16-1568
Constitution Pipeline Co. v.
New York State Department of
Environmental Conservation
UNITED STATES COURT OF APPEALS 1
FOR THE SECOND CIRCUIT 2
- - - - - - 3
August Term, 2016 4
(Argued: November 16, 2016 Decided: August 18, 2017) 5
Docket No. 16-1568 6
_________________________________________________________ 7
CONSTITUTION PIPELINE COMPANY, LLC, 8
Petitioner, 9
- v. - 10
NEW YORK STATE DEPARTMENT OF ENVIRONMENTAL 11
CONSERVATION; BASIL SEGGOS, Acting Commissioner, New York State 12
Department of Environmental Conservation; JOHN FERGUSON, Chief Permit 13
Administrator, New York State Department of Environmental Conservation, 14
Respondents, 15
STOP THE PIPELINE, CATSKILL MOUNTAINKEEPER, INC., SIERRA 16
CLUB, RIVERKEEPER, INC., 17
Intervenors.*
18
_________________________________________________________ 19
Before: KEARSE, WESLEY, and DRONEY, Circuit Judges. 20
Petition for review of respondents' decision denying application for certification 21
* The Clerk of Court is directed to amend the official caption to conform with the
above.
-- 1 of 27 --
pursuant to § 401 of the Clean Water Act, 33 U.S.C. § 1341, that petitioner's proposed interstate 1
natural gas pipeline would comply with New York State water quality standards ("§ 401 2
certification"). Respondents denied the application on the ground that petitioner had not complied 3
with requests for relevant information. Petitioner contends (1) that respondents exceeded the statutory 4
time limitations for the State's review of the application and that they must therefore be ordered to 5
notify the United States Army Corps of Engineers ("USACE") that the State waives its right to issue 6
or deny § 401 certification, thereby allowing USACE to issue a permit to petitioner under § 404 of 7
the Clean Water Act, see 33 U.S.C. § 1344(a); and (2) alternatively, that respondents' decision should 8
be vacated on the ground that the denial of the application was arbitrary, capricious, and ultra vires, 9
and that respondents should be ordered to grant the requested § 401 certification. To the extent that 10
petitioner challenges the timeliness of respondents' decision, we conclude that we lack jurisdiction 11
over that challenge. As to the merits, we conclude that respondents' actions were within their 12
statutory authority and that the decision was not arbitrary or capricious. 13
Petition dismissed in part and denied in part. 14
JOHN F. STOVIAK, Philadelphia, Pennsylvania (Saul Ewing, 15
Philadelphia, Pennsylvania, Elizabeth Utz Witmer, Saul Ewing, 16
Wayne, Pennsylvania; Yvonne E. Hennessey, Barclay Damon, 17
Albany, New York, on the brief), for Petitioner. 18
BRIAN LUSIGNAN, Assistant Attorney General, Albany, New York 19
(Eric T. Schneiderman, Attorney General of the State of New 20
York, Barbara D. Underwood, Solicitor General, Andrew B. 21
Ayers, Senior Assistant Solicitor General, Frederick A. Brodie, 22
Assistant Solicitor General, Lisa M. Burianek, Deputy Bureau 23
Chief, Albany, New York, on the brief), for Respondents. 24
2
-- 2 of 27 --
KARA E. PAULSEN**
, White Plains, New York (Karl S. Coplan, 1
Todd D. Ommen, Anne Marie Garti, Pace Environmental 2
Litigation Clinic, Inc., White Plains, New York, on the brief), 3
for Intervenor Stop the Pipeline. 4
MONEEN NASMITH, New York, New York (Deborah Goldberg, 5
Christine Ernst, Earthjustice, New York, New York, on the 6
brief), for Intervenors Catskill Mountainkeeper, Inc., Sierra 7
Club, and Riverkeeper, Inc. 8
SIDLEY AUSTIN, Washington, D.C. (Roger R. Martella, Jr., Ryan C. 9
Morris, Tobias S. Loss-Eaton, Washington, D.C.; Linda E. 10
Kelly, Quentin Riegel, Leland P. Frost, Manufacturers' Center 11
For Legal Action, Washington, D.C.; Steven P. Lehotsky, 12
Sheldon B. Gilbert, U.S. Chamber Litigation Center, 13
Washington, D.C.; Kevin B. Belford, Michael L. Murray, 14
Washington, D.C.; Leslie A. Hulse, Washington, D.C.; Dena 15
E. Wiggins, Washington, D.C.; Andrea J. Chambers, Katie 16
Leesman, Ballard Spahr, Washington, D.C., of counsel), filed 17
a brief for Amici Curiae National Association of 18
Manufacturers, Chamber of Commerce of the United States of 19
America, Interstate Natural Gas Association of America, 20
American Gas Association, American Petroleum Institute, 21
American Chemistry Council, Natural Gas Supply Association, 22
American Forest & Paper Association, and Process Gas 23
Consumers Group, in support of Petitioner. 24
Kimberly Ong, New York, New York (Albert K. Butzel, New York, 25
New York, of counsel), filed a brief for Amici Curiae Natural 26
Resources Defense Council, Water Defense, Waterkeeper 27
Alliance, Earthworks, PennEnvironment, Peconic Baykeeper, 28
and Chesapeake Bay Foundation, in support of Respondents. 29
KEARSE, Circuit Judge: 30
Petitioner Constitution Pipeline Company, LLC ("Constitution"), petitions pursuant 31
to 15 U.S.C. § 717r(d)(1) for review of an April 22, 2016 decision of the New York State Department 32
of Environmental Conservation ("NYSDEC" or the "Department") denying Constitution's application 33
