Question juridique clé
Whether the planned nearby redevelopment had to be included in the emission assessment for the mobile antenna permit
Solution extraite
No. For partly built-up land, the existing Nutzungsreserven generally need not be considered when granting a mobile-antenna permit; future uses matter only if a sufficiently concretized project is shown, and in any event compliance with limit values must be secured for newly created sensitive uses.
Motifs extraits
The court confirmed its case law distinguishing unbuilt land from partly built-up parcels. It held that the city’s practice, which obliges the antenna operator to verify and if necessary adapt the installation once the new sensitive uses are authorized, sufficiently secures compliance with the NISV limit values.