Brown v. Smith

CourtListener 10285689Coloctapp27 nov. 2024

Texte intégral

23CA1037 & 23CA1038 Brown v Smith 11-27-2024

COLORADO COURT OF APPEALS

Court of Appeals Nos. 23CA1037 & 23CA1038
City and County of Denver District Court No. 21CV30831
Honorable Alex C. Myers, Judge
Honorable Sarah B. Wallace, Judge

Brown & Caldwell, a California corporation,

Defendant-Appellee and Cross-Appellant,

v.

Smith Environmental & Engineering, Inc., a Colorado corporation,

Third-Party Defendant-Appellant and Cross-Appellee.

JUDGMENT AFFIRMED AND CASE
REMANDED WITH DIRECTIONS

Division II
Opinion by JUDGE FOX
Schock and Bernard*, JJ., concur

NOT PUBLISHED PURSUANT TO C.A.R. 35(e)
Announced November 27, 2024

Snell & Wilmer L.L.P., Michael E. Lindsay, James Kilroy, Ellie Lockwood,
Denver, Colorado, for Defendant-Appellee and Cross-Appellant

Lewis Roca Rothgerber Christie LLP, Kendra N. Beckwith, Joseph Hykan,
Denver, Colorado; Overturf McGath & Hull, P.C., David M. Bost, Lindsey W.
Jay, Denver, Colorado, for Third-Party Defendant-Appellant and Cross-Appellee

*Sitting by assignment of the Chief Justice under provisions of Colo. Const. art.
VI, § 5(3), and § 24-51-1105, C.R.S. 2024.
¶1 Third-party defendant, Smith Environmental & Engineering,

Inc. (Smith), appeals several pretrial rulings, the district court’s

judgment, and the jury’s verdict finding Smith liable to Brown &

Caldwell (B.C.) for damages incurred by the City and County of

Denver, acting by and through its Board of Water Commissioners

(Denver Water), after work performed by B.C. (Denver Water’s

contractor) and Smith (B.C.’s subcontractor) resulted in an

asbestos-containing-materials (ACM) spill during a reservoir

demolition project. B.C. cross-appeals one issue. We affirm and

remand the case with directions, so the district court may

determine the reasonable amount of B.C.’s appellate attorney fees.

I. Background

¶2 This appeal arises from a breach of contract dispute between

Denver Water, B.C., and Smith after an asbestos spill occurred

during demolition work at Denver Water’s Hillcrest water storage

facility in Denver, Colorado (Hillcrest).

¶3 When Denver Water sought to replace the existing facilities at

Hillcrest — constructed in the 1960s — it approached B.C. to

handle part of the project. B.C.’s obligations were memorialized in

a contract executed in August 2014 (the Prime Agreement).

1
¶4 Denver Water knew that the Hillcrest facilities contained ACM

that would need to be specially handled in the demolition. B.C.

thus subcontracted with Smith to prepare a report identifying

where asbestos and other hazardous materials were located within

the building (the Subcontract), so they could be properly handled

during demolition.

¶5 Brian Keyes authored the hazardous materials report for

Smith (the Smith Report or the Report). The Smith Report

identified several areas within Hillcrest that might contain ACM.

The Report included a review of Hillcrest’s original construction

plans to determine where asbestos might have originally been

placed. The Report included a diagram that used red boxes to

highlight “areas with suspect ACM” (the ACM diagram). A

reproduction of the ACM Diagram is depicted below with enlarged

references to the ordinal orientation of each wall.

2
The ACM Diagram
¶6 The ACM Diagram shows that ACM is suspected to be present

around the “box conduit” pipes running the entire length of the

reservoir’s northeast (NE) and southeast (SE) walls (toward the top

and right sides) in the form of “transite” panels containing cement

and asbestos. On the right side of the ACM Diagram, in a cross

section labeled “Section B,” there is a red box around the northwest

(NW) wall to the box conduit. This cross section is depicted with

two arrows labeled Section B. On the left of the ACM Diagram, at

the NW wall, there is an arrow pointing up toward the NE wall. On

3
this side of the ACM Diagram, there is no red box around the NW

wall or the Section B arrow. The other arrow appears on the SE

wall, similarly pointing up toward the NE wall. There is a red box

around the SE wall and the Section B label.

¶7 The Smith Report failed to identify a continuous strip of

transite panels that ran around the edge of the entire reservoir,

including along the southwest (SW) wall. Keyes stated in a

deposition that he “missed” the diagram’s reference to a continuous

strip of transite panels along the SW wall and did not mark it with a

red box in the Smith Report.