** Law student appearing pursuant to Local Rule 46.1(e).
3
-- 3 of 27 --
for certification pursuant to § 401 of the Federal Water Pollution Control Act, more commonly known 1
as the Clean Water Act (or "CWA"), 33 U.S.C. § 1341 ("§ 401 certification"), that Constitution's 2
proposed interstate natural gas pipeline would comply with New York State (or "State") water quality 3
standards (or "WQS"). NYSDEC denied the application on the ground that Constitution had not 4
provided sufficient information. In its petition, Constitution contends principally (1) that NYSDEC 5
exceeded the § 401(a) time limitations for the State's review of the application and that NYSDEC 6
must therefore be ordered to notify the United States Army Corps of Engineers ("USACE" or "Army 7
Corps of Engineers" or "Army Corps") that the State has waived its right to act upon Constitution's 8
§ 401 certification application, thereby allowing USACE to issue a permit to petitioner under § 404 9
of the Clean Water Act, see 33 U.S.C. § 1344(a); and (2) alternatively, that Constitution submitted 10
sufficient information and that NYSDEC's decision should be vacated on the ground that its denial 11
of the application was arbitrary, capricious, and ultra vires, and that NYSDEC should be ordered to 12
grant the requested § 401 certification. To the extent that Constitution challenges the timeliness of 13
the NYSDEC decision, we dismiss the petition for lack of jurisdiction. As to the merits, we conclude 14
that NYSDEC's actions were within its statutory authority and that its decision was not arbitrary or 15
capricious, and we deny the petition. 16
I. BACKGROUND 17
Constitution proposes to construct a 121-mile interstate natural gas pipeline in 18
Pennsylvania and New York, approximately 98 miles of which would be in New York. In connection 19
with this project (the "Project"), Constitution applied for, to the extent pertinent here, a "certificate 20
4
-- 4 of 27 --
of public convenience and necessity" from the Federal Energy Regulatory Commission ("FERC"), 1
15 U.S.C. § 717f(c), a CWA § 401 water quality certification (or "WQC") from New York State that 2
the Project would comply with State water quality standards (see 6 N.Y.C.R.R. parts 701 to 704), and 3
a CWA § 404 permit from the Army Corps of Engineers to allow discharges into United States 4
navigable waters. 5
A. Proceedings Before FERC 6
In September 2012, FERC announced that it would prepare an environmental impact 7
statement ("EIS") for Constitution's Project and asked Constitution to submit a feasibility study 8
explaining how it would install the pipeline across waterbodies (generally using that term to refer to 9
streams but not wetlands). For such installations, there is a trenched method--a dry open-cut crossing- 10
-which involves diverting a stream, digging a trench through the banks and stream bed, installing and 11
burying the pipeline, and then allowing the stream to resume flowing in the stream bed. (See, e.g., 12
FERC Final Environmental Impact Statement ("FEIS") pages 2-21 to 2-22.) There are also trenchless 13
crossing methods--including Horizontal Directional Drill (or "HDD"), Direct Pipe (or "DP"), and 14
conventional bore--which involve digging pits on either side of a waterbody and boring or drilling 15
underneath the stream. FERC asked Constitution to provide information with regard to trenchless 16
construction methods for crossing several categories of streams, including those classified by the 17
states as sensitive or high quality and those greater than 30 feet wide where a dry construction method 18
would not be feasible. 19
5
-- 5 of 27 --
1. Constitution's Trenchless Feasibility Study 1
Constitution submitted to FERC a study discussing trenchless crossing methods. (See 2
Constitution, Feasibility Study: Trenchless Construction Methods for Sensitive Environmental 3
Resource Crossings (Nov. 2013) ("Constitution 2013 Feasibility Study" or "Study") pages 1-3 to 1-5.) 4
Trenchless methods do not disturb soil or organisms in the stream banks, stream bed, or in the stream 5
itself, but require disturbing surrounding areas to clear space for installation pits; there are also risks 6
of mid-project drill breakage, with leakage of drill fluid into the waterbody. (See Constitution 2013 7
Feasibility Study page 2-3; FEIS page 2-24.) Use of the trenched method does not require as much 8
installation space or present the risk of drill failure; but it requires stream diversion and digging into 9
the stream bed and banks. (See, e.g., FEIS pages 2-21 to 2-22.) 10
The Constitution feasibility study dealt principally with locations where the waterbody 11
was designated by New York or Pennsylvania as sensitive or high quality. (See Constitution 2013 12
Feasibility Study pages 2-2 to 2-3.) As a result, Constitution eliminated from consideration for 13
trenchless crossings all but 89 of the 251 New York waterbodies that would be crossed by the pipeline 14
or affected by pipeline construction. 15
The remaining 89 locations were addressed in three phases. The Study's "Phase I[] 16
Desktop Analysis" (id. pt. 1.0 page 1-1) further reduced the number of New York waterbodies 17
considered by Constitution for trenchless crossings from 89 to 26, in part by eliminating streams less 18
than 30 feet wide, even if they were classified by New York as sensitive or high-quality (see id. pages 19
2-1, 2-3). Constitution stated that trenchless crossings for such narrower waterbodies would 20
potentially require workspace requirements significantly greater than those generally needed for a 21
conventional dry crossing method. (See id. page 2-3.) Thus, unless such a waterbody was 22
6
-- 6 of 27 --
immediately associated with a larger wetland and/or waterway complex crossed by the Project or was 1
located in the immediate vicinity of a proposed rail or roadway crossing, "Constitution did not 2
evaluate waterbody crossings less than 30 feet in width" (id.). 3
Phase II was a "Cost/Time/Construction Workspace Impact Analysis." (Id. page 3-1; 4
see also id. pt. 1.0 page 1-1 ("Trenchless construction methods are limited" not only by such matters 5
as "underlying geology, available workspace, [and] available time," but also by "available finances 6
budgeted for a capital project.").) This phase eliminated waterways from trenchless-crossing 7
consideration largely on the basis of expense; as a result, there remained only 13 waterbody crossings 8
in New York for which Constitution planned to investigate a "formal trenchless construction design." 9
(Id. pages 3-2 to 3-4 & tbl.3.2-1.) The Study stated that Phase III, a "geotechnical field analysis" of 10
each of the 13 locations, was in progress. (Id. page 5-1.) Constitution thus planned to use the 11
