Question juridique clé
Whether Article 14 of the Göschenalp concession obliges the concessionaires to supply Göschenen power as prior supply for Uri's electricity needs.
Solution extraite
No enforceable obligation to deliver the claimed concession energy exists; Article 14 does not impose the requested prior supply duty.
Motifs extraits
The court found either a contrary actual common intent or, failing that, an objective interpretation under the trust principle leading to the same result. The parties aimed to create a partner plant, accepted no partner-energy delivery, and nothing in the contract or subsequent conduct showed an agreed duty to supply concession energy beyond the specific Article 14 paragraph 2 arrangement.