¶8 In April 2019, during demolition, Denver Water learned that

about 200 feet of transite panels were disturbed, and asbestos was

found in the soil and on the equipment used to “crush” concrete for

reuse. The resulting spill forced Denver Water to halt the project

and engage in asbestos remediation, causing delays and additional

costs for Denver Water’s demolition contractor.

¶9 In March 2021, Denver Water sued B.C. for breach of the

Prime Agreement, seeking the costs it incurred to mitigate the spill.

Soon after, B.C. filed third-party claims against Smith, alleging that

Smith (1) had breached the Subcontract, (2) had contractual and

4
common law indemnification duties, and (3) was required to defend

B.C.

¶ 10 The Prime Agreement made B.C. “responsible for the

professional quality, technical accuracy, timely completion, and

coordination of all studies, reports and other Work” covered by the

Prime Agreement, and B.C. agreed to conduct all work “with the

usual thoroughness and competence and in accordance with

generally accepted standards of care of [B.C.’s] profession prevailing

in Colorado and utilized by competent engineering firms.”

¶ 11 B.C. also “agree[d] to indemnify, defend, and hold [Denver

Water] harmless from and against any liability to the extent arising

out of the negligent errors or negligent omissions of [B.C.], its

agents, employees, or representatives, in the performance of [B.C.’s]

duties.”

¶ 12 The Subcontract, in turn, obligated Smith to “perform its

services with the standard of care, diligence and skill ordinarily

exercised by firms providing similar services and in accordance with

accepted and sound professional practices and procedures.”

¶ 13 The Subcontract also obligated Smith to

5
indemnify, defend and hold harmless Client,
[B.C.], their officers, directors, agents, and
employees (“Indemnitees”) from and against all
claims, damages, losses and expenses
(including attorneys’ fees and other legal
expenses) arising out of, or in connection with
any negligent act or omission, willful
misconduct or breach of contract by
Subcontractor, its employees, or others for
whom Subcontractor may be legally liable.

¶ 14 Finally, the Subcontract added that

[t]hose obligations [B.C.] has assumed to
[Denver Water] under the Prime Agreement,
which are applicable to [Smith’s] Scope of
Services herein, shall in turn be assumed by
[Smith] to [B.C.]

II. Procedural History

¶ 15 The most pertinent events in the case’s procedural history are

included in the timeline below.

6
Feb. 28,
Mar. 2022:
10, Denver Feb. 3,
2021: Water 2023:
Denver moves for Dec. 28, Court
Water partial 2022: issues
Sues summary Court Indemni-
B.C. judgment issues PSJ fication
(PSJ). Order. Order.

Apr. 16, June Jan. 11, Feb. 6,
2021: 30, 2023: 2023:
B.C. sues 2022: Smith Trial
Smith Court requests begins.
(Smith issues leave to
retains Duty to file
counsel Defend summary
May 6, Order. judgment.
2021).

Procedural History Timeline

¶ 16 In December 2021, B.C. moved for a determination of law

under C.R.C.P. 56(h) against Smith, requesting the court determine,

as a matter of law, that the Subcontract included a duty to defend

and that Smith assumed and breached its duty to defend B.C.

against Denver Water. Smith contended that the Subcontract did

not impose a duty to defend (nor a duty to indemnify) B.C. unless

and until the court made a finding of Smith’s fault, asserting that,

outside the insurance context, the scope of the duty to defend is

narrow.

7
¶ 17 Later, in February 2022, Denver Water moved for partial

summary judgment against B.C. Denver Water argued that there

was no genuine dispute of material fact that (1) B.C. had entered

into the Prime Agreement with Denver Water; (2) Denver Water had

performed its duties under the Prime Agreement; and (3) B.C. had

breached the Prime Agreement because Smith’s Report was

technically inaccurate and “did not comply with accepted industry

standards for asbestos inspections”; thus, B.C. was liable. Denver

Water attached the report of its expert, Robert Szynskie, with his

sworn affidavit, to support its motion.

¶ 18 B.C. soon filed a competing cross-motion for summary

judgment, arguing that Denver Water “failed to disclose an expert to

establish that B.C. breached the applicable standard of care” and

that Denver Water was not entitled to indemnification for damages

it suffered directly. Smith’s counsel entered an appearance on May

6, 2021, but Smith took no position on the competing summary

judgment motions.