trenched method for 238 of the 251 New York waterbodies to be crossed. 12
2. NYSDEC Comments and the FEIS 13
In connection with FERC's announcement of a planned EIS for the Constitution 14
pipeline--and its subsequent draft EIS ("DEIS")--NYSDEC submitted numerous letters to FERC. The 15
first noted that NYSDEC's preferred method for crossing waterbodies is a trenchless method, in 16
particular 17
Horizontal Directional Drilling (HDD) because it has the advantages of 18
minimizing land disturbance, avoiding the need for dewatering of the stream, 19
leaving the immediate stream bed and banks intact, and reducing erosion, 20
sedimentation and Project-induced watercourse instabilities. 21
(November 7, 2012 Letter from NYSDEC to FERC at 3 (emphasis added).) Stating that the DEIS 22
should identify the New York classification of each stream the proposed pipeline would cross, 23
7
-- 7 of 27 --
NYSDEC urged FERC to "evaluate cases where other methods are proposed" and have Constitution 1
"explain why HDD will not work or is not practical for that specific crossing." (Id. (emphasis 2
added).) 3
A May 2013 letter again stated that "NYSDEC's preferred methodology for all stream 4
crossings is . . . (HDD)"; that letter also stated that "[w]ithin stream crossings, pipelines should be 5
buried at least 6' below a stream bottom. Minimum cover depth is not subject to variance based on 6
field conditions." (May 28, 2013 Letter from NYSDEC to FERC ("NYSDEC May 2013 Letter") 7
at 1-2 (emphasis added).) 8
In September 2013, NYSDEC wrote to join a request by the Army Corps for additional 9
analysis of whether the Constitution pipeline could be routed along a certain interstate highway, a 10
route referred to as "Alternative M." (September 25, 2013 Letter from NYSDEC to FERC at 1.) 11
Constitution responded by arguing that Alternative M would have greater environmental impact than 12
Constitution's proposed route and noting likely difficulties in obtaining highway agencies' approvals. 13
(See October 22, 2013 Letter from Constitution to NYSDEC at 2-4.) 14
In 2014, FERC issued its DEIS, which drew criticism from several sources including 15
NYSDEC. (See, e.g., March 24, 2014 Letter from NYSDEC to FERC and Army Corps at 1-2 (urging 16
a revised DEIS to include "geotechnical feasibility studies for all trenchless crossing locations," as 17
well as "site specific blasting plans that include protocols for in-water blasting and the protection of 18
aquatic resources and habitats" (emphasis added)); April 7, 2014 Letter from NYSDEC to FERC and 19
Army Corps ("NYSDEC April 2014 Letter") at 1-5 (adding additional comments and requesting 20
additional analysis of Alternative M which, in NYSDEC's view, would reduce the amount of 21
disturbance of higher-quality waterbodies).) 22
8
-- 8 of 27 --
FERC issued its FEIS in 2014 without significantly expanding on several aspects of 1
the DEIS. It did not address NYSDEC's concern that Constitution had not developed site-specific 2
blasting plans. (See FEIS pages 4-15 to 4-16; DEIS page 4-16.) The FEIS added discussion of two 3
new versions of Alternative M proposed by NYSDEC (see FEIS pages 3-46 to 3-47), but rejected 4
them without analyzing disturbances to high-quality waterbodies (compare id. pages 3-32 to 3-47 with 5
NYSDEC April 2014 Letter at 3-4). And the FEIS stated that the pipeline would be buried 60 inches 6
below streams in normal soil conditions and 24 inches in areas of "consolidated rock" (FEIS 7
page 2-16), as contrasted with the NYSDEC May 2013 Letter's statement that the pipe needed to be 8
buried "at least 6' below a stream bottom" (NYSDEC May 2013 Letter at 2). 9
The FEIS expanded on the DEIS's waterbody crossing information but repeated DEIS 10
explanations for why relatively few crossings were slated to be crossed by trenchless techniques, 11
stating, inter alia, that "[a]ccording to Constitution, trenchless crossing methods are not practical 12
[except in limited circumstances] for waterbody crossings less than 30 feet in width" and that 13
"Constitution indicated that such crossings would be impractical due to minimum length requirements, 14
depth of pipeline considerations, and workspace requirements," and describing the areas that would 15
be required for trenchless crossing "[a]ccording to Constitution" (FEIS page 4-50). The FEIS stated 16
that 17
[t]he potential impacts on waterbodies associated with the use of conventional 18
bore or Direct Pipe trenchless crossing methods are considered minimal when 19
compared to other crossing methods. The waterbody and its banks, and 20
typically the entire immediate riparian zone, would not be disturbed by 21
clearing or trenching; rather, the pipe would be installed below the feature. 22
(Id. page 4-56 (emphasis added).) FERC added: 23
We concur with Constitution's assessment that it is not practicable to use 24
trenchless crossing methods where waterbodies were listed as ephemeral or 25
9
-- 9 of 27 --
intermittent (because these waterbodies are likely to be dry at the time of 1
crossing) or for waterbodies less than 30 feet in width (as extra workspaces 2
needed would offset potential benefits). . . . 3
(FEIS, App'x S, page S-52 (emphases added).) The FEIS noted that Constitution had completed 4
geotechnical feasibility studies at only two New York sites. (See FEIS page 4-4.) 5
B. Proceedings Before NYSDEC 6
While its application to FERC for a certificate of public convenience and necessity was 7
pending, Constitution submitted an application to the Army Corps for a CWA § 404 permit for the 8
discharge of dredged or fill material while constructing the pipeline and to NYSDEC for a CWA 9
§ 401 certification that the Project would comply with State water quality standards. In December 10
2014, NYSDEC issued a notice that Constitution's application was complete; but on December 31, 11
it asked Constitution for more information about stream crossings. In January-March 2015, 12
Constitution submitted more information to NYSDEC, and on April 27, 2015, at NYSDEC's request, 13
Constitution withdrew and resubmitted its § 401 application. (Constitution had also withdrawn and 14
resubmitted its § 401 application at NYSDEC's request in May 2014.) 15
1. Stream-Crossing Information Requests by NYSDEC 16
On January 23, 2015, staff from Constitution and NYSDEC met to discuss trenchless 17
stream-crossing methods (see January 14, 2015 email from NYSDEC Project Manager Stephen M. 18
Tomasik to Constitution engineering consultant Keith Silliman; January 27, 2015 email from Tomasik 19
to Constitution Environmental Project Mananger Lynda Schubring ("NYSDEC January 27, 2015 20
