation - $567,000)

(Design and Contingencies - $63,000)

(F) Upgrades to maintenance building189,000

(Base Project Allocation - $170,000)

(Design and Contingencies - $19,000)

(G) Paint water tank105,000

(Base Project Allocation - $95,000)

(Design and Contingencies - $10,000)

(H) Upgrades to groundskeeping building150,000

(Base Project Allocation - $135,000)

(Design and Contingencies - $15,000)

(I) Pharmacy design and relocation240,000

(Base Project Allocation - $216,000)

(Design and Contingencies - $24,000)

(iii) Scotland School for Veterans' Children, Franklin County
(A) Repairs for the student center, Frey Gym, 13 cottages and maintenance buildings4,100,000

(Base Project Allocation - $3,690,000)

(Design and Contingencies - $410,000)

(B) Package four, replacement of steam and hot water supply lines in cottage area2,691,000

(Base Project Allocation - $2,422,000)

(Design and Contingencies - $269,000)

(iv) Southwestern Veterans Center, Allegheny County
(A) Modification to Alzheimer's unit and dining room143,000

(Base Project Allocation - $129,000)

(Design and Contingencies - $14,000)

(B) Site work and perimeter fencing154,000

(Base Project Allocation - $139,000)

(Design and Contingencies - $15,000)

(C) Driveway and parking lot repairs153,000

(Base Project Allocation - $138,000)

(Design and Contingencies - $15,000)

(D) Replace flooring288,000

(Base Project Allocation - $259,000)

(Design and Contingencies - $29,000)

(E) Finish storage area124,000

(Base Project Allocation - $112,000)

(Design and Contingencies - $12,000)

(v) Southeastern Veterans Center, Chester County
(A) Additional funds for DGS project 960-5511,340,000
(B) Renovation and modernization of commandant's quarters250,000

(Base Project Allocation - $225,000)

(Design and Contingencies - $25,000)

(C) Decommission old power plants200,000

(Base Project Allocation - $180,000)

(Design and Contingencies - $20,000)

(D) Construction of domiciliary/personal care unit building, Phase 22,975,000

(Base Project Allocation - $2,678,000)

(Design and Contingencies - $297,000)

(E) Installation of security camera system262,000

(Base Project Allocation - $237,000)

(Design and Contingencies - $25,000)

(vi) Pennsylvania Soldiers and Sailors Home, Erie County
(A) Design and modernization of food production and storage area250,000

(Base Project Allocation - $225,000)

(Design and Contingencies - $25,000)

(B) Replacement of perimeter fence350,000

(Base Project Allocation - $315,000)

(Design and Contingencies - $35,000)

(vii) Combined Readiness Center, State Area Command
(A) Construction of combined readiness center14,950,000

(Base Project Allocation - $13,000,000)

(Design and Contingencies - $1,950,000)

(viii) Combined Readiness Center, Greene County
(A) Construction of combined readiness center2,788,000

(Base Project Allocation - $1,772,000)

(Land Allocation - $750,000)

(Design and Contingencies - $266,000)

(ix) Combined Readiness Center, York County
(A) Construction of combined readiness center2,902,000

(Base Project Allocation - $1,871,000)

(Land Allocation - $750,000)

(Design and Contingencies - $281,000)

(x) Joint Headquarters Readiness Center, Lebanon County
(A) Construction of joint headquarters readiness center6,738,000

(Base Project Allocation - $6,064,000)

(Design and Contingencies - $674,000)

(xi) Readiness Center, Bedford County
(A) Construction of readiness center2,314,000

(Base Project Allocation - $2,083,000)

(Design and Contingencies - $231,000)

(xii) Readiness Center, Bucks County
(A) Addition/alteration to readiness center1,021,000

(Base Project Allocation - $919,000)

(Design and Contingencies - $102,000)

(xiii) Readiness Center, Chester County
(A) Construction of readiness center2,663,000

(Base Project Allocation - $2,397,000)

(Design and Contingencies - $266,000)

(xiv) Readiness Center, Columbia County
(A) Construction of readiness center2,105,000

(Base Project Allocation - $1,894,000)

(Design and Contingencies - $211,000)

(xv) Readiness Center, Lawrence County
(A) Construction of readiness center3,169,000

(Base Project Allocation - $2,852,000)

(Design and Contingencies - $317,000)

(xvi) Readiness Center, Luzerne County
(A) Construction of readiness center3,041,000

(Base Project Allocation - $2,737,000)

(Design and Contingencies - $304,000)

(xvii) Readiness Center, Lycoming County
(A) Construction of readiness center2,599,000

(Base Project Allocation - $2,339,000)

(Design and Contingencies - $260,000)

(xviii) Readiness Center, McKean County
(A) Construction of readiness center1,739,000

(Land Allocation - $1,739,000)

(xix) Readiness Center, Schuylkill County
(A) Construction of readiness center3,378,000

(Base Project Allocation - $3,040,000)

(Design and Contingencies - $338,000)

(xx) Dauphin and Lebanon Counties
(A) Expansion of the range safety zones at Fort Indiantown Gap in Dauphin and/or Lebanon Counties to accommodate range upgrades for training of military personnel5,000,000

(Land Allocation - $5,000,000)

(xxi) Combined Readiness Center/Operations Maintenance Shop, Crawford County1,750,000

(Land Allocation - $1,750,000)

(12) Department of Public Welfare
(i) Clarks Summit State Hospital
(A) Install new heating and cooling systems1,800,000

(Base Project Allocation - $1,500,000)

(Design and Contingencies - $300,000)

(ii) Danville State Hospital
(A) Replace steam generation equipment2,500,000

(Base Project Allocation - $2,083,000)

(Design and Contingencies - $417,000)

(iii) Hamburg Center
(A) Install new flooring and ceilings840,000

(Base Project Allocation - $700,000)

(Design and Contingencies - $140,000)

(iv) Harrisburg State Hospital
(A) Upgrade HVAC systems in DPW Complex No.26,600,000

(Base Project Allocation - $5,500,000)

(Design and Contingencies - $1,100,000)

(B) Upgrade electrical distribution system, fire and security systems in Buildings 33, 41, 42 and 433,600,000

(Base Project Allocation - $3,000,000)

(Design and Contingencies - $600,000)

(v) Loysville Complex
(A) Construction of a new 80-unit juvenile facility12,900,000

(Base Project Allocation - $10,750,000)

(Design and Contingencies - $2,150,000)

(vi) Selinsgrove Center
(A) Upgrade fire alarm and suppression systems2,400,000

(Base Project Allocation - $2,000,000)

(Design and Contingencies - $400,000)

(vii) Torrance State Hospital
(A) Expansion and/or replacement of Building 71,200,000

(Base Project Allocation - $1,000,000)

(Design and Contingencies - $200,000)

(13) Pennsylvania State Police
(i) Butler Headquarters, Butler County
(A) Construct new Butler Headquarters building4,011,000

(Base Project Allocation - $3,610,000)

(Design and Contingencies - $401,000)

(ii) Department Headquarters, Dauphin County
(A) Construct new crime laboratory facility10,000,000

(Base Project Allocation - $9,600,000)

(Design and Contingencies - $400,000)

(B) Construct new crime laboratory facility38,160,000

(Base Project Allocation - $34,344,000)

(Design and Contingencies - $3,816,000)

(C) Construct new annex to department headquarters building33,000,000

(Base Project Allocation - $29,700,000)

(Design and Contingencies - $3,300,000)

(D) Renovate department headquarters building8,322,000

(Base Project Allocation - $7,490,000)

(Design and Contingencies - $832,000)

(iii) Police Academy, Dauphin County
(A) Renovations to academy, Phase 44,800,000

(Base Project Allocation - $4,320,000)

(Design and Contingencies - $480,000)

(iv) Lima Laboratory, Delaware County
(A) Construct new crime laboratory facility6,760,000

(Base Project Allocation - $6,084,000)

(Design and Contingencies - $676,000)

(v) Wyoming Headquarters, Luzerne County
(A) Construct new headquarters building5,787,000

(Base Project Allocation - $5,208,000)

(Design and Contingencies - $579,000)

(vi) Wyoming Laboratory, Luzerne County
(A) Construct new crime laboratory facility876,000

(Base Project Allocation - $730,000)

(Design and Contingencies - $146,000)

(B) Construct new forensic crime laboratory facility5,760,000

(Base Project Allocation - $5,184,000)

(Design and Contingencies - $576,000)

(vii) Philadelphia Headquarters, Philadelphia County
(A) Renovate headquarters building8,209,000

(Base Project Allocation - $7,388,000)

(Design and Contingencies - $821,000)

(14) State System of Higher Education
(i) Bloomsburg University
(A) Renovation of Ben Franklin Building5,700,000
(B) Renovation or addition to Haas Auditorium12,700,000
(C) Renovation of Nelson Field House14,900,000
(D) Construction of addition to Sutliff Hall8,600,000
(E) Renovation of Waller Administration Building6,500,000
(F) Construction of a classroom addition6,000,000
(ii) California University
(A) Construction of a convocation center38,400,000
(B) Construction of science building20,093,000
(C) Renovation of old Industrial Arts building6,859,000
(D) Construction of university support facility4,703,000
(E) Pedestrian and vehicular enhancement, Phase II8,700,000
(iii) Cheyney University
(A) Renovation of Humphreys Hall interior4,000,000
(B) Renovation of Emlen Hall interior5,343,000
(C) Renovation of potable water lines5,640,000
(D) Renovation of lower campus steam lines5,780,000
(E) Renovation of campus infrastructure, Phase III5,340,000
(F) Renovation of tennis and athletic facilities1,800,000
(G) Renovation of power plant and garage480,000
(H) Athletic facilities addition/renovation8,000,000
(iv) Clarion University
(A) Conversion and renovation of Becht Hall7,914,000
(B) Renovation of Moore Hall1,628,000
(C) Addition and renovation of Marwick Boyd Fine Arts Center21,000,000
(D) Renovation of Still Hall7,877,000
(E) Addition and renovation of Tippin Gymnasium7,831,000
(F) Modification of facilities for ADA compliance3,600,000
(v) East Stroudsburg University
(A) Renovation and replacement of Monroe Hall8,000,000
(B) Replacement of Rosenkrans Hall18,000,000
(C) Addition and renovation of Eiler-Martin Stadium9,000,000
(D) Addition and renovation of Abeloff Convocation Center11,000,000
(vi) Edinboro University
(A) Construction of Tool & Mold Institute3,420,000
(B) Addition and renovation of Cooper Science, Phase II23,000,000
(vii) Indiana University
(A) Replacement of Old Main, Punxsutawney Campus10,201,000
(B) Steam distribution/tunnel system renovation1,800,000
(C) Electrical distribution system upgrade2,100,000
(D) Boiler plant renovation3,600,000
(viii) Kutztown University
(A) Upgrade Keystone Hall5,034,000
(B) Upgrade Beeky Education Building1,912,000
(C) Upgrade Stratton Administration Building2,226,000
(D) Addition and renovation of Lytle Hall3,974,000
(E) Addition and upgrade of Kemp Building900,000
(F) Acquisition of 137-acre campus, design, development, construction and implementation of an e-campus23,000,000
(G) Renovation and addition to Shaffer Auditorium11,000,000
(ix) Lock Haven University
(A) Demolish E&G structures1,620,000
(B) Clearfield Campus, design and construction of a new health services building to include laboratories, classrooms, clinical facilities and multipurpose rooms15,000,000
(C) Clearfield Campus, design and construction of classrooms and laboratories for programs in engineering technologies and computers and multipurpose rooms15,000,000
(D) Clearfield Campus, design and construction of new education building10,600,000
(E) Old KCSD High School renovation12,000,000
(x) Mansfield University
(A) Addition to and renovation of Grant Science Center10,993,000

(Base Project Allocation - $9,161,000)

(Design and Contingencies - $1,832,000)

(B) Addition and renovation of Grant Science Center, Phase II10,993,000
(C) Renovation/replace Allen Hall6,500,000
(xi) Millersville University
(A) Addition of theater arts facility14,210,000
(B) Addition of Sports Education Center12,325,000
(C) Addition and renovation of Palmer/Bishop Buildings3,552,000
(D) Upgrade campus infrastructure4,532,000
(xii) Shippensburg University
(A) Renovation of steam distribution system6,660,000
(B) Renovation of electrical distribution system8,730,000
(C) Renovation of Memorial Auditorium5,360,000
(D) Renovation of Dauphin Humanities Center8,570,000
(E) Campus steam plant modernization7,300,000
(xiii) Slippery Rock University
(A) Central heating plant renovation, Phase III3,500,000
(xiv) West Chester University
(A) Construction of academic classroom and office complex24,984,000
(B) Renovation of E.O. Bull Center13,000,000
(C) Update infrastructure and chilled water plant3,800,000
(D) Renovation of FHG Library20,400,000
(E) Steam line replacement6,000,000
(15) Department of Transportation
(i) Adams County
(A) Construction of new welcome center along Route 155,000,000
(ii) Allegheny County
(A) Construction of a new county maintenance garage1,800,000
(iii) Bradford County
(A) Construction of a new county maintenance office and garage10,000,000
(iv) Bucks County
(A) Relocation of maintenance shed located in Doylestown Borough1,000,000
(B) Construction of a new county maintenance office3,400,000
(C) Renovation of Safety Rest Area Site P, I-95 Southbound518,000
(v) Clearfield County
(A) Construction of a new Engineering District 2-0 office10,000,000
(vi) Clinton County
(A) Construction of a new county maintenance garage10,000,000
(vii) Cumberland County
(A) Construction of a new county maintenance garage10,000,000
(viii) Dauphin County
(A) Construction of a new materials testing laboratory18,000,000
(B) Renovation of Safety Rest Area Site 48, I-81 Southbound1,780,000
(C) Renovation of Safety Rest Area Site 47, I-81 Northbound1,000,000
(ix) Lackawanna County
(A) Renovation of Safety Rest Area Site 55, I-81 Northbound1,300,000
(x) Lawrence County
(A) Construction of a new regional salt distribution/storage facility380,000
(xi) Lehigh County
(A) Construction of a new Engineering District 5-0 office8,700,000
(xii) Luzerne County
(A) Construction of a new county maintenance garage10,000,000
(B) Renovation of Safety Rest Area Site 54, I-81 Southbound1,100,000
(C) Renovation of Safety Rest Area Site 53, I-81 Northbound1,100,000
(xiii) Pike County
(A) Construction of a new county maintenance garage10,000,000
(xiv) Schuylkill County
(A) Construction of a new regional salt distribution/storage facility380,000
(xv) Sullivan County
(A) Construction of a new county maintenance garage5,000,000
(xvi) Susquehanna County
(A) Construction of a new county maintenance garage10,000,000
(xvii) Washington County
(A) Construction of a new county maintenance office2,900,000
(xviii) York County
(A) Construction of a new county maintenance garage10,000,000
(16) Philadelphia Regional Port Authority
(i) Piers 78, 80 and 80A
(A) Improvements to Pier 78, including roof replacement, floor replacement and lighting4,000,000
(B) Floor replacement at Pier 80A2,000,000
(C) Paving project in the area of Piers 78 and 801,500,000
(D) Improvements to Pier 80, including roof replacement, floor replacement and lighting4,000,000
(E) Demolition and construction of a new terminal and warehouse at Pier 80A52,000,000
(ii) Piers 38 and 40
(A) Improvements to Pier 38, including floor replacement and lighting1,350,000
(B) Parking lot project in the Garden Area of Piers 38 and 402,000,000
(C) Improvements to Pier 40, including roof and floor replacement and lighting4,000,000
(iii) Portwide improvements
(A) Blocking up of all doors not being used at all locations within the port1,000,000
(B) Acquisition and installation of three container cranes, acquisition of two Kocks cranes and electrification of diesel crane28,000,000
(C) Acquisition and development of property located beneath Walt Whitman Bridge5,000,000
(D) Acquisition and development of property adjacent to Pier 98 Annex facility for expansion and development of off-port warehousing and light manufacturing7,000,000
(E) Packer Avenue North expansion to include acquisition and development of Piers 92 through 10470,000,000
(F) Land acquisition, site preparation, related infrastructure improvements, including transportation access and new construction of terminal facilities for the operation of a fresh food distribution center in Philadelphia150,000,000
(G) Acquisition of a floating dry dock to be moored at a PRPA pier2,500,000
(iv) Packer Avenue Marine Terminal
(A) Refrigeration and dry warehouse expansion18,000,000
(B) Terminal automation and gate complex renovations5,000,000
(C) General improvements to facilities, including paving and acquisition of 20-foot spreaders7,500,000
(D) General port property expansion, including acquisition and development of refrigerated building located at Packer Avenue Marine Terminal5,500,000
(E) Expansion south of Packer Avenue Marine Terminal from Berth 6 through Piers 122/124 to the Navy Yard, including development of 1,800-foot deepwater berth85,000,000
(v) Pier 82
(A) Acquisition of cargo-handling equipment and infrastructure improvements to Pier 822,500,000
(17) Office of Administration
(i) Commonwealth Technology Center
(A) Alternate site, colocation with CTC21,500,000
(ii) Statewide Mobile Radio and Microwave System
(A) Additional funds for DGS project 950-10, Statewide mobile radio and microwave system5,000,000

Compiler's Note: The Department of Public Welfare, referred to in this section, was redesignated as the Department of Human Services by Act 132 of 2014.

Section 4. Itemization of furniture and equipment projects.

Additional capital projects in the category of public improvement projects consisting of the acquisition of movable furniture and equipment to complete public improvement projects and to be purchased by the Department of General Services, its successors or assigns and to be financed by the incurring of debt are hereby itemized, together with their respective estimated financial costs, as follows:

ProjectTotal Project Allocation
(1) Department of Conservation and Natural Resources
(i) Benjamin Rush State Park
(A) Original furniture and equipment, DGS 160-1217,000
(ii) Cook Forest State Park
(A) Original furniture and equipment, DGS 191-41114,000
(iii) Delaware Canal State Park
(A) Original furniture and equipment, DGS 141-7200,000
(iv) Nescopeck State Park
(A) Original furniture and equipment, DGS 132-1150,000
(v) Pine Grove Furnace State Park
(A) Original furniture and equipment, DGS 156-1200,000
(vi) Presque Isle State Park
(A) Original furniture and equipment, DGS 163-28400,000
(2) Department of Corrections
(i) Forest County State Correctional Institution
(A) Original furniture and equipment for DGS project 377-1, construction of a 1,000-cell facility to change the security level from medium to close5,500,000
(3) Department of Education
(i) The Pennsylvania State University
(A) Original furniture and equipment for Sharon Hall, Shenango Campus325,000
(B) Original furniture and equipment for Henderson Building, University Park Campus2,500,000
(C) Original furniture and equipment for Borland Lab, University Park Campus1,500,000
(D) Original furniture and equipment for Chandlee Lab, University Park Campus2,100,000
(E) Original furniture and equipment for McAllister, University Park Campus1,200,000
(F) Original furniture and equipment for Library Depository, University Park Campus1,650,000
(G) Original furniture and equipment for Ferguson Building, University Park Campus1,000,000
(H) Original furniture and equipment for Swift Building, DuBois Campus500,000
(I) Original furniture and equipment for Delaware Administration/Classroom Building, Delaware Campus600,000
(J) Original furniture and equipment for hydrogen fueling station700,000
(ii) Temple University
(A) Original furniture and equipment for Paley Library renovation and expansion6,000,000
(B) Original furniture and equipment for computer lab in Bell Building1,755,000
(C) Original furniture and equipment for the addition to Presser Hall for School of Music569,000
(D) Original furniture and equipment for the construction of welcome center/admissions office630,000
(E) Original furniture and equipment, Baptist Temple restoration. This project shall be construed as a supplement to the project authorized in section 4(3)(iii)(C) of the act of October 30, 2002 (P.L.891, No.131), known as the Capital Budget Project Itemization Act of 2001-2002.201,000
(F) Original furniture and equipment for renovation of existing facilities to consolidate instructional spaces for Tyler Main Campus programs350,000
(iii) University of Pittsburgh
(A) Original furnishings and equipment for Owen Library renovation for Johnstown Campus300,000
(B) Original equipment and furniture for the Bio-Sciences Medical Tower at the University of Pittsburgh20,000,000
(iv) Harrisburg Area Community College
(A) Original furniture and equipment for expansion of Lancaster Campus3,200,000
(v) Luzerne County Community College
(A) New furniture and instructional equipment necessary to keep pace with technology250,000
(vi) Community College of Philadelphia
(A) New equipment to establish network core redundancy required to complete migration from leased mainframe services to an inhouse client/server environment238,000
(4) Department of Environmental Protection
(i) Dauphin County
(A) Original furniture and equipment to support construction of a PEM fuel cell demonstration project in laboratory326,000
(5) Department of General Services
(i) Department of General Services
(A) Original equipment for productivity enhancements25,000,000
(B) Additional original furniture and equipment for DGS Project 948-22, Rachel Carson State Office Building, to include equipment necessary to install a fuel cell demonstration project1,600,000
(C) Pennsylvania Judicial Center, original equipment and furniture for the Pennsylvania Judicial Center22,100,000
(6) Pennsylvania Historical and Museum Commission
(i) Brandywine Battlefield
(A) Original furniture and equipment for expansion of visitors center540,000
(ii) Daniel Boone Homestead
(A) Original furniture and equipment for expansion of visitors center280,000
(iii) Drake Well Museum
(A) Original furniture and equipment for renovation of museum250,000
(iv) Fort Pitt Museum
(A) Original furniture and equipment for DGS project 989-2, expansion of visitors center250,000
(v) Old Economy Village
(A) Original furniture and equipment for DGS project 947-8 for visitors center275,000
(vi) Landis Valley Museum
(A) Original equipment for the Blitzer Barn improvement project120,000
(vii) Railroad Museum of Pennsylvania
(A) Original furniture and equipment for renovation and expansion of museum550,000
(7) Department of Military and Veterans Affairs (Reserved)
(8) Office of Administration
(i) Statewide mobile radio and microwave system
(A) Additional funds for DGS project 950-10, Statewide mobile radio and microwave system5,000,000
(9) Department of Public Welfare
(i) Loysville Complex
(A) Original furniture and equipment for new 80-unit juvenile facility792,000
(ii) Torrance State Hospital
(A) Original furniture and equipment for expansion and/or renovation of Building 7792,000
(10) State System of Higher Education
(i) Bloomsburg University
(A) Original furniture and equipment for the Nelson Fieldhouse renovation1,500,000
(B) Original furniture and equipment for Haas Auditorium renovation/addition1,300,000
(C) Original furniture and equipment for classroom addition600,000
(ii) Cheyney University
(A) Original furniture and equipment for Foster Union Building490,000
(B) Original furniture and equipment for renovation of Humphreys Hall380,000
(iii) Clarion University
(A) Original furniture and equipment for Becht Hall conversion and renovation600,000
(iv) Dixon Center
(A) Original furniture and equipment for the construction of Education Building330,000
(v) East Stroudsburg University
(A) Original furniture and equipment for Monroe Hall656,000
(B) Original furniture and equipment for Rosenkrans Hall1,978,000
(vi) Edinboro University
(A) Original furniture and equipment for construction of Institute for Human Services550,000
(vii) Indiana University
(A) Original furniture and equipment for Regional Development Center4,500,000
(viii) Kutztown University
(A) Original furniture and equipment for construction of Advanced High Technology Classroom Building440,000
(B) Original furniture and equipment for Shaeffer Auditorium renovation/addition1,100,000
(ix) Lock Haven University
(A) Original furniture and equipment for the new education building at Clearfield Campus1,200,000
(B) Original furniture and equipment for the Old KCSD High School renovation1,500,000
(x) Mansfield University
(A) Original furniture and equipment for addition and renovation of Grant Science Center, Phase II1,100,000
(B) Original furniture and equipment for South Hall renovation/replacement600,000
(xi) Millersville University
(A) Original furniture and equipment for renovation of Wickersham Hall300,000
(B) Original furniture and equipment for renovation of Ganser Library1,600,000
(xii) Shippensburg University
(A) Original furniture and equipment for Dauphin Humanities Center Renovation900,000
(B) Original furniture and equipment for Huber Arts600,000
(xiii) Slippery Rock University
(A) Original furniture and equipment for construction of North Hills Education Alliance Facility1,176,000
(B) Original furniture and equipment for Morrow Field House renovation1,400,000
(11) Department of Transportation (Reserved)

Compiler's Note: The Department of Public Welfare, referred to in this section, was redesignated as the Department of Human Services by Act 132 of 2014.

Section 5. Itemization of transportation assistance projects.

(a) Mass transit.--Additional capital projects in the category of transportation assistance projects for mass transit in which an interest is to be acquired or constructed by the Department of Transportation, its successors or assigns and to be financed by the incurring of debt are hereby itemized, together with their estimated financial costs, as follows:

ProjectTotal Project Allocation
(1) Adams County Transit Authority
(i) Construct operating facility83,000

(Base Project Allocation - $75,000)

(Design and Contingencies - $8,000)

(2) Alle-Kiski Commuter Rail
(i) New Kensington and Arnold
(A) Infrastructure development and improvement study for Phase II of the Alle-Kiski Commuter Rail - Arnold to Pittsburgh250,000
(B) Property acquisition, rehabilitation and improvements to the rail base and rail line as part of the Alle-Kiski Commuter Rail Project18,000,000
(2.1) Beaver County Transit Authority
(i) Replacement of two buses and expansion of Park-N-Ride lot in Rochester175,000

(Base Project Allocation - $157,000)

(Design and Contingencies - $18,000)

(2.2) Berks and Reading Transit Authority
(i) Engineering and design of transportation complex at the Franklin Street Station100,000

(Base Project Allocation - $90,000)

(Design and Contingencies - $10,000)

(ii) Purchase of 13 transit buses833,000

(Base Project Allocation - $750,000)

(Design and Contingencies - $83,000)

(iii) Replacement of four paratransit vehicles and related equipment167,000

(Base Project Allocation - $150,000)

(Design and Contingencies - $17,000)

(2.3) Butler Township
(i) Provide for Pullman Center Multimodal Transfer Center1,133,000

(Base Project Allocation - $1,020,000)

(Design and Contingencies - $113,000)

(3) Butler Township-City Joint Municipal Transit Authority
(i) Acquisition, construction, rehabilitation and infrastructure development of the Pullman Center multimodal project1,200,000
(ii) Acquisition and development of a park-and-ride lot with the Port Authority of Allegheny County2,280,000
(iii) Acquisition and development of a transit center to accommodate the Southern Butler County Transit Program1,800,000
(iv) Purchase bus equipment and facility for mass transportation within the county3,000,000
(3.1) Cambria County Transit Authority
(i) Transit center rehabilitation and inclined plane cable replacement257,000

(Base Project Allocation - $231,000)

(Design and Contingencies - $26,000)

(4) Capital Area Transit
(i) Purchase of ten transit buses517,000

(Base Project Allocation - $465,000)

(Design and Contingencies - $52,000)

(ii) Additional funds for Corridor One rail project4,200,000
(iii) Acquisition of rail routes and facilities, infrastructure improvements, vehicle acquisition and final design for commuter rail system in conjunction with Modern Transit Partnership25,000,000
(4.1) Centre Area Transit Authority
(i) Construction of pass sales office167,000

(Base Project Allocation - $ 150,000)

(Design and Contingencies - $17,000)

(5) Endless Mountain Transit Authority
(i) Replacement of fixed-route vehicles and communication equipment and facility improvements55,000

(Base Project Allocation - $50,000)

(Design and Contingencies - $5,000)

(6) Erie Metropolitan Transit Authority
(i) Replacement of five support vehicles26,000

(Base Project Allocation - $23,000)

(Design and Contingencies - $3,000)

(ii) City of Erie, Glenwood Park Learning/Transportation Center250,000
(6.1) Fayette County
(i) Intermodal transit center and administrative maintenance building160,000

(Base Project Allocation - $144,000)

(Design and Contingencies - $16,000)

(ii) Fueling station, computer hardware, office and facility equipment187,000

(Base Project Allocation - $168,000)

(Design and Contingencies - $19,000)

(6.2) Hazleton Public Transit
(i) Construction of intermodal facility and bus replacement625,000

(Base Project Allocation - $562,000)

(Design and Contingencies - $63,000)

(6.3) Lehigh and Northampton Transportation Authority
(i) Purchase of 12 heavy-duty buses576,000

(Base Project Allocation - $518,000)

(Design and Contingencies - $58,000)

(ii) Expansion of Eastern Garage167,000

(Base Project Allocation - $150,000)

(Design and Contingencies - $17,000)

(iii) Purchase of 20 minibuses360,000

(Base Project Allocation - $324,000)

(Design and Contingencies - $36,000)

(6.4) Mid Mon Valley Transit Authority
(i) Acquisition of maintenance facility625,000

(Base Project Allocation - $562,000)

(Design and Contingencies - $63,000)

(ii) Replace seven transit vehicles233,000

(Base Project Allocation - $210,000)

(Design and Contingencies - $23,000)

(7) Port Authority of Allegheny County
(i) Acquisition of transit buses10,000,000

(Base Project Allocation - $9,000,000)

(Design and Contingencies - $1,000,000)

(ii) FFY 2004-2005 Section 5307 formula program7,235,000

(Base Project Allocation - $6,511,000)

(Design and Contingencies - $724,000)

(iii) FFY 2004-2005 Section 5309 fixed-guideway program5,850,000

(Base Project Allocation - $5,265,000)

(Design and Contingencies - $585,000)

(iv) FFY 2004-2005 flex funds program1,350,000

(Base Project Allocation - $1,215,000)

(Design and Contingencies - $135,000)

(v) Planning and implementation of transit improvements in the Oakland area500,000
(vi) Construction of the South Hills Village T parking garage in Bethel Park Borough15,000,000
(vii) FFY 2006-2007 Section 5307 formula program7,235,000

(Base Project Allocation - $6,511,000)

(Design and Contingencies - $724,000)

(viii) FFY 2006-2007 Section 5309 fixed-guideway program6,000,000

(Base Project Allocation - $5,400,000)

(Design and Contingencies - $600,000)

(ix) FFY 2005-2006 flex funds program1,350,000

(Base Project Allocation - $1,215,000)

(Design and Contingencies - $135,000)

(x) FFY 2003-2004 infrastructure safety renewal program15,000,000

(Base Project Allocation - $13,500,000)

(Design and Contingencies - $1,500,000)

(xi) FFY 2006-2007 flex funds program1,350,000

(Base Project Allocation - $1,215,000)

(Design and Contingencies - $135,000)

(xii) FFY 2006-2007 infrastructure safety renewal program17,000,000

(Base Project Allocation - $15,300,000)

(Design and Contingencies - $1,700,000)

(xiii) FFY 2006-2007 vehicle overhaul3,000,000
(xiv) Major rehabilitation of 15 light rail vehicles4,832,000
(xv) Construction of East Busway from Swissvale to Turtle Creek connecting at the Tri Boro Expressway20,000,000
(xvi) North Shore connector project, including expansion of the LRT to the northside, an extension of the Convention Center and an intermodal transportation center43,600,000

(Base Project Allocation - $39,240,000)

(Design and Contingencies - $4,360,000)

(xvii) Federal Fiscal Year 2004 bus procurement10,000,000

(Base Project Allocation - $9,000,000)

(Design and Contingencies - $1,000,000)

(8) Pottstown Urban Transit
(i) Acquisition of two new buses600,000
(8.1) Red Rose Transit Authority
(i) Construction of Paradise rail station458,000

