Question juridique clé
Whether the building permit violated noise-protection requirements because Rue Centrale had not yet been rehabilitated or resurfaced.
Solution extraite
The permit was lawful because the authorities could rely on a sufficiently certain future rehabilitation of Rue Centrale, including a noise-reducing pavement, when assessing compliance with noise limits.
Motifs extraits
Under Art. 22 LPE and Art. 36(2) OPB, future reduction of immissions may be considered if the planned measures are concrete and sufficiently certain, even if the assainissement project is not yet finally executed; here the municipality's commitment and the approved credit made the measure reliable enough.