A. The Duty to Defend Order

¶ 19 In June 2022, the district court ruled on B.C.’s Rule 56(h)

motion (the Duty to Defend Order). The court found that, even

8
outside the insurance context, Smith’s duty to defend B.C. was

triggered by Denver Water’s allegations implicating the Report and

Smith’s work. The court, relying on Lafarge North America, Inc. v.

K.E.C.I. Colorado, Inc., 250 P.3d 682, 688 (Colo. App. 2010), noted

that Smith undertook a duty to defend B.C. for Smith’s acts arising

out of, as relevant here, breach of the Subcontract.

¶ 20 Furthermore, the court found that the Subcontract

unambiguously imposed separate duties for Smith to defend and to

indemnify B.C. Rejecting Smith’s invitation to merge the two

duties, the district court declared that, as a matter of law, Smith

had a duty to defend B.C. against Denver Water’s claims, and Smith

had breached that duty.

B. The Partial Summary Judgment Order

¶ 21 In December 2022, the district court ruled on Denver Water

and B.C.’s competing motions for partial summary judgment (the

PSJ Order). In ruling on Denver Water’s motion, the court found

that Denver Water established that (1) a contract — the Prime

Agreement — existed between B.C. and Denver Water; (2) Denver

Water had substantially performed its duties under the Prime

9
Agreement; and (3) the Smith Report resulted in a breach of two

duties B.C. owed to Denver Water under the Prime Agreement.

¶ 22 As to the breach of B.C.’s first duty — that it was “responsible

for the professional quality, technical accuracy, timely completion,

and coordination of all studies, reports and other Work” — the

district court found the Smith Report was “not technically accurate

in that it failed to identify transite and assumed ACM from the

original construction drawings.” The court noted it was undisputed

that the Report missed some ACM areas despite them being “plainly

marked” in the original construction plans. Because B.C. was

responsible for the technical accuracy of its own and its

subcontractors’ reports and work, it had breached that duty.

¶ 23 For the second duty, the court found that B.C. also breached

its duty to conduct all work “with the usual thoroughness and

competence and in accordance with generally accepted standards of

care of [B.C.’s] profession prevailing in Colorado and utilized by

competent engineering firms.” While B.C. and Denver Water

disagreed about the applicable standard of care, Denver Water

supported its motion with unrebutted sworn expert testimony

concluding that the Report was inaccurate and that “neither Smith

10
nor [B.C.] complied with the generally acceptable standards of

care.”

¶ 24 The court added that B.C. filed no sworn testimony to rebut

these conclusions, and it rejected B.C.’s argument that Szynskie

could not testify to the applicable standard of care because he was

not a licensed engineer. The court noted that “[B.C.] represent[ed]

that all work w[ould] be performed in accordance with any generally

accepted standards of care (plural) of its profession . . . and utilized

by competent engineering firms . . . consistent with the scope of the

Agreement which include[d] engineering and non-engineering

services.”

¶ 25 Because the Prime Agreement covered both engineering and

non-engineering services (like asbestos inspections), the court noted

that construing the Prime Agreement to subject B.C. to only the

standard of care for professional engineers would be “unworkable.”

Thus, the district court accepted Szynskie’s testimony and, without

any contrary evidence, found B.C. had failed to meet the applicable

standard of care constituting a breach of the Prime Agreement.

¶ 26 The district court therefore granted Denver Water’s motion for

a determination of law that B.C. was liable to Denver Water for its

11
breach of the Prime Agreement — leaving only the question of

whether Denver Water suffered damages because of B.C.’s breach

for trial. The district court also rejected B.C.’s cross-motion for

summary judgment on Denver Water’s indemnification claim based

on competing evidence concerning the sources of Denver Water’s

damages, though the court agreed that Denver Water was limited to

indemnification damages for costs incurred by third parties only,

not other damages it directly incurred.

C. The Indemnification Order

¶ 27 In January 2023, Smith moved for leave to file a motion for

summary judgment against B.C., arguing that B.C. had failed to

disclose expert testimony that Smith violated the applicable

standard of care.

¶ 28 B.C. responded that Smith had failed to meet its contractual

duty to defend B.C. and that expert testimony on Smith’s standard

of care had no bearing on its claims against Smith. B.C., however,

did not oppose Smith’s request to file the motion if (1) it was able to

respond to it and file a competing summary judgment motion, and

(2) the district court resolved the issue before trial.