email")). Prior to that meeting, Constitution wrote to NYSDEC stating that it had 21
10
-- 10 of 27 --
conducted subsurface geotechnical investigations at the majority of the 1
proposed . . . (HDD) and . . . (DP) trenchless locations. Results of the 2
subsurface geotechnical investigations revealed crossing locations that present 3
a high risk of failure if a trenchless method is used. As a result, trenchless 4
crossing locations with a high risk of failure are not feasible and have been 5
modified to a dry open cut design. Since the last . . . submissions to the 6
USACE, three (3) HDD or DP locations affecting six (6) wetlands or 7
waterbodies have changed to an open cut construction method . . . . 8
(January 22, 2015 Letter from Schubring to Tomasik at 1.) Constitution also stated that six other 9
originally proposed trenchless crossings would be crossed by a trenched method, "to address various 10
concerns raised by [state and local] authorities relative to the trenchless crossings of specific public 11
roadways and associated infrastructure." (Id. at 2.) After the January 23 meeting, NYSDEC 12
requested additional documents that Constitution personnel had said informed its decision to use the 13
trenched crossing method at two locations, as well as "information about stream crossings that we 14
requested on 12/31/2014." (NYSDEC January 27, 2015 email). 15
In response, Constitution submitted feasibility evaluations based on geotechnical 16
studies for four locations: two wetlands crossings and two waterbody crossings. One of the 17
waterbody feasibility evaluations concluded that using either HDD or DP was infeasible due to 18
subsurface soil conditions; the other did not address the feasibility of trenchless crossing methods, and 19
instead discussed only a contingency open-cut crossing to be used if the proposed DP crossing failed. 20
In February 2015, Constitution submitted to NYSDEC a document titled "Draft 21
Trenchless Feasibility Study Edits" ("Constitution 2015 Feasibility Draft") that appears to be a version 22
of part of the 2013 trenchless feasibility study that Constitution had submitted to FERC, merely 23
expanding on the manner in which each trenchless method operates. Again there was no discussion 24
of stream crossings site-by-site. The Constitution 2015 Feasibility Draft stated that 25
Constitution recognizes that, in general, performing . . . (HDD) for streams 26
11
-- 11 of 27 --
less than 30 feet in width causes greater net environmental impacts than a dry 1
open cut method and this threshold is an industry recognized standard. 2
Constitution has not identified any NYSDEC regulation, formally adopted 3
policy or guidance document that would warrant deviating from this standard. 4
(Id. at 1 (emphases added).) It also discussed the Direct Pipe method, stating that "it is likely that 5
additional forest will require clearing to perform DP for most of the protected stream crossings," and 6
that "[m]any" streams are in valleys whose slopes make the DP method infeasible. (Id. at 2-3 7
(emphases added).) In addition, the Constitution 2015 Feasibility Draft stated that DP technology is 8
of "limited availability," leading Constitution to conclude that using "DP technology for . . . streams 9
less than 30 feet in width is not a realistic or viable expectation within a reasonable period of time." 10
(Id. at 3 (emphasis added).) 11
In March 2015, NYSDEC sent Constitution a list of 20 waterbody locations that 12
NYSDEC "wants crossed via HDD," stating that NYSDEC "is still expecting an evaluation as to 13
whether an HDD is technically feasible for each of these streams." (March 17, 2015 email from 14
NYSDEC Major Project Management Unit Chief Christopher M. Hogan to Silliman (emphasis 15
added).) In April 2015, as indicated above, Constitution withdrew and resubmitted its § 401 WQC 16
request. 17
2. Subsequent Discussions 18
In May 2015, NYSDEC noted that it had agreed to "eliminate" four streams from 19
"further consideration for trenchless crossing methods." (May 22, 2015 email from Tomasik to 20
Schubring, Silliman, et al.) 21
In July 2015, a member of NYSDEC's staff emailed to certain Army Corps staff 22
members a "Confidential" message attaching a "VERY PRELIMINARY version of a Constitution 23
12
-- 12 of 27 --
permit" (July 20, 2015 email from Tomasik to Kevin J. Bruce et al., Army Corps), which included a 1
table of 19 locations that "shall be crossed using a trenchless construction method"--unless an 2
"experienced and qualified engineer" concludes that the techniques are "not constructible or not 3
feasible" (Confidential Draft NYSDEC Certification Conditions at 17). The draft, however, required 4
Constitution, "[p]rior to beginning construction of any trenchless stream crossing," to "submit a[] 5
. . . 'Trenchless Crossing Plan' for each trenchless stream crossing," including "detailed engineering 6
plans" for each location. (Id. at 18 (emphases added).) 7
In September 2015, Constitution submitted to NYSDEC an Environmental 8
Construction Plan, attached to which was a Blasting Plan. (See Constitution, Environmental 9
Construction Plan 50 (Aug. 2015).) This plan listed 253 "[a]reas of shallow depth to bedrock crossed 10
by the [pipeline]" in New York, but stated that "[a] final determination on the need for blasting will 11
be made at the time of construction." (Constitution, Blasting Plan (Aug. 2015) ("Blasting Plan") 12
pages 1-1, 1-2 & tbl.1.2-2, 4-1.) The Blasting Plan identified regulations and a permit that would 13
govern blasting in Pennsylvania, but stated that "[a]ll blasting operations in New York will be 14
conducted in accordance with an in-stream b[l]asting protocol to be prepared by Constitution." (Id. 15
page 4-1 (emphasis added).) 16
C. NYSDEC's Decision Denying § 401 Certification 17
In a 14-page letter to Constitution dated April 22, 2016, NYSDEC denied 18
Constitution's application for CWA § 401 certification ("NYSDEC Decision" or "Decision"), stating 19
that "the Application fails in a meaningful way to address the significant water resource impacts that 20
could occur from this Project and has failed to provide sufficient information to demonstrate 21
13
-- 13 of 27 --
compliance with New York State water quality standards," NYSDEC Decision at 1. Although also 1
noting the lack of adequate information as to such issues as the feasibility of the Alternative M route, 2
blasting information, pipe burial depth, and wetlands crossings, see, e.g., id. at 11-14, the Decision 3
focused principally on Constitution's failure to provide information with respect to stream crossings. 4
NYSDEC noted that Constitution's Project "would disturb a total of 251 streams . . . , 5