(Base Project Allocation - $412,000)

(Design and Contingencies - $46,000)

(ii) Replacement of 15 buses750,000

(Base Project Allocation - $675,000)

(Design and Contingencies - $75,000)

(iii) Operations center renovations and expansion250,000

(Base Project Allocation - $225,000)

(Design and Contingencies - $25,000)

(9) Schuylkill Transportation System
(i) Design and construction of a new intermodal complex in downtown Pottsville4,000,000
(10) Southeastern Pennsylvania Transportation Authority
(i) FFY 2000 Section 5309 fixed-guideway program10,413,000

(Base Project Allocation - $9,372,000)

(Design and Contingencies - $1,041,000)

(ii) FFY 2003 safety and security program5,208,000

(Base Project Allocation - $4,687,000)

(Design and Contingencies - $521,000)

(iii) Additional funding for Frankford Transit Center3,125,000

(Base Project Allocation - $2,812,000)

(Design and Contingencies - $313,000)

(iv) FFY 2003 improve facilities1,563,000

(Base Project Allocation - $1,407,000)

(Design and Contingencies - $156,000)

(v) Girard Avenue streetscape104,000

(Base Project Allocation - $94,000)

(Design and Contingencies - $10,000)

(vi) Suburban Station streetscape104,000

(Base Project Allocation - $94,000)

(Design and Contingencies - $10,000)

(vii) FFY 2004 Federal program30,000,000

(Base Project Allocation - $27,000,000)

(Design and Contingencies - $3,000,000)

(viii) FFY 2003 Federal highway flex program833,000

(Base Project Allocation - $750,000)

(Design and Contingencies - $83,000)

(ix) FFY 2004 bus purchase program3,563,000

(Base Project Allocation - $3,207,000)

(Design and Contingencies - $356,000)

(x) Design and construction of Schuylkill Valley and Cross-County Metros400,000,000
(xi) FFY 2003-2004 Vehicle Overhaul Program45,000,000
(xii) FFY 2004-2005 Vehicle Overhaul Program47,000,000
(xiii) FFY 2003-2004 Infrastructure Safety Renewal Project33,000,000
(xiv) FFY 2004-2005 Infrastructure Safety Renewal Project33,000,000
(xv) Land acquisition, construction of access to rail connections at Suburban Station, streetscape and public amenities developed at One Pennsylvania Place30,000,000
(xvi) Acquisition of three buses for connector service to Perkasie, Quakertown and Sellersville300,000
(xvii) Federal Fiscal Year 2004 safety and security program4,167,000

(Base Project Allocation - $3,750,000)

(Design and Contingencies - $417,000)

(xviii) Federal Fiscal Year 2005 Federal Program30,333,000

(Base Project Allocation - $27,300,000)

(Design and Contingencies - $3,033,000)

(xix) Fiscal Year 2004-2005 vehicle overhaul program45,000,000

(Base Project Allocation - $40,500,000)

(Design and Contingencies - $4,500,000)

(xx) Federal Fiscal Year 2004 Federal highway flex projects833,000

(Base Project Allocation - $750,000)

(Design and Contingencies - $83,000)

(10.1) Schuylkill Transit System
(i) Site acquisition and construction of Union Station terminal facility833,000

(Base Project Allocation - $750,000)

(Design and Contingencies - $83,000)

(11) Williamsport Bureau of Transit
(i) Replace transit vehicles588,000

(Base Project Allocation - $529,000)

(Design and Contingencies - $59,000)

(ii) Replacement of six heavy-duty buses333,000

(Base Project Allocation - $300,000)

(Design and Contingencies - $33,000)

(12) York County Transit Authority
(i) Replace transit vehicles398,000

(Base Project Allocation - $358,000)

(Design and Contingencies - $40,000)

(13) Department of Transportation
(i) Rail passenger improvements10,000,000

(Base Project Allocation - $9,000,000)

(Design and Contingencies - $1,000,000)

(ii) For Class 3 and Class 4 rural public transportation systems, other than SEPTA and the Port Authority of Allegheny County, to fund projects, including, but not limited to, purchase of vehicles, vehicle overhaul, purchase of facilities, facility renovations and other capital equipment and associated capital items4,400,000
(14) Centre Area Transportation Authority
(i) Construction of a new transit station located on Beaver Avenue, State College Borough500,000
(ii) State College Hydrogen Refueling Station, upgrading of infrastructure to accommodate Hythane and hydrogen refueling for buses1,000,000
(15) Lehigh County
(i) City of Allentown, intermodal transportation center, including design, development and construction10,000,000
(16) Luzerne County
(i) City of Hazleton, Hazleton Public Transit, construction of intermodal facility, related equipment and bus replacements625,000
(17) California University of Pennsylvania
(i) Preconstruction and construction of Projects I and II of an urban maglev shuttle system utilizing passive levitation technology with an air gap of greater than one inch. Funds would be used to match Federal funds.40,000,000
(18) Allegheny County (Reserved)
(19) Berks Area Reading Transportation Authority
(i) Renovation of BARTA administration and operations facility500,000
(20) Washington County
(i) Building acquisition for Transportation Authority1,000,000
(21) Morristown & Erie Railway, Inc.
(i) Improvements to the Octoraro Branch Rail Line from Chadds Ford to Nottingham3,000,000
(22) Philadelphia County
(i) Roosevelt Boulevard Corridor Transit improvements2,500,000
(ii) Eastwick Transportation Center2,500,000
(iii) City Hall subway station rehabilitation10,000,000
(iv) Broad Street subway stations rehabilitation5,000,000
(v) Light rail infrastructure engineering4,168,000
(vi) 52nd Street/City Branch Connector Transit improvements2,500,000

(b) Rural and intercity rail.--Additional capital projects in the category of transportation assistance projects for rural and intercity rail service projects to be constructed or with respect to which an interest is to be acquired by the Department of Transportation, its successors or assigns and to be financed by the incurring of debt are hereby itemized, together with their respective estimated financial costs, as follows:

ProjectTotal Project Allocation
(1) Allegheny and Eastern Railroad
(i) Complete rail rehabilitation from Erie to Ridgeway, including, but not limited to, rails, ties, bridge deck repairs, surfacing and road crossing improvements3,300,000

(Base Project Allocation - $3,000,000)

(Design and Contingencies - $300,000)

(ii) Build and expand transload center in Erie to accommodate new highway access, including the new replacement of rails, ties, ballast, surface, switch, road crossings, bridge and other rail-related infrastructure2,750,000

(Base Project Allocation - $2,500,000)

(Design and Contingencies - $250,000)

(1.1) Allegheny Valley Railroad Company
(i) Allegheny Branch rail rehabilitation1,336,000

(Base Project Allocation - $1,203,000)

(Design and Contingencies - $133,000)

(ii) Rehabilitation of Allegheny, Brilliant and River Branches1,032,000

(Base Project Allocation - $929,000)

(Design and Contingencies - $103,000)

(2) Bessemer and Lake Erie Railroad
(i) Rehabilitation and replacement of rail infrastructure to maintain capacity and operating capability, including replacement of deteriorating ballast, rail, ties and turnouts; renew grade crossings and profile grind existing rail from MP 0 to MP 80 in Allegheny, Butler and Mercer Counties10,467,000

(Base Project Allocation - $10,467,000)

(ii) Expand track capacities in Butler County to support the Victory Road Industrial Park located at Saxonburg, including rehabilitation and reconstruction of existing rail infrastructure, switches, turnouts and other related material1,000,000

(Base Project Allocation - $1,000,000)

(iii) Rehabilitation and replacement of rail infrastructure to correct poor drainage and bad ballast in main line track structure and to rehabilitate and replace rail, ties and turnouts; renew grade crossings and profile grind existing rail to maintain current tonnage and speed capacities of the line. MP 81 to MP 134 in Mercer, Crawford and Erie Counties8,425,000

(Base Project Allocation - $8,425,000)

(iv) Develop new yard track structure within Greenville complex to support expanded rail-truck transfer market in the Mercer County area667,000

(Base Project Allocation - $667,000)

(3) Buffalo and Pittsburgh Railroad, Inc.
(i) Rehabilitation of rail line to Petrolia, including the replacement of rails, ties, ballast, surface, switch, road crossings, bridge and other rail-related infrastructure in Butler County8,600,000

(Base Project Allocation - $8,000,000)

(Design and Contingencies - $600,000)

(ii) Upgrade Riker Yard at Punxsutawney to Rossiter in Jefferson County to increase capacity, including rail, railroad ties, ballast, switches and other related infrastructure improvements and expand Butler Yard capacity, including rails, railroad ties, ballast, additional switches and other related infrastructure improvements1,100,000

(Base Project Allocation - $1,000,000)

(Design and Contingencies - $100,000)

(iii) Rehabilitation and infrastructure improvements to the Buffalo and Pittsburgh Railroad and Dubois Yard for a new transload facility, including the replacement of rails, ties, ballast, surface, switch, road crossings, bridge and other rail-related infrastructure2,200,000

(Base Project Allocation - $2,000,000)

(Design and Contingencies - $200,000)

(iv) Rehabilitate the Buffalo and Pittsburgh railroad from Eidenau to New Castle, including the replacement of rails, ties, ballast, surface, switch, road crossings, bridge and other rail-related infrastructure6,640,000

(Base Project Allocation - $6,000,000)

(Design and Contingencies - $640,000)

(v) Replace selected rail and railroad ties on various curves and replace various switches and signals to handle additional stress and weight between Punxsutawney and Bradford2,750,000

(Base Project Allocation - $2,500,000)

(Design and Contingencies - $250,000)

(vi) Rehabilitation of main line track to restore service from Creekside to Homer City, Indiana County, including ties, rail, surface, bridge switches, road crossings, signal, communication and any other related work2,800,000

(Base Project Allocation - $2,520,000)

(Design and Contingencies - $280,000)

(vii) Rehabilitation of 12 bridges and replacement of three bridges on the Buffalo and Pittsburgh line to Petrolia in Butler County600,000

(Base Project Allocation - $600,000)

(viii) Phase 2 of the rehabilitation project to upgrade an additional 24 miles of track to Homer City8,400,000

(Base Project Allocation - $7,560,000)

(Design and Contingencies - $840,000)

(ix) Allegheny River bridge project1,325,000

(Base Project Allocation - $1,193,000)

(Design and Contingencies - $132,000)

(x) Beaver County rail rehabilitation project3,000,000

(Base Project Allocation - $2,700,000)

(Design and Contingencies - $300,000)

(xi) Northern subdivision rail rehabilitation project3,000,000

(Base Project Allocation - $2,700,000)

(Design and Contingencies - $300,000)

(4) Delaware and Hudson Railway Company
(i) Construct an additional two-mile passing siding on the Delaware and Hudson Railway in Lackawanna County between Scranton and the New York State line to facilitate increased rail traffic from the Port of Philadelphia to Canada, including signals, switches, rail, ballast, ties and other related rail infrastructure2,750,000

(Base Project Allocation - $2,500,000)

(Design and Contingencies - $250,000)

(ii) Rehabilitate and construct a two-mile passing siding in Luzerne County between Sunbury and Scranton on the Delaware and Hudson Railway to facilitate increased traffic from the Port of Philadelphia to Canada, including signals, switches, rail, ballast, ties and other related rail infrastructure2,750,000

(Base Project Allocation - $2,500,000)

(Design and Contingencies - $250,000)

(iii) Rehabilitation of Delaware and Hudson main line in Luzerne County from MP 688 to MP 713, including ballast undercuts and replacement of ties and worn rail1,084,000

(Base Project Allocation - $985,000)

(Design and Contingencies - $99,000)

(iv) Rehabilitate and construct facility village intermodal facility in Luzerne County at Avoca for transloading various customer commodities at a former brownfield2,200,000

(Base Project Allocation - $2,000,000)

(Design and Contingencies - $200,000)

(v) Construction and rehabilitation of rail transportation control systems along the Delaware and Hudson rights-of-way from Sunbury to State line to improve communications system and safety for handling increased traffic from the Port of Philadelphia5,500,000

(Base Project Allocation - $5,000,000)

(Design and Contingencies - $500,000)

(vi) Rehabilitation of existing track and construction of new track to service bulk handling facility module in Lackawanna County, including new switching timbers, turnouts, track upgrade, including, but not limited to, track infrastructure materials, grading, filing, drainage, lighting, fencing and other associated improvements495,000

(Base Project Allocation - $450,000)

(Design and Contingencies - $45,000)

(vii) Refurbish approximately 3,000 feet of track and install and rehabilitate turnout at former Nanticoke Yard to handle transfer of bulk commodities990,000

(Base Project Allocation - $900,000)

(Design and Contingencies - $90,000)

(viii) Rebuild approximately 5,000 feet of track infrastructure at Old Honey Pot Yard at Nanticoke for the location of a bulk transfer facility633,000

(Base Project Allocation - $575,000)

(Design and Contingencies - $58,000)

(ix) Main line rehabilitation and new siding construction, construction of new track and rehabilitation of existing track to service bulk handling facility module495,000
(x) Rail rehabilitation project5,250,000

(Base Project Allocation - $4,725,000)

(Design and Contingencies - $525,000)

(5) Kiski Junction Railroad
(i) Extension of a railroad line from the terminus of Kiski Junction's line to the Logansport area of Bethel Township3,000,000
(5.1) Lackawanna County Railroad Authority
(i) Scranton to Mt. Pocono rail rehabilitation675,000

(Base Project Allocation - $607,000)

(Design and Contingencies - $68,000)

(5.2) Monroe County Railroad Authority
(i) Track and signal rehabilitation project356,000

(Base Project Allocation - $321,000)

(Design and Contingencies - $35,000)

(6) Pittsburgh and Shawmut Railroad, Inc.
(i) Rehabilitation and infrastructure improvements to the railroad in the Clearfield area3,300,000
(ii) Construction of rail siding in Armstrong County to access Freeport terminal located in Freeport, from the Pittsburgh and Shawmut Railroad, including a new rail spur with multiple sidings for transfer and loading and unloading of various commodities and construction of a connection to existing railroad including access under the Norfolk Southern Conemaugh line3,850,000

(Base Project Allocation - $3,500,000)

(Design and Contingencies - $350,000)

(iii) Rehabilitate railroad in Armstrong County from Freeport to Redco and the Mosgrove Industrial, including replacement of ties, rail, ballast, switches and other rail-related infrastructure3,850,000

(Base Project Allocation - $3,500,000)

(Design and Contingencies - $350,000)

(iv) Rehabilitate the Pittsburgh and Shawmut railroad from Sligo to DuBois, including the replacement of rails, ties, ballast, surface, switch, road crossings, bridge and other rail-related infrastructure3,300,000

(Base Project Allocation - $3,000,000)

(Design and Contingencies - $300,000)

(v) Armstrong County rail rehabilitation project400,000

(Base Project Allocation - $360,000)

(Design and Contingencies - $40,000)

(vi) Rail rehabilitation project600,000

(Base Project Allocation - $540,000)

(Design and Contingencies - $60,000)

(6.2) Redevelopment Authority of Luzerne County
(i) Rail and bridge maintenance516,000

(Base Project Allocation - $464,000)

(Design and Contingencies - $52,000)

(7) RJ Corman Railroad
(i) Rehabilitate and reconstruct 3.1-mile coal-loading spur on railroad in Clearfield County near Westover2,000,000
(ii) Rehabilitation of the rail line known as the Clearfield Cluster, located in Cambria, Clearfield, Centre, Indiana and Jefferson Counties3,000,000
(8) Wheeling & Lake Erie Railway Company
(i) Rehabilitate Clairton branch of Wheeling & Lake Erie Railway in Allegheny County to access major customer, including rail, ties, ballast and other infrastructure and bridge improvements660,000

(Base Project Allocation - $600,000)

(Design and Contingencies - $60,000)

(ii) Rehabilitation, restoration and infrastructure improvements for portions of the main line of the Wheeling & Lake Erie railway, including rails, ties, ballast, switches and development of rail sidings in Westmoreland, Fayette and Allegheny Counties2,750,000

(Base Project Allocation - $2,500,000)

(Design and Contingencies - $250,000)

(iii) Purchase of West End Branch and a portion of the main line of the Wheeling & Lake Erie Railway from Bridgeville to Longview Branch, including Rook Yard and the Railroad Tunnel under Greentree Hill to facilitate highway and mass transit improvements, including the construction of the Banksville Connector and the creation of two new transportation corridors to downtown Pittsburgh as well as the reconstruction and relocation of the Wheeling Lake-Erie interchange facilities at Rook Yard and the reconstruction of the Wheeling & Lake Erie Interchange with CSX at a new location55,000,000
(9) York Railway Company
(i) Consulting, preliminary engineering, environmental studies and construction and expansion of existing rail line corridor to the southern end of Conewago Township in York County20,000,000
(10) Elk County
(i) St. Mary's
(A) Construction and development of a rail system to serve the Intermodal Warehouse within a Keystone Opportunity Zone250,000
(11) Philadelphia County
(i) Rotem Company
(A) Rebuild and construct railroad infrastructure at the Philadelphia Naval Yard in coordination with Rotem Company and Philadelphia Authority for Industrial Development, including rails, switches, crossings, ballast and other related materials such as electrical signals and other appurtenances leading to and including Building 6032,750,000

(Base Project Allocation - $2,500,000)

(Design and Contingencies - $250,000)

(ii) James J. Anderson Construction Company
(A) Rehabilitation of the existing rail unloading facility and side track, including rail, ties, crossings and other track-related improvements300,000
(12) Wayne and Pike Counties
(i) Lackawaxen - Honesdale Shippers Association
(A) Track maintenance between mileposts 110 and 13270,000
(13) Mercer County
(i) Duferco Farrell Corporation
(A) Rehabilitation and additions to the railroad infrastructure5,000,000
(14) Western New York and Pennsylvania Railroad, LLC
(i) Additions and betterments to the former Erie Lackawanna Railway track in Crawford, Erie, Warren and surrounding counties, as necessary, to assure the ability to continue to provide through rail freight service necessary to the economic development of these counties. Work may include, but is not limited to, grading, ballast, cross ties, rail replacement and renewal, bridge rehabilitation, grade crossing and grade crossing protection renewal and signal repair.8,000,000

(Base Project Allocation - $7,200,000)

(Design and Contingencies - $800,000)

(ii) State line to Meadville rail rehabilitation project1,933,000

(Base Project Allocation - $1,740,000)

(Design and Contingencies - $193,000)

(iii) Track connections project1,200,000

(Base Project Allocation - $1,080,000)

(Design and Contingencies - $120,000)

(15) CSX Transportation
(i) Establishment of double-stack vertical clearances on the CSX Trenton Line between Park Junction at City of Philadelphia and the State Line in Bucks and Philadelphia Counties10,000,000

(Base Project Allocation - $10,000,000)

(ii) Coal yard rehabilitation6,075,000

(Base Project Allocation - $5,468,000)

(Design and Contingencies - $607,000)

(iii) Construction of Engleside connection2,500,000

(Base Project Allocation - $2,250,000)

(Design and Contingencies - $250,000)

(iv) Fairless Branch rail rehabilitation project2,250,000

(Base Project Allocation - $2,025,000)

(Design and Contingencies - $225,000)

(v) Rehabilitation of South Broad Street tracks1,125,000

(Base Project Allocation - $1,013,000)

(Design and Contingencies - $112,000)

(vi) Rehabilitation of 25th Street viaduct7,500,000

(Base Project Allocation - $6,750,000)

(Design and Contingencies - $750,000)

(16) Mid-Atlantic Rail Operation Study
(i) For Phase I projects identified in the MAROPS as part of their Pilot Demonstration Program. The projects will increase rail freight and intercity rail capacity. Grant participants are Norfolk Southern Railroad, CSX Transportation and Amtrak. Project locations include from New Jersey, North-South through Philadelphia to the Delaware State Line from Philadelphia to Harrisburg and from Harrisburg to Maryland State Line.114,600,000

(Base Project Allocation - $114,600,000)

(17) Norfolk Southern
(i) Construction of a connecting track from the Lurgan Branch at Lemoyne to milepost 66.8 on Port Road Secondary/Enola Branch in order to access Enola Yard directly9,600,000
(ii) Construction of a second track on the main line between Harris to CP Rockville3,500,000

(Base Project Allocation - $3,500,000)

(iii) Construction of a second track on the Reading Line between Blandon and Laurel to create a double track line, including the construction of four new bridges, two new interlockings, TCS and crossing upgrades9,500,000

(Base Project Allocation - $9,500,000)

(iv) Rehabilitation of track to improve horizontal and vertical clearances and upgrade track to accommodate the 286K railcars on the Keystone Line of the Amtrak Keystone Corridor10,000,000
(v) Restore connection between Philadelphia freight bypass track and Amtrak's Northeast Corridor at Zoo interlocking10,000,000
(vi) Construct 1.5 miles of additional main line track between Wyomissing Junction and Valley Junction15,600,000
(vii) Construct four miles of additional main line track between Penn Junction and Bethlehem16,000,000
(18) North Shore Railroad
(i) Construction of new interchange track with SEDA-COG system of North Shore Railroad and Delaware and Hudson to handle new customer traffic demands2,171,000

(Base Project Allocation - $1,953,000)

(Design and Contingencies - $218,000)

(19) Reading Blue Mountain and Northern Railroad
(i) Upgrade of welded rail on the Lehigh Line due to increased traffic and to accommodate the use of the 286K rail car in Carbon, Luzerne, Lackawanna and Wyoming Counties1,100,000

(Base Project Allocation - $1,000,000)

(Design and Contingencies - $100,000)

(ii) Rehabilitation of Tamaqua Tunnel to remove clearance obstruction on the Reading Division in Schuylkill County450,000

(Base Project Allocation - $400,000)

(Design and Contingencies - $50,000)

(iii) Construction of Nesquehoning Bridge wye and runaround at Nesquehoning Junction in Carbon County900,000

(Base Project Allocation - $810,000)

(Design and Contingencies - $90,000)

(iv) CNJ Bridge project563,000

(Base Project Allocation - $507,000)

(Design and Contingencies - $56,000)

(v) Nesquehoning Bridge Project
(A) Construction of a second span over the Lehigh River adjacent to the existing bridge5,000,000
(20) SEDA-COG Joint Rail Authority
(i) Removal of an existing railroad bridge that crosses the Loyalsock Creek near Montoursville Borough and construction of a new combination highway/railroad bridge that will interconnect with SR 2014 and Interstate 180 and raising the trackage at both approaches to the Lycoming Valley Railroad Bridge4,600,000

(Base Project Allocation - $3,450,000)

(Land Allocation - $150,000)

(Design and Contingencies - $1,000,000)

(21) Lycoming Valley Railroad
(i) Construction of replacement railroad bridge over Loyalsock Creek located in Montoursville, Lycoming County, including related track improvements and the removal of existing bridge5,600,000
(22) Air Products and Chemicals
(i) Improvement of railroad clearances between Wilkes-Barre and the Port of Novolog, Bucks County3,500,000
(23) Bethlehem Commerce Center Railroad Facilities
(i) Construct railroad storage tracks and access tracks to customer facilities within the Bethlehem Commerce Center8,000,000
(24) Valley Distributing and Storage Company
(i) Rehabilitation and reconstruction of existing siding in Laflin and Jenkins Townships, Luzerne County, to include crosstie replacement, surfacing and other related work to handle inbound shipments and to allow for increase in the volume of rail freight business and provide a more efficient and safer rail operation231,000
(25) Morristown and Erie Railroad (Octoraro Line)
(i) Improvements to the former Penn Central Octoraro Line in Chester and Delaware Counties, including, but not limited to, repair and rehabilitation of embankments, bridges, ballast, ties, rail, grade crossings and crossing signal systems1,100,000

(Base Project Allocation - $1,000,000)

(Design and Contingencies - $100,000)

(ii) Improvements to the Octoraro Branch Rail Line from Chadds Ford to Nottingham3,000,000
(26) Carbon County
(i) Former CNJ Bridge, rehabilitation of the former CNJ Bridge located near Nesquehoning to include construction of the approaches into the bridge and connections required on each side to the main lines227,000
(27) Clearfield County
(i) River Hill Coal Company, Inc.
(A) Rehabilitate and reconstruct 3.1-mile coal-loading spur on the RJ Corman Railroad near Westover, including switches, signals, rail, ties, ballast and other related railroad construction materials needed for creating an efficient loading site for unit trains of coal2,200,000

(Base Project Allocation - $2,000,000)

(Design and Contingencies - $200,000)

(ii) Sunnyside Ethanol LLC
(A) Rehabilitation and replacement of rail trackage to begin rail shipments, including replacement of deteriorating and/or missing ballast, rail, ties, switches and turnouts and the construction of a bridge, culverts and ditches1,250,000
(28) Northampton County
(i) City of Bethlehem
(A) Acquisition of abandoned Norfolk Southern Railroad right-of-way from Hellertown/Bethlehem municipal line, west to former Union Station and development of new Linear Park and Urban Greenway2,000,000
(29) Allegheny County
(i) Allegheny Valley Commuter Rail
(A) Improvements to existing rail lines and purchase of passenger train cars and engine to develop commuter rail from New Kensington to downtown Pittsburgh27,000,000
(ii) Allegheny Valley Intermodal Center
(A) Acquisition and development of an intermodal center10,000,000

(Base Project Allocation - $8,000,000)

(Design and Contingencies - $2,000,000)

(30) Pittsburgh and Ohio Central Railroad
(i) Rehabilitation of 5.1 miles of existing rail track on Neville Island to Duff's Junction (mileposts 0.0 to 5.1) for the handling of Neville Island freight traffic. Rehabilitation will include, but not be limited to, ties, switch timbers, track upgrade, track infrastructure materials, grading, drainage and other associated improvements.867,000
(ii) Rehabilitation of 5.5 miles of existing track from Houston to the end of the line at Arden on the Arden Branch (mileposts 14.85 to 20.35) for the hauling of rail freight traffic. Rehabilitation will include, but not be limited to, ties, switch timbers, track upgrade, track infrastructure materials, grading, drainage and other associated improvements.834,000
(31) Fayette County
(i) Fayette Rail Project, building and track construction and renovation for passenger service750,000
(32) Westmoreland County
(i) City of Monessen
(A) Monessen Riverfront Industrial Park, construct new rail spur, including switches, signals, ties, ballast, rail and other related railroad construction materials, from CSX and Wheeling and Lake Erie rail lines to serve the new Maronda, Inc., facility550,000
(B) Monessen Riverfront Industrial Park, reconstruct 12th Street rail crossing to service CSX and Wheeling and Lake Erie Lines to serve the industrial park450,000
(33) Lackawanna County
(i) Extension of Lackawanna County rail authority line in Dunmore3,500,000
(34) Clarion and Jefferson Counties
(i) RFI Energy
(A) Rehabilitation of 48 miles of rail line, install crossties, raise line and surface, Laurel subdivision and Sligo branch, including Shannon Coal Yard2,000,000
(35) United States Steel Corporation, Clairton Works
(i) Rehabilitation and replacement of rail infrastructure to maintain capacity and operating capability, including replacement of deteriorating ballast, rail, ties, switches and turnouts and the reconstruction of culverts and ditches. Enhance existing bridges and load out tracks to accommodate heavier cars, increased loading frequency and upgrade rail rating from 115 pounds to 136 pounds.5,020,000

(Base Project Allocation - $5,000,000)

(Design and Contingencies - $20,000)

(36) Warren County
(i) Ellwood National Forge, Irvine Plant
(A) Rehabilitation and replacement of rail infrastructure to maintain capacity and operating capability, including replacement of deteriorating ballast, rail, ties, switches and turnouts and the construction of culverts and ditches. Enhance loadout tracks to accommodate heavier cars, increased loading frequency and upgrade rail load rating.420,000
(ii) Hyma-Devore Lumber Company
(A) Rehabilitation and replacement of rail siding to begin rail shipments, including replacement of deteriorating ballast, rail, ties, switches and turnouts and the construction of culverts and ditches250,000
(37) Bucks County
(i) Improvement of railroad clearances between Wilkes-Barre and the Port of Novolog3,500,000
(38) Wyoming County
(i) Repair and rehabilitation of Tunkhannock Viaduct railroad bridge located in Nicholson Township7,000,000
(39) Franklin County
(i) Franklin Storage L.P.
(A) Construct a 4,000-foot rail siding, including a new switch from the Norfolk Southern track located in Guilford Township to access a 200-acre development serving warehousing logistics facilities for local distribution850,000
(B) Construct a 2,000-foot rail siding, including a new switch from the Norfolk Southern track located in Guilford Township to access a 100-acre development serving warehousing logistics facilities for local distribution600,000
(C) Construct two rail sidings totaling 3,000 feet, including two switches from the Norfolk Southern track located in Antrim Township to access a business park serving warehousing logistics for local distribution900,000
(40) Franklin & Marshall, Lancaster County
(i) Relocation of Norfolk Southern's Dillerville Yard to the proposed Northside Yard in Lancaster County. Work to include, but not be limited to, relocation of track, switches, power transmission lines, railroad office buildings, unloading facilities, road crossings, earth work, engineering and any other costs associated with this project.13,500,000

(Base Project Allocation - $11,430,000)

(Land Allocation - $250,000)

(Design and Contingencies - $1,820,000)

(41) Resource Recovery LLC - Clearfield County and Centre County
(i) Rehabilitation and replacement of 17 miles of rail trackage to begin rail shipments, including replacement of deteriorating and/or missing ballast, rails, ties, switches and turnouts and the construction of a bridge, culverts and ditches8,500,000

(c) Air transportation.--Additional capital projects in the category of transportation assistance projects for air transportation service to which an interest is to be acquired by the Department of Transportation, its successors or assigns and to be financed by the incurring of debt are hereby itemized, together with their respective estimated financial costs, as follows:

ProjectTotal Project Allocation
(1) Allegheny County
(i) Pittsburgh International Airport
(A) Environmental impact studies and preliminary engineering10,000,000
(B) Construction of maintenance and repair facility and improve and/or upgrade existing facilities50,000,000
(1.1) Beaver County
(i) Zelienople Airport
(A) Construction of T-hangars108,000
(B) Construction of airport access road275,000
(1.2) Bedford County
(i) Bedford County Air Industrial Park Authority
(A) Acquisition of snow removal equipment115,000
(B) Expansion of FBO public parking40,000
(C) Land acquisition for runway obstruction removal650,000
(D) Conduct archeological study100,000
(E) Conduct environmental assessment200,000
(1.3) Blair County
(i) Blair County Airport Authority
(A) Construction of two T-hangar units750,000
(1.4) Bradford County
(i) Bradford County Airport
(A) Construction of corporate hangars250,000
(B) Construction of T-hangars150,000
(2) Bucks County
(i) Doylestown Airport
(A) Acquisition of land for runway extension and development and construction of hangars1,965,000
(B) Airport improvements, including rehabilitation of access road and storm water facility and other improvements500,000
(ii) Quakertown Airport
(A) Construction of hangars and land acquisition for airport development702,000
(3) Butler County
(i) Butler County Airport
(A) Acquisition, construction, restoration, rehabilitation and infrastructure improvements for the Butler County Airport Expansion Project3,000,000
(B) Construction of an 800-foot extension to Runway 8-26225,000
(4) Chester County
(i) G.O. Carlson
(A) Construction of east T-hangar taxiways, 900 feet by 35 feet, Phase II, design463,000
(ii) New Garden Flying Field
(A) Land acquisition for airport transfer and construction of hangars2,194,000
(5) Clarion County
(i) Clarion County Airport
(A) Runway expansion3,000,000
(5.1) Clinton County
(i) William T. Piper Memorial Airport
(A) Renovations to Hangar 1/Terminal Building100,000
(B) Installation of two automated card-reading fuel dispensing systems30,000
(6) Cumberland County
(i) Capital City Airport
(A) Rehabilitation of existing aviation facilities and construction of new hangars200,000
(ii) Carlisle Airport
(A) Land acquisition for airport transfer and construction of hangars3,000,000
(7) Dauphin County
(i) Harrisburg International Airport
(A) Construction of multimodal terminal facility20,000,000
(B) Enhancement to existing airport terminal facilities and construction of new terminal area improvements6,000,000
(7.1) Elk County
(i) St. Marys Area Airport Authority
(A) Construction of a terminal/administration building, hangars, runway extension and various other airport improvements1,000,000
(8) Erie County
(i) Erie International Airport
(A) Construction of an extension to Runway 6-24 and related improvements1,125,000
(9) Fayette County
(i) Connellsville Airport
(A) Construction of a 1,200-foot extension to Runway 5-23963,000
(9.1) Greene County
(i) Franklin Township
(A) Construction, infrastructure development and improvements as part of the Greene County Airport expansion, including, but not limited to, a business airpark, new T-hangars and expanding the terminal building facility4,000,000
(10) Indiana County
(i) Jimmy Stewart Airport
(A) Airport improvements, including relocation of Geesey Road for runway extension and construction of runway extension475,000
(11) Lancaster County
(i) Lancaster Airport
(A) Runway extension and related projects and acquisition and/or construction of hangar facilities900,000
(B) Infrastructure and site development improvements for airport business park2,000,000
(C) Site development and construction of corporate hangar and offices1,600,000
(D) Site development and construction of T-hangar complex750,000
(12) Lehigh County
(i) Lehigh Northampton Airport Authority
(A) Braden Airpark, for rehabilitation of the General Aviation Terminal1,000,000
(B) Lehigh Valley International Airport, for construction of an aircraft hangar, offices and shops5,000,000
(C) Lehigh Valley International Airport, for construction of a North Side General Aviation Pilot Facility325,000
(D) Queen City Airport, for rehabilitation and expansion of the General Aviation Terminal Building1,150,000
(E) Queen City Airport, for hangar door systems replacement at Hangars 1 through 3238,000
(13) Lycoming County
(i) Williamsport Regional Airport
(A) Construction of new hangars, including demolition of existing hangars and site preparation1,000,000
(ii) Jersey Shore Airport
(A) Land acquisition, design and construction of a secondary runway500,000
(14) McKean County
(i) Bradford Regional Airport
(A) Infrastructure improvements at Bradford Regional Airport900,000
(B) Installation of utility infrastructure for airport development400,000
(15) Mercer County
(i) Grove City Airport
(A) Construction of T-hangars for aircraft storage175,000
(16) Mifflin County
(i) Mifflin County Airport
(A) T-hangars and other airport improvements and acquisitions, including land acquisition613,000
(17) Monroe County
(i) Pocono Mountain Municipal Airport
(A) Construction of terminal hangar combination2,100,000
(18) Montour County
(i) Danville, restoration and rehabilitation of airport runway300,000
(19) Philadelphia County
(i) Philadelphia International Airport
(A) Mechanical, electrical and structural improvements to existing facilities3,000,000
(20) Schuylkill County
(i) Joe Zerbey Airport
(A) Design and construction of Runway No.11 extension to 5,100 feet2,000,000
(B) Construction of runway safety area improvements, including runway extension39,000
(21) Snyder County
(i) Penn Valley Airport Authority
(A) Airport improvements, including, but not limited to, rehabilitation of existing hangars and construction of new hangars500,000
(22) Somerset County
(i) Somerset County Airport
(A) Construction of a 300-foot extension to Runway 6-2441,000
(22.1) Washington County
(i) Washington County Airport
(A) Construction of terminal building2,000,000
(B) Northside access road2,900,000
(C) T-hangars800,000
(23) Westmoreland County
(i) Westmoreland County Airpark
(A) Phase II Project, infrastructure development and improvements500,000
(ii) Arnold Palmer Regional Airport
(A) Terminal building expansion and improved parking facilities2,000,000
(B) Aviation hangar750,000
(C) Runway extension2,500,000
(D) Public Safety Building2,500,000
(24) York County
(i) Air Transportation Authority of York County
(A) Construction of new hangars at the York Airport200,000

Section 6. Itemization of redevelopment assistance projects.