12
¶ 29 The district court, with Judge Sarah B. Wallace now

presiding,1 denied Smith’s motion but ordered expedited briefing on

two legal questions that it determined needed to be decided ahead

of trial:

(1) Whether Judge [Myers] explicitly or
implicitly has already ruled that Defendant
Smith is in breach of its indemnification
obligation based on his recent summary
judgment ruling or prior rulings. If not, is that
the necessary corollary of his rulings?

(2) If this issue has not already been decided
and [B.C.] must prove Smith’s breach, does
[B.C.] need an expert to prove Smith’s breach
and if so, must I grant judgment in Smith’s
favor?

¶ 30 In its briefing, Smith argued that the Duty to Defend Order did

not explicitly rule that Smith had breached its indemnification duty,

a duty distinct from the duty to defend. And Smith argued that the

PSJ Order never implicitly or explicitly found that Smith breached

its indemnification duty — despite finding that the Smith Report

1 Between the issuance of the PSJ Order and the Indemnification

Order, a division rotation in the district court replaced Judge Alex
C. Myers with Judge Sarah B. Wallace, who presided over the case
through the end of trial.

13
was technically inaccurate. According to Smith, expert testimony

was required to show that it breached the Subcontract.

¶ 31 B.C., in turn, argued that the necessary corollary of both

orders was that Smith breached its indemnification duty. B.C.

argued that the court’s finding that B.C. breached the Prime

Agreement was based on the deficient Report, and since the

Subcontract incorporated B.C.’s obligations in the Prime Agreement

for Smith’s services, Smith’s duty to indemnify B.C. was necessarily

triggered.

¶ 32 B.C. also noted that Smith was a party to the lawsuit and had

every opportunity, indeed a contractual obligation, to defend its

position — yet it never responded to Denver Water’s motion, and it

should be precluded from relitigating this issue. And, regardless,

expert testimony was not required to prove Smith breached the

standard of care.

¶ 33 On February 3, 2023, the district court orally ruled that the

PSJ Order’s conclusion that B.C. breached the Prime Agreement

“hinged exclusively on Smith’s [c]onduct” and the Report’s accuracy

(the Indemnification Order). The court also found that (1) Smith

“assumed [B.C.]’s obligations” under the Prime Agreement; (2) the

14
PSJ Order “found that [B.C.] breached its contractual obligations as

they relate to Smith’s work”; and (3) “Smith agreed to indemnify for

damages arising from its breach of contract.”

¶ 34 The court acknowledged that Smith wanted to present

evidence “that it was not negligent and that the Smith report was

technically accurate [but that] the time to do that was when [B.C.]

was defending [Denver Water’s] summary judgment motion.” The

court added that “[i]t was very obvious that Denver [Water] was

asking for summary judgment on issues that would directly impact

Smith’s liability, but Smith did not ask to participate in the briefing.

Instead, it sat on the sidelines.”

¶ 35 Because the Subcontract subsumed B.C.’s contractual

obligations to Denver Water and bound Smith to those same

obligations — including to provide an accurate report — and

because the PSJ Order found that B.C. had breached the Prime

Agreement based on the Smith Report’s inaccuracies, “it necessarily

follows that Smith breached the contract with [B.C.]” Smith’s

indemnification duty was therefore triggered.

¶ 36 The court ruled that “the necessary corollary to Judge Myers’

prior rulings is that Smith is liable to [B.C.] under its claim for

15
breach of contract and breach of indemnification with the amount

of damages to be determined at trial.”

¶ 37 Smith filed a motion to reconsider the ruling, arguing that the

court improperly conflated B.C.’s contractual obligations to Denver

Water with Smith’s obligations to B.C. and that Smith could now be

held liable for B.C.’s breaches of contract unrelated to Smith’s

conduct. Smith also argued that it would be prejudiced if denied

the opportunity to present a defense at trial.

¶ 38 The district court orally denied the motion for reconsideration,

clarifying that “the inevitable conclusion” of the Duty to Defend and

PSJ Orders was that Smith was liable but only for the work it

undertook. The court added, “I want to make it very clear that I

have absolutely not precluded evidence . . . [that B.C.] had

additional breaches beyond the Smith [R]eport,” and reiterated that

its ruling was limited to B.C.’s and Smith’s breach as it related to

the Report.