87 of which support trout or trout spawning," and that "[c]umulatively, construction would disturb 6
a total of 3,161 linear feet of streams and result in a combined total of 5.09 acres of temporary stream 7
disturbance impacts." NYSDEC Decision at 8. It stated that although 8
[f]rom inception of its review of the Application, NYSDEC directed 9
Constitution to demonstrate compliance with State water quality standards and 10
required site-specific information for each of the 251 streams impacted by the 11
Project[, and] NYSDEC informed Constitution that all 251 stream crossings 12
must be evaluated for environmental impacts and that trenchless technology 13
was the preferred method for stream crossing[, and that t]his information was 14
conveyed to Constitution and FERC on numerous occasions since November 15
2012[,] . . . Constitution has not supplied the Department with the necessary 16
information for decision making. 17
Id. (emphasis in original). 18
The Decision stated that because some form of trenchless technology is the "most 19
protective method for stream crossings," 20
NYSDEC directed Constitution to determine whether a trenchless technology 21
was constructible for each stream crossing. On a number of occasions 22
NYSDEC identified the need to provide information so that it could evaluate 23
trenchless stream installation methods (see Table 2, below); however, 24
Constitution has not provided sufficient information . . . . 25
Id. (footnote omitted) (emphasis added). 26
Table 2 in the Decision principally chronicled NYSDEC's requests of Constitution-- 27
both directly and indirectly in its submissions to FERC--and noted Constitution's resistance, including 28
14
-- 14 of 27 --
the following: 1
# In June 2012, "NYSDEC stated in a letter to Constitution that for protected 2
streams and wetlands, trenchless technology is the preferred method for crossing and 3
should be considered for all such crossings (emphasis added)." 4
# On November 7, 2012, "[i]n comments to FERC, NYSDEC stated that for 5
streams and wetlands the preferred method for crossing is trenchless technology," and 6
that as to each crossing where another method is proposed "Constitution should 7
explain why trenchless crossing technology will not work or is not practical for that 8
specific crossing." 9
# On April 9, 2013, "FERC[] . . . directed Constitution to address all of the 10
comments filed in the public record by other agencies . . . including all comments from 11
the NYSDEC." 12
# On May 28, 2013, at a "[m]eeting" of "Constitution and NYSDEC staff . . . 13
NYSDEC reiterate[d] that acceptable trenchless technology was the preferred 14
installation method and that stream crossings should be reviewed for feasibility of 15
using those technologies." 16
# In July and August 2013, on "[f]ield visits of proposed stream crossings 17
prior to permit applications to the Department[, a]t each crossing, NYSDEC 18
emphasized to Constitution staff that trenchless technology is preferred/most 19
protective." 20
# In its November 2013 Trenchless Feasibility Study, Constitution 21
"arbitrarily eliminated from any consideration for trenchless crossing methods" 22
"all streams less than 30' wide." 23
# On December 31, 2014, at a meeting with Constitution staff, "NYSDEC 24
indicated that the Trenchless Feasibility Study was inadequate, e.g. provided 25
insufficient justification and removed all streams less than 30 feet in width from 26
analysis." NYSDEC gave Constitution "an informational request table including 27
required technical information." 28
# On January 13, 2015, an "Army Corps of Engineers letter reiterate[d] a 29
request for a feasibility analysis of trenchless crossings." 30
# At a January 23, 2015 "[m]eeting between Constitution and NYSDEC staff 31
. . . Constitution stated it was unable to complete the [informational request] table 32
[it received from NYSDEC] on December 31, 2014[]. NYSDEC staff indicated that 33
the justification for stream crossing methods was insufficient and that appropriate site 34
specific information must be provided." 35
15
-- 15 of 27 --
# In a January 28, 2015 "[c]onference call[,] NYSDEC reiterated its request 1
for a site specific analysis of trenchless stream crossings for all streams including 2
those under 30 feet wide." 3
# On February 5, 2015, "Constitution provided an updated example of 4
a trenchless feasibility study but that example continued to exclude streams up to 5
30 feet wide from analysis and did not provide detailed information of the 6
majority of streams." 7
NYSDEC Decision at 9-10 (emphases added). 8
Although the Decision's Table 2 ended with the February 2015 entry, the Decision 9
noted that Constitution's "unwillingness to provide a complete and thorough[] Trenchless Feasibility 10
Study" persisted: 11
[I]n May 2015, Constitution provided detailed project plans for 25 potential 12
trenchless crossings, but only two of those plans were based on full 13
geotechnical borings that are necessary to evaluate the potential success 14
of a trenchless design. Detailed project plans including full geotechnical 15
borings for the remaining stream crossings have not been provided to the 16
Department. 17
Id. at 11 (emphasis added). The NYSDEC Decision stated that 18
[d]ue to the lack of detailed project plans, including geotechnical 19
borings, the Department has determined to deny Constitution's WQC 20
Application because the supporting materials supplied by Constitution do not 21
provide sufficient information for each stream crossing to demonstrate 22
compliance with applicable narrative water quality standards for turbidity and 23
preservation of best usages of affected water bodies. Specifically, the 24
Application lacks sufficient information to demonstrate that the Project will 25
result in no increase that will cause a substantial visible contrast to natural 26
conditions.10
27
Furthermore, the Application remains deficient in that it does not 28
contain sufficient information to demonstrate compliance with 6 NYCRR Part 29
701 setting forth conditions applying to best usages of all water classifications. 30
Specifically, "the discharge of sewage, industrial waste or other wastes shall 31
not cause impairment of the best usages of the receiving water as specified by 32
the water classifications at the location of the discharge and at other locations 33
16
-- 16 of 27 --
that may be affected by such discharge." 11
1
10 6 NYCRR § 703.2. 2 11 6 NYCRR § 701.1. 3
NYSDEC Decision at 12 & nn.10-11. The Decision added that 4
[c]umulatively, impacts to both small and large streams from the 5
construction and operation of the Project can be profound and include loss of 6