Additional capital projects in the category of redevelopment assistance projects for capital grants by the Department of Community and Economic Development, its successors or assigns authorized under the provisions of the act of May 20, 1949 (P.L.1633, No.493), known as the Housing and Redevelopment Assistance Law, and redevelopment assistance capital projects to be financed by the incurring of debt are hereby itemized, together with their estimated financial costs, as follows:

ProjectTotal Project Allocation
(1) Adams County
(i) County Projects
(A) Infrastructure development, site development and design and construction of buildings and exhibits related to the construction of a new museum and visitors center at the Gettysburg National Military Park, including preservation, restoration and conservation of artifacts and manuscripts, including the Cyclorama painting. This project shall be construed as a supplement to the project authorized in section 6(1)(i)(B) of the act of October 30, 2002 (P.L.891, No.131), known as the Capital Budget Project Itemization Act of 2001-2002.10,000,000
(B) Construction and development of visitor center10,000,000
(ii) Borough of Gettysburg
(A) Construction, rehabilitation and improvement of the Majestic Theatre12,000,000
(B) Construction and development of the Music Shed at Gettysburg2,000,000
(C) Redevelopment of a blighted one-block area of Downtown Gettysburg just north of the CSX Rail tracks between Carlisle Street and Stratton Street, including planning, engineering, property acquisition, demolition, remediation, infrastructure improvements and site development3,000,000
(2) Allegheny County
(i) City of Pittsburgh
(A) Acquisition, construction and rehabilitation of properties as part of the Garden Square North Development Project within a Keystone Opportunity Zone2,000,000
(B) Acquisition and construction of the Centre Avenue mixed-use development project in the Hill District1,500,000
(C) Acquisition, construction and rehabilitation of an education facility, gallery space and improvements to the Mattress Factory Museum844,000
(D) Development of a recreation and tourism facility as part of the South Shore Riverfront Park development3,500,000
(E) Construction of a new Community/Recreation Center, 31st Ward, City of Pittsburgh1,000,000
(F) Grant Street Transportation Center, construction of an intermodal transportation facility in downtown Pittsburgh4,000,000
(G) SouthSide Works Parking Garages, construction of two parking garages to support mixed-use redevelopment at the former LTV SouthSide Works3,000,000
(H) Washington Boulevard, below the Veteran's Hospital, preparation of sites for office development on a 15-acre parcel owned by the Urban Redevelopment Authority5,000,000
(I) Nine Mile Run Phase II, site preparation and development for Phase II of the Summerset development in the City of Pittsburgh5,000,000
(J) Construction, site development and infrastructure improvements as part of the Three Rivers Rowing Association Expansion Project2,200,000
(K) Convention Center Hotel, site preparation and construction of hotel facility adjacent to the David Lawrence Convention Center in the City of Pittsburgh54,000,000
(L) Construction, restoration, rehabilitation and infrastructure improvements of Panther Hollow7,500,000
(M) West Carson Street from Station Square to the West End Bridge, acquisition, site preparation and infrastructure to remove blight and create development sites5,000,000
(N) Construction, renovation and infrastructure improvements to the Pittsburgh Center for the Arts643,000
(O) Uptown/Oakland corridor development, acquisition, demolition, site preparation and infrastructure to prepare sites for development. This project shall be construed as a supplement to the project authorized in section 6(2)(i)(EE) of the Capital Budget Project Itemization Act for 2001-2002.5,000,000
(P) Children's Home of Pittsburgh, construction of a new facility for the acute care hospital, pediatric extended care program and a pediatric transition unit, including land acquisition12,000,000
(Q) Construction of the 31st Ward Building and Recreational Center1,000,000
(R) North Shore redevelopment and public improvements13,000,000
(S) Development of hotel in conjunction with David L. Lawrence Convention Center expansion27,000,000
(T) YMCA of Pittsburgh, refurbishing and repair to existing buildings2,500,000
(U) Children's Hospital of Pittsburgh, development and construction of a pediatric oncology center10,000,000
(V) Children's Hospital of Pittsburgh, development and construction of a 235-bed pediatric inpatient tower20,000,000
(W) Children's Hospital of Pittsburgh, expansion and renovation for additional research and support10,000,000
(X) Pittsburgh Mercy Health System, construction of a new parking garage and demolition of existing structures to provide additional patient parking spaces at Mercy Hospital10,000,000
(Y) Pittsburgh Mercy Health System, improvements to Mercy Health Center outpatient primary care and specialty clinics, including construction of an addition and renovation of existing spaces4,000,000
(Z) Pittsburgh Mercy Health System, renovation and expansion of the Mercy Hospital Emergency Department4,000,000
(AA) Pittsburgh Mercy Health System, reconstruction and relocation of the Mercy Hospital Pediatrics Ward700,000
(BB) Pittsburgh Mercy Health System, expansion and reconstruction of the Mercy Hospital Obstetrics Ward1,300,000
(CC) Downtown parking garages and intermodal facilities10,000,000
(DD) 8th Street block development10,000,000
(EE) North Shore public improvements and redevelopment, including development of entertainment venues20,000,000
(FF) Heinz Hall, renovations and improvements of the Downtown Music Education School4,000,000
(GG) Carnegie Museum of Art and Museum of Natural History, renovations5,500,000
(HH) Homewood industrial/commercial site acquisition4,000,000
(II) Pittsburgh Air and Space Museum, new construction55,000,000
(JJ) Renovation of Allegheny County Courthouse10,000,000
(KK) Pittsburgh Children's Museum, renovations and expansion of facility and construction and renovation to develop a collaborative children's campus of buildings on grounds of adjacent property5,000,000
(LL) Additional renovations to the WQED Pittsburgh facility2,000,000
(MM) Carlow College, construction of a campus center for health and wellness10,000,000
(NN) The Western Pennsylvania Hospital School of Nursing, renovations, equipment and improvements5,000,000
(OO) Andy Warhol Museum, renovations and expansion1,000,000
(PP) Forbes Avenue Pavilion, renovations and expansion10,000,000
(QQ) Construction and renovation of Regent Square Theater1,450,000
(RR) Renovation of existing buildings and acquisition and renovation of adjacent buildings to create the Pittsburgh Filmmakers Media Campus in the North Oakland section of Pittsburgh10,000,000
(SS) Renovations to the Soldiers and Sailors National Military Museum and Memorial2,500,000
(TT) Broadway Avenue revitalization in Beechview neighborhood, City of Pittsburgh2,000,000
(UU) Construction of film studio/media center/sound stage located within the City of Pittsburgh10,000,000
(VV) Arlington Heights, site stabilization, grading, site preparation and infrastructure needed to transform this former public housing project into a mixed-use development that will stabilize a neighborhood in transition2,500,000
(WW) Hazelwood, renovation of former middle school and acquisition, construction and site preparation in the area surrounding the 4700 and 4800 blocks of Second Avenue and on Monongahela Street10,000,000
(XX) Revitalization of the Fifth Avenue and Forbes Avenue corridor in the central business district of downtown Pittsburgh10,000,000
(YY) Construction of the Junction Hollow R & D Center for technology and research companies10,000,000
(ZZ) Construction of the North Shore Amphitheater4,000,000
(AAA) East Liberty industrial/commercial acquisition and development including site preparation and infrastructure improvements6,000,000
(BBB) Construction of a multipurpose community center in the Lincoln-Larimar area of Pittsburgh1,400,000
(CCC) Bedford Hill, Phase II2,000,000
(DDD) Development and construction of a parking garage on the Mercy Hospital Campus10,000,000
(EEE) Expansion and renovation of the Mercy Hospital Emergency Department4,000,000
(FFF) Expansion and renovation of the Mercy Hospital Obstetrics Unit1,300,000
(GGG) Carnegie Music Hall, renovations and preservation measures1,000,000
(ii) Bloomfield
(A) Construction, rehabilitation, restoration and infrastructure improvements to the school of nursing5,000,000
(iii) County Projects
(A) Navigational signage in the Alle-Kiski Region on State and local highways to promote tourism and cultural heritage and improve safety within portions of Allegheny, Armstrong, Butler and Westmoreland Counties2,000,000
(B) Coordinate system of tourist and heritage facilities10,000,000
(C) Pittsburgh Mills Entertainment/Retail Complex, development of commercial and office space22,500,000
(D) The Carrie Furnace Redevelopment Area, Braddock, site acquisition, preparation and construction associated with the development of a mixed-use residential/professional/commercial area in the Mon Valley7,000,000
(E) Carnegie, restoration and revitalization of the Andrew Carnegie Library to be used as a cultural community center for Chartiers Valley communities3,454,000
(F) Collier Commerce Center, site preparation and development for a business park in Collier Township5,000,000
(G) Lincoln Larimer redevelopment, East Liberty, infrastructure, acquisition, demolition, reconstruction and public space improvements10,000,000
(H) Leetsdale Industrial Park Internal Access Road, provide ingress and egress to the Borough's business areas and surrounding community1,800,000
(I) Infrastructure realignment and improvements to the Ross Township Business District1,000,000
(J) Construction and infrastructure improvements as part of the Shaler Township Water Storage Project3,000,000
(K) Streetscape development of the Braddock riverfront area, including the Carrie Furnace site and 130 acres of brownfields and creation of the Steel Heritage Park3,000,000
(L) Andy Warhol Museum, extensive renovations to the museum located in Pittsburgh1,000,000
(M) Forbes Avenue Pavilion Project, construction of a 26,500-square-foot addition to consolidate the visitor functions for the Museum of Art and History in Pittsburgh10,000,000
(N) Construction related to the Winged Pines mine drainage passive purification project1,500,000
(O) South Park, rehabilitation of park amphitheater, refurbishing of existing and construction of new public restrooms and rehabilitation of the Schoonmaker Hall building and skate park2,000,000
(P) South Park, rehabilitation of ice rink, including replacement of chilling equipment, refurbishment of skating surface and improvements to the lodge1,500,000
(Q) Settlers Cabin Park, rehabilitation of park infrastructure, shelters and groves and improvements to the Botanical Gardens, resurfacing of tennis courts and construction of new restrooms1,000,000
(R) Panhandle Trail, rehabilitation and reconstruction of trail surface, adjoining easements and bridge spans comprising the Panhandle trail system in Allegheny County650,000
(S) Montour Trail, rehabilitation and reconstruction of trail surface, adjoining easements and bridge spans comprising the Montour Trail system in Allegheny County2,000,000
(T) Phipps Conservatory, Botanical Gardens, construction and renovation of conservatory, education pavilion and related buildings, Phase II5,125,000
(U) Allegheny County Regional Center for Health, Skills and Safety Training, development and construction of the western Pennsylvania training center for apprentices and journeypersons in health, safety and skill development2,750,000
(V) Carnegie Library of Pittsburgh, infrastructure improvements in the library system7,500,000
(W) Southside Riverfront Development Project, brownfield reclamation for mixed-use riverfront development, including site preparation and construction3,500,000
(X) Northland Public Library, renovations to facilities1,000,000
(Y) Pittsburgh International Airport Maintenance and Training Complex, development and expansion of heavy maintenance and engine overhaul facility and accompanying training and simulation complex for existing and future airline companies based at Pittsburgh International150,000,000
(Z) Phase I of Point State Park, excluding State-owned lands for capital development, including design, engineering and construction for riverfront trail and park connections to the Eliza Furnace Trail and to the David L. Lawrence Convention Center8,000,000
(AA) Infrastructure and building projects associated with an established enterprise zone, including Millvale, Sharpsburg, Blawnox, Etna, Shaler, Aspinwall and O'Hara250,000
(BB) Site acquisition, remediation and infrastructure development of brownfield sites15,000,000
(CC) Redevelopment of the former Carrie Furnace site into a mixed-use industrial park9,000,000
(DD) Site preparation and development for the Cochrandale redevelopment area3,700,000
(EE) Redevelopment of the former Edgewater Steel site6,000,000
(FF) Redevelopment of a former Westinghouse nuclear research facility2,500,000
(GG) Infrastructure improvements to the Leetsdale Industrial Park3,300,000
(HH) Site preparation of the LVC Coke Works for office and research and development space25,000,000
(II) Maintenance, redevelopment and cleanup of the main street corridors surrounding brownfield revitalization and redevelopment projects5,000,000
(JJ) Replacement of the trail surrounding the North Park Lake1,200,000
(KK) Rehabilitation of the ski slope area at Boyce Park1,500,000
(LL) Rehabilitation of the nature centers within North Park, South Park and Boyce Park1,400,000
(MM) Rehabilitation of the ice skating rink in North Park1,200,000
(NN) Completion of the Botanical Garden Project at Settler's Cabin Park1,500,000
(OO) Site rehabilitation and improvement at South Park3,500,000
(PP) Pittsburgh Airport Area Enterprise Foundation, development of a center for business education, training, incubation and women in business initiatives2,000,000
(QQ) Family Retreat Center, renovation and rehabilitation of facilities, including new construction925,000
(RR) Allegheny General Hospital, development of a comprehensive cardiovascular institute and construction of a cardiac/peripheral catheterization laboratory4,500,000
(SS) World War II Veterans of Allegheny County Memorial Fund, Inc., for the construction of a World War II memorial in Allegheny County250,000
(TT) Major renovations and construction at Keystone Commons office park3,000,000
(UU) Site development and construction of the Hampton Community Center2,000,000
(VV) Renovations and expansion of the Laurie Ann West Library2,000,000
(WW) Hazlett Theater revitalization project1,000,000
(XX) University of Pittsburgh Medical Center - Braddock, construction and renovations for hospital expansion project2,975,000
(iv) Fawn Township
(A) Site preparation and infrastructure to support industrial development on a 50-acre vacant parcel of land2,000,000
(B) Mixed-use development of a parcel adjacent to the Fawn Township Municipal Building2,202,000
(v) Findlay Township
(A) McClaren West Business Park, acquisition and development of 170 acres located in the airport corridor for a mixed-use business park8,000,000
(B) Construction of a new recreational center for youth and adults4,600,000
(C) Site preparation and construction of Clinton Industrial Park, Phase I7,500,000
(D) Site preparation and infrastructure development for Route 30 Industrial Park7,000,000
(vi) Frazer Township
(A) Site preparation, infrastructure improvements to Frazer Business Park10,000,000
(vii) Hampton Township
(A) Design and construction of an indoor multipurpose community center4,000,000
(viii) Harrison Township
(A) Harrison Township Mixed-Use Development Project, site preparation for a mixed-use facility5,000,000
(ix) Homestead Borough
(A) Property acquisition, site preparation and construction of new city hall/fire station500,000
(B) Kennywood site development3,500,000
(x) Jefferson Hills Borough
(A) Route 51 Industrial Park, redevelopment of the former Westinghouse Research Center which includes infrastructure improvements, demolition and renovations to existing buildings5,000,000
(B) Construction of a fire rescue and emergency medical service building benefiting Jefferson Hills, I-43 and surrounding communities1,500,000
(xi) Municipality of Monroeville
(A) Forbes - Project Emergency, expansion and renovation of emergency department at Forbes Regional Hospital2,000,000
(xii) Moon Township
(A) Redevelopment of University Boulevard50,000
(B) Construction of a municipal complex and community center for youth and adults in Moon Township and surrounding communities2,000,000
(C) Site preparation and construction of the Cherrington Parkway Corridor site3,000,000
(xiii) Munhall Borough
(A) Junior Achievement Exchange City Program, for construction and/or renovation of a multipurpose educational facility1,500,000
(B) Property acquisition, construction and infrastructure improvements for the Munhall Senior Center250,000
(C) The Carnegie Library of Homestead, renovations and infrastructure improvement, including roof replacement250,000
(xiv) Tarentum Borough
(A) Infrastructure improvements and development related to the Keystone Opportunity Zone in Tarentum Borough5,000,000
(B) Engineering, demolition and site development for Tarentum Borough Redevelopment District1,000,000
(xv) City of Duquesne
(A) Provide access to business development in the City of Duquesne5,000,000
(B) Construction, rehabilitation and infrastructure improvements to the carpenter shop within a keystone opportunity zone250,000
(C) Redevelopment of the former Duquesne Works site in the Mon Valley, including 85 acres of a Keystone Opportunity Zone for the City Center in Duquesne5,000,000
(D) Land acquisition, site preparation and development for the conversion of a blighted area located within a Keystone Opportunity Zone into a commercial-light industrial area3,000,000
(xvi) City of McKeesport
(A) Industrial Center of McKeesport Ramps, provide access to business development in the City of McKeesport3,000,000
(B) Construction, rehabilitation and infrastructure improvements within a keystone opportunity zone for the pipe storage relocation500,000
(C) Property acquisition, construction, rehabilitation and restoration for the Walnut Street Industrial Park1,250,000
(D) Construction and infrastructure development and improvements to improve business access400,000
(E) Development of former United States Steel Tube Works site in Mon Valley, including 25 acres of a Keystone Opportunity Zone for the Industrial Center of McKeesport7,000,000
(F) Acquisition, remediation, demolition and site preparation of the Firth Sterlin site2,000,000
(xvii) Millvale Borough
(A) Acquisition, construction and infrastructure improvements as part of the Millvale Borough Economic Development Project, including a combined Public Works and Volunteer Fire Department Building1,950,000
(B) Millvale Community Center expansion project, new construction, site preparation and renovations to the community center for NHCO satellite facility and development of commercial rental space250,000
(xviii) Versailles Borough
(A) Construction and infrastructure improvements to the Versailles Industrial Park500,000
(xix) White Oak Borough
(A) Construction and infrastructure development for the new White Oak Community Center500,000
(B) Construction and infrastructure improvements to the White Oak Industrial Park500,000
(xx) Bethel Park Borough
(A) Construction of a recreation center and gymnasium for youth and adults in Bethel Park and surrounding communities3,600,000
(B) Millennium Park, park improvements and infrastructure improvements500,000
(C) Pittsburgh Mercy Health System, SmartHealth Outpatient Center, construction of additional physician offices, ambulatory surgical center and freestanding emergency department7,500,000
(xxi) Upper Saint Clair Township
(A) Demolition and construction of the Boyce/Mayview Regional Park2,000,000
(B) Construction of a new Environmental Education Center Building3,600,000
(C) Construction of a new Public Works Maintenance Facility900,000
(D) Construction of a new fire station1,500,000
(E) Tri-Community EMS, construction of an emergency medical services building1,800,000
(xxii) Castle Shannon Borough
(A) Construction and renovation of a regional emergency medical service building1,000,000
(xxiii) Coraopolis Borough
(A) Sports Legacy Facility, construction of a regional soccer complex15,000,000
(xxiv) Leetsdale Borough
(A) Leetsdale Industrial Park, infrastructure improvements, including storm sewer systems and road reconstruction500,000
(xxv) Collier Township
(A) Site preparation and infrastructure development for the Collier Commerce Center7,000,000
(xxvi) Ohio Township
(A) Construction of a municipal park, including a nature center, playground shelters and picnic pavilions1,200,000
(xxvii) Pleasant Hills Borough
(A) Mowery Park, infrastructure improvements, including widening and paving of main access road, construction of a permanent stage, parking expansions, ADA accessible restrooms, rehabilitation of shelters and improvements and upgrades necessary to improve accessibility to the South Hills regional fire training tower500,000
(xxviii) Shaler Township
(A) Construction of a storage garage for the public works facilities500,000
(xxix) West Deer Township
(A) West Deer No.2 VFD, renovation and repair of garages and social hall235,000
(xxx) McCandless Township
(A) UPMC-NORCOM and NEWCOM Emergency Medical Centers, radio and conventional network upgrade, including base stations and satellite receiving stations1,690,000
(B) UPMC, facility upgrades, including sprinkler systems, HVAC improvements, electrical upgrades, elevator upgrades, roadway and parking improvements, flexible monitoring systems and technology upgrades and improvements4,259,000
(xxxi) North Versailles Township
(A) Site acquisition, preparation and construction associated with the development of a mixed-use area14,500,000
(xxxii) Braddock/Rankin
(A) North Rankin industrial sites development20,000,000
(xxxiii) Churchill Borough
(A) Development of multipurpose facility2,000,000
(xxxiv) Urban Redevelopment Authority of Pittsburgh
(A) Northside Community Development Fund, renovations of social hall for commercial office space350,000
(B) Lawrenceville Master Planning and Housing Redevelopment Initiative500,000
(xxxv) Borough of Carnegie
(A) Andrew Carnegie Free Library and Cultural Center, interior renovations and construction for Phase II project3,454,000
(xxxvi) Swissvale
(A) Our Kids Have Big Dreams Phase II2,000,000
(xxxvii) Borough of Forest Hills
(A) Reconstruction of the Frank Conrad Home at the Forest Hills Recreation Center and transportation and infrastructure improvements250,000
(3) Armstrong County
(i) County Projects
(A) Belmont Complex, East Franklin Township, building construction and site improvements500,000
(B) IUP Campus Reuse Project, rehabilitation and retrofit of former IUP Campus2,000,000
(C) Apollo Borough, remediation and redevelopment of former industrial site for reuse3,000,000
(D) Rebuilding of fire-damaged recreational facilities located at Belmont Complex1,000,000
(E) Crooked Creek Horse Park, construction of indoor coliseum1,000,000
(F) Ford City Heritage and Technology Park, site preparation of 50-acre brownfield parcel to combine industrial lots with riverfront green space and recreational areas and for the renovation of adjacent 7-acre brownfield, including three industrial buildings2,500,000
(G) Kittanning Riverfront Park, construction of raised stage and tent/roof structure over amphitheater area1,000,000
(H) Northpoint Exhibit Hall, construction of 10,000-square-foot facility to house ARMtech Showcase of Commerce1,500,000
(4) Beaver County
(i) County Projects
(A) Westgate Business Park, site preparation and development of a business park at the Big Beaver KOZ site5,000,000
(B) Lincoln Park Performing Arts Center, for planning and construction of a new facility on the site of the former Lincoln High School13,425,000
(C) Phillips Power Station, Beaver and Allegheny Counties, site acquisition, site improvements and site cleanup5,000,000
(D) B&W site redevelopment, site acquisition, site improvements and site cleanup5,000,000
(E) Rochester Area Digital District Authority, Oriental CyberCommons Incubator, Oriental Property Development, construction of high-tech business facility5,000,000
(F) Construction of the Beaver County Industrial Heritage Museum on the former Marino Scrapyard property along the Ohio River5,000,000
(G) Construction of barge facility along the Ohio River in Hopewell Township5,000,000
(H) Construction of a fish habitat/mitigation site, Borough of Monaca225,000
(I) Development and construction of the Center for the Arts, in association with Geneva College8,000,000
(J) Construction of new multitenant facility. This project shall be construed as a supplement to the project authorized in section 6(4)(i)(E) of the Capital Budget Project Itemization Act of 2001-2002.2,000,000
(ii) Corporation for Economic Development
(A) Beaver River Dredging Project for enhanced river navigation and economic development2,500,000
(iii) City of Aliquippa
(A) Design and construction for the new Aliquippa Salvation Army facility estimated total project cost of $1,000,000250,000
(iv) North Sewickley Township
(A) Rehabilitation and restoration of the Riverside Youth Athletic Association athletic fields500,000
(B) Construction, rehabilitation, restoration and infrastructure improvements to the Riverside Athletic Complex1,000,000
(C) Acquisition, construction and infrastructure improvements to the North Sewickley Park500,000
(v) Aliquippa, Hopewell, Center and Monaca
(A) Corporation for Economic Development, infrastructure improvements to Aliquippa site10,000,000
(vi) Ambridge, Harmony
(A) Site acquisition, site improvements and site cleanup of brownfield site in Ambridge10,000,000
(vii) Big Beaver
(A) Site acquisition, site improvements and site cleanup of Route 60 North development area5,000,000
(viii) Center Township
(A) Site improvements to the Center Township development area5,000,000
(B) Construction and development of the Gateway Youth Services Center2,000,000
(ix) Hopewell
(A) Site acquisition, site improvement and site cleanup of Route 60 South development area10,000,000
(x) Koppel, Big Beaver
(A) Site acquisition, site improvements, site cleanup to Koppel industrial sites5,000,000
(xi) Midland
(A) Site acquisition, site improvements and site cleanup of Midland industrial sites5,000,000
(xii) Monaca
(A) Site acquisition, site improvements and site cleanup of Monaca industrial sites5,000,000
(xiii) Potter Township
(A) Site acquisition, site improvements and site cleanup of Potter Township industrial sites5,000,000
(xiv) South Heights, Crescent
(A) Site acquisition, site improvements, site cleanup for riverfront site5,000,000
(xv) Beaver Falls
(A) Site acquisition, site development and construction of the Beaver Falls Community Center750,000
(B) Geneva College Stadium redevelopment project2,000,000
(xvi) Rochester
(A) Rochester riverfront brownfield revitalization project2,000,000
(5) Bedford County
(i) County Projects
(A) Redevelopment, rehabilitation and renovation of Bedford Springs Hotel and Resort, Phase II26,000,000
(B) Bedford County Business Park, Phase II5,000,000
(C) Expansion and improvement of the Bedford County Bedford Business Center1,300,000
(ii) Bedford County Development Association
(A) Property acquisition, development and redevelopment of sites and facilities; access roads, sewer, water and telecommunications infrastructure; other physical improvements in support of initiatives of I-99 Innovation Corridor Alliance7,000,000
(6) Berks County
(i) County Projects
(A) Construction and renovation of the Community Health Campus and infrastructure development for the reuse of existing operational facility, St. Joseph's Medical Center, Reading5,000,000
(B) Infrastructure improvements to support economic development projects in northern Berks County, including water, sewer and road improvements5,000,000
(C) Construction of a new science building for Albright College10,000,000
(D) Demolition of existing athletic stadium and construction of a new stadium for Albright College2,000,000
(E) Construction of a science building for Alvernia College5,500,000
(ii) City of Reading
(A) Construction, infrastructure upgrades and restoration of First Energy Stadium facilities in the City of Reading600,000
(B) Sovereign Center, renovations to southwest corner of 8th and Penn Streets2,000,000
(C) 5th and Penn revitalization, Sovereign Bank Office Building project2,000,000
(D) Reading Public Museum, construction of new art education center and storage facility and renovations of planetarium and exhibits2,000,000
(E) (Reserved)
(F) Reading Public Museum, for renovations to the Native American, Hispanic and Ancient Civilizations exhibit areas750,000
(G) Reading Public Museum, construction of a climate-controlled collections storage facility2,000,000
(H) Reading Public Museum, renovations to facilities and construction of an Art Education Center and Science Exploratorium550,000
(I) Reading Public Museum, renovations and technology upgrades to the Planetarium theater facilities650,000
(J) Site and infrastructure improvements to support the development of the Keystone Food Industry Park12,000,000
(K) West Reading Main Street development2,000,000
(L) Construction of the African-American Museum and Cultural Center that will include a day-care center, senior citizens center, a Head Start center, a job training center and community meeting and dining room facilities3,000,000
(M) Rehabilitation of the Antietam Lake Dam2,000,000
(N) Purchase of a warehouse for the storage of Latino food products for distribution to Latino grocery stores and a public marketplace for consumers and vendors to display products from Central and South America1,000,000
(O) Trexler Mansion, 5th and Franklin Streets, acquisition and restoration of a historic landmark building into a multitenanted office, meeting and technology center4,000,000
(P) Community Arts and Media Center, construction of a multifaceted arts and entertainment center in downtown Reading near the Sovereign Center3,000,000
(Q) Riverfront development project, clean and dredge the Schuylkill riverfront for purposes of creating a multipurpose recreation and cultural center5,000,000
(R) Rehabilitation of the Stichler Building, 505 Penn Street, for office complex, including site development and construction500,000
(S) Alvernia College, acquisition and rehabilitation of the Maier Building5,000,000
(T) Fifth and Penn Streets Project, demolition of existing buildings and construction of an operations center for Sovereign Bank1,000,000
(U) 700 Penn Street Project, construction of a hotel, multiplex theater, parking garage and pedestrian bridge to the Sovereign Center5,000,000
(V) Downtown Arts Center, rehabilitation of the vacant Dalloz Safety Products Manufacturing building into a multipurpose arts and recreation center5,000,000
(W) St. Joseph Medical Center Complex at 12th and Walnut Street, selective demolition and renovation of buildings into residential, commercial and community-based entrepreneurial entities8,000,000
(X) Reading Outlet Center, 9th and Douglass Street, conversion of vacant outlet center into a multiuse commercial and education facility6,000,000
(Y) Franklin Street Station, renovation and construction for conversion into a rail museum and restaurant4,000,000
(Z) Penn Avenue and Rt. 422 revitalization, demolition of blighted motel property in West Reading at Rt. 422 interchange for construction of new motel/office space2,500,000
(AA) Rehabilitation and renovation of the former Meridian Bank building at 6th and Washington Streets1,400,000
(iii) Bethel Township
(A) Development of Keystone Food Industry Park10,000,000
(iv) Muhlenberg Township
(A) Acquisition and redevelopment of former Agere facility for multitenant business park4,000,000
(v) Greater Berks Development Fund
(A) To assist in equipping a major targeted industry expansion in Richmond Township2,000,000
(vi) Bern Township
(A) Construction of a new 220-bed state-of-the-art hospital and health campus and infrastructure development by St. Joseph's Medical Center10,000,000
(7) Blair County
(i) County Projects
(A) Logantowne Center, offsite improvements10,000,000
(B) Blair County Ballpark, parking lot development250,000
(C) Design and construction of an indoor year-round community and school district recreation facility at Mansion Park5,000,000
(ii) Altoona-Blair County Development Corporation
(A) Property acquisition, development and redevelopment of sites and facilities; access roads, sewer, water and telecommunications infrastructure; other physical improvements in support of initiatives of I-99 Innovation Corridor Alliance7,000,000
(8) Bradford County
(i) Towanda Township
(A) Central Bradford Multi-tenant Manufacturing Facility, continued development of facility to accommodate new business tenants650,000
(ii) Sayre Borough
(A) Enterprise Center KOZ multitenant facility, continued development of facility to accommodate new business tenants500,000
(B) Construction of an addition to the Paxar Corporation's Wilcox Street Facility to accommodate the expansion of operations in Pennsylvania1,500,000
(C) Construction and development of business incubator500,000
(iii) Athens Township
(A) Construction, renovation or expansion of Ingersoll-Rand Corporation facility to accommodate expanded operations in Pennsylvania1,000,000
(iv) North Towanda Township
(A) OSRAM Sylvania Inc., construction, renovation or expansion and environmental upgrades1,500,000
(B) Construction and development of a technological vocational training center2,500,000
(v) Towanda Borough
(A) Construction and development of Northern Tier Regional Athletics Complex1,500,000
(9) Bucks County
(i) County Projects
(A) Children's Hospital of Philadelphia, construction of Bucks County Specialty Care Center, including expansion of existing medical and surgical outpatient facilities500,000
(B) James A. Michener Library2,000,000
(C) Bensalem Ministries of St. Mary Medical Center, land acquisition and new building construction to expand the programs and services to the indigent and low-income residents of Bensalem2,500,000
(D) Design and construction of a community and senior center facility in Middletown Township for senior services, recreation and other community activities and programs3,000,000
(E) Rehabilitation and renovation of Northampton Library, including structural and technological improvements2,000,000
(F) Rehabilitation and renovation of Northampton Senior Center, including structural improvements2,000,000
(G) Construction of a new facility in Silverdale for Pennridge Community Senior Center500,000
(ii) Bristol Township
(A) Construction of a bicycle pedestrian bridge over the north and southbound lanes of Route 13 approximately one mile south of Levittown (PA Turnpike Area) to reconnect the Delaware Canal Towpath1,000,000
(B) Neighborhood improvements in the Newportville section of Bristol Township2,000,000
(C) Business district improvements in the Croyden section of Bristol Township1,000,000
(iii) Bucks County Redevelopment Authority
(A) Infrastructure rehabilitation project related to the Edgley Industrial Site1,200,000
(B) Acquisition, demolition and redevelopment of the A.E. Staley industrial site located in Morrisville Borough2,000,000
(C) Construction of a new engine house for the Morrisville Fire Company500,000
(D) Redevelopment of the United States Magnet Site located in Yardley Borough, including land acquisition for open space purposes1,000,000
(E) Riverside Construction Materials, Inc., acquisition and installation of self-contained pneumatic handling system for bulk cement2,000,000
(F) Acquisition of Doylestown Armory1,000,000
(G) Construction of two new court-mandated district justice courthouses3,000,000
(H) Family Service Association of Bucks County, land acquisition and construction for a new headquarters facility5,000,000
(iv) Doylestown Borough
(A) Expansion of James A. Michener Art Museum6,000,000
(B) Parking garage to be used for visitor parking for the Mercer Museum, James A. Michener Art Museum and the Bucks County Free Library3,000,000
(v) New Hope Borough
(A) New Hope Cultural Canal Walk, construction of a pedestrian link to the retail museum shop for the Mercer Museum which includes the construction of one dock for water trail access750,000
(vi) Northampton Township
(A) Northampton Township Municipal Park, for Phase II funding of the construction of the Northampton Township Municipal Park1,500,000
(vii) Solebury Township
(A) Land acquisition, design and development of a regional park consisting of a trout fish hatchery, a conference center, a Native American cultural center and a trail system700,000
(viii) Upper Makefield Township
(A) Development of Brownsburg Park1,300,000
(B) Streetscape development project within the Village of Washington Crossing2,000,000
(ix) Warminster Township
(A) Development and construction of a new municipal park located on the former NAWC site1,765,000
(x) Warwick Township
(A) Acquisition and development of Camp Bishop Newmann1,500,000