D. The Verdict and Post-Trial Motions

¶ 39 A jury heard Denver Water’s claims over five days of trial,

beginning on February 6, 2023. Before trial, Denver Water took the

position that it would be pursuing additional breach of contract

16
claims against B.C. beyond the breach related to the Report. When

B.C. and Denver Water finalized the jury instructions, Denver Water

first notified the court that it would not pursue breach of contract

claims other than those related to the Smith Report, noting in the

“simplified” joint proposed jury instructions that “Denver Water no

longer intends to seek[] a factual finding of liability from the jury on

the alleged additional breaches of the contract.”

¶ 40 The jury awarded Denver Water $1,257,926.67 for its claims

against B.C. and awarded B.C. $999,352.86 for its third-party

claims against Smith. After trial, B.C. and Smith filed separate

motions for judgment notwithstanding the verdict (JNOV).

1. B.C.’s JNOV Motion

¶ 41 In B.C.’s JNOV motion, it argued that the jury was erroneously

allowed to award damages on different, additional breaches when

Denver Water chose not to pursue any other claims for breach of

contract beyond the Smith Report breach. B.C. argued that

because Smith was required to indemnify B.C. for all damages

awarded to Denver Water, B.C.’s damages award against Smith

should have been amended to match Denver Water’s award.

17
¶ 42 Denver Water argued that the differing damages awards

resulted from B.C.’s failure to prove that all of the damages the jury

awarded to Denver Water were caused by Smith’s breach. Smith

made the same argument, adding that some of Denver Water’s

damages were caused by B.C.’s use of the Report.

¶ 43 The district court denied B.C.’s motion. It noted that despite

Denver Water’s supposed withdrawal of claims unrelated to the

Smith Report, the jury instructions (which B.C. consented to)

supported Denver Water’s pursuit of additional breach of contract

claims, noting that several instructions would have been

unnecessary if the only breach related to the Report. Thus, the

court declined to modify the damages award.2

2. Smith’s JNOV Motion

¶ 44 Smith also filed a JNOV motion requesting a new trial or a

reversal of the verdict. Smith argued that the Indemnification

Order should be vacated because a conflict between B.C. and Smith

prevented Smith from defending B.C. without undermining Smith’s

own claims. Smith also argued it was denied the right to litigate

2 The district court agreed, however, that B.C. was entitled to

prejudgment interest against Smith.

18
B.C.’s liability after B.C. failed to contest the PSJ Order with “due

diligence and reasonable prudence” by failing to rebut Denver

Water’s expert. Thus, Smith argued it was not bound by the PSJ

Order.

¶ 45 Alternatively, Smith argued that the Indemnification Order

should be vacated because the PSJ Order was granted in error,

contending that Szynskie could not have testified about the

applicable standard of care because he was not a licensed engineer,

and the court improperly assessed Szynskie’s credibility. Smith

also argued that the Indemnification Order was granted without

giving it an opportunity to dispute facts. Further, Smith argued

that B.C. and Smith’s standards of care differed.

¶ 46 Finally, Smith argued that the court’s decision to exclude

evidence that the spill occurred in an area marked by red boxes in

the Report was erroneous and that it should have been allowed to

dispute causation, so a new trial was warranted.

¶ 47 B.C. responded that Smith owed B.C. a duty to defend and

acted unreasonably; breached its duty to defend months before the

PSJ Order and did not contest the Duty to Defend Order; and had

every opportunity to litigate its liability but failed to do so. B.C. also

19
argued that the PSJ Order was proper, that the court properly

excluded Smith’s evidence about the spill’s location, and that any

error was harmless because Smith had amply questioned witnesses

on this topic.

¶ 48 The district court denied Smith’s motion, because Smith never

raised its conflict-of-interest argument ahead of trial and thus

waived it. Moreover, Smith was a party to the litigation from the

start and could have protected its interests.

¶ 49 Because Smith failed to challenge the PSJ Order, the court

found Smith waived any argument that it was improper. The PSJ

Order was based on the undisputed fact that the Report was

inaccurate. The court did not based its inaccuracy findings on

credibility determinations; it rejected B.C.’s arguments concerning

Szynzkie’s qualifications and granted summary judgment largely

because Szynzkie’s testimony was unrebutted.

¶ 50 Next, the district court found that Smith had ample

opportunity to contest its liability. Smith knew that the Report, and

its accuracy, were the crux of the PSJ Order, as the court noted,

“The fact that for trial strategy, [Smith] decided to not defend the

Smith Report does not equate to not having an opportunity to be

20
heard. . . . [T]he time to defend the Smith Report was prior to the

Court’s finding, as a matter of law, it was technically deficient.” It

also noted that no party asked to continue trial, so its expedited

briefing order was necessary.