available habitat, changes in thermal conditions, increased erosion, creation of 7
stream instability and turbidity, impairment of best usages, as well as 8
watershed-wide impacts resulting from placement of the pipeline across water 9
bodies in remote and rural areas (See Project Description and Environmental 10
Impacts Section, above). Because the Department's review concludes that 11
Constitution did not provide sufficient detailed information including site 12
specific project plans regarding stream crossings (e.g. geotechnical borings) 13
the Department has determined to deny Constitution's WQC Application for 14
failure to provide reasonable assurance that each stream crossing will be 15
conducted in compliance with 6 NYCRR §608.9. 16
NYSDEC Decision at 12; see 6 N.Y.C.R.R. § 608.9(a)(2) ("The applicant" for a CWA § 401 17
certification "must demonstrate compliance with sections 301-303, 306 and 307 of the Federal Water 18
Pollution Control Act, as implemented by . . . water quality standards and thermal discharge criteria 19
set forth in Parts 701, 702, 703 and 704 of this Title . . . ."). 20
II. DISCUSSION 21
In its petition for review (or "Petition"), Constitution contends principally (1) that 22
NYSDEC failed to issue its Decision within a reasonable time as required by § 401 and thus must be 23
required to inform USACE that NYSDEC has waived its right to rule on Constitution's application 24
for a WQC, thereby enabling the Army Corps to grant Constitution a permit for its pipeline Project, 25
or (2) alternatively, that Constitution submitted sufficient information and that NYSDEC's decision 26
17
-- 17 of 27 --
should be vacated on the ground that its denial of the application was arbitrary, capricious, and ultra 1
vires, and that NYSDEC should be ordered to grant the requested § 401 certification. For the reasons 2
that follow, we (1) conclude that Constitution's first contention, which would have us treat NYSDEC's 3
Decision as an act that is void, lies beyond the jurisdiction of this Court, and (2) conclude that 4
NYSDEC's Decision was not ultra vires, arbitrary, or capricious. 5
A. Constitution's Argument that NYSDEC Waived Its § 401 Authority 6
The Natural Gas Act (or "NGA"), 15 U.S.C. §§ 717-717z, sets out provisions with 7
respect to, inter alia, the construction of transportation facilities for natural gas, see id. § 717f. Such 8
projects are also subject to restrictions under other federal statutes, including provisions of the Clean 9
Water Act, see, e.g., id. § 717b(d)(3). Section 401 of the CWA requires an applicant for a federal 10
permit to conduct any activity that "may result in any discharge into the navigable waters" of the 11
United States to obtain "a certification from the State in which the discharge . . . will originate . . . that 12
any such discharge will comply with," inter alia, the state's water quality standards. 33 U.S.C. 13
§ 1341(a)(1). 14
As to petitions for review relating to such applications, § 717r of the NGA divides 15
jurisdiction between the Circuit in which the facility is proposed to be constructed and the United 16
States Court of Appeals for the District of Columbia Circuit. It states, in pertinent part, as follows: 17
(1) In general 18
The United States Court of Appeals for the circuit in which a facility 19
subject to . . . section 717f of this title is proposed to be constructed . . . shall 20
have original and exclusive jurisdiction over any civil action for the review of 21
an order or action of a Federal agency (other than [FERC]) or State 22
administrative agency acting pursuant to Federal law to issue, condition, or 23
deny any permit, license, concurrence, or approval (hereinafter collectively 24
18
-- 18 of 27 --
referred to as "permit") required under Federal law . . . . 1
(2) Agency delay 2
The United States Court of Appeals for the District of Columbia shall 3
have original and exclusive jurisdiction over any civil action for the review of 4
an alleged failure to act by a Federal agency (other than [FERC]) or State 5
administrative agency acting pursuant to Federal law to issue, condition, or 6
deny any permit required under Federal law . . . . 7
15 U.S.C. §§ 717r(d)(1)-(2) (emphases added). We regard subsection (2)--titled "Agency delay"--as 8
encompassing not only "an alleged failure to act" but also an allegation that a failure to act within a 9
mandated time period should be treated as a failure to act. This is the nature of Constitution's first 10
argument. 11
Constitution points out that CWA § 401 provides that "[i]f" a "State . . . agency" from 12
which an applicant for a federal permit has sought a water quality certification "fails or refuses to act 13
on [the] request for certification, within a reasonable period of time (which shall not exceed one year) 14
after receipt of such request, the certification requirements of this subsection shall be waived with 15
respect to such Federal application." 33 U.S.C. § 1341(a)(1). Constitution argues that NYSDEC did 16
not issue its Decision until 32 months after Constitution submitted its initial application, 16 months 17
after NYSDEC issued notice that that initial application was complete, 15 months after the deadline 18
imposed by FERC, nearly a year ("359 days") after Constitution's 2015 withdrawal-and-resubmission 19
of its application--and eight months after Constitution claims it was advised by NYSDEC that 20
NYSDEC "had everything it needed to issue a Section 401 Certification." (Constitution brief in 21
support of Petition at 28-29.) Constitution argues that NYSDEC "waived its right" to rule on the 22
certification application and must be required to so notify the Army Corps. (Id. at 37.) 23
We note first that there is nothing in the administrative record to show that NYSDEC 24
19
-- 19 of 27 --
received the information it had consistently and explicitly requested over the course of several years-- 1
much less anything to support Constitution's claim that NYSDEC said "it had" all of the information 2
it required "to issue" the requested certification (id. at 29). Although Constitution proffered in this 3
Court non-record declarations from certain of its personnel, those "outside-the-record declarations and 4
associated portions of [Constitution]'s brief" were stricken. Constitution Pipeline Co. v. Seggos, No. 5
16-1568 (2d Cir. Oct. 3, 2016). 6
Second, Constitution's "waive[r]" argument is that the NYSDEC Decision must be 7
treated as a nullity by reason of NYSDEC's "failing to act within the prescribed time period under the 8
CWA" (Constitution brief in support of Petition at 37 (emphasis added)). Such a failure-to-act claim 9
is one over which the District of Columbia Circuit would have "exclusive" jurisdiction, 15 U.S.C. 10