(B) Redevelopment of a 50-acre park located in the Mignatti Heritage Creek Development1,000,000
(xi) Richland Township
(A) Upper Bucks YMCA, construct expansion of facility7,500,000
(xii) Milford Township
(A) Unami Waterfront Park, acquisition and demolition of existing structures and development of a community park2,000,000
(xiii) Quakertown Borough
(A) St. Luke's Quakertown Hospital, expansion of emergency department1,500,000
(B) Broad Street, streetscape improvements, intersection improvements and replacement of sidewalks and traffic controls1,000,000
(xiv) West Rockhill Township
(A) Grand View Hospital, expansion and renovation of the Department of Emergency Medicine1,000,000
(xv) Lower Makefield Township
(A) Land acquisition, construction and renovation of buildings for senior center1,500,000
(xvi) Doylestown Township
(A) Renovations and expansion of the James A. Michener Art Museum, including creation of additional galleries, a new educational complex, renovations to the storage facility and infrastructure repairs12,500,000
(xvii) Middletown Township
(A) Construction and expansion of a Cardiac Care Unit for St. Mary's Medical Center13,000,000
(B) Expansion and renovation of the Cancer Care Center at St. Mary's Medical Center4,200,000
(C) Expansion and renovation of the Orthopedic Care and Surgical Services Facility at St. Mary's Medical Center8,000,000
(D) Expansion and renovation of the Emergency Department at St. Mary's Medical Center2,000,000
(E) Acquisition of the Stone Meadow Farm for open space preservation5,000,000
(xviii) Bensalem Township
(A) Bristol Pike improvement project1,250,000
(xix) Bucks County Airport Authority
(A) Quakertown Airport, construction of hangars and other airport development702,000
(10) Butler County
(i) County Projects
(A) Acquisition, construction and infrastructure improvements for the Pullman Business Park Expansion Project1,500,000
(B) Acquisition and development of the former Pullman Standard Office Building for use as a multiuse shared resources education center3,000,000
(C) Acquisition, construction and renovation of Main Street corridor as part of the Central Business District Revitalization Phase I6,000,000
(D) Land acquisition, construction and site development of a complex to include an ice rink and exhibition hall3,000,000
(E) Construction of a state-of-the-art emergency response communications center with CAD dispatch capabilities for all of the fire departments within Butler and Beaver Counties1,940,000
(F) Pittsburgh Mercy Health System, construction of a new SmartHealth Outpatient Center in Adams Township5,000,000
(G) Renovation, restoration and historic preservation of the Strand Theater940,000
(ii) Clinton Township
(A) Acquisition, construction, site development and infrastructure improvements to 200-plus acres as part of the Victory Road Business Park II2,500,000
(B) Agribusiness site development project at the Victory Road Business Park3,000,000
(iii) Forward Township
(A) Acquisition, construction and infrastructure improvements to the Forward Township Business Park1,500,000
(iv) Penn Township
(A) Acquisition, construction and infrastructure improvements of the former Franklin Glass facility for the Renfrew Business Park located within a keystone opportunity zone1,500,000
(v) Slippery Rock Borough
(A) Construction, restoration and infrastructure improvement and development as part of the Slippery Rock Downtown Economic Development Project500,000
(B) Development of technology-based business park2,000,000
(vi) Slippery Rock and Liberty Townships
(A) Acquisition, construction site development and infrastructure improvements as part of the Slippery Rock Business Park II (Phase I) Project1,250,000
(vii) Slippery Rock Township
(A) Development and construction of Slippery Rock Business Park, including reclamation and remediation of surface-mined property1,250,000
(viii) Butler Township
(A) Shearer Road Business Park, remediation and redevelopment of brownfield site1,250,000
(ix) City of Butler
(A) Pullman Center Park, renovation and improvement to accommodate minor league baseball team2,000,000
(x) Evans City Borough
(A) Renovation and rehabilitation of the Citizens Transport Bank building located on South Jackson Street for Borough Offices, the Evans City Public Library, the Evans City Historical Society and other community purposes364,000
(xi) Zelienople Borough
(A) Municipal Authority of the Borough of Zelienople, infrastructure improvements associated with the development of the Zelienople Airport Commerce Park600,000
(11) Cambria County
(i) County Projects
(A) St. Francis University, development of a multipurpose outdoor recreational field for campus and community uses1,500,000
(B) Renovations for Mount Aloysius College Alumni Hall Community Center2,000,000
(C) Construction of sports and multipurpose fields for Mount Aloysius College1,200,000
(D) Southern Alleghenies Museum of Art, construction and renovation of facilities1,000,000
(ii) Cambria County Industrial Development Corporation
(A) Acquisition, construction and infrastructure development of an outdoor recreation conference center and rustic lodge with amenities10,000,000
(B) Construction and infrastructure improvements for an industrial multitenant complex, including mining operations, coke plant, rail and utilities within the ISG/Sunoco KOEZ10,000,000
(iii) City of Johnstown
(A) Acquisition and rehabilitation of the Reliant Building for a business development partnership between the City of Johnstown and Johnstown Area Regional Industries2,500,000
(B) Construction, rehabilitation and infrastructure improvements for the development of Point Stadium into a multiuse athletic/events facility3,000,000
(C) Acquisition, rehabilitation and infrastructure improvements to a warehouse for the Arts Works economic and cultural development incubator project2,500,000
(D) Construction and infrastructure upgrades for Phase I of the Sandyvale Memorial Botanical Gardens and Arboretum improvement project1,500,000
(E) Acquisition and construction of a new recreational center for youth and adults in the City of Johnstown1,000,000
(F) Design and construction for Phase II of the Johnstown Heritage Discovery Center to enhance the area as a heritage tourism destination1,700,000
(G) Acquisition, construction, rehabilitation and infrastructure improvements for an incubator/multitenant business facility as part of the Johnstown Renewal Project1,000,000
(H) Johnstown Sani-Dairy Development Project, demolition, site development, renovations and construction for business site development1,000,000
(I) Demolition, renovations and construction of the Swank Building in downtown Johnstown1,000,000
(iv) Richland Township
(A) Acquisition and construction of a regional technology complex/mixed-use facility with office space and business and educational development activities6,000,000
(B) Construction and rehabilitation of the National Neuroscience Center to enhance research, study and treatment in different areas related to neurologic disorders1,600,000
(v) Johnstown Redevelopment Authority
(A) Bethlehem Steel/Cambria Iron Works Complex, historical properties, renovations, restoration and preservation of abandoned underutilized industrial brownfield sites into mixed-use complex2,600,000
(B) Pedestrian Skywalk, Downtown Renaissance Project, critical linkages to the Johnstown Renaissance projects, including War Memorial Arena, Conference and Convention Center and intermodal transportation center1,500,000
(C) Kernville urban renewal, acquisition, construction, rehabilitation and infrastructure improvements for a multitenant business facility in Kernville as part of the Johnstown Renewal Project1,200,000
(D) Cylindrical Project, rehabilitation, upgrades and infrastructure improvements to the former Magnesium Brownfield Facility to house and equip Cylindrical Product Operations Division1,000,000
(12) Cameron County (Reserved)
(12.1) Cameron, Clearfield, Elk, Jefferson, McKean and Potter Counties
(i) North Central Pennsylvania Regional Planning and Development Commission
(A) North Central Multi-Tenant/Incubator Facilities Regional Network, development of at least four new incubators and rehabilitation of at least four multitenant industrial facilities10,500,000
(13) Carbon County
(i) County Projects
(A) Construction of a new courthouse annex building with parking to headquarter county offices1,100,000
(B) Rehabilitation of the former Lehighton Junior High School for borough headquarters and office space, including other public and private uses1,000,000
(C) Construction and infrastructure improvement to the Jamestown district in Mahoning Township estimated total project cost of $1,000,000300,000
(D) Tourism infrastructure development and improvement funds to implement the Pocono Mountain Wayfinding Signing Program in Pike and Wayne Counties750,000
(ii) Lansford Borough
(A) Construction, rehabilitation and infrastructure development and improvements for the Panther Valley High School Stadium1,500,000
(B) Rehabilitation, restoration and infrastructure improvements to the Panther Valley Middle School Building1,000,000
(iii) Lehighton Borough
(A) Rehabilitation, restoration and infrastructure improvements to the Lehighton Middle School Building500,000
(iv) Mahoning Township
(A) Property acquisition, construction rehabilitation infrastructure improvements and development of the Packerton Yard Industrial Park located within a Keystone Opportunity Zone1,000,000
(v) Nesquehoning Borough
(A) Property acquisition, construction, rehabilitation, infrastructure improvements and development of the Green Acres Industrial Park located within a Keystone Opportunity Zone1,000,000
(B) New construction of a second multitenant building to create jobs and foster economic growth for new and existing businesses in Carbon County1,000,000
(vi) Jim Thorpe Borough
(A) Construction, restoration and infrastructure development and improvements as part of the Jim Thorpe Sidewalk Restoration Project1,250,000
(B) Construction, rehabilitation, restoration and infrastructure improvements and development for the Switchback Gravity Railroad Heritage Site1,250,000
(vii) Weatherly
(A) Acquisition, construction, rehabilitation, restoration and infrastructure development and improvements for the railroad/steel revitalization project1,500,000
(14) Centre County
(i) Centre County Industrial Development Authority
(A) Development of an industrial park, including land acquisition3,000,000
(B) Development and construction of baseball complex15,000,000
(C) Property acquisition, development and redevelopment of sites and facilities; access roads, sewer, water and telecommunications infrastructure; other physical improvements in support of initiatives of I-99 Innovation Corridor Alliance7,000,000
(ii) County Projects
(A) Penns Valley Area Historical Museum Association, expansion and renovation of the Penns Valley Historical Museum400,000
(B) State Theatre, Inc., restoration and capital improvements to the State Theatre1,500,000
(C) State College Baseball, Inc., development of the Shaner Sports Complex and Shaner Park2,000,000
(D) Development of a county fire training center2,000,000
(E) Site acquisition and development of infrastructure to support an industrial park3,000,000
(F) Construction of the Moshannon Valley YMCA Arts and Culture Center300,000
(G) Philipsburg Area Hospital, improvements and renovations of hospital facilities, including new roofing, HVAC and fire alarm systems and renovations and expansion of the Dialysis Treatment Facility3,500,000
(iii) Pennsylvania State Coroners Association
(A) Purchase and equipping of four trailers to be utilized as emergency response vehicles during tragedies involving mass fatalities800,000
(iv) Potter Township
(A) Extension of sewer line from Country Club Park to Centre-Hall-Potter sewage forced main at Meadows Psychiatric Center700,000
(v) Centre Region Council of Governments
(A) Centre Region Recreation Authority, construction of new facilities and improvements for the Millbrook Marsh Nature Center1,250,000
(15) Chester County
(i) County Projects
(A) Devereux Beneto Center, construction of educational facility, recreation center and site improvements4,500,000
(B) Devereux Kanner Center, renovation of educational facility and site improvements4,600,000
(C) Devereux Whitlock Center, renovation of indoor recreational and vocational spaces, site work and construction of a natatorium2,500,000
(D) Acquisition, construction, site preparation and development and infrastructure development and improvements for the National Center for the American Revolution7,000,000
(E) People's Light & Theatre Company, construction, reconstruction and equipment2,000,000
(F) Construction of a Chester County public safety training facility7,500,000
(G) People's Light & Theatre Company, construction and reconstruction of the theater facility, Phase II2,000,000
(H) Revitalization of the Worthington Steel brownfield site located at Route 202 South and Route 29, including infrastructure and site improvements4,300,000
(ii) City of Coatesville
(A) Construction of new office building located at the northwest corner of Route 30 bypass and Route 82, including infrastructure improvements4,000,000
(B) Construction of a new hotel and conference center located at the southwest corner of Route 30 bypass and Route 82, including acquisition and infrastructure4,000,000
(C) Urban Center Revitalization, redevelopment of former industrial site for office, commercial and retail development, including the construction of an office park, parking garage and commercial and retail space20,000,000
(iii) Atglen Borough
(A) Construction of a new municipal complex, including site development and land acquisition1,000,000
(iv) Downingtown Borough
(A) Sonoco Downingtown Paper Mill, upgrades to the wastewater treatment system, including a new aeration system, a new color removal system and a new dissolved oxygen system1,750,000
(B) Downingtown KOZ, design and construction of a structured parking facility3,780,000
(C) Infrastructure development to support the ingress, egress and regress of pedestrian and vehicular traffic5,130,000
(D) Design and construction of a pedestrian tunnel3,240,000
(v) West Vincent Township
(A) Hope Springs Equestrian Therapy, construction of a new barn and indoor riding arena500,000
(vi) City of Chester
(A) Chester Towers, mixed-use development that includes acquisition and infrastructure construction2,000,000
(vii) Tredyffrin Township
(A) Construction of the Paoli Intermodal Transportation Facility at the Paoli Railyard situate in Tredyffrin Township and Willistown Township8,000,000
(16) Clarion County
(i) County Projects
(A) Beaver Creek Recreational Project, construction of a dam for development, conservation and recreational purposes3,000,000
(B) Clarion County KOEZ, development of a biotechnology business development center to be located in Monroe Township5,000,000
(C) Clarion County Commerce Center Industrial Park, development of a multitenant building and infrastructure improvements1,400,000
(17) Clearfield County
(i) County Projects
(A) Design, acquisition and installation of equipment to provide high-speed Internet to the rural areas of Clearfield County500,000
(B) Construction of a retail/visitors center to support tourism5,000,000
(C) Development of ethanol plant2,000,000
(D) Development of intermodal freight terminal at Clearfield Firemen's Industrial Park3,000,000
(E) Acquisition and construction of Visitors Gateway Center proximate to Interstate 805,000,000
(F) Acquisition, construction and infrastructure development to fund the establishment of an ethanol manufacturing plant or plants in Clearfield County60,000,000
(G) Infrastructure to support regional efforts in oncology and dialysis in the Philipsburg, Clearfield and Dubois Hospitals5,000,000
(H) Acquisition, construction and infrastructure improvements to a manufacturing facility located in Curwensville3,000,000
(I) Acquisition, construction and infrastructure improvements to various waste tire recycling facilities in Clearfield County6,000,000
(J) Acquisition, construction and infrastructure improvements to fund the establishment of an electric generation facility that utilizes waste coal in Clearfield County60,000,000
(K) Acquisition, development, rehabilitation and infrastructure improvements of a county-owned and -operated ATV trail to promote tourism and recreation5,000,000
(L) Infrastructure improvements to the County 911 Communication Center2,000,000
(M) Construction of a recreational facility located near the Curwensville Dam3,000,000
(ii) Beccaria
(A) Construction, rehabilitation and improvements to the K&F Woods facility500,000
(iii) Bradford Township
(A) Redevelopment of industrial facility formerly occupied by Robert Bryce Containers to establish an advanced technology facility6,000,000
(iv) Clearfield Borough
(A) Property acquisition, rehabilitation, restoration and infrastructure improvements to redevelop the FCI/BERG industrial site1,000,000
(B) Clearfield Hospital, rehabilitation and renovations of patient reception to streamline patient evaluation and admittance600,000
(C) Restoration and infrastructure improvements to the Clearfield Business District1,000,000
(v) Girard Township
(A) Rehabilitation, restoration and infrastructure improvements for the redevelopment of industrial sites in Girard Township1,000,000
(vi) Grampian Borough
(A) Property acquisition, site preparation, rehabilitation, restoration and infrastructure improvements to redevelop Grampian Borough sites and facilities1,000,000
(vii) Lawrence Township
(A) Design, land acquisition, construction and equipment for manufacturing facility expansion7,000,000
(viii) Penn Township
(A) Rehabilitation, restoration and infrastructure improvements for the redevelopment of industrial sites in Penn Township500,000
(ix) Gulich Township
(A) Construction of a water impoundment structure in Gulich Township12,000,000
(x) Clearfield County Economic Development Corporation
(A) Construction of a secondary roadway access into the Sandy Township-Developac Industrial Park onto State Route 2551,000,000
(B) Development of an ethanol production facility utilizing wood chips and other renewable feedstocks60,000,000
(xi) Sandy Township
(A) Infrastructure development for Sandy Township, Developac Industrial Park1,000,000
(B) Acquisition, construction and rehabilitation of a business development center5,000,000
(18) Clinton County
(i) Castanea Township
(A) Acquisition, rehabilitation and infrastructure improvement to the Cognis plant site2,850,000
(ii) Lamar Township
(A) Acquisition and infrastructure development of the Lamar Township Business Park2,900,000
(iii) Renovo
(A) Rehabilitation, restoration and infrastructure improvements in the Renovo Industrial Park1,000,000
(B) Acquisition, construction and rehabilitation of a business development center5,000,000
(iv) County Projects
(A) Site acquisition, infrastructure improvements, parking to support the development of elk viewing area5,000,000
(v) City of Lock Haven
(A) Opera House renovation project, acquisition and renovations to building for conversion to commercial space and future development375,000
(19) Columbia County
(i) Town of Bloomsburg
(A) Bloomsburg Health Systems, renovation and rehabilitation of the Bloomsburg Hospital3,600,000
(ii) County Projects
(A) Acquisition, infrastructure development and site preparation for an industrial park5,000,000
(iii) Columbia County Redevelopment Authority
(A) Design and construction of Northern Columbia Community and Cultural Center in Benton Borough1,200,000
(20) Crawford County
(i) City of Meadville
(A) City of Meadville, Meadville Medical Center - Coke Building, renovations to former Coca-Cola building to establish facilities for outpatient rehabilitation services and a professional learning center2,000,000
(B) Allegheny College, construction of a modern theater and communications arts center10,000,000
(C) Renovation and rehabilitation of the former Meadville Jr. High Building for reuse as a multiuse facility1,000,000
(D) Renovation and rehabilitation of buildings located at the former Talon Plant No. 7 for mixed-use development, including demolition1,500,000
(E) Renovation of a three-story building for Precision Manufacturing Institute of Technology and Education Center1,450,000
(ii) City of Titusville
(A) Renovation of the central city block downtown1,000,000
(B) Renovation of existing properties in downtown1,000,000
(iii) County Projects
(A) Construction of a recycling facility1,700,000
(B) Rehabilitation of Hotel Conneaut and construction of an adjacent convention center3,000,000
(C) Crawford County Industrial Park - East, infrastructure improvements and renovation of existing structures2,000,000
(21) Cumberland County
(i) County Projects
(A) Cumberland County Historical Society, completion of museum project800,000
(B) Construction of an Army Museum on land adjacent to the U.S. Military Reservation, Carlisle Barracks30,000,000
(ii) Shippensburg Township
(A) Construction, rehabilitation and infrastructure upgrades to the Shippensburg Fogelsanger Road Bridge350,000
(iii) Redevelopment Authority of Cumberland County
(A) Rehabilitation of upper floors of Business Central, Downtown Business Center, Carlisle Borough2,000,000
(B) Construction of a multitenant business facility, including acquisition and necessary demolition, Newville Borough3,000,000
(C) Acquisition and rehabilitation of structures for a technology center, Shippensburg Borough2,000,000
(D) Rehabilitation of former Beistle Factory for multitenant building, Shippensburg Borough3,000,000
(E) Construction of a multitenant building, including acquisition and necessary demolition, East Pennsboro Township2,000,000
(F) Construction of a special events area and Exposition Center, Borough of Carlisle1,000,000
(G) Renovation and expansion of Dickinson School of Law, Borough of Carlisle30,000,000
(H) Construction of parking facility for Dickinson School of Law4,000,000
(I) Construction of a parking garage in Wormleysburg Borough10,000,000
(iv) Shippensburg Borough
(A) Construction of loop roadway to facilitate building expansion6,500,000
(B) Construction and infrastructure development and improvements for the South Queen Street Pedestrian Bridge Project350,000
(v) Borough of Carlisle
(A) Land acquisition and construction of a parking garage4,000,000
(B) Construction of new life sciences facility for Dickinson College20,000,000
(22) Dauphin County
(i) County Projects
(A) Pinnacle Health System, expansion of laboratory at the Harrisburg Hospital5,000,000
(B) Construction of the Ned Smith Center for Nature and Art3,000,000
(C) Repairs and renovations to the Old Olmstead Air Force Base Headquarters Building located on the grounds of the Harrisburg International Airport5,000,000
(D) Design and construction of Pennsylvania Horticulture Research, Education and Demonstration Center in Susquehanna Township1,500,000
(E) Construction of recreational complex located on Elmerton Avenue, Susquehanna Township3,500,000
(ii) City of Harrisburg
(A) Expansion and improvement of Commerce Bank Park, formerly known as Riverside Stadium, and Skyline Sports Complex13,000,000
(B) Paxton Commons Area economic development and improvements7,400,000
(C) Development and construction of the National Museum of African-American History. This project shall be construed as a supplement to the project authorized in section 6(22)(ii)(D) of the act of June 22, 2000 (P.L.136, No.27), known as the Capital Budget Project Itemization Act for 2001-2002.2,000,000
(D) Neighborhood Streetscape Improvement Project29,000,000
(E) Development and construction of the National Museum of the Old West20,000,000
(F) Development and construction of the Susquehanna Art Museum, including land and building acquisition5,000,000
(G) Development of the Harrisburg Institute for Community Research and Collaborative Partnerships, including acquisition of land and buildings and necessary construction, rehabilitation and renovation2,500,000
(H) Development of National Center for Civil War Studies at National Civil War Museum14,900,000
(I) Expansion and upgrade of Harrisburg Parks System7,000,000
(J) Furlow Building Project2,300,000
(K) Expansion and upgrade of Harrisburg Transportation Center2,900,000
(L) Construction of parking garage3,000,000
(iii) Derry Township
(A) Derry Township Industrial Development Authority, renovations to downtown Hershey25,000,000
(B) Development and rehabilitation of Hershey Area Playhouse500,000
(iv) Swatara Township
(A) TecPort Business Park and East Mall redevelopment projects25,000,000
(B) Property acquisition, site preparation and construction of a commercial/retail development5,000,000
(C) Design and construction of a state-of-the-art indoor/outdoor sports complex3,000,000
(v) Hummelstown Borough
(A) Renovations to the downtown Hummelstown Square2,000,000
(vi) Middletown Borough
(A) Renovations to the downtown Middletown Square2,000,000
(vii) Highspire Borough
(A) Site development, site preparation, rehabilitation, restoration and infrastructure improvements and development of the Reservoir Park Project250,000
(viii) Lower Swatara Township
(A) Harrisburg International Airport, construction of a new terminal complex10,000,000
(ix) Derry Township Industrial Development Authority
(A) Construction of the Pennsylvania State Police Historical Educational and Memorial Center7,500,000
(x) Derry Township Industrial Development Authority
(A) Construction of medical facilities for children's and cancer treatment, Hershey Medical Center, including original furnishings and equipment56,000,000
(xi) Steelton Borough
(A) Capital Region Economic Development Corporation, rehabilitation and renovation of the Pipe Mill, including the replacement of the roof and facade, environmental remediation and demolition8,000,000
(xii) Susquehanna Township
(A) Construction of a recreational tennis and fitness complex3,500,000
(23) Delaware County
(i) County Projects
(ii) Tinicum Township
(A) Construction of a fire station and emergency evacuation center3,500,000
(B) Acquisition and restoration of the Lazaretto3,000,000
(C) Tyler Arboretum, Village Green Project, facility improvements, including development of arrival space, ADA accessibility, infrastructure and utility improvements, landscaping and pedestrian and vehicular improvements1,900,000
(iii) City of Chester
(A) Design and new construction of the Chester Boys and Girls Club recreational facility1,750,000
(B) Construction of a recreational facility and library3,500,000
(C) Restoration of the Deshong Museum Complex6,000,000
(D) Widener University, construction of a performing and cultural arts center, including a 750-seat theater, production and preparation spaces and academic and administrative facilities5,000,000
(iv) Ridley Park
(A) Historical renovations of existing borough buildings and construction of a new police building and highway garage2,000,000
(v) Chester Heights Borough
(A) Complete renovation and rehabilitation of Pathways Center for Families500,000
(vi) Redevelopment Authority of Delaware County
(A) Penn Terminals, port/pier expansion and construction of improvements necessary for the operation of Penn Terminals2,500,000
(B) Penn Terminals, pier extension, paving, lighting, port security enhancements, warehouse construction and remediation and access improvements and other infrastructure improvements17,500,000
(vii) Glenolden Borough
(A) Land acquisition, construction of a recreation center and park improvements1,500,000
(viii) Middletown Township
(A) Open space preservation and recreational improvements for the Smedley Tract7,500,000
(ix) Ridley Township
(A) Design, construction and acquisition of land for a research and training facility for the advancement of aviation30,000,000
(B) Rehabilitation and renovation of Ridley Township Municipal Marina, including construction of access road, catering facility and rehabilitation of docks and pilings2,000,000
(x) Radnor Township
(A) Eastern University, planetarium and Science Education Center, construction, site preparation and improvements1,000,000
(xi) Upland Borough
(A) Expansion and upgrade of Regional Burn Treatment Center at Crozer-Chester Medical Center2,000,000
(24) Elk County
(i) County Projects
(A) Construction of the Johnsonburg Community Senior Center325,000
(ii) Fox Township
(A) Construction, expansion and improvement of the Fox Township Community Park250,000
(B) Construction, rehabilitation and infrastructure improvements to the Elk County Fairgrounds750,000
(C) Construction of a new senior/recreation community center in Fox Township325,000
(iii) St. Marys
(A) Construction, property acquisition and rehabilitation of the St. Marys Municipal Building3,000,000
(B) Acquisition, construction, rehabilitation and infrastructure development and improvements for the revitalization of downtown St. Marys, including a convention center and park7,500,000
(iv) St. Marys Area Economic Development Corporation
(A) Development of intermodal warehousing within the City of St. Marys4,300,000
(v) Johnsonburg
(A) Infrastructure improvements to the Harrison Avenue Corridor500,000
(vi) Elk County Redevelopment Authority
(A) Acquisition and revitalization of various historic and commercial properties located in downtown historic Ridgway1,710,000
(25) Erie County
(i) City of Corry
(A) Rehabilitation and infrastructure improvements of a former industrial facility for the Corry multitenant facility located within an enterprise zone and Keystone Opportunity Zone1,700,000
(B) Construction, site development and infrastructure improvements for a lodge, recreation and campsite development project15,000,000
(C) Construction of Corry Memorial Hospital building6,000,000
(ii) County Projects
(A) Acquisition, site preparation, construction for the Invest ERIE Program1,000,000
(B) Site preparation and construction of a regional community international center1,000,000
(C) Lake Erie College of Osteopathic Medicine (LECOM), construction of a multipurpose building to house a medical library, student union and classrooms14,800,000
(iii) Union City Borough
(A) Acquisition and rehabilitation of the Ethan Allen manufacturing facility to develop a business incubator facility1,000,000
(B) Union City Dam, site development and infrastructure improvements15,000,000
(iv) City of Erie
(A) Acquisition, construction, infrastructure development of brownfield site within a keystone opportunity zone for the GAF Relocation and Bayfront Development Project40,000,000
(B) Development of Erie Convention Center26,000,000
(C) Fenestra Freight Facility5,000,000
(D) Erie Zoo, Children's Zoo Renovation3,200,000
(v) Erie-Western Pennsylvania Port Authority
(A) Keystone Opportunity Zone Industrial Park Subdivision1,500,000
(B) Construction of Erie Bay Front Convention Center12,500,000
(vi) Millcreek Township
(A) Provide safe access to rails, renovations and development of education and recreational facilities and resource management at Asbury Woods Greenway1,691,000
(26) Fayette County
(i) City of Uniontown
(A) Uniontown Revitalization Project, acquisition, renovation, demolition and construction of various buildings in downtown Uniontown6,000,000
(B) Uniontown Parking Project, development of parking facilities in the City of Uniontown1,500,000
(C) Community Action Campus Project, campus repairs and expansion1,000,000
(ii) North Union Township
(A) University Technical Park, construction within the park, including transportation access2,000,000
(B) Fay-Penn Development Center, construction and renovation of new and existing building2,500,000
(iii) County Projects
(A) Fayette County Heritage Projects, development and renovation2,000,000
(B) Fayette County Industrial/Business/Technology Park Project, construction and expansion of new and existing parks5,000,000
(C) Fayette County Courthouse renovations10,000,000
(D) Fayette County Downtown Revitalization Project, Perryopolis, Masontown, Connellsville, Point Marion and Brownsville4,000,000
(E) Construction of a Coal and Coke Interpreting Center3,000,000
(F) Fayette County Infrastructure Development Project, development of infrastructure and construction projects throughout several Fayette County communities5,000,000
(G) Fayette County Multiple Occupancy Building, development and construction of incubator project2,100,000
(H) Fayette County Visitors Center Project, development and construction of visitors center650,000
(I) Fayette County Agricultural and Environmental Center, development and construction of agricultural and environmental center1,500,000
(J) Recreational Trail Development Project, redevelopment of the Sheepskin Trail and other Yough Trail connector trails1,500,000
(K) Jennings Run Creek Sewage Project, installation of sewage lines to Franklin Industrial Park, Menallen Township industrial site2,500,000
(iv) Uniontown and Brownsville
(A) Fayette County Train and Streetcar Museum, development and construction of a train and streetcar museum500,000
(v) Brownsville
(A) Brownsville Riverside Project, rehabilitation and beautification of Brownsville's riverside, including construction1,000,000
(vi) Connellsville
(A) Downtown Connellsville Redevelopment Project, redevelopment of downtown Connellsville1,500,000
(27) Forest County (Reserved)
(27.1) Forest, Clarion, Venango and Warren Counties
(i) County Projects
(A) Development and construction of a wireless broadband connectivity system for rural Pennsylvania counties500,000
(28) Franklin County
(i) County Projects
(A) Design and construction of fire hall facilities, including site development and infrastructure development for various consolidated fire companies3,665,000
(29) Fulton County
(i) Fulton Industrial Development Association
(A) Business Park II, development of a business park near Warfordsburg5,000,000
(B) Construction of a multitenant building2,000,000
(30) Greene County
(i) Greene County Industrial Development Authority
(A) Acquisition and redevelopment of the former Waynesburg Prison site2,000,000
(ii) County projects
(A) Greene County Team Pennsylvania Careerlink, construction and renovations for expansion of Careerlink's office space in the Ben Franklin Building400,000
(B) Greene County swimming pool and tennis courts, including, but not limited to, land acquisition, onsite construction and facility improvements2,200,000
(31) Huntingdon County
(i) County Projects
(A) Upper Corners development at Raystown Lake, infrastructure development2,000,000
(B) East Broad Top Railroad, restoration of rail shops and adjoining facilities8,200,000
(C) Development of multicounty bike trail1,500,000
(32) Indiana County
(i) Indiana County Development Corporation
(A) Land acquisition, design, site preparation, infrastructure improvements, demolition, construction and renovations to an existing building within Route 22 Corridor2,000,000
(B) White Township, construction, renovations and expansion of a vacant building in Indiana County Commerce Park1,250,000
(C) Green Township Business Park, Phase I of a redevelopment project that consists of land acquisition, planning, site clearance, infrastructure development and access road construction500,000
(D) Green Township Business Park, Phase II of a redevelopment project that consists of design, site preparation, infrastructure improvements and construction of a multitenant business facility1,000,000
(E) Airport Industrial Park, site improvements and building construction3,000,000
(F) Indiana Players Theater, site improvements and building construction2,000,000
(G) White Township, construction and site improvements for a multitenant facility5,000,000
(H) Construction of a multitenant facility including land/building acquisition and site developments2,000,000
(I) Development of the Jimmy Stewart Airport Industrial Park and Distribution Facility6,500,000
(J) Indiana Regional Medical Center, development and construction of a breast cancer center3,250,000
(33) Jefferson County
(i) Jefferson County Industrial and Economic Development Council
(A) Infrastructure development for a 90-acre industrial park adjacent to the I-80 corridor and located in Union Township2,000,000
(B) Rehabilitation/revitalization of the Eberhard Building located in downtown Punxsutawney1,050,000
(ii) Punxsutawney Regional Development Corporation
(A) Acquisition, construction, rehabilitation and restoration of the Jensen Building in Punxsutawney Borough1,600,000
(34) Juniata County
(i) Juniata business and industry
(A) Empire Kosher Poultry, construction and improvement of existing facility3,000,000
(35) Lackawanna County
(i) City of Carbondale
(A) Construction, rehabilitation and restoration of commercial district as part of the Greater Carbondale Initiative650,000
(B) Anthracite Historical Discovery Center, new construction and site development2,400,000
(ii) Covington Township
(A) Rehabilitation and restoration of a historic mansion to establish the Moffit Museum and Community House1,000,000
(iii) City of Scranton
(A) Construction of a parking garage in downtown Scranton1,000,000
(B) Lackawanna College/Scranton Lace Community Heritage Area, development of a health and fitness center, historical center/corridor, river walk and recreational fields9,100,000
(C) University of Scranton/City of Scranton, revitalization of downtown area including the development of mixed-use parking and retail structure4,000,000
(D) New construction of Southern Union Company's national headquarters1,500,000