¶ 51 The district court then found that the Indemnification Order

had not conflated the applicable standards of care. Rather, it found

that, because B.C. breached the Prime Agreement when it

submitted the inaccurate Report, Smith had therefore breached the

Subcontract, requiring Smith to indemnify B.C.

¶ 52 Finally, the district court rejected any suggestion that it

improperly limited Smith’s challenge to whether the spill occurred

in a red-boxed area. It understood Smith “was seeking an

admission from the Denver Water employee that the . . . Report was

not technically inaccurate because Denver Water should have

known that transite existed on the [NW] wall despite there not being

a red box calling it out.”

¶ 53 The PSJ Order, however, was based on the fact that the Report

was inaccurate, so the excluded testimony would therefore have

contradicted the PSJ Order. And Smith “presented considerable

evidence throughout the trial . . . that the asbestos spill fell within

21
one of the red boxes that [Smith] identified. The jury rejected that

defense.” As a result, the court found that the excluded testimony

would have been cumulative.

III. Issues on Appeal

¶ 54 Smith’s appeal raises several issues, namely that (1) the Duty

to Defend Order violated the Subcontract’s plain language; (2) the

Indemnification Order was improper; (3) the district court

erroneously excluded the red-box-causation evidence; and (4) the

district court wrongly amended the duty to defend judgment to add

a “new category of damages.”

¶ 55 On cross-appeal, B.C. argues that the district court erred by

allowing the jury to decide B.C.’s indemnification claim and

allowing the jury to award B.C. and Denver Water different amounts

of damages. B.C. also requests appellate attorney fees. Denver

Water initially joined this appeal but was dismissed on October 25,

2024, pursuant to the parties’ stipulation.

IV. Standard of Review

¶ 56 “We review a trial court’s summary judgment order de novo.”

Edwards v. New Century Hospice, Inc., 2023 CO 49, ¶ 14.

“Summary judgment is appropriate when the pleadings and

22
supporting documents establish that there is no genuine issue as to

any material fact and that the moving party is entitled to judgment

as a matter of law.” Gibbons v. Ludlow, 2013 CO 49, ¶ 11.

¶ 57 “The construction of a contract is a question of law” that we

review de novo. Boulder Plaza Residential, LLC v. Summit Flooring,

LLC, 198 P.3d 1217, 1220 (Colo. App. 2008); see also Mid Century

Ins. Co. v. Gates Rubber Co., 43 P.3d 737, 739 (Colo. App. 2002).

We must strive to effectuate the contracting parties’ intent, as

determined primarily from the contract’s language. E. Ridge of Fort

Collins, LLC v. Larimer & Weld Irrigation Co., 109 P.3d 969, 974

(Colo. 2005); Boulder Plaza, 198 P.3d at 1220-21.

¶ 58 To do this, we look to the language of the provision at issue,

giving the words and phrases used their plain and ordinary

meanings, and to any other related provisions so as to interpret the

contract in a way that harmonizes and gives effect to all its

provisions. E. Ridge, 109 P.3d at 974; Boulder Plaza, 198 P.3d at

1221; Mid Century, 43 P.3d at 739.

¶ 59 If, after applying these principles, we conclude that the

provision is unambiguous, we must apply it as written. B & B

Livery, Inc. v. Riehl, 960 P.2d 134, 136 (Colo. 1998); Mapes v. City

23
Council, 151 P.3d 574, 577 (Colo. App. 2006). A contract provision

is ambiguous “if it is fairly susceptible to more than one

interpretation.” Dorman v. Petrol Aspen, Inc., 914 P.2d 909, 912

(Colo. 1996) (citation omitted); accord E. Ridge, 109 P.3d at 974.

However, the mere fact that the parties express different opinions as

to the meaning of the provision does not itself establish ambiguity.

Cherokee Metro. Dist. v. Simpson, 148 P.3d 142, 146 (Colo. 2006); E.

Ridge, 109 P.3d at 974.

¶ 60 We may affirm the district court on any ground supported by

the record. City of Aurora v. Dep’t of Revenue, 2023 COA 17, ¶ 11.

V. Analysis

A. The Duty to Defend Order was Proper

¶ 61 Smith first argues that the Duty to Defend Order violated the

plain language of the Subcontract. According to Smith, until there

was a finding of liability, it had no duty to defend B.C. B.C.

counters that Smith’s obligation to provide a defense was triggered

by the allegations in Denver Water’s complaint.