§ 717r(d)(2). See generally Weaver's Cove Energy, LLC v. Rhode Island Department of 11
Environmental Management, 524 F.3d 1330, 1332 (D.C. Cir. 2008). Accordingly, we dismiss 12
Constitution's timeliness argument for lack of jurisdiction. 13
B. Constitution's Challenge to the Merits of NYSDEC's Decision 14
Judicial review of an administrative agency's denial of a CWA § 401 certificate is 15
limited to grounds set forth in the Administrative Procedure Act, 5 U.S.C. §§ 701-706. We review 16
the agency's interpretation of federal law de novo; if the agency correctly interpreted federal law, we 17
review its factual determinations under the arbitrary-and-capricious standard, see id. § 706(2)(A); 18
Islander East Pipeline Co. v. McCarthy, 525 F.3d 141, 150 (2d Cir. 2008) ("Islander East II"); 19
Islander East Pipeline Co. v. Connecticut Department of Environmental Protection, 482 F.3d 79, 94 20
(2d Cir. 2006) ("Islander East I"). 21
20
-- 20 of 27 --
1. Federal Law 1
Constitution argues that as a matter of law, NYSDEC's "jurisdiction to review"--and 2
"in effect, veto"--FERC determinations is preempted by FERC's performance of its obligations under 3
the National Environmental Policy Act ("NEPA"), 42 U.S.C. §§ 4321-4370h, to prepare a DEIS and 4
a FEIS. (Constitution brief in support of Petition at 37, 39.) We disagree that NYSDEC's action was 5
preempted. 6
Although NEPA requires federal-agency review of virtually any possible 7
environmental effect that a proposed action may have, see generally 40 C.F.R. § 1502.16, it does not 8
impose substantive standards. See Robertson v. Methow Valley Citizens Council, 490 U.S. 332, 350 9
(1989). "[T]hrough a set of action-forcing procedures," NEPA "require[s] that agencies take a hard 10
look at environmental consequences," but it is "well settled that NEPA itself does not mandate 11
particular results[; it] simply prescribes the necessary process." Id. (internal quotation marks omitted). 12
Thus, NEPA states, in pertinent part, that "[n]othing in section 4332 or 4333 of this title shall in any 13
way affect the specific statutory obligations of any Federal agency . . . to act, or refrain from acting 14
contingent upon the recommendations or certification of any . . . State agency." 42 U.S.C. § 4334. 15
We note also that while the Natural Gas Act generally preempts state laws, it states that 16
"[e]xcept as specifically provided[,] . . . nothing" in the NGA "affects the rights of States under . . . 17
the [CWA] (33 U.S.C. § 1251 et seq.)," 15 U.S.C. § 717b(d). CWA § 511, in turn, preserves the 18
states' authority to determine issues of a planned project's effect on water quality. See 33 U.S.C. 19
§ 1371(c)(2)(A). CWA § 401(a)(1) requires that an entity such as Constitution, proposing to construct 20
an interstate pipeline, obtain from each state in which the pipeline is to be constructed a certification 21
that "any . . . discharge" from a proposed activity "will comply with the applicable provisions of [33 22
21
-- 21 of 27 --
U.S.C. §§] 1311, 1312, 1313, 1316, and 1317." 33 U.S.C. § 1341(a)(1). Sections 1311, 1312, 1316, 1
and 1317 establish, and allow the Environmental Protection Agency ("EPA") to establish, standards 2
governing numerous aspects of water quality; and § 1313 allows states to develop their own water 3
quality standards and submit them to the EPA for approval. If the EPA approves a state's water 4
quality standards, it publishes a notice of approval and they become the state's EPA-approved 5
standards, regulating water quality in that state. See 33 U.S.C. §§ 1313(a), (c). 6
The New York State water quality standards, approved by the EPA, see generally 42 7
Fed. Reg. 56,786, 56,790 (Oct. 28, 1977), are found in 6 N.Y.C.R.R. parts 701 to 704, and were 8
invoked by the NYSDEC Decision, which stated that "[d]enial of a WQC may occur when an 9
application fails to contain sufficient information to determine whether the application demonstrates 10
compliance with the above stated State water quality standards and other applicable State statutes and 11
regulations due to insufficient information." NYSDEC Decision at 7; see also id. at 12 nn.10-11 and 12
accompanying text (quoted in Part I.C. above). The State standards classify waterbodies in terms of, 13
inter alia, potability and their suitability for various activities such as swimming and fishing, see 6 14
N.Y.C.R.R. pt. 701; they set standards for characteristics such as water odor, color, and turbidity, see 15
id. pt. 703; and they regulate thermal discharges into waterbodies, see id. pt. 704. 16
Thus, the relevant federal statutes entitled NYSDEC to conduct its own review of the 17
Constitution Project's likely effects on New York waterbodies and whether those effects would 18
comply with the State's water quality standards. 19
CWA § 401(a)(1), as pertinent here, states that "[n]o license or permit shall be granted 20
if [a § 401] certification has been denied by the State," 33 U.S.C. § 1341(a)(1). Thus, we have indeed 21
referred to § 401 as "a statutory scheme whereby a single state agency effectively vetoes an energy 22
22
-- 22 of 27 --
pipeline that has secured approval from a host of other federal and state agencies." Islander East II, 1
525 F.3d at 164 (emphases added); accord Keating v. FERC, 927 F.2d 616, 622 (D.C. Cir. 1991) 2
("Through [the § 401 certification] requirement, Congress intended that the states would retain the 3
power to block, for environmental reasons, local water projects that might otherwise win federal 4
approval." (emphasis added)). 5
Constitution also argues that NYSDEC's demands for information with regard to, e.g., 6
possible alternative routes for the planned pipeline (see, e.g., NYSDEC Decision at 3 (NYSDEC 7
"asked Constitution to analyze alternative routes that could have avoided or minimized impacts to an 8
extensive group of water resources")), as well as Constitution's planned blasting sites and the depth 9
at which the pipe would be buried, exceeded NYSDEC's authority (Constitution brief in support of 10
Petition at 38). We need not address all of these contentions. A state's consideration of a possible 11
alternative route that would result in less substantial impact on its waterbodies is plainly within the 12
state's authority. See, e.g., Islander East II, 525 F.3d at 151-52. And where an agency decision is 13
sufficiently supported by even as little as a single cognizable rationale, that rationale, "by itself, 14
warrants our denial of [a] petition" for review under the arbitrary-and-capricious standard of review. 15
See, e.g., id. at 158. 16
2. Application of the Arbitrary-and-Capricious Standard 17