(E) Marywood University, construction of a health care-related facility1,964,000
(F) The Black Diamonds Discovery Center at McDade Park, development of a new visitors and interpretation center, including design and site construction for improvements to the Coal Mine Tour and the Anthracite Heritage Museum and a new children's recreation center5,000,000
(G) Construction of parking garage on Lackawanna Avenue5,000,000
(H) Construction of new downtown office building5,000,000
(I) Neighborhood Commercial District Revitalization Plan, construction, design and site development4,000,000
(J) Lackawanna Avenue Redevelopment Project, construction, design and site development10,000,000
(K) Rehabilitation of Connell Building in downtown Scranton6,000,000
(L) Lackawanna County Courthouse, building renovations and technology upgrades10,500,000
(M) Scranton School District stadium, renovations and new construction2,100,000
(iv) Blakely Borough
(A) Swansea Little League Field improvements645,000
(B) Improvements to little league field and multipurpose field at local park2,300,000
(v) County Projects
(A) Northeast Pennsylvania Fire and Emergency Services Training Center, acquisition, renovations and new construction for a regional fire and emergency response training center3,000,000
(B) The Montage Gateway Project, design and construction of the Lackawanna Valley Interpretive Center and development of a recreation complex next to the Lackawanna County Stadium, including extension of the trolley excursion7,000,000
(C) Northeast Regional Cancer Institute Headquarters facility3,600,000
(D) Renovation of former North Scranton Jr. High School for use by Goodwill Industries4,873,000
(E) Allied Health Services, renovation and expansion of assisted living facility1,000,000
(vi) LaPlume
(A) Keystone College, construction of an early childhood education center800,000
(vii) South Abington Township
(A) Infrastructure for Victorian Village project2,000,000
(B) Development of South Abington Commons750,000
(viii) Jessup Borough
(A) Construction of multitenant building in Jessup Business Park2,750,000
(ix) Borough of Old Forge
(A) Recreation area project, site development and construction3,280,000
(x) Jessup and Archbald Boroughs
(A) Site development and infrastructure improvements to the Valley View Business Park4,500,000
(xi) Taylor Borough
(A) Construction of approximately 300,000 square feet of distribution and warehouse space at the Stauffer Industrial Park Complex500,000
(xii) Dunmore Borough
(A) Extension of Lackawanna County rail authority line3,500,000
(B) Acquisition, construction and renovations to stadium and related recreation area2,000,000
(36) Lancaster County
(i) County Projects
(A) Expansion and renovations to the Lancaster General Hospital14,000,000
(B) Construction of multipurpose ballpark13,000,000
(C) Pennsylvania Academy of Music, for expansion of the existing space to accommodate additional teaching studios and recital hall12,000,000
(D) Elizabethtown College, development and construction of a science, math and engineering center5,000,000
(E) Lancaster County Solid Waste Authority, construction of an ethanol production plant, including land acquisition and site development7,500,000
(F) Development and construction of the Early Childhood Training Institute1,000,000
(ii) Elizabethtown Area Regional Authority
(A) Mount Joy Township, construction of Regional Recreational Park Complex4,000,000
(iii) Borough of Mount Joy
(A) Land acquisition and construction of Mount Joy Train Station365,000
(iv) Elizabethtown Borough
(A) Revitalization project in downtown Elizabethtown, including land acquisition, construction and renovations5,000,000
(B) Renovation, restoration and historic preservation of Elizabethtown Train Station and Intermodal Transportation Center500,000
(v) Millersville Borough
(A) Design and construction of a new municipal building1,000,000
(vi) City of Lancaster
(A) Acquisition and rehabilitation of properties and facilities as part of the Pennsylvania College of Art and Design's neighborhood enhancement project2,000,000
(B) Acquisition, rehabilitation and infrastructure improvements of property as part of the Center City Neighborhood Enhancement Corporation's neighborhood improvement project1,500,000
(C) Acquisition, construction, rehabilitation, restoration and infrastructure improvements to property as part of the historic Lancaster Central Market District Development Initiative12,500,000
(D) Acquisition, construction, rehabilitation and restoration of property to revitalize the East King Street corridor6,500,000
(E) Infrastructure development and improvements to property as part of the James Street Improvement District's Gateway Enhancement Project2,000,000
(F) Acquisition, construction, rehabilitation and renovation of property as part of the Fulton Opera House Foundation Arts Development Project5,000,000
(G) Property acquisition, rehabilitation and restoration for the Heritage Orientation and Interpretive Center Project6,000,000
(H) Property acquisition, rehabilitation, restoration and infrastructure development for the Lancaster Museum of Art Expansion Project4,000,000
(I) Property acquisition, site development and construction of the Lancaster Labor Foundation Employment and Education Services Center700,000
(J) Property acquisition, site preparation, construction, rehabilitation, restoration and infrastructure improvements for the Penn Square Center Project10,000,000
(K) Lancaster Bethel AME Cultural Center Museum7,450,000
(L) Property acquisition, reconstruction and rehabilitation of Lancaster Square including the Ramada/Brunswick Hotel and Bulova Building for the Phoenix Art Center Project20,000,000
(M) Revitalization of the South Duke Street Gateway Corridor, including Roberto Clemente Recreation Area1,000,000
(N) Development of Lancaster Square, including construction of a new urban park, outdoor performance facilities, carousel complex and necessary infrastructure and structural improvements including demolition8,000,000
(O) Acquisition, rehabilitation, construction, restoration and infrastructure improvements to the Eastern Market Building, Tabor Community Services project225,000
(P) Franklin & Marshall College, construction of a new life sciences facility10,000,000
(Q) Spanish American Civic Association, renovation, repair and rehabilitation of facilities, including the Centro Hispano Building, La Academia and Nuestra Clinca Residencial880,000
(R) Construction and renovation of facility to house military arms museum2,500,000
(S) Construction of hotel adjacent to convention center22,000,000
(vi.1) Redevelopment Authority of the City of Lancaster
(A) Redevelopment of the historic Watt & Shand department store as part of the Lancaster County Convention Center/Hotel project22,000,000
(vii) Bird in Hand
(A) Heritage and Information Center, design and construction of an information, orientation and interpretative center3,800,000
(viii) Ephrata Borough
(A) Ephrata Community Hospital, renovations to the hospital's laboratory facilities which include equipment and technology upgrades1,000,000
(B) Downtown revitalization, including the renovation and restoration of the historic railroad station for a visitors center and office space500,000
(C) Acquisition, rehabilitation and renovation of the Mountain Springs Hotel, including auxiliary buildings and facilities5,000,000
(ix) Columbia Borough
(A) Land acquisition, site development and construction of the Heritage Inn and Conference Center to be located at the former silk mill at Third and Linden Streets2,500,000
(x) Lititz Borough
(A) Lititz Springs Park, restoration, rehabilitation and construction of the band shell1,750,000
(B) Renovation and expansion of the Lititz Community Center2,750,000
(xi) West Donegal Township
(A) Improvements to Rheems Athletic Complex500,000
(xii) Earl Township
(A) Construction of New Holland Recreation Center4,000,000
(xiii) Little Britain Township
(A) Design and construction of a new maintenance building500,000
(xiv) West Lampeter Township
(A) Construction of the Lampeter-Strasburg Recreation Center to be located in West Lampeter Community Park2,000,000
(37) Lawrence County
(i) Neshannock Township
(A) Millennium Park Phase II, site acquisition, preparation and construction of a business park in Neshannock Township15,000,000
(ii) New Castle
(A) Riverview Commerce Park Phase II, site acquisition, planning and development for the expansion of a business park in the City of New Castle3,000,000
(B) Property acquisition, restoration and rehabilitation of the former Elk's building for a mixed-use community facility1,000,000
(C) Jameson Hospital - North Campus, renovate and construct a new inpatient and outpatient surgical department7,000,000
(D) Jameson Hospital, renovation of surgical suites5,000,000
(E) Jameson Hospital, renovation and expansion of emergency services department1,500,000
(iii) Shenango Township
(A) Construction, rehabilitation and expansion of the Shenango Community Park500,000
(iv) Ellwood City Borough
(A) Construction, restoration and rehabilitation of Ewing Park3,000,000
(v) New Beaver Township
(A) Property acquisition, site development, construction and infrastructure improvements for the New Beaver Commerce Park5,000,000
(vi) New Wilmington Borough
(A) Westminster College, expansion of the McGill Library5,000,000
(B) Westminster College, renovations and expansion of the community reading and children's book areas located in the Westminster College Library3,500,000
(38) Lebanon County
(i) City of Lebanon
(A) Lebanon Community Arts Project, rehabilitation of existing building to serve as a community arts center4,000,000
(B) Upgrade of Coleman Park pool1,000,000
(C) Market House revitalization project3,000,000
(ii) County Projects
(A) Lebanon Valley Economic Development Corporation, land acquisition and site development associated with the Lebanon Valley Business Park1,500,000
(B) Lebanon Valley Economic Development Corporation, expansion of Aspens-Hanford Business Park2,000,000
(C) Lebanon Valley Economic Development Corporation, land acquisition and site development associated with I-81/I-78 Business Park4,000,000
(D) Lebanon Valley College, renovation of Garber Science Hall and construction of a new science center7,500,000
(39) Lehigh County
(i) City of Allentown
(A) Reclamation and redevelopment of the former city incinerator site and adjacent properties10,000,000
(B) Development of an artist incubator on Hamilton Street in conjunction with the city's arts and entertainment district plan375,000
(C) Construction and development of an indoor recreational facility in the 1st Ward community in conjunction with the city's weed and seed community plan1,500,000
(D) Construction and development of a police substation/community center to cover east side of city5,000,000
(E) Rehabilitation, renovation and reuse of Schoen Building for loft apartments750,000
(F) Infrastructure improvements and development of an arts and entertainment district around arts and cultural institutions1,000,000
(G) Property acquisition, site development, construction and infrastructure improvements for the Allentown Performing Arts Center20,000,000
(H) Upper Floor Program to rehabilitate and reuse the upper floors in older buildings in the Central Business District250,000
(I) Construction and infrastructure improvements for the Agricultural Hall expansion project2,000,000
(J) Redevelopment of the south side of 800 block of Hamilton Street into a mixed commercial/retail site2,500,000
(K) Property acquisition, construction and infrastructure development of the Lehigh Valley Convention Center34,000,000
(L) Construction, site preparation and infrastructure rehabilitation at the Allentown incineration site10,000,000
(M) Redevelopment of a 50-acre site into a mixed development environment2,500,000
(N) Lehigh Valley Hospital, 17th and Chew Streets, renovation of operating rooms1,000,000
(O) Promise Child Life Institute, Inc., acquisition and renovation of light industrial building at 391 Auburn Street to house daycare, preschool, after-school and parenting programs1,550,000
(P) Agere property redevelopment, redevelopment of 75-acre Agere property, including infrastructure improvements to roads, sewers and water utilities for industrial park11,800,000
(Q) Design, development and construction of an intermodal transportation center5,000,000
(R) Development of a downtown arts and entertainment district, including infrastructure and streetscape improvements, an emerging artist incubator on Hamilton Street and expansion of the Art Museum and Symphony Hall5,875,000
(S) Construction of a parking garage3,000,000
(T) Redevelopment of Downtown Allentown Hotel2,500,000
(U) Redevelopment of Lehigh Valley Dairy Property Site, including infrastructure improvements, demolition of existing dairy facility and site remediation1,500,000
(V) Redevelopment of former Tarkett property, including demolition, remediation and infrastructure development1,000,000
(W) Acquisition and demolition of adjacent structures and construction of an addition to the Allentown Art Museum10,000,000
(X) Korea/Vietnam Memorial, construction of a national educational center2,000,000
(Y) Sacred Heart Hospital, renovation of existing primary parking structure800,000
(ii) Salisbury Township
(A) Rehabilitation and construction of the KidsPeace-Broadway Campus Project3,000,000
(B) Lehigh Valley Hospital, Cedar Crest and I-78, expansion of the Neonatal Intensive Care Unit (NICU)500,000
(iii) Schnecksville
(A) KidsPeace, the National Center for Kids Overcoming Crisis, design and construction of an educational and residential facility at the Orchard Hills Campus1,900,000
(B) Schnecksville Community Fair, construction of a convention/exhibition center1,000,000
(iv) City of Bethlehem
(A) Lehigh Valley Hospital, Muhlenberg, expansion and renovation of the Cancer Center1,325,000
(v) County Projects
(A) Construction of an addition to and renovation of the Lehigh County Courthouse, including parking and other urban improvements35,500,000
(B) Lehigh Landing Riverfront Redevelopment project, site assembly and development500,000
(C) Development and construction of the America on Wheels Museum12,000,000
(D) National Museum of Industrial History, construction of preview center and main museum30,000,000
(E) Banana Factory, renovations and expansion750,000
(F) Parkland Community Library, construction of a new library facility, including land acquisition2,500,000
(G) Construction of a new minor league ball field/stadium12,000,000
(vi) Slatington Borough
(A) Construction and development of the Northern Lehigh Community Center500,000
(vii) Borough of Emmaus
(A) Renovation and expansion of police station and administrative building1,350,000
(viii) North Whitehall Township
(A) Purchase of farmland/development rights500,000
(B) Development of the Minnich Tract for recreation1,500,000
(C) Erect new public works building1,546,000
(D) Acquisition of property for open space and recreation1,500,000
(E) Development of Schnecksville Park for recreation589,000
(ix) Whitehall Township
(A) Redevelopment of Tarkett facility, infrastructure development, demolition and remediation2,000,000
(x) DeSales University
(A) Construction of a Conference/Community Center2,000,000
(xi) Sacred Heart Hospital
(A) Expansion and renovation of an Older Adult Behavior Modification Center and Adult Psychiatric Unit2,000,000
(40) Luzerne County
(i) County Projects
(A) Hanover and Newport Townships and Nanticoke, construction and infrastructure development as part of the Earth Conservancy South Valley Park's Mixed-Use Plan along the State Route 29 Corridor1,000,000
(B) Construction and renovations to county administration building5,000,000
(C) Renovations and expansion to Luzerne County Courthouse1,500,000
(D) Construction of county parking garage1,300,000
(E) Renovation and improvements to Moon Lake Park550,000
(F) Construction and improvements to Luzerne County Sports Complex450,000
(G) Development of Cranberry Creek Gateway Park in Hazle Township, Phase I1,714,000
(H) Development of Cranberry Creek Gateway Park in Hazle Township, Phase II5,574,000
(I) Development of Cranberry Creek Gateway Park in Hazle Township, Phase III9,781,000
(J) Hazleton General Hospital, expansion and renovation of emergency room7,000,000
(K) Pittston Area School District, construction and renovations to athletic facility250,000
(L) College of Misericordia, development and construction of an arts center2,500,000
(M) Acquisition and development of mixed-use recreational and commerce industrial site6,500,000
(N) Improvements to Valley View Business Park4,500,000
(O) Acquisition, construction and infrastructure development of a site for a new manufacturing facility and economic development project30,000,000
(P) Infrastructure development of former Kaminski Brothers' lands, approximately 900 acres of greyfields located in Jenkins and Pittston Townships20,000,000
(Q) Construction of a multiuse community center in Butler Township1,500,000
(ii) Hanover Township
(A) Reclamation of a 100-acre abandoned anthracite mine site for the Hanover Crossings Business Park Phase III1,000,000
(B) Infrastructure development for the Hanover Crossings Business Park Phase IV1,000,000
(C) Construction of community recreation center500,000
(iii) City of Nanticoke
(A) Acquisition of properties and the construction of facilities as part of the Nanticoke City Downtown Development Project, including parking facilities2,000,000
(B) Construction and development of the Nanticoke City Greenway Project to enhance tourism and recreational opportunities500,000
(C) Acquisition costs, infrastructure development and improvement and construction costs related to the rehabilitation and restoration of the Greater Nanticoke Area Recreation Complex500,000
(D) Acquisition costs, infrastructure development and improvements, and construction costs related to an emergency services responder training facility1,000,000
(E) Acquisition costs, infrastructure development and improvements, and construction costs related to the rehabilitation and restoration of the Susquehanna Coal Building1,500,000
(iv) Newport Township
(A) Construction and development of infrastructure improvements to the Newport Township Ridgeview Mixed-Use Park1,000,000
(B) Construction of Newport Motor Sports Park1,000,000
(C) Construction of Penobscot Ridge Mountain bike retreat area250,000
(D) Construction of an intermodal facility to support the development of the Dan Flood Industrial Park2,000,000
(v) Wright Township
(A) Rehabilitation and infrastructure improvements for the Crestwood Industrial Park Expansion Project located within a Keystone Opportunity Zone1,000,000
(vi) City of Wilkes-Barre
(A) Renovations to vacant 100,000-square-foot office tower on public square4,000,000
(B) Construction of Coal Street parking garage in Wilkes-Barre5,000,000
(C) Downtown Economic and Redevelopment Project22,000,000
(D) Construction of downtown parking garage5,000,000
(E) Acquisition, rehabilitation and demolition of the abandoned Murray Complex1,000,000
(F) Acquisition, demolition and rehabilitation of the abandoned Shapiro Scrap Yard, Sanitary Laundry and Sea Isle Sports Wear1,000,000
(G) Construction of an office tower and adjoining parking garage10,350,000
(H) Renovation of Hotel Sterling into a commercial complex7,500,000
(I) Construction of a 12-plex cinema and 400-car parking garage in downtown Wilkes-Barre6,000,000
(J) Construction and renovation of a multipurpose Susquehanna River theme technology, heritage, convention and tourism center and supporting infrastructure and parking facilities, including the acquisition of the Irem Temple Mosque and the adjacent properties32,500,000
(K) Acquisition, demolition and rehabilitation of abandoned redevelopment authority buildings in Diamond Corporate Park1,500,000
(L) Acquisition and rehabilitation of land and buildings for the Weinberg Northeast Pennsylvania Regional Food Bank1,000,000
(M) Expansion of Park N. Nock North, addition of two new decks to existing structure2,500,000
(N) Construction of an office tower and adjoining parking garage10,350,000
(O) Acquisition of site work for a 200-job expansion of an existing manufacturing corporation, Trion Corporation750,000
(P) Renovation to the FM Kirby Center for Performing Arts3,200,000
(Q) Property acquisition, site preparation and construction of a commercial/retail development5,000,000
(vii) City of Pittston
(A) The Downtown Redevelopment Project, acquisition of properties, development and infrastructure improvements in downtown Pittston5,000,000
(B) Site improvement and expansion of Riverfront Park1,800,000
(viii) Lehman Township
(A) Land acquisition, site infrastructure and construction of the Black Mountain Recreation Complex4,000,000
(41) Lycoming County
(i) County Projects
(A) Hughesville Public Library, construction of a new library building500,000
(B) Jersey Shore YMCA, for a portion of a million dollar redevelopment project that includes renovations and conversion of facilities and installation of an elevator500,000
(C) Lycoming County Communications System, system upgrades to the County 911 Communications Center2,000,000
(D) Lycoming County Industrial Park, Brady Township Keystone Opportunity Zone site preparation and construction6,500,000
(E) Design and construction of the East Lycoming YMCA Community Center3,000,000
(F) Williamsport-Lycoming Chamber of Commerce and Industrial Properties Corporation, acquisition and redevelopment of the Williamsport Wirerope Works facility3,000,000
(ii) Jersey Shore Borough
(A) A portion of a million-dollar recreational improvement plan that includes land acquisition to be developed into recreational areas and repair, renovation and upgrading of an existing community swimming pool250,000
(iii) East Lycoming Recreation Authority
(A) Construction of a multipurpose recreational building and facilities2,000,000
(iv) City of Williamsport
(A) Development of the Central Area Fire Chiefs' Association Emergency Services Training Facility1,000,000
(B) Design and construction of a new centralized law enforcement facility1,000,000
(42) McKean County
(i) Kane Area Industrial Development Corporation
(A) Westmore Township, for the Kane Area Multi-Tenant Center project750,000
(ii) City of Bradford
(A) Land acquisition, demolition, site clearance, building rehabilitation, building construction, development of related facilities, infrastructure, streetscape and recreation improvements10,500,000
(43) Mercer County
(i) County Projects
(A) Rehabilitation and redevelopment of the Westinghouse Plant located in Sharon20,000,000
(B) Development of an industrial park to be located within Mercer County8,000,000
(C) Renovation and rehabilitation of buildings in the Reynolds Industrial Park in Pymatuning Township500,000
(D) Reynolds East Business Park, construction of a multitenant building850,000
(E) Reynolds East Business Park, Phase II infrastructure improvements600,000
(F) Rehabilitation and improvements to the railroad infrastructure at the Duferco Farrell Corporation Facility5,000,000
(G) Renovation and rehabilitation of the Columbia Theater for the Arts8,000,000
(H) City of Sharon, The Vocal Group Hall of Fame & Museum, for renovations to the historic Columbia Theater4,000,000
(I) Construction of a 50,000-square-foot manufacturing facility in Sharon1,000,000
(J) Sharon Regional Health System, construction of an outpatient diagnostic center in the City of Hermitage3,000,000
(K) Buhl Farm Trust, infrastructure improvements875,000
(L) Community ACTION Partnership of Mercer County, acquisition and renovation of building located in Sharon for organization headquarters500,000
(M) Infrastructure improvements and redevelopment in the City of Sharon1,500,000
(44) Mifflin County
(i) Mifflin County Industrial Development Corporation
(A) Acquisition and development of a 300-acre site for the expansion of the Mifflin County Industrial Park5,000,000
(45) Monroe County
(i) County Projects
(A) Pocono Mountains Industries, expansion of business park19,575,000
(B) Pocono Mountains Enterprise Center, construction1,000,000
(46) Montgomery County
(i) Jenkintown Borough
(A) Acquisition and restoration of a landmark historic theater in Jenkintown for the purpose of preserving this historic building and expanding cultural offerings in the area805,000
(ii) Borough of Pottstown
(A) Land acquisition, design and construction of a parking garage in downtown Pottstown1,102,000
(B) Completion of a redevelopment project restoring the former PECO building500,000
(C) Acquisition and redevelopment of properties within the Pottstown KOZ for an office park, parking garage and commercial and retail development1,500,000
(D) Development and construction of a commercial/mixed-use business park, including demolition, remediation and site preparation at the former Mrs. Smith's Pies site located at Hanover Street and the Industrial Highway2,500,000
(E) Schuylkill River Greenway Association, building renovations and development of a Montgomery County Community College satellite campus1,000,000
(iii) Redevelopment Authority of the County of Montgomery
(A) Lower Moreland Township, land acquisition, demolition and removal of blighted buildings for reuse as a recreational area1,300,000
(B) Norristown Borough, additional funds for the development and construction of a parking garage in the downtown area4,000,000
(C) Conshohocken Borough, Central Business District Redevelopment Project, acquisition, site development and construction5,000,000
(iv) Springfield Township
(A) Acquisition, rehabilitation, restoration and infrastructure improvement of a historic building in Springfield Township1,200,000
(B) Keystone House Project Phase II and Phase III1,000,000
(v) Upper Providence Township
(A) Schuylkill Canal Association, for wastewater weir riverbank stabilization, Locktender's House restorations and upgrades, handicapped accessible pathway to restrooms and control gate overflow channel repair500,000
(vi) Collegeville and Trappe Boroughs
(A) Mainstreet redevelopment and streetscape improvements, including, but not limited to, new pedestrian crosswalks, street lighting and tree planting1,000,000
(vii) Souderton Borough
(A) Construction of a new boys and girls club on Washington Avenue2,000,000
(B) Partial funding for the construction of a $3,000,000 Indian Valley Boys & Girls Club100,000
(viii) Lower Providence Township
(A) Eagleville Hospital, renovations, including roof replacements, exterior building repairs, window replacements, HVAC and boiler replacements, fire alarm replacements, handicapped patient transportation replacement and parking lot resurfacing1,558,000
(ix) Trappe Borough
(A) Muhlenberg House, purchase and restoration of the historic Frederick Muhlenberg House and conversion to a living museum500,000
(x) Philadelphia Theological Seminary of St. Charles Borromeo Seminary
(A) Improvements and renovations to Ryan Memorial Library3,000,000
(B) Installation of life safety systems on campus3,000,000
(C) Classroom renovations and technology improvements600,000
(xi) Saint Josephs University
(A) Land acquisition, demolition and construction for the purpose of expanding the campus30,000,000
(xii) Upper Merion Township and Valley Forge Historical Society
(A) Construction of the National Museum of the American Revolution20,000,000
(xiii) County Projects
(A) Pennsylvania College of Optometry, site acquisition, development and construction for a student community center3,000,000
(B) Delaware Valley Historical Aircraft Association, construction of the Wings of Freedom Aviation Museum6,000,000
(C) Construction of the Abington School District stadium complex to serve the community, including public, parochial and community athletic events1,500,000
(D) National Audubon Society, renovations and new construction of a climate-controlled facility to house the artifacts of John James Audubon1,000,000
(E) The Elmwood Park Zoo of Norristown, Phase I expansion, including renovations and new construction4,200,000
(F) Plymouth Meeting Mall redevelopment10,000,000
(G) Construction of police firearms and homeland security training center1,250,000
(xiv) Lansdale Borough
(A) Acquisition, renovation and demolition of freight station700,000
(xv) Abington Township
(A) Expansion of Abington Arts Center500,000
(B) Abington School District, construction of a field facility for Abington Senior High School500,000
(xvi) Borough of Conshohocken
(A) Property acquisition, design and construction of a 165,000-square-foot building at the Millennium IV Brownfield site located on Washington Street for the headquarters of Philadelphia Consolidated Holding Corp. t/a Philadelphia Insurance Companies (NASDAQ: PHLY)3,000,000
(xvii) Upper Merion Township
(A) Acquisition, design, rehabilitation and renovation at 935 First Avenue by GSI Commerce, Inc. and/or its subsidiaries and/or affiliates (GSI) for the World Headquarters of GSI3,000,000
(xviii) Skippack Township
(A) Streetlight installation and general improvements on Skippack Road between Forty Foot Road and Cressman Road1,000,000
(xix) Upper Moreland Township
(A) Construction of a new branch facility for the Settlement Music School, including land acquisition and demolition5,000,000
(47) Montour County
(i) County Projects
(A) Site acquisition and development of infrastructure to support an industrial park3,600,000
(48) Northampton County
(i) County Projects
(A) Design and construction of the Slate Belt Community Center and regional recreation facility3,000,000
(B) Acquisition of abandoned Norfolk Southern Railroad right-of-way from Hellertown/Bethlehem municipal line, west to former Union Station and development of a new Linear Park and Urban Greenway2,000,000
(C) Property acquisition, site development and construction for a minor league baseball stadium12,000,000
(ii) City of Bethlehem
(A) (Reserved)
(B) Acquisition, rehabilitation and infrastructure development of a 135-acre brownfield as part of the Bethlehem Works Project60,000,000
(C) Acquisition, rehabilitation and infrastructure development to establish the south side Bethlehem job training center4,500,000
(D) Design and construction of an enclosed garage and external parking lot at the Lehigh Riverport in the south side of Bethlehem3,000,000
(E) Bethlehem Technology Center Business Incubator for land acquisition, site preparation, brownfield rehabilitation and site construction4,000,000
(F) Bethlehem Technology Research Center, acquisition, remediation and renovation of former Bethlehem Steel research facility for Bethlehem Biotech Business Incubator5,000,000
(G) Construction of a parking garage for the Lehigh University Campus Square Project3,000,000
(H) Construction of a business incubator and technology center in South Bethlehem on the former Bethlehem Steel site3,000,000
(I) Construction of a shell, flex building in South Bethlehem in the new Commerce Center Industrial Park5,000,000
(J) Renovation and restoration of Sister's House in Historic Bethlehem3,000,000
(K) Improvements to the Elizabeth Avenue and Center Street corridor2,500,000
(L) Construction of a parking garage in the vicinity of Monacacy Road on the former silk mill site2,500,000
(M) Construction of a parking garage in the Historic Bethlehem Quarter to be located behind the Hotel Bethlehem2,500,000
(N) Construction of Arts Park on former Bethlehem Steel property in the south side of Bethlehem20,000,000
(O) Restoration of the Illick's Mill, construction and reuse of now-vacant stone structure into an environmental education center600,000
(P) Historic renovation of Brethren's House3,000,000
(Q) Construction of the Just Born Visitors Center to be located in northeast Bethlehem at the Just Born, Inc., headquarters17,500,000
(R) Lehigh Heavy Forge Industrial Park, demolition, infrastructure improvements, renovation and new construction for new industrial park1,550,000
(iii) Northampton County Industrial Development Authority
(A) Construction of a community recreation center in the Township of Bethlehem8,000,000
(iv) City of Easton and Wilson Borough
(A) Construction, restoration and infrastructure improvements and development for the purpose of creating an intermunicipal recreation complex1,000,000
(v) City of Easton
(A) Property acquisition, site improvements, rehabilitation and restoration of 10+ acres for the Simon Silk Mill Redevelopment Project7,500,000
(B) Property acquisition, site preparation, construction, rehabilitation, restoration and infrastructure improvements for the Heil Sports Complex2,000,000
(C) Construction, rehabilitation, restoration and reuse of the vacant former Sigal's Bridal Store for a museum2,000,000
(D) Property acquisition, construction, restoration and infrastructure development for the Easton Community Center2,500,000
(E) Construction of Easton intermodal visitors center5,000,000
(F) Revitalization and construction to State Theatre Center for the Arts3,400,000
(G) Expansion of the Family YMCA of Easton, Phillipsburg and vicinity4,000,000
(H) Hugh Moore Park Center for History and Technology, renovation and facility improvements1,800,000
(I) Bushkill Creek River Walk, site acquisition and bikeway development along Bushkill Creek3,500,000
(J) Lehigh Yards, rehabilitation of the Valley Passenger Rail Station and railway yards2,500,000
(K) Two Rivers Intermunicipal Bikeway, construction of a bikeway system2,500,000
(L) Lafayette College, acquisition, renovation, demolition and landscaping to promote economic development3,000,000
(M) Construction of a multilevel parking garage and surface lots, including land acquisition1,800,000
(N) Redevelopment of Third and Snyder Streets corridor, including land acquisition and infrastructure improvements10,000,000
(O) Redevelopment of Northampton Street corridor from Larry Holmes Drive to 6th Street, including land acquisition and infrastructure improvements12,000,000
(P) Renovation and site improvements to Bachmann Tavern800,000
(Q) Redevelopment of South Easton industrial sites2,500,000
(R) Redevelopment and rehabilitation of properties located in Easton and West Easton Enterprise Zone, including land acquisition2,500,000
(S) Construction of a downtown parking garage and surface lots, including property acquisition7,000,000
(vi) Hellertown Borough
(A) Property acquisition, restoration, renovations, infrastructure improvements for the Hellertown Downtown Revitalization Project500,000
(vii) Williams Township
(A) Acquisition, demolition, remediation, construction and redevelopment of stadium site along Cedarville Road1,250,000
(B) Construction of a new municipal office building, including original movable furniture and equipment500,000
(viii) Bushkill and Plainfield Townships
(A) Industrial park development and associated road improvements in the Route 33/Route 512 corridor5,000,000
(ix) Forks Township
(A) Construction and expansion of township building, fire station and police station, including site improvements3,000,000
(x) Borough of Northampton
(A) Apparel factory site, design and construction of off-street parking facilities, public restroom facilities and museum/visitors center500,000
(49) Northumberland County
(i) County Projects
(A) Renovations to historical Pottsgrove School House350,000
(B) Riverbank stabilization in conjunction with amphitheater project1,800,000
(ii) Lower Mahanoy Township
(A) Construction of an addition to the Township Municipal Building150,000
(B) Construction of a water line addition1,500,000
(iii) Herndon Borough
(A) Community redevelopment project that includes land acquisition, renovations and construction3,500,000
(B) Renovations to Northumberland County Courthouse1,000,000
(C) Turbotville Community Hall, capital improvements400,000
(iv) Susquehanna Industrial Development Corporation
(A) Development of an industrial park, including land acquisition1,200,000
(v) City of Shamokin
(A) Development of commercial-ready sites, including infrastructure improvements, land acquisition and demolition for the former PP&L maintenance facility, the former Weller Vending Building and the former Shamokin shoe factory1,150,000
(B) Renovation and rehabilitation of the Shamokin Legion Building for use by the Shamokin Public Library, Northumberland County Senior Action Center and the Shamokin Youth Basketball Program750,000
(C) Construction and development of a public works and maintenance complex364,000
(vi) Coal Township
(A) Infrastructure development and improvements, including, but not limited to, highway access to the Coal Township/SEEDCO Industrial Park3,500,000
(50) Perry County
(i) County Projects
(A) Purchase and development of Business Campus I industrial park2,000,000
(ii) Capital Area Intermediate Unit
(A) Development of a broadband service for schools, government, emergency management agencies and economic development entities400,000
(51) Philadelphia County
(i) County Projects
(A) Lutheran Settlement House, construction of new building to expand and enhance program services5,000,000
(B) (Reserved)
(C) Please Touch Museum at Memorial Hall, facility construction and renovation20,000,000
(D) Point Breeze Revitalization Project2,500,000
(E) Construction, rehabilitation and restoration of the South Philadelphia recreational centers1,000,000
(F) Pleasant Playground, demolition of existing building and construction of a new facility, to include a gymnasium, activities rooms and staff offices1,000,000