1. The Subcontract’s Indemnity Clause

¶ 62 Recall that the indemnity clause, section VIII of the

Subcontract, provides that Smith “shall indemnify, defend and hold

24
harmless Client, [B.C.], their officers, directors, agents and

employees (“Indemnitees”) from and against all claims, damages,

losses and expenses (including attorneys’ fees and other legal

expenses) arising out of, or in connection with any . . . breach of

contract by Subcontractor.”3 We construe the indemnity clause

using the same principles that govern the interpretation of

contracts generally, reviewing them de novo. See E. Ridge, 109 P.3d

at 974; Boulder Plaza, 198 P.3d at 1221; Mid Century, 43 P.3d at

739.

2. Analysis of the Indemnity Clause

¶ 63 We conclude that the indemnity clause unambiguously

requires Smith to defend B.C. “from and against all claims . . .

arising out of, or in connection with” Smith’s breach of the

Subcontract. A “claim” is the “assertion of a right.” Black’s Law

Dictionary 311-12 (12th ed. 2024). Nothing in the definition

suggests that the claim must first be judicially recognized. Id. (A

claim is “any right to payment . . . even if contingent or

3 B.C.’s contract with Denver Water also had indemnity provisions,

but the parties agree that the subcontract’s provision is the
operative one here.

25
provisional.”); see also Trosper v. Wilkerson, 764 P.2d 375, 377

(Colo. App. 1988) (concluding that a tax audit was part of a “claim,

demand, or action” leading to a potential duty to indemnify). So the

district court did not need to adjudicate Smith’s liability before

concluding that Smith’s duty to defend was triggered. Rather, the

duty was triggered when B.C. demanded a defense after Denver

Water filed its complaint advancing “claims” related to B.C.’s and

Smith’s alleged contractual breaches.

¶ 64 Smith could have requested a judicial declaration concerning

its duty to defend B.C., see EMC Ins. Cos. v. Mid-Continent Cas. Co.,

884 F. Supp. 2d 1147, 1156 (D. Colo. 2012) (declaratory relief may

define the contractual obligations), or it could have agreed to defend

B.C. under a reservation of rights, see, e.g., Shelter Mut. Ins. Co. v.

Vaughn, 2013 COA 25, ¶ 7. It did neither. Rather, B.C. made the

first request for a determination concerning Smith’s duty to defend

on December 13, 2021, when it filed its Rule 56(h) motion. In the

Duty to Defend Order the district court ruled that Smith had a duty

to defend B.C. and that Smith breached that duty. Even with this

ruling, however, Smith did not assume B.C.’s defense.

26
¶ 65 Relying on Lafarge, 250 P.3d at 688, the district court

concluded that Smith’s duty to defend was triggered by the

allegations in Denver Water’s complaint because those allegations

could trigger (if proven) Smith’s obligation to indemnify B.C.

¶ 66 As noted, Denver Water’s Amended Complaint alleged that

Smith’s work was deficient because Smith failed to identify ACM at

the project site. Because the Smith Report failed to alert Denver

Water’s contractors to areas with ACM, their demolition activities

disturbed ACM; caused an asbestos spill that had to be remediated;

and created unexpected (and costly) delays, resulting in damages.

The district court concluded these allegations were sufficient to

trigger Smith’s duty to defend B.C., and because Smith had not

provided B.C. a defense, the court also concluded that Smith

breached it.

¶ 67 On appeal, Smith continues to argue that without establishing

Smith’s liability, its duty to defend B.C. was not triggered. But the

duty to defend is distinct from the duties laid out in the indemnity

clause. True, the duty to indemnify is typically not triggered until

liability is imposed. See Cyprus Amax Mins. Co. v. Lexington Ins.

Co., 74 P.3d 294, 299 (Colo. 2003) (examining duties to defend and

27
indemnify in an insurance context); see also Serna v. Kingston

Enters., 72 P.3d 376, 380 (Colo. App. 2002) (common law duty to

indemnify does not arise until the liability of the party seeking

indemnity results in damage). But the duty to defend may (and

often does) arise well before the duty to indemnify takes root.

Cyprus Amax, 74 P.3d at 299 (recognizing that the duty to defend is

broader than the duty to indemnify); Const. Assocs. v. N.H. Ins. Co.,

930 P.2d 556, 563 (Colo. 1996) (noting that “duty to defend arises

where the alleged facts even potentially” are covered).