Under the arbitrary-and-capricious standard, "[a] reviewing court may not itself weigh 18
the evidence or substitute its judgment for that of the agency." Islander East II, 525 F.3d at 150. 19
"Rather," we "consider[] whether the agency 'relied on factors which Congress has not intended it to 20
23
-- 23 of 27 --
consider, entirely failed to consider an important aspect of the problem, offered an explanation for its 1
decision that runs counter to the evidence before the agency, or is so implausible that it could not be 2
ascribed to a difference in view or the product of agency expertise.'" Id. at 150-51 (quoting Motor 3
Vehicle Manufacturers Ass'n of the United States, Inc. v. State Farm Mutual Automobile Insurance 4
Co., 463 U.S. 29, 43 (1983) ("State Farm")). 5
[W]ithin the prescribed narrow sphere, judicial inquiry must be searching and 6
careful. . . . Notably, a court must be satisfied from the record that the agency 7
. . . examine[d] the relevant data and articulate[d] a satisfactory explanation for 8
its action. . . . Further, the agency's decision must reveal a rational connection 9
between the facts found and the choice made. 10
Islander East II, 525 F.3d at 151 (internal quotation marks omitted). If there is "sufficient evidence 11
in the record to provide rational support for the choice made by the agency," we must uphold its 12
decision. Id. at 152. 13
Usually, the agency's choice concerns whether the applicant's submission of the 14
relevant information warrants the granting of the application. In the present case, as summarized in 15
Part I.C. above, NYSDEC denied Constitution's application because Constitution refused to provide 16
information that NYSDEC had repeatedly requested with regard to, inter alia, issues such as those 17
just discussed in Part II.B.1. above, and issues as to the feasibility, site-by-site, of trenchless methods 18
for most of the 251 stream crossings planned in New York. Constitution does not contend that those 19
requests were not made. Indeed, in its own brief in this Court, Constitution acknowledges that the 20
NYSDEC Decision (the "Denial") explained that NYSDEC had requested but had not received 21
sufficient information with regard to: 22
Ë construction methods and site-specific project plans for stream crossings 23
(Denial at 8-11 . . .); 24
Ë alternative routes (Id. at 11 . . .); 25
24
-- 24 of 27 --
Ë pipeline burial depth in stream beds (Id. at 12-13 . . .); 1
Ë procedures and safety measures Constitution would follow in the event that 2
blasting is required (Id. at 13 . . .); 3
Ë Constitution's plans to avoid, minimize, or mitigate discharges to navigable 4
waters and wetlands (Id. at 13-14 . . .); and 5
Ë cumulative impacts (Id. at 3, 5, 7, 14 . . .). 6
(Constitution brief in support of Petition at 21-22.) Nowhere does Constitution claim to have 7
provided the above categories of information; rather, it insists that it provided NYSDEC with 8
"sufficient" information (id. at 52-62) because use of trenchless crossing methods for streams less than 9
30 feet wide is not "an industry recognized standard" (Constitution 2015 Feasibility Draft at 1). 10
However, in order to show that an agency's decision--or its request for additional 11
information as to alternative methods--is arbitrary and capricious, "it is not enough that the regulated 12
industry has eschewed a given [technology]." State Farm, 463 U.S. at 49. Industry preferences do 13
not circumscribe environmental relevance. 14
In Marsh v. Oregon Natural Resources Council, 490 U.S. 360 (1989), the Supreme 15
Court considered whether a federal agency, presented with new evidence, should have been required 16
to file a new supplemental environmental impact statement; the Court stated that the matter of whether 17
additional information is "significant" is "a classic example of a factual dispute the resolution of 18
which implicates substantial agency expertise," as to which the courts "must defer to the informed 19
discretion of the responsible . . . agencies," id. at 376-77 (internal quotation marks omitted). We 20
cannot conclude that any less deference is due an agency's determination that it should not grant a 21
permit application where it has already determined that additional information is needed, and the 22
applicant refuses to supply it. Cf. University of Iowa Hospitals & Clinics v. Shalala, 180 F.3d 943, 23
25
-- 25 of 27 --
955 (8th Cir. 1999) (where agency regulations required substantiation of costs for which 1
reimbursement was sought, denial of reimbursement based on inadequate documentation was not 2
arbitrary and capricious); Mendoza v. Secretary, DHS, 851 F.3d 1348, 1356 (11th Cir. 2017) (denial 3
of visa application where applicants declined to answer relevant questions relating to eligibility was 4
not arbitrary and capricious; the applicants "were free to refuse to answer [the agency's] questions 5
. . . but they did so at their own peril"). Indeed, an agency's decision may be found "arbitrary and 6
capricious" for "issuing a permit with insufficient information." Utahns For Better Transportation 7
v. United States Department of Transportation, 305 F.3d 1152, 1192 (10th Cir. 2002) (emphasis 8
added). 9
Here, the record amply shows, inter alia, that Constitution persistently refused to 10
provide information as to possible alternative routes for its proposed pipeline or site-by-site 11
information as to the feasibility of trenchless crossing methods for streams less than 30 feet wide--i.e., 12
for the vast majority of the 251 New York waterbodies to be crossed by its pipeline--and that it 13
provided geotechnical data for only two of the waterbodies. 14
In sum, NYSDEC is responsible for evaluating the environmental impacts of a 15
proposed pipeline on New York waterbodies in light of the State's water quality standards. Applying 16
the arbitrary-and-capricious standard of review, we defer to NYSDEC's expertise as to the 17
significance of the information requested from Constitution, given the record evidence supporting the 18
relevance of that information to NYSDEC's certification determination. We conclude that the denial 19
of the § 401 certification after Constitution refused to provide relevant information, despite repeated 20
NYSDEC requests, was not arbitrary or capricious. 21
26
-- 26 of 27 --
CONCLUSION 1
We have considered all of Constitution's arguments and have found in them no basis 2
for granting the petition for review. Insofar as the petition contends that the NYSDEC Decision is 3
a nullity on the ground that it was untimely, the petition is dismissed for lack of jurisdiction; to the 4
extent that the petition challenges the NYSDEC Decision on the merits, the petition is denied. 5
27
-- 27 of 27 --