(G) Renovation and infrastructure improvements to the historic Saint Vincent Community Center1,000,000
(H) Construction and development of the 160,000-square-foot multilevel, multiuse New Progress complex5,000,000
(I) Construction of the Morning Star Community Center500,000
(J) Land acquisition and construction of the 4200 Mitchell Street Senior Assisted Services Center, including renovation of a one-story industrial building for assisted services for senior citizens for providing access to primary health care delivery, personal care, fitness and adult day care1,200,000
(K) Construction of the Philadelphia Parent Child Care Center500,000
(L) Infrastructure and rehabilitation improvements for a technology business incubator3,000,000
(M) Construct for the Philadelphia Theatre Company a new state-of-the-art 400-seat performance theater as part of Phase II of the Avenue of the Arts10,000,000
(N) Acquisition and rehabilitation of infrastructure for a youth mall and training center for at-risk youth1,500,000
(O) Construction of a rehearsal facility with administrative offices and other spaces, final appurtenances and habiliments to the Pennsylvania Ballet2,500,000
(P) Independence Mall, improvements including streetscapes, physical plant improvements and landscaping12,000,000
(Q) Moore College of Art and Design, air conditioning and infrastructure improvements to 1918 and 1920 Race Street in Philadelphia8,000,000
(R) National Museum of American Jewish History, construction of facility to house interactive galleries, expanded exhibition halls, resource center, auditorium, additional storage space and other improvements50,000,000
(S) Acquisition, planning, design and construction of a Youth Mini Mall and Pennsylvania Hall of Fame facility6,000,000
(T) University of Pennsylvania, for construction of an ambulatory care/cancer care facility50,000,000
(U) Citizens Acting Together Can Help (CATCH) for the construction of a facility in Philadelphia to house child and adult behavioral health services1,500,000
(V) Acquisition, construction, site preparation and infrastructure improvements and development to renovate and expand the historic Boyd Theatre on the 1900 Block of Chestnut Street12,500,000
(W) Concerned Black Men, Inc. Youth Center, acquisition, construction, site preparation and infrastructure development1,500,000
(X) The Philadelphia Museum of Art, renovations of museum galleries15,000,000
(Y) Rehabilitation of Brewery Park Plaza at Thirty-first and Masters Streets2,000,000
(Z) Revitalization of Chel Wayne1,000,000
(AA) Academy of Music, facility renovations, restoration and improvements20,000,000
(BB) One Pennsylvania Place, land acquisition, site development and construction of public amenities related to the development of One Pennsylvania Place30,000,000
(CC) (Reserved)
(DD) Restoration and upgrade of critical instructional facilities on the campus of Drexel University, including Commonwealth Hall10,000,000
(EE) Construction of a new teaching and research center at the School of Veterinary Medicine at the University of Pennsylvania18,000,000
(FF) House of Umoja1,000,000
(GG) Settlement Music School, for facility construction, renovation and acquisition1,250,000
(HH) Fox Chase Cancer Center, expansion and modernization of the Diagnostic Radiology Department and related outpatient space10,000,000
(II) Fox Chase Cancer Center, construction of a cancer research pavilion and parking garage23,000,000
(JJ) Fox Chase Cancer Center, renovation and modernization of research laboratories1,250,000
(KK) Fox Chase Cancer Center, acquisition of structural biology research equipment1,250,000
(LL) Fox Chase Cancer Center, acquisition of high-field MRI imaging equipment1,500,000
(MM) Construction of a Heritage Tourism Experience facility5,000,000
(NN) Acquisition, demolition, improvements and redevelopment of vacant lots and structures located in the City of Philadelphia600,000,000
(OO) Germantown Settlement, for renovations to the 25,000-square-foot historic Germantown Town Hall4,000,000
(PP) Germantown Settlement, Burgess Building Phase II to include existing structure, located at 220 W. Chelten Avenue, to house various programs such as job training, economic development, work force development and housing2,000,000
(QQ) Saint Joseph's University, acquisition of Episcopal Academy's 38-acre campus located in Lower Merion Township, Montgomery County30,000,000
(RR) Universal Companies, land acquisition, design and construction of The Rhythm and Blues Hall of Fame35,000,000
(SS) Fox Chase Cancer Center, renovations to auditorium600,000
(TT) Fox Chase Cancer Center, roof replacements, research buildings800,000
(UU) Fox Chase Cancer Center, construction of electrical switchgear plant1,250,000
(VV) Site acquisition, infrastructure development to support development along the Schuylkill River15,000,000
(WW) Site acquisition, infrastructure development and construction of "smart building" as part of the University City Science Center20,000,000
(XX) Germantown Settlement, revitalization of Chel Wayne2,000,000
(YY) Wagner Free Institute of Science, Phase I of a complete restoration and rehabilitation program2,000,000
(ZZ) Enhancements and renovations to the Betsy Ross House500,000
(AAA) Saint Joseph's University Science Center renovation, for the renovation of laboratories, classrooms, infrastructure improvements and air handling system12,650,000
(BBB) Saint Joseph's University field house, for the demolition of existing field house and construction of new field house with athletic offices30,000,000
(CCC) Saint Joseph's University library addition and renovation, for the renovation of the library and addition of new space for the library5,000,000
(DDD) Saint Joseph's University 54th Street redevelopment, for the construction of a parking garage14,000,000
(EEE) New Courtland Elder Services, for construction of the New Courtland Logistics Center2,000,000
(FFF) Construction and development of the Kimmel Cancer Center4,000,000
(GGG) Building acquisition, renovations and construction in association with the Lancaster Avenue Medical Center project1,000,000
(HHH) Construction and expansion of an assisted care facility for senior citizens2,000,000
(III) Land acquisition and construction of the Northeast Rockers gymnasium and community center1,000,000
(JJJ) Construction of a new 80-unit addition to the Fleischmann Building at the Pilgrim Gardens retirement communit1,000,000
(KKK) Germantown Settlement, Belmont Nursing Home acquisition and renovations of a 180-bed facility located at Belmont and Parkside Avenue3,500,000
(LLL) Germantown Settlement, Charter School/Goodwill Baptist Church land development and construction of new classrooms to be utilized by the Germantown Settlement Charter School3,000,000
(MMM) Greater Germantown Housing Development Corporation, land acquisition and redevelopment of land located along Germantown Avenue and adjacent to Freedom Square2,000,000
(NNN) Greater Germantown Housing Development Corporation, redevelopment of ten acres of vacant land and construction of student housing for LaSalle University and the Einstein Hospital10,000,000
(OOO) Philadelphia Museum of Art, acquisition, renovation and development of new building facilities30,000,000
(PPP) Philadelphia Museum of Art, improvement and expansion of educational facilities7,000,000
(QQQ) Philadelphia Museum of Art, expansion and improvement of library3,000,000
(RRR) Philadelphia Museum of Art, infrastructure improvements in tunnel and loading dock20,000,000
(SSS) Construction, renovations and building upgrades related to Phases I and II of the Master Plan25,000,000
(TTT) The Mann Center, Phase II renovations and construction of an education center, concessions, restroom facilities and handicapped access area1,500,000
(UUU) Family Practice and Counseling Network, renovation of health center250,000
(VVV) Cancer Treatment Centers of America, new construction and renovations of Parkview Hospital25,000,000
(ii) City of Philadelphia
(A) Land acquisition, infrastructure improvements, rehabilitation, new construction and the removal of blight from South Philadelphia area1,000,000
(B) Children's Hospital of Philadelphia, replacement of the entire main hospital exterior cladding5,000,000
(C) Children's Hospital of Philadelphia, construction of West Infill Building with state-of-the-art digital operating rooms and a pediatric imaging center35,000,000
(D) Construction and expansion of an assisted care facility for senior citizens2,000,000
(E) Boeing Limited, site reclamation and remediation for future business reuse50,000,000
(F) Free Library of Philadelphia, renovations and expansion to the central building25,000,000
(G) Greater Philadelphia Urban Affairs Coalition, construction and development of a culinary institute and restaurant2,000,000
(H) WHYY Technical Operation Center, restructuring, construction and equipping the operations center2,000,000
(I) Construction, rehabilitation, renovation and infrastructure improvements to the Good Shepherd Arm Institute including Phase II projects and improvements1,000,000
(J) 21st Ward Athletic Association recreational infrastructure development and improvements, including necessary equipment upgrades1,000,000
(K) Construction and infrastructure improvements for a replacement building at Pleasant Playground1,000,000
(L) Property acquisition, site preparation, renovations and infrastructure development and improvements as part of the Lancaster Avenue Arts Center Revitalization Project12,000,000
(M) Rehabilitation, renovation and infrastructure improvements for the Allen's Lane Art Center expansion project1,000,000
(N) Haines and Stenton Avenue Gateway Project, acquisition, site preparation, construction, rehabilitation and infrastructure improvements3,000,000
(O) Erlen Theatre Economic Development Project, acquisition, site preparation, construction, rehabilitation and infrastructure improvements2,000,000
(P) Simon Recreation Center Project, construction, rehabilitation, restoration and infrastructure improvements1,000,000
(Q) Construction of a new multiservice center for the Exodus Outreach Project3,019,000
(R) Acquisition of a former school, renovations and construction of a community senior center5,000,000
(S) North Philadelphia Health System, construction and renovation of facilities5,000,000
(T) Restoration, renovation and infrastructure improvements to the Moore College of Art and Design8,000,000
(U) Infrastructure development and improvements as part of the Independence National Historical Park recreation and tourism area2,500,000
(V) Schuylkill River vacant industrial sites, acquisition and remediation of vacant industrial sites40,000,000
(W) Schuylkill River Development Corporation, waterfront infrastructure improvements22,500,000
(X) Cahill Trust Building, reconstruction and expansion, including gymnasium, theater and fine art center10,000,000
(Y) Friends Hospital, site preparation and building construction and renovations12,000,000
(Z) North Broad Street, construction of urban mixed-use commercial and retail development8,000,000
(AA) Center City Mixed Use Theater, construction of new mixed-use theater complex5,000,000
(BB) Philadelphia Naval Business Center Industrial Building, renovations to accommodate sound stage and production space5,000,000
(CC) Temple University Hospital, development and construction of a multilevel ambulatory care building, to include an emergency room, radiation oncology and other health care facilities5,000,000
(DD) Pennsylvania Academy of Fine Arts, expansion of facility and galleries25,000,000
(EE) Girard Avenue Revitalization Project, 19th Street to 32nd Street2,500,000
(FF) Philabundance, construction of a new multipurpose facility at 3650 South Galloway Street for hunger relief and community activities1,000,000
(GG) Girard Avenue Streetscape Project, from I-95 to 33rd Street, to include infrastructure improvements, including land acquisition5,000,000
(HH) Construction of the Heritage Tourism Experience5,000,000
(II) The Masonic Temple, restoration, repairs and refurbishment of the historic building3,000,000
(JJ) Gift of Life Donor Program, acquisition, construction, renovation and equipment purchases for the structure at 401 North Third Street, to provide new office space, laboratories, clinical facilities, education center and meeting facilities8,800,000
(KK) The Calder Museum, new construction of museum on the Benjamin Franklin Parkway20,000,000
(LL) The University of the Arts, construction of a Skyline Performing Arts Center on the top floors of 211 South Broad Street on the Avenue of the Arts3,000,000
(MM) Rhythm and Blues Hall of Fame, construction of building on the Avenue of the Arts35,000,000
(NN) Mother Bethel Foundation, the Richard and Sarah Allen Center, new construction of museum and educational center and library6,000,000
(OO) Eastern State Penitentiary, renovations and improvements3,000,000
(PP) West Parkside retail complex, renovation and expansion8,000,000
(QQ) Smith Memorial Playground, design, construction and improvements2,200,000
(RR) Philadelphia Housing Authority, for public infrastructure improvements associated with the Mill Creek Development Plan, including underground utilities, curbing/sidewalks, street paving and landscape/lighting/signage7,300,000
(SS) North Broad Street Projects, east side of the street economic development project, including construction, renovation and improvements5,000,000
(TT) Penrose Recreation Center renovations500,000
(UU) Berean Technologies and Research Center, new construction1,500,000
(VV) Progress Trust project, infrastructure improvements and renovations5,000,000
(WW) Old Met Retail and Commercial Center, infrastructure improvements and renovations1,500,000
(XX) Nondenominational middle school, new construction1,500,000
(YY) Wagner Free Institute of Science, infrastructure improvements and renovations2,000,000
(ZZ) Wistar Institute, design and construction of biomedical laboratories and related exterior facade renovations2,150,000
(AAA) Land acquisition, site preparation, related infrastructure improvements, including transportation access and new construction of terminal facilities for the operation of a fresh food distribution center in Philadelphia150,000,000
(BBB) Greater Germantown Housing Development Corporation2,000,000
(CCC) East Falls Development Corporation4,750,000
(DDD) Hope Partnership for Education, land acquisition and construction of a Middle School and Adult Education Center2,500,000
(EEE) Renovations to the Women's Alternative Center500,000
(FFF) South Street lighting and streetscape improvements, from Front Street to 8th Street2,000,000
(GGG) Inglis Foundation, for renovations and necessary upgrades at its facilities located at 2600 Belmont Avenue708,000
(HHH) Trinity Center for Urban Life, shelter renovation project250,000
(III) Arthur Ashe Youth Tennis Center. This project shall be construed as a supplement to the project authorized in section 6(51)(i)(RRRR) of the act of October 30, 2002 (P.L.891, No.131), known as the Capital Budget Project Itemization Act of 2001-2002.3,000,000
(JJJ) Impact Services, construction and renovations at facilities located at 1952 E. Allegheny Avenue, 111 W. Erie Avenue and 124 E. Indiana Avenue3,200,000
(KKK) Impact Services, acquisition, renovations and development at 3158 Kensington Avenue, The Flomar Building, for multiuse facility1,000,000
(LLL) Mill Creek Recreation Center, renovation and new construction12,000,000
(MMM) Philadelphia Jewish Archives Center, acquisition, renovation and construction of a facility for preservation and storage of historical records and related public programming, including exhibitions and educational programs1,800,000
(NNN) Nueva Esperanza, new construction and renovations for expansion of facilities' infrastructure improvements2,500,000
(OOO) Fort Mifflin on the Delaware, restoration of the Commandant's House1,300,000
(PPP) Infrastructure improvements and site preparation for development of the Philadelphia Naval Yard26,000,000
(QQQ) Construction of a new 200,000-square-foot office building and underground parking garage3,500,000
(RRR) Renovations to the Philadelphia Food Bank533,000
(SSS) Rehabilitation of the We Care Adult Day Center1,500,000
(TTT) Acquisition of the West Oak Lane Plaza3,250,000
(UUU) Construction, rehabilitation, restoration and infrastructure improvements for environmental and recreation development projects at Pleasant Hill Park500,000
(VVV) Development and construction of inpatient, outpatient, research and parking facilities at the Children's Hospital of Philadelphia75,000,000
(WWW) Renovation and transformation of Saint Agnes Medical Center into a Continuing Care Medical Center5,000,000
(XXX) Construction of the La Salle University Science and Technology Learning Center9,000,000
(YYY) Philadelphia Industrial Development Corporation, renovation of the Northeast High School stadium complex to serve the Greater Northeast community, including public, parochial and community athletic events2,500,000
(ZZZ) Holy Family University, construction of a state-of-the-art School of Business3,000,000
(AAAA) Philadelphia University, construction of a Center for Community Fitness5,000,000
(BBBB) Baltimore Avenue Redevelopment Corporation, for construction of the Baltimore Avenue Community Development Center in the 51st and Baltimore Avenue Urban Renewal Area3,000,000
(CCCC) North Delaware Riverfront Transit improvements12,500,000
(DDDD) North Delaware River Road7,500,000
(EEEE) Mill Creek, additional infrastructure costs2,686,000
(FFFF) Spring Garden Community Development Corporation, Spring Garden area improvement projects4,000,000
(GGGG) The Lutheran Theological Seminary, construction of new learning center9,000,000
(HHHH) Spring Garden District, for streetscaping and lighting5,250,000
(IIII) Spring Garden District, for construction of two parking garages and parking beautification20,300,000
(JJJJ) Beech Corporation - Broadway, development of a retail center on North Broad Street between Cecil B. Moore and Oxford Avenue8,000,000
(KKKK) Resources for Human Development, Inc., acquisition and renovation of property for use as a central office facility5,000,000
(LLLL) Enterprise Heights, acquisition, renovation and new construction of a first-class, four-phase, 500,000-square-foot urban entrepreneurial campus for retail enterprises and an automotive technology training center in West Philadelphia1,000,000
(MMMM) Mercy Health System, design, construction, renovations and expansion to the Emergency Room at Mercy Nazareth Hospital4,500,000
(NNNN) Acquisition, rehabilitation and renovations for the Fabric Workshop and Museum relocation project4,500,000
(OOOO) Philadelphia Housing Authority, acquisition and development associated with the Croydon Development Project, west of University City in West Philadelphia6,000,000
(PPPP) Philadelphia Housing Authority, demolition and development associated with the Liddonfield Homes Development Project in the northeast section of Philadelphia12,850,000
(QQQQ) Philadelphia Housing Authority, Croydon Development Project, Phase II infrastructure development12,500,000
(RRRR) Monell Chemical Senses Center, renovation and expansion of research labs1,000,000
(SSSS) African American Museum, upgrade of exhibits and services10,000,000
(TTTT) Intercultural Family Services, upgrade of existing facilities2,000,000
(UUUU) Major structural renovations to The Franklin Institute Science Museum, including restoration and modernization of its historically significant 1934 building and repairs to the major expansion of the Benjamin Franklin National Memorial20,000,000
(VVVV) Acquisition, development and construction of facility to headquarter the Women's Opportunity Center1,000,000
(iii) Center City District Authority
(A) New sidewalks, benches and other pedestrian and landscape amenities for the entire length of the Benjamin Franklin Parkway between 16th Street and Eakins Oval3,000,000
(B) Streetscape and landscape enhancements for outer park areas in Logan Square1,000,000
(C) Streetscape improvements along the Benjamin Franklin Parkway from Logan Square to Eakins Oval to relocate curb lanes providing additional bicycle and pedestrian paths2,000,000
(D) Reconstruction of Eakins Oval to improve traffic flow, create safer pedestrian crossings to art museum and to the new Schuylkill River Park and provide new recreational and athletic facilities for adjacent communities20,000,000
(E) Improvements to Pennsylvania Avenue that will reduce traffic accidents, provide safer pedestrian crossings to recreational and cultural facilities and add new roadway lighting4,500,000
(52) Pike County
(i) Pike County Industrial and Commercial Development Authority
(A) Mountain Laurel Center for the Performing Arts Inc., Phase II facilities modification and development6,500,000
(ii) County Projects
(A) Grey Towers National Historic Landmark, construction of a new visitor/interpretive center, a state-of-the-art parking lot and entry drive4,000,000
(53) Potter County
(i) Potter County Redevelopment Authority
(A) Improvements to CARP park and municipal swimming pool, Coudersport Borough1,000,000
(B) Restoration/improvements to Water Channel, Coudersport Borough3,000,000
(C) Infrastructure improvement to municipal water system, Coudersport Borough1,600,000
(D) Acquisition/renovations/construction to blighted building for public library/community center, Coudersport Borough1,500,000
(E) Restoration and rehabilitation of historic district/downtown streetscape, Coudersport Borough1,200,000
(F) Infrastructure improvements, Galeton Borough2,400,000
(G) Streetscape improvements to Main Street/Union Street, accessway to Center Town Park, Galeton Borough1,200,000
(H) Expand elderly housing complex, site preparation and development, Coudersport Borough1,000,000
(I) Coudersport Industrial Park, site cleanup, Phase I study, land development and infrastructure improvements1,500,000
(J) Coudersport Industrial Park, construction and site development for small businesses expansion/incubator facility1,400,000
(54) Schuylkill County
(i) County Projects
(A) Million-dollar redevelopment project that consists of acquisition, demolition and redevelopment of blighted properties100,000
(B) Joe Zerbey Airport, for the development of several hundred acres of open space surrounding the airport3,000,000
(C) Schuylkill County Municipal Authority, infrastructure improvements to a 300-acre industrial site located in Ryan Township3,000,000
(ii) Schuylkill County Industrial Development Authority, Tremont Township
(A) Development of a 30-acre Keystone Opportunity Zone and construction of a business park500,000
(B) Development of a 280-acre Keystone Opportunity Zone3,000,000
(C) Aquatic Ecosystem Restoration project at Sweet Arrow Lake532,000
(D) Renovations and construction of the former Tremont Elementary School Building500,000
(E) Renovations and redevelopment of the Mattern500,000
(F) Building acquisition and renovation of vacant properties in the City of Pottsville2,400,000
(iii) City of Pottsville
(A) Preparation and construction of the Union Station site in downtown Pottsville4,000,000
(B) Yuengling Visitors Center, for building acquisition and renovation of vacant properties for creation and retention of administrative, manufacturing and tourism-related jobs2,400,000
(iv) Rush Township
(A) Tidewood East Industrial Park, infrastructure1,000,000
(B) Expansion of Air Products manufacturing facility, including the acquisition of capital equipment1,200,000
(v) Mahanoy City Borough
(A) Construction, renovation and rehabilitation associated with the development of the Mahanoy City Community Learning Technology and Education Center5,000,000
(55) Snyder County
(i) Susquehanna Industrial Development Corporation
(A) Development of an industrial park including land acquisition1,200,000
(56) Somerset County
(i) Windber Borough
(A) Construction and upgrade of laboratory infrastructure to meet increased demand for the diagnosis, prognosis and predictive therapeutic interventions for cancer patients3,000,000
(ii) Conemaugh Valley Conservancy
(A) Construction and infrastructure of the Stoneycreek Development Initiative1,800,000
(iii) Paint Township
(A) The Windber Area KOZ, infrastructure improvement and remediation for industrial/business park250,000
(iv) Somerset County General Authority
(A) Quemahoning water pipeline project, including the Townships of Conemaugh, Jenners, Lincoln and Somerset and the Boroughs of Boswell and Somerset, infrastructure development for the Somerset Industrial Park, Quemahoning Industrial Park and the NorthStar Business Park7,500,000
(57) Sullivan County
(i) County Projects
(A) Renovations to buildings and grounds of Sullivan County Fairgrounds2,000,000
(B) Renovation of the Mattern Building located in Cherry Township1,500,000
(C) Site acquisition and development for a multitenant industrial building1,000,000
(D) Redevelopment of historic downtown Eagles Mere to include property acquisition, renovation of existing properties, construction and site development2,000,000
(58) Susquehanna County
(i) Montrose Borough
(A) Endless Mountains Health Systems, construction of clinic and inpatient care units, including the installation of necessary equipment6,000,000
(59) Tioga County
(i) Borough of Wellsboro
(A) Design and construction of a new performing arts facility. This is part of a million-dollar project.600,000
(ii) Tioga County Development Corporation
(A) Development and construction of an industrial park in Tioga County, including land acquisition2,000,000
(B) Development of a countywide technical training center to assist employers in certification training1,200,000
(C) Renovation and restoration of the Tioga County Jail and sheriff residence to its original interior design and the development of additional offices and meeting rooms for community and nonprofit organizations1,200,000
(D) Development of the Mill Creek site located in Tioga Township into a multiuse environmental/recreational facility1,000,000
(60) Union County
(i) SEDA Council of Governments (SEDA-COG), Union Township
(A) For land acquisition, facility construction and site development for the proposed Susquehanna River Museum and Visitor Center1,300,000
(ii) County Projects
(A) Evangelical Community Hospital, construction of an expanded radiological department6,000,000
(B) Site improvements to Great Stream Commons Industrial Park750,000
(C) Construction or renovation of a building for an innovation center3,000,000
(61) Venango County
(i) County Projects
(A) Route 62 Corridor Enterprise Development Project2,000,000
(B) Renovation and redevelopment of the Franklin and Oil City Hospitals for reuse as a health care technology and training facility2,000,000
(C) Two Mile Run County Park, construction of an environmental center, amphitheater and overnight accommodations2,000,000
(62) Warren County
(i) Warren County Chamber of Business and Industry
(A) Design, planning and construction of an Industrial Development Center1,000,000
(ii) Brokenstraw Township
(A) National Forge Industrial and Office Park, land acquisition and infrastructure development500,000
(iii) City of Warren
(A) Construction of parking garage600,000
(iv) Warren County Industrial Development Authority
(A) Acquisition of a CT scanner for Warren General Hospital1,500,000
(v) County Projects
(A) Design and construction of a museum-aquarium facility8,000,000
(63) Washington County
(i) California Borough
(A) Construction of a 30,000-square-foot community recreation/wellness center2,000,000
(ii) Canonsburg Borough
(A) Construction of a new library building3,000,000
(iii) North Strabane Township
(A) Construction of a new emergency care department at the Canonsburg General Hospital as part of the regional trauma care network3,000,000
(iv) Carroll Township
(A) Construction expansion of the Mon Valley YMCA - community recreational facility1,000,000
(B) Mon Valley Hospital, expansion and development of emergency medical facility2,000,000
(v) Redevelopment Authority of Washington County
(A) Construction of a 25,000-square-foot industrial building at the California Technology Park767,000
(vi) County Projects
(A) Mel Blount Youth Home of Pennsylvania Infrastructure, site preparation and construction of new buildings, including a farm equipment building, youth equestrian building and a multipurpose recreation and physical education building5,798,000
(B) Panhandle Trail, rehabilitation and reconstruction of trail surface, adjoining easements and bridge spans comprising the Panhandle Trail system in Washington County2,000,000
(C) Montour Trail, rehabilitation and reconstruction of trail surface, adjoining easements and bridge spans comprising the Montour Trail system in Washington County2,000,000
(D) Meadowcraft Museum of Rural Life, preservation, renovations and construction to Prehistoric Archeological Site4,500,000
(E) Western Center, for the restoration of the administration building as an educational center and public use facility, including infrastructure improvements6,000,000
(F) Sovereign and permanent burial site museum for ancestral remains2,500,000
(G) Centerville Clinic, improvements to radiology services facility in Washington and Greene Counties1,000,000
(H) Building acquisition for Transportation Authority1,000,000
(vii) Peters Township
(A) Land acquisition and construction related to Peters Township parks expansions and improvements1,100,000
(viii) Cecil Township
(A) Western Center Redevelopment5,000,000
(ix) North Franklin Township
(A) Construction, site development, rehabilitation and infrastructure improvements for Falconi Field, Washington Crown Place and an athletic campus, including parking facilities1,000,000
(x) City of Washington
(A) Washington and Jefferson College, development of a multiuse economic development facility in the downtown Washington area4,000,000
(B) Crossroads Project, construction of parking garage14,500,000
(C) Washington and Jefferson College, rehabilitation and repairs of buildings1,000,000
(D) Land acquisition and construction of the Washington County Historical Society History and Education Center for a mixed-use facility1,500,000
(E) Restoration and infrastructure improvements to the Citizens Library1,000,000
(F) Construction of a multiuse recreational facility, estimated total project cost of $1,200,000250,000
(G) Acquisition, construction and infrastructure development of an abandoned industrial site for the Washington Industrial Park Project700,000
(H) Construction, restoration and infrastructure improvements to the South Main Street gateway900,000
(I) Property acquisition, rehabilitation, restoration and infrastructure improvements to the former Pennsylvania Station on South Main Street for a mixed-use facility865,000
(xi) Bentleyville Borough
(A) Municipal building complex, construction, site acquisition and development1,000,000
(xii) Canton Township
(A) Jessop Exit revitalization project, property acquisition, infrastructure and rehabilitation/restoration14,000,000
(xiii) Chartiers Township
(A) Community center and recreational facility, new construction1,500,000
(B) Pennsylvania Trolley Museum, for the development of the museum display area and infrastructure improvements2,000,000
(C) Washington County Agricultural Education Center850,000
(xiv) Fallowfield Township
(A) MIDA - Alta Vista Business Park, infrastructure and site development2,000,000
(xv) South Strabane Township
(A) Property acquisition, site preparation and construction of a commercial/retail development5,000,000
(64) Wayne County
(i) Sterling Township
(A) Property acquisition, construction, site development and infrastructure improvements for the Wayne County Business Park2,500,000
(65) Westmoreland County
(i) County Projects
(A) Purchase and adaptive use of structures for recreation and environmental education for the Westmoreland County Conservation District1,000,000
(B) Rehabilitation and restoration of Palace Theatre and Harrison Avenue4,000,000
(C) Westmoreland County Food Bank facilities expansion and renovation2,000,000
(D) Development of historic Hanna's Town as a heritage tourism attraction2,000,000
(E) Acquisition and renovation of the old Alcoa building for use as offices and housing of the Alcoa Museum2,500,000
(F) Monessen Riverfront Industrial Park, Phase III2,000,000
(G) Renovation and refurbishment of the Fort Ligonier Museum800,000
(H) Saint Vincent College, Fred M. Rogers Center for Early Learning and Children's Media, development of an early learning center for educational, demonstration and training purposes6,000,000
(I) Land acquisition, construction and renovation for Seton College Theater Arts Building5,000,000
(J) Latrobe Area Hospital, for construction of Emergency Department with capabilities to deal with biological, chemical and nuclear threats2,000,000
(ii) City of Monessen
(A) Acquisition, construction and rehabilitation of the Monessen Riverfront located within a Keystone Opportunity Zone5,000,000
(B) Southwest Pennsylvania Human Services Building renovation1,000,000
(iii) Allegheny Township
(A) Construction and infrastructure development for the River Forest Development Project600,000
(iv) Arnold
(A) Arnold Industrial Redevelopment Project, acquisition, construction and rehabilitation of the former American Gobain glass manufacturing plant3,000,000
(B) Acquisition and site development of the former Arnold Glass Plant for light industrial and economic development1,000,000
(C) Property acquisition, rehabilitation and site development as part of the Arnold 5th Avenue Redevelopment Project1,000,000
(v) East Huntingdon Township
(A) Westmoreland Technology Park II - Commerce Center, construction of a 50,000-square-foot flex-space facility2,000,000
(B) Westmoreland Distribution Park - Phase II, improvements and development3,400,000
(vi) Greensburg
(A) Renovation and expansion of the Westmoreland Museum of American Art2,500,000
(B) Land acquisition, site development and construction for St. Clair Park, the Coshey Building and other improvements1,100,000
(C) Land acquisition, construction and renovation for Seton Hill University Theatre Arts Building5,000,000
(vii) Hempfield Township
(A) Construction of the Westmoreland County Center for Economic Development1,000,000
(viii) Jeannette
(A) Acquisition and rehabilitation of property as part of the Jeannette Downtown Redevelopment Project2,000,000
(ix) New Kensington
(A) Property acquisition, rehabilitation and infrastructure for the creation of the Alle-Kiski Aluminum Heritage Museum2,000,000
(B) Property acquisition and rehabilitation of blighted area on 5th Avenue, light industrial site, for economic development1,000,000
(C) Acquisition, rehabilitation and retrofit former industrial site into a mixed-use municipal center, including the Alcoa Aluminum Heritage Museum2,500,000
(x) South Greensburg Borough
(A) Rehabilitation and infrastructure improvements to enhance the business district of South Greensburg1,500,000
(xi) Trafford Borough
(A) Property acquisition, construction, rehabilitation and infrastructure improvements as part of the Trafford Downtown Redevelopment Project1,500,000
(xii) Upper Burrell Township
(A) Property acquisition and rehabilitation of brownfield, formerly the Alcoa Laboratory1,500,000
(xiii) Murrysville Economic and Community Development Corporation
(A) Construction and development of the Murrysville Streetscape Project1,500,000
(xiv) Unity Township
(A) Site preparation, facilities and infrastructure of the National Center for Defense Manufacturing and Machining5,000,000
(xv) Murrysville
(A) Murrysville Streetscape Project1,400,000
(xvi) Latrobe
(A) Relocate and rebuild the Emergency Department at Latrobe Area Hospital2,000,000
(66) Wyoming County (Reserved)
(67) York County
(i) City of York
(A) Acquisition and historical rehabilitation of the Dallmeyer Project into commercial office space, a brownfield site within a Keystone Opportunity Zone as part of the Boundary Avenue Project5,000,000
(B) Acquisition and rehabilitation of a brownfield site for a mixed-use commercial/office facility as part of the Northwest York Triangle Project8,000,000
(C) Restoration and infrastructure development and improvements as part of the Codorus Creek Ecosystem Restoration Project2,000,000
(D) Construction of multipurpose stadium12,000,000
(E) York City Education Foundation, development of multiple neighborhood centers6,000,000
(F) Construction of a multitenant building, including a child-care facility located at 400 Stillmeadow Lane1,420,000
(G) Renovation and expansion of the Martin Library250,000
(ii) County projects
(A) York County Technology Park, redevelopment of approximately 220 acres of blighted industrial property for reuse as an industrial park25,000,000
(iii) Springettsbury Township
(A) Camp Security, acquisition and public education/museum development of the Camp Security site2,500,000
(iv) Hellam Township
(A) Horn Farm Center for Agricultural Education, renovation and construction of farm buildings and orientation center facilities500,000
(v) York County Industrial Development Authority
(A) P. H. Glatfelter Company, improvement, modernization and rehabilitation of Spring Grove Facility11,000,000
(68) Multiple Counties
(i) The Community Action Association of Pennsylvania
(A) Infrastructure development improvements and acquisitions, including necessary technology upgrades to Community Action Agencies located in single and multiple counties within this Commonwealth42,000,000

Section 7. Itemization of flood control projects.

Additional capital projects in the category of flood control projects to be constructed by the Department of Environmental Protection, its successors or assigns and to be financed by the incurring of debt are hereby itemized, together with their respective estimated costs, as follows:

ProjectTotal Project Allocation
(1) Department of Environmental Protection
(i) Indiana County, flood control project
(A) Clymer Borough for completion of the Two Lick Creek Restoration Project, a Federal flood control project1,000,000
(ii) Luzerne County
(A) Plymouth Borough, flood mitigation as part of the Coal Creek Flood Control Project1,000,000
(B) West Wyoming Borough, Shoemaker Avenue, Stites Street flood control project184,000

(Base Project Allocation - $150,000)

(Engineering - $19,000)

(Design and Contingencies - $15,000)

(iii) Northumberland County, flood control project
(A) Flood mitigation on Shamokin Creek and Butternut Creek in Mount Carmel Borough and Mount Carmel Township15,000,000
(iv) Somerset County
(A) Continuation of Somerset Borough's Federal Flood Protection Project in the area of Coxes1,200,000
(v) (Reserved)
(vi) Northampton County
(A) Williams Township, flood control improvements to Raubsville Creek within a federally designated flood control district200,000
(vii) Lancaster County
(A) Lititz Borough, Lititz Run Watershed Storm Water Control Facility950,000
(B) Lititz Borough, storm water improvements, Lititz Springs Park500,000
(viii) Lycoming County
(A) Lower Lycoming Creek flood mitigation3,100,000
(B) South Williamsport Borough, repair and reconstruction of the Hill Street, Ecks Run and Main Street pumping stations, including interior and exterior building improvements and the repair or replacement of pumps and associated equipment1,000,000
(ix) Washington County
(A) City of Washington, for stream dredging and flood control development on the Catfish Creek drainage area1,000,000
(B) Canton Township, for stream dredging and flood control development on the Catfish Creek drainage area1,000,000
(C) North Strabane and Peters Township, Canonsburg Lake, dredging and repair2,000,000
(x) Chester County
(A) Borough of Downingtown, Downingtown Flood Protection Project4,800,000

(Base Project Allocation - $4,000,000)

(Design and Contingencies - $800,000)

(B) Borough of Downingtown, Downingtown Flood Protection Diversion Channel Project5,400,000

(Base Project Allocation - $4,500,000)

(Design and Contingencies - $900,000)

(C) Glade Run flood protection project3,000,000

(Base Project Allocation - $3,000,000)

(D) Wilmore flood protection project810,000

(Base Project Allocation - $810,000)

(xi) Monroe County
(A) Additional funds for the construction of Brady's Lake800,000

Section 8. Itemization of Keystone Recreation, Park and Conservation Fund projects.

Projects in the category of public improvement projects to be constructed by the Department of Conservation and Natural Resources, its successors or assigns and to be financed by current revenues of the Keystone Recreation, Park and Conservation Fund are hereby itemized, together with their respective estimated costs, as follows:

ProjectTotal Project Allocation
(1) Department of Conservation and Natural Resources
(i) Caledonia State Park
(A) Replace comfort station240,000

(Base Project Allocation - $240,000)

(ii) Cook Forest State Park
(A) Park renovations and improvements1,142,000

(Base Project Allocation - $1,142,000)

(B) Rehabilitate water system700,000

(Base Project Allocation - $700,000)

(iii) Cowans Gap State Park
(A) Replace bridge on main park road over South Branch Little Aughwick Creek190,000

(Base Project Allocation - $190,000)

(iv) Delaware Canal State Park
(A) Replacement of Bridge No.50-1469225,000

(Base Project Allocation - $225,000)

(B) Replacement of Bridge No.50-1668250,000

(Base Project allocation - $250,000)

(C) Replacement of Bridge No.50-2470300,000

(Base Project Allocation - $300,000)

(v) Evansburg State Park
(A) Install sewer/lift station300,000

(Base Project Allocation - $300,000)

(B) Replace dam300,000

(Base Project Allocation - $300,000)

(vi) Forbes State Forest
(A) Expand district office1,000,000
(B) Rehabilitate three bridges374,000
(vii) Forest District 2
(A) Rehabilitate Bear Valley foreman headquarters510,000

(Base Project Allocation - $510,000)

(viii) Forest District 5
(A) Rehabilitate Stone Creek Road500,000

(Base Project Allocation - $500,000)

(ix) Forest District 8
(A) District office addition850,000

(Base Project Allocation - $850,000)

(x) Forest District 19
(A) Replace Egypt Meadows Dam350,000

(Base Project Allocation - $350,000)

(xi) Frances Slocum State Park
(A) Rehabilitate sewage treatment plant300,000

(Base Project Allocation - $300,000)

(xii) Greenwood Furnace State Park
(A) Rehabilitate sewage treatment plant400,000

(Base Project Allocation - $400,000)

(xiii) Hickory Run State Park
(A) Repair bridge300,000

(Base Project Allocation - $300,000)

(B) Replacement of Bridge No.09-0503130,000

(Base Project Allocation - $130,000)

(xiv) Hyner Run State Park
(A) Replacement of Bridge No.10-0600240,000

(Base Project Allocation - $240,000)

(B) Replacement of Bridge No.10-0601140,000

(Base Project Allocation - $140,000)

(xv) Kettle Creek State Park
(A) Renovate restrooms750,000

(Base Project Allocation - $750,000)

(xvi) Laurel Hill State Park
(A) Replace bathhouse/concession and comfort stations1,350,000
(B) Rehabilitate bathhouses400,000

(Base Project Allocation - $400,000)

(C) Rehabilitate sewage treatment plant and lift stations600,000

(Base Project Allocation - $600,000)

(xvii) Little Pine State Park
(A) Construct road and remove debris500,000

(Base Project Allocation - $500,000)

(xviii) Marsh Creek State Park
(A) Rehabilitate swimming pool500,000
(B) Rehabilitate swimming pool filter250,000

(Base Project Allocation - $250,000)

(xix) Maurice K. Goddard State Park
(A) Rehabilitate marina building350,000
(B) Rehabilitate marina building500,000

(Base Project Allocation - $500,000)

(xx) Neshaminy State Park
(A) Waterway dredging and jetty repair300,000

(Base Project Allocation - $300,000)

(xxi) Norristown Farm Park
(A) Replacement of Bridge No.52-15041,500,000

(Base Project Allocation - $1,500,000)

(B) Replacement of Bridge No.52-1502700,000

(Base Project Allocation - $700,000)

(C) Replacement of Bridge No.52-1500625,000

(Base Project Allocation - $625,000)

(D) Replacement of Bridge No.52-1503125,000

(Base Project Allocation - $125,000)

(E) Replacement of Bridge No.52-1501500,000

(Base Project Allocation - $500,000)

(xxii) Ohiopyle State Park
(A) Rehabilitate Jonathan Run Culvert375,000

(Base Project Allocation - $375,000)

(B) Repair and paint Ferncliff High Bridge600,000

(Base Project Allocation - $600,000)

(C) Repair Ferncliff High Bridge224,000

(Base Project Allocation - $224,000)

(D) Rehabilitate Jonathan Run600,000
(E) Rehabilitate Middle Yough take-out concession800,000
(xxiii) Oil Creek State Park
(A) Construct train station restroom350,000
(B) Construct train station restroom parking500,000

(Base Project Allocation - $500,000)

(xxiv) Parker Dam State Park
(A) Replace campground restroom450,000

(Base Project Allocation - $450,000)

(xxv) Presque Isle State Park
(A) Rehabilitate park office500,000

(Base Project Allocation - $500,000)

(B) Rehabilitate roadways and parking lots3,300,000

(Base Project Allocation - $3,300,000)

(C) Replacement of Bridge No.20-11011,500,000

(Base Project Allocation - $1,500,000)

(D) Replacement of Bridge No.20-10001,500,000

(Base Project Allocation - $1,500,000)

(xxvi) Promised Land State Park
(A) Rehabilitate boat rental area500,000

(Base Project Allocation - $500,000)

(B) Rehabilitate lower lake dam400,000

(Base Project Allocation - $400,000)

(C) Replacement of Bridge No.14-08021,000,000

(Base Project Allocation - $1,000,000)

(xxvii) Pymatuning State Park
(A) Replace boat launch350,000
(B) Rehabilitate campground washhouses900,000
(C) Resurface Jamestown boat livery315,000
(D) Rehabilitate spillway1500,000

(Base Project Allocation - $1,500,000)

(xxviii) Raccoon Creek State Park
(A) Replace pit latrines550,000
(B) Repair group camp dam350,000
(C) Resurface and repave roads350,000
(D) Group camp repairs1,000,000

(Base Project Allocation - $1,000,000)

(E) Replacement of Bridge No.13-1200100,000

(Base Project Allocation - $100,000)

(F) Replacement of Bridge No.13-1201250,000

(Base Project Allocation - $250,000)

(G) Replacement of Bridge No.13-1203122,000

(Base Project Allocation - $122,000)

(xxix) Ralph Stover State Park
(A) Replace pit latrines500,000
(xxx) Ravensburg State Park
(A) Replace two chemical toilets350,000

(Base Project Allocation - $350,000)

(xxxi) Reeds Gap State Park
(A) Addition to park residence structure320,000

(Base Project Allocation - $320,000)

(xxxii) Ridley Creek State Park
(A) Replacement of Bridge No.27-1100140,000

(Base Project Allocation - $140,000)

(xxxiii) Ryerson Station State Park
(A) Rehabilitate sewage and water office250,000
(B) Rehabilitate campground350,000
(C) Water supply for campground, office complex and pool250,000
(xxxiv) Shawnee State Park
(A) Rehabilitate park buildings1,700,000

(Base Project Allocation - $1,700,000)

(xxxv) Shikellamy State Park
(A) Replace boat docks500,000

(Base Project Allocation - $500,000)

(xxxvi) Susquehannock State Park
(A) Renovate restrooms450,000

(Base Project Allocation - $450,000)

Section 9. Itemization of Environmental Stewardship Fund projects.

Projects in the category of public improvement projects to be constructed by the Department of Conservation and Natural Resources, its successors or assigns and to be financed by current revenues of the Environmental Stewardship Fund are hereby itemized, together with their respective estimated financial costs, as follows:

ProjectTotal Project Allocation
(1) Department of Conservation and Natural Resources
(i) Bald Eagle State Park
(A) Renovate restrooms to a flush system50,000
(ii) Bendigo State Park
(A) Replace latrine No. 3300,000
(B) Renovate restrooms to a flush system300,000
(C) Replace bathhouse with comfort station1,000,000

(Base Project Allocation - $1,000,000)

(iii) Chapman State Park
(A) Replace beach house and campground restrooms1,500,000

(Base Project Allocation - $1,500,000)

(iv) Clear Creek State Park
(A) Renovate restrooms2,000,000

(Base Project Allocation - $2,000,000)

(v) Codorus State Park
(A) Rehabilitate park office and visitors center850,000

(Base Project Allocation - $850,000)

(vi) Cook Forest State Park
(A) Repair park roadways1,500,000

(Base Project Allocation - $1,500,000)

(B) Rehabilitate park office and visitors center2,000,000

(Base Project Allocation - $2,000,000)

(C) Rehabilitate restrooms and roadways2,000,000

(Base Project Allocation - $2,000,000)

(vii) Evansburg State Park
(A) Resurface roadways335,000
(viii) Forest District 2
(A) Rehabilitate Bear Valley maintenance building500,000

(Base Project Allocation - $500,000)

(ix) Forest District 3
(A) Rehabilitate forest headquarters750,000

(Base Project Allocation - $750,000)

(x) Forest District 11
(A) Construct new district office2,000,000

(Base Project Allocation - $2,000,000)

(xi) Forest District 19
(A) Construct forest headquarters750,000

(Base Project Allocation - $750,000)

(xii) Forest District 20
(A) Improvements to Brush Valley tract1,000,000

(Base Project Allocation - $1,000,000)

(xiii) Gouldsboro State Park
(A) Replace bathhouse, comfort station and sewage system600,000
(xiv) Hickory Run State Park
(A) Replace office and visitors center1,500,000

(Base Project Allocation - $1,500,000)

(B) Rehabilitate comfort stations2,300,000

(Base Project Allocation - $2,300,000)

(xv) Keystone State Park
(A) Rehabilitate park office and roadways1,750,000

(Base Project Allocation - $1,750,000)

(B) Infrastructure rehabilitation1,800,000

(Base Project Allocation - $1,800,000)

(xvi) Kooser State Park
(A) Rehabilitate roads and bridges1,000,000

(Base Project Allocation - $1,000,000)

(xvii) Lackawanna State Park
(A) Rehabilitate pool complex and day use area1,250,000
(xviii) Laurel Hill State Park
(A) Rehabilitate beach bathhouses1,500,000

(Base Project Allocation - $1,500,000)

(xix) Leonard Harrison State Park
(A) Rehabilitate restrooms and maintenance building1,000,000
(B) Rehabilitate comfort station1,500,000

(Base Project Allocation - $1,500,000)

(xx) Lyman Run State Park
(A) Replace washhouses1,000,000

(Base Project Allocation - $1,000,000)

(B) Replace Daggot Campground washhouse1,000,000

(Base Project Allocation - $1,000,000)

(xxi) Moraine State Park
(A) Rehabilitate sewage treatment plant1,500,000

(Base Project Allocation - $1,500,000)

(xxii) Nockamixon State Park
(A) Road paving improvements500,000
(xxiii) Parker Dam State Park
(A) Construct 75 campsites and washhouse1,500,000
(B) Rehabilitate campground restrooms300,000
(xxiv) Pine Grove Furnace State Park
(A) Rehabilitate bathhouse and comfort station1,990,000

(Base Project Allocation - $1,990,000)

(xxv) Poe Valley State Park
(A) Expand existing spillway2,000,000
(B) Rehabilitate sewage treatment plant500,000

(Base Project Allocation - $500,000)

(C) Rehabilitate comfort station1,500,000

(Base Project Allocation - $1,500,000)

(xxvi) Presque Isle State Park
(A) Rehabilitate roadways3,300,000

(Base Project Allocation - $3,300,000)

(xxvii) Prince Gallitzin State Park
(A) Replace visitors center400,000

(Base Project Allocation - $400,000)

(xxviii) Promised Land State Park
(A) Rehabilitate dump station and sewer office300,000
(B) Replace four washhouses1,100,000
(C) Rehabilitate boat rental area500,000
(D) Repair lower lake dam300,000
(E) Rehabilitate Pick Point/Deer2,600,000
(Base Project Allocation - $2,600,000)
(xxix) Pymatuning State Park
(A) Rehabilitate roadways, phase 21,850,000
(Base Project Allocation - $1,850,000)
(B) Rehabilitate water and sewage plant2,200,000
(Base Project Allocation - $2,200,000)
(C) Rehabilitate roadways, phase 31,500,000
(Base Project Allocation - $1,500,000)
(xxx) Raccoon Creek State Park
(A) Rehabilitate cabin and group camp roads1,000,000
(Base Project Allocation - $1,000,000)
(xxxi) Reeds Gap State Park
(A) Replace campground shower house500,000
(Base Project Allocation - $500,000)
(xxxii) Ricketts Glen State Park
(A) Resurface and repave roads1,000,000
(B) Replace pit latrine - Route 118400,000
(C) Repair sewer treatment plant/water treatment plant430,000
(D) Rehabilitate bathhouse and comfort station2,050,000
(E) Rehabilitate park2,500,000
(Base Project Allocation - $2,500,000)
(xxxiii) Ridley Creek State Park
(A) Resurface and repave parking areas300,000
(xxxiv) Sinnemahoning State Park
(A) Repair dam and existing spillway300,000
(B) Repair concrete spillway1,000,000
(Base Project Allocation - $1,000,000)
(xxxv) Sizerville State Park
(A) Rehabilitate bathhouse and comfort station1,500,000
(Base Project Allocation - $1,500,000)
(xxxvi) Tiadaghton State Forest
(A) Rehabilitate equipment storage building300,000
(xxxvii) Tyler State Park
(A) Extension of water and electric service to the west side of the park, including 900 acres2,000,000
(xxxviii) Point State Park
(A) Phase I of park capital development, including design, engineering and construction for riverfront trail and park connections to the Eliza Furnace Trail and to the David L. Lawrence Convention Center8,000,000
(B) Rehabilitate the reflecting pool350,000
(C) Rehabilitate restrooms, including ADA250,000
(xxxix) Fayette County
(A) Recreational Trail Development Project, development of the Sheepskin Trail and other Yough Trail connector trails1,500,000

Section 10. Itemization of Pennsylvania Fish and Boat Commission capital projects.

The individual capital projects in the category of public improvement projects to be acquired or developed by the Pennsylvania Fish and Boat Commission and to be financed by the incurring of debt or by the current revenues of the Fish Fund and the Boat Fund pursuant to executive authorizations are hereby itemized, together with their respective estimated costs, as follows:

ProjectTotal Project Allocation
(1) Pennsylvania Fish and Boat Commission
(i) Beaver County
(A) Hereford Manor Lakes, design and construction of a new dam or dams or rehabilitation of existing dams at Upper and Lower Hereford Manor Lakes11,000,000

(Base Project Allocation - $9,500,000)

(Design and Contingencies - $1,500,000)

(ii) Centre County
(A) Colyer Lake, rehabilitate dam and lake1,200,000

(Base Project Allocation - $1,000,000)

(Design and Contingencies - $200,000)

(iii) Cumberland County
(A) Huntsdale Fish Culture Station, rehabilitate and reconstruct fish-rearing facilities3,000,000

(Base Project Allocation - $2,250,000)

(Design and Contingencies - $750,000)

(iv) Elk County
(A) Blue Valley Demonstration Fish Culture Station, additional funds1,200,000
(v) Union County
(A) Gregg Township, land acquisition and construction of a public boat access and launch ramp100,000
(vi) Washington County
(A) Peters and North Strabane Townships, rehabilitation of Canonsburg Lake, including, but not limited to, rehabilitation of dam and spillway, erosion stabilization and mitigation and dredging and remediation of material from lake bottom17,500,000
(vii) Philadelphia County
(A) Frankford Arsenal and Tacony Access Properties, revitalization and improvements10,000,000
(viii) Carbon County
(A) Upgrade dam at Mauch Chunk Lake. This project shall be construed as a supplement to the project authorized in section 3(1)(iv)(A) of the Pennsylvania Fish and Boat Commission Capital Budget Act for 2002-2003675,000

(Base Project Allocation - $563,000)

(Design and Contingencies - $112,000)

Section 11. Itemization of Pennsylvania Game Commission capital projects.

The individual capital projects in the category of public improvement projects to be acquired by the Pennsylvania Game Commission and to be financed from current revenues of the Game Fund pursuant to executive authorizations are hereby itemized, together with their respective estimated costs, as follows:

ProjectTotal Project Allocation
(1) Pennsylvania Game Commission (Reserved)

Section 12. Itemization of General Fund current revenue projects.

The individual capital projects in the category of public improvement projects to be developed by the Department of General Services, its successors or assigns for the Department of Conservation and Natural Resources and to be financed from current revenues are hereby itemized, together with their respective itemized costs, as follows:

ProjectTotal Project Allocation
(1) Department of Conservation and Natural Resources
(i) Northampton County
(A) Linear Park and Urban Greenway, City of Bethlehem, acquisition of abandoned Norfolk Southern Railroad right-of-way from Hellertown/Bethlehem municipal line, west to former Union Station and development of new Linear Park and Urban Greenway2,000,000
(ii) Lackawanna County
(A) Blakely Borough, improvement of recreational facilities2,950,000

Section 13. Itemization of Motor License Fund current revenue projects.

The individual capital projects in the category of public improvement projects to be developed by the Department of General Services, its successors or assigns for the Department of Transportation and to be financed from current revenues of the Motor License Fund are hereby itemized, together with their respective itemized costs, as follows:

ProjectTotal Project Allocation
(1) Department of Transportation
(i) Engineering District 11-0, Allegheny County
(A) Construct an addition and renovate Engineering Office District 11-01,500,000
(ii) Highway Maintenance Facility, Washington County
(A) Construct storage facility1,000,000
(iii) Highway District Office No.11 Building, Allegheny County
(A) Construct a new second floor addition to the TMC building1,500,000
(Base Project Allocation - $1,500,000)
(iv) Salt storage facility, Beaver County
(A) Construct a new salt storage facility380,000
(Base Project Allocation - $380,000)
(v) Highway maintenance facility, Bucks County
(A) Construct or acquire a replacement maintenance facility2,750,000
(Base Project Allocation - $2,500,000)
(Design and Contingencies - $250,000)
(vi) Salt storage facility, Bucks County
(A) Construct a salt storage facility450,000
(Base Project Allocation - $450,000)
(vii) Salt storage facility, Carbon County
(A) Construct a salt storage facility450,000
(Base Project Allocation - $450,000)
(vii.1) Highway Maintenance Facility, Chester County
(A) Construction or acquisition of a replacement maintenance facility1,000,000
(Base Project Allocation - $1,000,000)
(viii) Salt storage facility, Clinton County
(A) Construct a salt storage facility380,000
(Base Project Allocation - $380,000)
(ix) Salt storage facility, Dauphin County
(A) Construct a salt storage facility380,000
(Base Project Allocation - $380,000)
(x) Salt storage facility, Lebanon County
(A) Construct a salt storage facility with composite materials650,000
(Base Project Allocation - $650,000)
(xi) Highway District No.5 Office, Lehigh County
(A) Renovate existing District No.5 office building2,750,000
(Base Project Allocation - $2,500,000)
(Design and Contingencies - $250,000)
(xii) Highway maintenance facility, Luzerne County
(A) Construct or acquire a replacement maintenance facility3,300,000
(Base Project Allocation - $3,000,000)
(Design and Contingencies - $300,000)
(xiii) Salt storage facility, Luzerne County
(A) Construct a salt storage facility450,000
(Base Project Allocation - $450,000)
(xiv) Highway maintenance facility, Washington County
(A) Construct or acquire a replacement maintenance facility3,750,000
(Base Project Allocation - $3,500,000)
(Design and Contingencies - $250,000)
(xv) Salt storage facility, Westmoreland County
(A) Construct a salt storage facility380,000
(Base Project Allocation - $380,000)

Section 14. Itemization of Manufacturing Fund current revenue projects.

The individual capital projects in the category of public improvement projects to be developed by the Department of General Services, its successors or assigns for the Department of Corrections and to be financed from current revenues of the Manufacturing Fund are hereby itemized, together with their respective itemized costs, as follows:

ProjectTotal Project Allocation
(1) Department of Corrections (Reserved)

Section 15. Itemization of State Stores Fund current revenue projects.

The individual capital projects in the category of public improvement projects to be developed by the Department of General Services, its successors or assigns for the Pennsylvania Liquor Control Board and to be financed from current revenues of the State Stores Fund are hereby itemized, together with their respective itemized costs, as follows:

ProjectTotal Project Allocation
(1) Pennsylvania Liquor Control Board (Reserved)

Section 16. Itemization of public highway projects.

Additional capital projects in the category of public highway projects to be constructed by the Department of Transportation, its successors or assigns and to be financed from current revenues of the Motor License Fund are hereby itemized, together with their respective estimated financial costs, as follows:

ProjectTotal Project Allocation
(1) Allegheny County
(i) I-79
(A) For the construction of missing ramps at the I-79/I-279 and SR 60 Interchange3,500,000
(ii) SR 228
(A) Construction of an access road to SR 228 in Cranberry Township3,000,000
(iii) SR 19
(A) Construction of connection between Freshcorn Road and SR 192,340,000
(iv) Route 19 to Bury Road
(A) For utilities and road improvements located in Pine Township and McCandless7,000,000
(v) Eliza Furnace Trail and Smithfield Street Bridge
(A) Design, engineering and construction of a pedestrian switchback ramp connecting the Eliza Furnace Trail and the Smithfield Street bridge3,000,000
(vi) West End Bridge
(A) Decorative and ornamental lighting of the West End Bridge1,000,000
(vii) Cherrington Parkway
(A) Construction of Cherrington Parkway Extension located in Moon Township4,000,000

(Base Project Allocation - $3,000,000)

(Design and Contingencies - $1,000,000)

(viii) PA 8 at SR 4070 - Wildwood Road
(A) Intersection improvements, including the expansion and construction of turning lanes and other related improvements300,000
(2) Berks County
(i) SR 0061
(A) Reconstruction, safety improvements and relocation of Mountain Road on SR 0061 in the vicinity of I-78 and associated intersections in the Hamburg area and Tilden Township5,125,000
(Base Project Allocation - $4,425,000)
(Design and Contingencies - $700,000)
(3) Blair County
(i) 17th Street and Frankstown Road
(A) Safety and traffic improvements at various intersections on 17th Street and Frankstown Road in Logan Township680,000
(Base Project Allocation - $600,000)
(Land Allocation - $20,000)
(Design and Contingencies - $60,000)
(3.1) Bucks County
(i) Bristol Township
(A) Improvements to SR 0013 and removal of S curve1,200,000
(Base Project Allocation - $1,000,000)
(Design and Contingencies - $200,000)
(4) Butler County
(i) Cranberry Township
(A) Construction of improvements to I-79 and SR 022815,700,000

(Base Project Allocation - $13,345,000)

(Design and Contingencies - $2,355,000)

(5) Carbon County
(i) SR 54
(A) Reconstruction and realignment of SR 54 in the Borough of Nesquehoning1,760,000
(ii) SR 209
(A) Intersection improvement and signalization at SR 3012, Jim Thorpe Borough1,500,000
(Base Project Allocation - $1,400,000)
(Land Allocation - $40,000)
(Design and Contingencies - $60,000)
(B) Truck pull-off prior to descending grade into Jim Thorpe Borough, with 10-foot-wide shoulder for 300 feet in advance of pull-off450,000
(6) Clarion County
(i) Monroe Township
(A) Widening of and improvements to SR 0068 between I-80 and Commerce Road825,000
(Base Project Allocation - $750,000)
(Design and Contingencies - $75,000)
(7) Cumberland County
(i) Borough of Mechanicsburg
(A) Signalization improvements to intersections along SR 0641, SR 2104, SR 0114, SR 0013 and SR 10111,500,000
(Base Project Allocation - $1,250,000)
(Design and Contingencies - $250,000)
(8) Dauphin County
(i) Lower Paxton Township
(A) Improvements to the intersection of SR 0039 and SR 3019 and extension of Blue Mountain Parkway3,850,000
(Base Project Allocation - $3,000,000)
(Design and Contingencies - $850,000)
(9) Delaware County
(i) Noise wall demonstration project, Nether Providence and Ridley Township
(A) Construct a noise wall along I-4766,000,000
(Base Project Allocation - $3,500,000)
(Land Allocation - $2,000,000)
(Design and Contingencies - $500,000)
(10) Huntingdon County
(i) Smithfield Township
(A) Construction of improvements to U.S. Route 22 and SR 00264,475,000
(Base Project Allocation - $3,800,000)
(Design and Contingencies - $675,000)
(11) Lancaster County
(i) Providence Township
(A) Improvements to the intersection of SR 0272 and Truce Road located north of Buck155,000
(Base Project Allocation - $125,000)
(Design and Contingencies - $30,000)
(12) Lebanon County
(i) SR 422
(A) Widen and reconstruct associated highways at US 422 and Lingle Avenue3,000,000
(Base Project Allocation - $3,000,000)
(ii) South Londonderry Township
(A) Construction of Campbelltown Connector between Lingle Avenue (SR 3017), Palmyra Road (SR 3019) and Forge Road (SR 0117)3,000,000
(Base Project Allocation - $2,200,000)
(Land Allocation - $300,000)
(Design and Contingencies - $500,000)
(13) Lehigh County
(i) Upper Saucon Township
(A) Improvements to the interchange of Route 309 and Center Valley Parkway and Saucon Valley Road17,500,000

(Base Project Allocation - $14,600,000)

(Design and Contingencies - $2,900,000)

(14) Lycoming County
(i) City of Williamsport
(A) Construction of improvements to the interchange of I-180, SR 0220 and U.S. Route 1510,000,000

(Base Project Allocation - $8,000,000)

(Design and Contingencies - $2,000,000)

(15) Monroe County
(i) I-80
(A) Transportation infrastructure improvements on I-80 at exits 298 and 299 and SR 715 and SR 611 in the Tannersville/Scotrun area9,000,000
(16) Montgomery County
(i) County Projects
(A) Reconstruction of Norristown Road from Horsham to Welsh85,000
(B) Improvements to Route 309 exit ramps onto Norristown Road5,000,000
(C) Bethlehem Pike improvements at Town Center2,800,000
(D) Maple Glen Triangle intersection improvements575,000
(E) Easton Road signal improvements, North Maple to Cheltenham Road170,000
(F) Upper Dublin improvements, left turning lane on Fort Washington Avenue at Susquehanna Road105,000
(G) Welsh Road improvements including signal upgrades1,500,000
(H) Sound barrier construction for Route 309 (Bethlehem Pike) in Upper Dublin1,000,000
(17) Northampton County
(i) SR 248
(A) Reconstruction, intersection upgrades, signalization and safety improvements on SR 248 in the vicinity of SR 22 and the associated intersections in the Palmer Township and Wilson area3,000,000
(Base Project Allocation - $2,300,000)
(Design and Contingencies - $700,000)
(18) Philadelphia County
(i) I-95
(A) Construct a noise wall along I-95 from Jackson Street to McKean Street18,500,000

(Base Project Allocation - $18,000,000)

(Design and Contingencies - $500,000)

(ii) Vine Expressway Corridor
(A) Safety improvements2,050,000
(iii) Vine Expressway Cover
(A) Logan Circle3,600,000
(iv) 26th Street
(A) Extension and improvements1,500,000
(v) Girard Avenue
(A) Street improvements, 19th to 32nd Streets5,000,000
(19) Schuylkill County
(i) City of Pottsville
(A) Widening of SR 0061 and improvements to intersections with Union Street and Norwegian Street3,000,000
(Base Project Allocation - $2,500,000)
(Design and Contingencies - $500,000)
(20) Westmoreland County
(i) North Huntingdon Township
(A) Construction of improvements to U.S. 30 and SR 30206,680,000

(Base Project Allocation - $4,680,000)

(Land Allocation - $1,000,000)

(Design and Contingencies - $1,000,000)

(21) York County
(i) County Projects
(A) ((A) repealed Nov. 23, 2004, P.L.1155, No.149)

Section 16.1. State forestry bridge projects itemized.

Projects in the category of State forestry bridge projects to be constructed by the Department of Conservation and Natural Resources, its successors or assigns and to be financed by oil company franchise tax revenues pursuant to 75 Pa.C.S. § 9502(a)(2)(iv) (relating to imposition of tax) are hereby itemized, together with their respective estimated costs, as follows:

ProjectTotal Project Allocation
(1) Adams County
(i) Forest District 1
(A) Replacement of Bridge No.01-0005250,000
(2) Cameron County
(i) Five Mile Road Bridge
(A) Replacement of Bridge No.13-0014 over North Creek300,000
(ii) Forest District 13
(A) Replacement of Bridge No.13-9024150,000
(3) Centre County
(i) Forest District 5
(A) Replacement of Bridge No.05-0004100,000
(B) Replacement of Bridge No.05-0003100,000
(C) Replacement of Bridge No.05-0005150,000
(ii) Forest District 7
(A) Replacement of Bridge No.07-0008200,000
(4) Clearfield County
(i) Forest District 9
(A) Replacement of Bridge No.09-0020165,000
(B) Replacement of Bridge No.09-0015100,000
(5) Clinton County
(i) Left Branch Hyner Run Road Bridge
(A) Replacement of Bridge No.10-0019 over left branch Hyner Run209,000
(ii) Mill Run Road
(A) Replacement of Culvert No.10-0046 over Mill Run150,000
(iii) Fork Hill Road
(A) Replacement of Culvert No.10-0050 over right branch Young Woman's Creek150,000
(iv) Forest District 10
(A) Replacement of Bridge No.10-0050150,000
(B) Replacement of Bridge No.10-9002300,000
(C) Replacement of Bridge No.10-9001150,000
(D) Replacement of Bridge No.10-0051168,000
(E) Replacement of Culvert No.10-0046150,000
(6) Cumberland County
(i) Forest District 1
(A) Replacement of Bridge No.01-0006150,000
(B) Replacement of Bridge No.01-0023138,000
(C) Replacement of Bridge No.01-0013120,000
(7) Dauphin County
(i) Forest District 18
(A) Replacement of Bridge No.18-9004100,000
(B) Replacement of Bridge No.18-0002300,000
(8) Elk County
(i) Forest District 13
(A) Replacement of Bridge No.13-0032110,000
(9) Franklin County
(i) Staley Road Bridge
(A) Replacement of Bridge No.1-0020 over Trucker Run300,000
(ii) Second Narrows Road Bridge
(A) Replacement of Bridge No.3-0001 over Conococheague Creek300,000
(iii) Forest District 1
(A) Replacement of Bridge No.01-9000120,000
(10) Huntingdon County
(i) Forest District 5
(A) Replacement of Bridge No.05-0027100,000
(11) Lycoming County
(i) Little Boyer Road
(A) Replacement of Culvert No.12-9020 over Trout Run170,000
(ii) Manor Fork Road
(A) Replacement of Culvert No.12-9021 over Manor Fork Creek110,000
(iii) Slate Run Road
(A) Replacement of Culvert No.12-9023 over unnamed tributary of Slate Run150,000
(iv) Hillsgrove Road
(A) Replacement of Culvert No.12-9018 over unnamed tributary150,000
(v) East Run Road Bridge
(A) Replacement of Bridge No.12-0029 over unnamed tributary300,000
(vi) Forest District 12
(A) Replacement of Bridge No.12-0013150,000
(B) Replacement of Bridge No.12-0023120,000
(12) Mifflin County
(i) Black Gap Road Bridge
(A) Replacement of Bridge No.7-0044 over White Deer Creek300,000
(ii) Forest District 7
(A) Replacement of Bridge No.07-0003125,000
(13) Perry County
(i) Forest District 3
(A) Replacement of Bridge No.03-0020100,000
(B) Replacement of Bridge No.03-0004300,000
(C) Replacement of Bridge No.03-0014100,000
(14) Pike County
(i) Forest District 19
(A) Replacement of Bridge No.19-0002115,000
(15) Potter County
(i) Benson Road
(A) Replacement of Culvert No.12-9022 and roadside slide over tributary of Benson Run125,000
(ii) Francis Road
(A) Replacement of Culvert No.12-9004 over School House Hollow150,000
(iii) Forest District 15
(A) Replacement of Bridge No.15-0014192,000
(B) Replacement of Bridge No.15-0025138,000
(16) Somerset County
(i) Forest District 4
(A) Replacement of Bridge No.04-0006140,000
(17) Sullivan County
(i) Forest District 20
(A) Replacement of Bridge No.20-9009140,000
(B) Replacement of Bridge No.20-9001100,000
(C) Replacement of Bridge No.20-0011110,000
(18) Tioga County
(i) Mine Hole Road Bridge
(A) Replacement of Bridge No.16-0019 over East Mine Hole Run300,000
(ii) Francis Road Bridge
(A) Replacement of Bridge No.12-0048 over Francis Branch300,000
(iii) Francis Road
(A) Replacement of Culvert No.12-9003 over Randall Hollow150,000
(iv) Francis Road
(A) Replacement of Culvert No.12-9016 over Kramer Hollow150,000
(v) Forest District 12
(A) Replacement of Bridge No.12-0049150,000
(vi) Forest District 16
(A) Replacement of Bridge No.16-0018150,000
(19) Union County
(i) Thomas Dam Road Bridge
(A) Replacement of Bridge No.7-0020 over Coral Run175,000
(ii) Forest District 7
(A) Replacement of Bridge No.07-0041107,000
(B) Replacement of Bridge No.07-0028102,000
(C) Replacement of Bridge No.07-0040165,000
(D) Replacement of Bridge No.07-0029240,000
(E) Replacement of Bridge No.07-0046212,000

Section 17. Limited waiver of local requirements.

The limitation on Department of Transportation funding of capital projects under 74 Pa.C.S. § 1302(4) (relating to program authorizations) shall be totally waived for the capital projects in the category of transportation assistance projects for mass transit contained in section 5(a)(7)(x), (xii) and (xiii) and (10)(xi), (xii), (xiii) and (xiv).

Section 18. Debt authorization.

(a) Public improvements.--The Governor, Auditor General and State Treasurer are hereby authorized and directed to borrow from time to time in addition to any authorization heretofore or hereafter enacted on the credit of the Commonwealth, subject to the limitations provided in the current capital budget, money not exceeding in the aggregate the sum of $3,957,146,000 as may be found necessary to carry out the acquisition and construction of the public improvement projects specifically itemized in a capital budget.

(b) Furniture and equipment.--The Governor, Auditor General and State Treasurer are hereby authorized and directed to borrow from time to time in addition to any authorization heretofore or hereafter enacted on the credit of the Commonwealth, subject to the limitations provided in the current capital budget, money not exceeding in the aggregate the sum of $135,024,000 as may be found necessary to carry out the public improvement projects consisting of the acquisition of original movable furniture and equipment specifically itemized in a capital budget.

(c) Transportation assistance.--The Governor, Auditor General and State Treasurer are hereby authorized and directed to borrow from time to time in addition to any authorization heretofore or hereafter enacted on the credit of the Commonwealth, subject to the limitations provided in the current capital budget, money not exceeding in the aggregate the sum of $1,772,370,000 as may be found necessary to carry out the acquisition and construction of the transportation assistance projects specifically itemized in a capital budget.

(d) Redevelopment assistance.--Subject to the limitation in section 317(b) of the act of February 9, 1999 (P.L.1, No.1), known as the Capital Facilities Debt Enabling Act, the Governor, Auditor General and State Treasurer are hereby authorized and directed to borrow from time to time in addition to any authorization heretofore or hereafter enacted on the credit of the Commonwealth, subject to the limitations provided in the current capital budget, money not exceeding in the aggregate the sum of $6,861,226,000 as may be found necessary to carry out the redevelopment assistance and the redevelopment assistance capital projects specifically itemized in a capital budget.

(e) Flood control.--The Governor, Auditor General and State Treasurer are hereby authorized and directed to borrow from time to time in addition to any authorization heretofore or hereafter enacted on the credit of the Commonwealth, subject to the limitations provided in the current capital budget, money not exceeding in the aggregate the sum of $42,944,000 as may be found necessary to carry out the acquisition and construction of the flood control projects specifically itemized in a capital budget.

(f) Pennsylvania Fish and Boat Commission projects.--The Governor, Auditor General and State Treasurer are hereby authorized and directed to borrow from time to time in addition to any authorization heretofore or hereafter enacted on the credit of the Commonwealth, subject to the limitations provided in the current capital budget, money not exceeding in the aggregate sum of $44,675,000 as may be found necessary to carry out the acquisition and construction of the Pennsylvania Fish and Boat Commission projects specifically itemized in this capital budget.

Section 19. Issue of bonds.

The indebtedness authorized in this act shall be incurred, from time to time, and shall be evidenced by one or more series of general obligation bonds of the Commonwealth in such aggregate principal amount for each series as the Governor, the Auditor General and the State Treasurer shall determine, but the latest stated maturity date shall not exceed the estimated useful life of the projects being financed as stated in section 21.

Section 20. Estimated useful life and term of debt.

(a) Estimated useful life.--The General Assembly states that the estimated useful life of the public improvement projects itemized in this act is as follows:

(1) Public improvement projects, 30 years.

(2) Furniture and equipment projects, 10 years.

(3) Transportation assistance projects:

(i) Rolling stock, 15 years.

(ii) Passenger buses, 12 years.

(iii) Furniture and equipment, 10 years.

(iv) All others, 30 years.

(b) Term of debt.--The maximum term of the debt authorized to be incurred under this act is 30 years.

Section 21. Appropriations.

(a) Public improvements.--The net proceeds of the sale of the obligations authorized in this act are hereby appropriated from the Capital Facilities Fund to the Department of General Services in the maximum amount of $3,951,146,000 to be used by it exclusively to defray the financial cost of the public improvement projects specifically itemized in a capital budget. After reserving or paying the expense of the sale of the obligation, the State Treasurer shall pay to the Department of Transportation the moneys as required and certified by it to be legally due and payable.

(b) Furniture and equipment.--The net proceeds of the sale of the obligations authorized in this act are hereby appropriated from the Capital Facilities Fund to the Department of General Services in the maximum amount of $135,024,000 to be used by it exclusively to defray the financial cost of the public improvement projects consisting of the acquisition of original movable furniture and equipment specifically itemized in a capital budget. After reserving or paying the expenses of the sale of the obligation, the State Treasurer shall pay to the Department of General Services the moneys as required and certified by it to be legally due and payable.

(c) Transportation assistance.--The net proceeds of the sale of the obligations authorized in this act are hereby appropriated from the Capital Facilities Fund to the Department of Transportation in the maximum amount of $1,772,370,000 to be used by it exclusively to defray the financial cost of the transportation assistance projects specifically itemized in a capital budget. After reserving or paying the expense of the sale of the obligation, the State Treasurer shall pay to the Department of Transportation the moneys as required and certified by it to be legally due and payable.

(d) Redevelopment assistance.--The net proceeds of the sale of the obligations authorized in this act are hereby appropriated from the Capital Facilities Fund to the Department of Community and Economic Development in the maximum amount of $6,861,226,000 to be used by it exclusively to defray the financial cost of the redevelopment assistance and redevelopment assistance capital projects specifically itemized in a capital budget. After reserving or paying the expenses of the sale of the obligation, the State Treasurer shall pay to the Department of Community and Economic Development the moneys as required and certified by it to be legally due and payable.

(e) Flood control.--The net proceeds of the sale of the obligations authorized in this act are hereby appropriated from the Capital Facilities Fund to the Department of Environmental Protection in the maximum amount of $42,944,000 to be used by it exclusively to defray the financial cost of the flood control projects specifically itemized in a capital budget. After reserving or paying the expense of the sale of the obligation, the State Treasurer shall pay to the Department of Environmental Protection the moneys as required and certified by it to be legally due and payable.

(f) Pennsylvania Fish and Boat Commission projects.--The net proceeds of the sale of the obligations authorized in this act are hereby appropriated from the Capital Facilities Fund to the Pennsylvania Fish and Boat Commission in the maximum amount of $44,675,000 to be used by it exclusively to defray the financial cost of the Pennsylvania Fish and Boat Commission projects specifically itemized in a capital budget. After reserving or paying the expense of the sale of the obligation, the State Treasurer shall pay to the Pennsylvania Fish and Boat Commission the moneys as required and certified by it to be legally due and payable.

Section 22. Federal funds.

(a) Projects itemized in this act.--In addition to those funds appropriated in section 21, all moneys received from the Federal Government for the projects specifically itemized in this act are also hereby appropriated for those projects.

(b) Projects not requiring itemization.--Department of Military and Veterans Affairs construction projects which are totally federally funded but which are to be administered by the Department of General Services are hereby authorized.

Section 23. (Reserved)

Section 24. Exemption of public improvement projects.

The project itemized in section 5(a)(10)(x) of this act shall be exempt from the first paragraph of section 1 of the act of May 1, 1913 (P.L.155, No.104), entitled "An act regulating the letting of certain contracts for the erection, construction, and alteration of public buildings."

Section 25. Allocation of funds.

Whenever as determined by the Department of Transportation that the full estimated financial costs of the projects itemized in section 16 of this act are not necessary for the proper design, acquisition or construction of such projects, the excess funds no longer required may be allocated by the Department of Transportation to increase the estimated costs of any one or more of the projects specifically itemized in a capital budget.

Section 26. Restriction on expenditure of certain funds for the Capitol Complex.

(a) The new and additional funds provided in section 3(8)(i)(A) and (B) shall only be disbursed upon written approval as follows:

(1) Finance Building - Chairman and executive director of the Capitol Preservation Committee.

(2) Forum Building - Chairman and executive director of the Capitol Preservation Committee.

(3) North Office Building - Chief Clerk of the Senate and the chairman and executive director of the Capitol Preservation Committee.

(4) Speaker K. Leroy Irvis Building - Chief Clerk of the House of Representatives and the chairman and executive director of the Capitol Preservation Committee.

(5) Main Capitol Building - Chief Clerk of the Senate, Chief Clerk of the House of Representatives and the chairman and executive director of the Capitol Preservation Committee.

(b) The new and additional funds provided in section 3(8)(i)(F) shall only be disbursed upon written approval of the Chief Clerk of the Senate.

(c) The new and additional funds provided in section 3(8)(i)(H) shall only be disbursed upon written approval of the Chief Clerk of the House of Representatives.

Section 26.1. Conditions and limitations on certain capital projects.

(a) Notwithstanding the provisions of section 3(9)(v) of the act of October 30, 2002 (P.L.891, No.131), known as the Capital Budget Project Itemization Act of 2001-2002, the land acquisition and construction of a new combined readiness center/operations maintenance shop may be in Adams or Franklin County.

(b) Notwithstanding the provisions of section 3(9)(xi) of the act of October 30, 2002 (P.L.891, No.131), known as the Capital Budget Project Itemization Act of 2001-2002, the land acquisition and construction of a new combined readiness center/operations maintenance shop may be in Erie or Crawford County.

(c) The authorization and appropriation for the capital projects itemized in section 3(8)(i)(G) and (H) shall be effective upon completion of the design phase for the capital project authorized in section 3(8)(i)(F). The capital projects itemized in section 3(8)(i)(G) and (H) shall not be released for design by the Department of General Services or the Office of the Budget until the project authorized in section 3(8)(i)(F) has been released for construction. The capital project itemized in section 3(8)(i)(E) shall not be released for construction by the Department of General Services or the Office of the Budget unless the project itemized in section 3(8)(i)(F) has been released for design.

Section 27. Delegation.

(a) Notwithstanding any provision of law to the contrary, the Department of General Services may delegate the design and construction of the project contained in section 3(1)(ii)(A) to the University of Pennsylvania.

(b) For the public improvement projects specifically itemized in section 3(16), the Department of General Services may delegate the authority to construct, improve, equip, furnish, maintain, acquire or operate such projects to the Philadelphia Regional Port Authority. Notwithstanding any provision of law to the contrary, the Philadelphia Regional Port Authority, at its discretion and subsequent to the aforementioned delegation, may contract with one or more of the tenant companies leasing or operating port facilities at the Port of Philadelphia for the purpose of constructing, improving, equipping, furnishing, maintaining, acquiring or operating the public improvement projects specifically itemized in section 3(16). Any project itemized in section 3(16) delegated to the Philadelphia Regional Port Authority for which the authority contracts with a tenant company for the purpose of constructing, improving, equipping, furnishing, maintaining, acquiring or operating the project, shall be exempt from the first paragraph of section 1 of the act of May 1, 1913 (P.L.155, No.104), entitled "An act regulating the letting of certain contracts for the erection, construction, and alteration of public buildings," and the provisions of the act of March 3, 1978 (P.L.6, No.3), known as the Steel Products Procurement Act, and any provisions of law requiring the bidding of projects.

(c) Notwithstanding any provision of law to the contrary, the Department of General Services may delegate the design and construction of the project authorized in section 3(8)(ii)(C) to the Pennsylvania Convention Center Authority. The project authorized in section 3(8)(ii)(C) shall require non-State participation in an amount determined by the Office of the Budget. Non-State participation shall not be less than 25% nor more than 50% of the total project cost. All contracts for the expenditure of funds for the expansion of the Pennsylvania Convention Center shall be subject to 64 Pa.C.S. Ch. 60 (relating to Pennsylvania Convention Center Authority).

Section 28. Exemption from certain procurement limitations.

Notwithstanding any other provision of law to the contrary, the project itemized in section 16(2)(i)(A) is exempt from 62 Pa.C.S. Chs. 5 (relating to source selection and contract formation) and 9 (relating to procurement of construction and design professional services) and from section 404.1 of the act of June 1, 1945 (P.L.1242, No.428), known as the State Highway Law, relating to prequalification of bidders.

Section 28.1. Special contract provisions.

Any Redevelopment Assistance Capital Program-eligible expenditure of funds incurred prior to the effective date of this act which is directly related to the redevelopment assistance capital project itemized in section 6(23)(vi)(A) shall be considered eligible to be utilized as a portion of the expenditure of matching funds and may be considered as eligible for reimbursement from a redevelopment assistance capital project grant made pursuant to the itemization in section 6(23)(vi)(A).

Section 29. Repeals.

The following acts and parts of acts are repealed:

Section 2 XLI(11) of the act of January 26, 1972 (1971 P.L.686, No.185), known as the Capital Budget Act of Fiscal Year 1971-1972, Highway Project Itemization Supplement.

Section 2 LI(7) of the act of July 6, 1973 (P.L.95, No.42), known as the Capital Budget Act for Fiscal Year 1972-1973, Highway Project Itemization Supplement.

Section 3(40)(i) of the act of December 19, 1990 (P.L.1399, No.218), known as the Highway Supplement to the Capital Budget Act of 1990-1991.

Sections 4(4)(ii)(A), (6)(ii)(E), (12)(i)(A), (ii)(A), (vii)(D), (E) and (F), (xii)(A) and (xiv)(D), 6(a)(10)(xiv), 7(41)(ii)(B) and 23 of the act of May 22, 2000 (P.L.104, No.22), known as the Capital Budget Debt Authorization and Project Itemization Act of 2000-2001.

Sections 3(7)(i)(F), (J) and (M), (13)(ii)(J), (iii)(B), (ix)(G) and (xi)(A), 4(7)(ix)(B) and (xi)(B) and (C), 6(41)(ii)(B) and 27 of the act of October 30, 2002 (P.L.891, No.131), known as the Capital Budget Project Itemization Act of 2001-2002.

Section 8 of the act of December 9, 2002 (P.L.1599, No.208), known as the Pennsylvania Fish and Boat Commission Capital Budget Act for 2002-2003.

Section 9 of the act of May 19, 2003 (P.L.5, No.2), known as the Capital Budget Project Itemization Act for 2002-2003.

Section 30. Editorial changes.

In editing and preparing this act for printing following the final enactment, the Legislative Reference Bureau shall insert or revise letters or numbers for projects where the letters or numbers are missing or require revision. The bureau shall also revise the total monetary amounts for the total authorization, debt authorization, appropriations and departmental totals as necessary to agree with the total monetary amounts of the projects.

Section 31. Effective date.

This act shall take effect immediately.