¶ 68 The challenged indemnity provision is similar in principle to

the one examined in Public Service Co. of Colorado v. United Cable

Television of Jeffco, Inc., 829 P.2d 1280 (Colo. 1992), superseded on

other grounds by statute, Ch. 118, sec. 1, § 13-21-111.5(6), 2007

Colo. Sess. Laws 446-48. That provision stated that the indemnitor

would “save and hold harmless” the indemnitee “from and against

all claims, liabilities, causes of action, or other legal proceedings”

for damage or injuries to property or persons “in any way arising

out of, connected with or resulting from the exercise by [the

indemnitor] of the rights granted” by the contract. Id. at 1282

(emphasis omitted). The court observed that the clause referred to

28
“liabilities” and broadly covered such liabilities “in any way arising

out of, connected with or resulting from” the indemnitor’s exercise

of its contractual rights. Id. at 1283.

¶ 69 The Subcontract’s indemnity clause does not use the term

“liability,” but it broadly refers to “claims, damages, losses and

expenses” “arising out of, or in connection with” Smith’s acts and

omissions or contractual breach. The differences in the indemnity

clause here and the clause examined in Public Service (liability

versus “claims, damages, losses and expenses”) are not so

qualitatively different to persuade us that the two clauses are

functionally distinguishable.

¶ 70 Smith’s duty to defend was triggered so long as the damaged

party (Denver Water) alleged facts even potentially triggering the

obligation to indemnify. See Const. Assocs., 930 P.2d at 563;

Cyprus Amax, 74 P.3d at 299; Hecla Mining Co. v. N.H. Ins. Co., 811

P.2d 1083, 1089 (Colo. 1991). Denver Water’s complaint did so,

alleging that B.C. and Smith failed to identify areas with ACM,

thereby causing Denver Water to incur damages. See Cyprus Amax,

74 P.3d at 299 (whether the duty to defend is triggered is answered

by looking no further than the four corners of the underlying

29
complaint); Hecla Mining, 811 P.2d at 1089-90 (same); see also Am.

Econ. Ins. Co. v. Schoolcraft, 551 F. Supp. 2d 1235, 1239 (D. Colo.

2007) (the issue is a question of law) (applying Colorado law).

Therefore, the district court properly determined, on summary

judgment, that Smith had breached its duty to defend B.C.

3. Smith Waived its Conflict-of-Interest Argument

¶ 71 Smith next contends that a conflict of interest existed between

Smith and B.C. that prevented it from defending B.C. without risk

to its own defenses and that B.C. failed to conduct its defense with

“reasonable prudence and due diligence” by failing to present

competent testimony to rebut Denver Water’s summary judgment

motion. Smith argues that reversal is required. This issue was

unpreserved for appeal.

¶ 72 Smith never raised a conflict-of-interest issue before trial — it

first appeared in Smith’s JNOV motion after trial concluded. Smith

relies on Public Service Co. of Colorado v. Osmose Wood Preserving,

Inc., 813 P.2d 785, 788-89 (Colo. App. 1991), for this position,

which approvingly cited section 57(2) of the Restatement (Second) of

Judgments:

30
If there is a conflict of interest between the
indemnitee and the indemnitor regarding the
injured person’s claim against the indemnitee,
so that the indemnitor could not properly have
assumed the defense of the indemnitee, a
judgment for the injured person precludes the
indemnitor only with respect to issues
determined in that action as to which:

(a) there was no conflict of interest between the
indemnitee and the indemnitor; and

(b) the indemnitee conducted a defense with
due diligence and reasonable prudence.

Restatement (Second) of Judgments § 57(2) (Am. L. Inst. 1982).

¶ 73 The Restatement provides that conflicts of interest arise “when

the injured person’s claim against the indemnitee is such that it

could be sustained on different grounds, one of which is within the

scope of the indemnitor’s obligation to indemnify and another of

which is not.” Id. § 57(3).

¶ 74 But a conflict-of-interest claim is akin to an affirmative

defense or claim for avoidance that Smith should have raised

pretrial. See C.R.C.P. 8(c) (“Any mitigating circumstances to reduce

the amount of damage shall be affirmatively pleaded.”); see also

Town of Carbondale v. GSS Props., LLC, 169 P.3d 675, 681 (Colo.

2007) (“If a defense is not raised in the answer or through a

31
successful amendment of the answer, it is waived.”). Smith had

ample opportunity to explain to the court why it could not defend

B.C. due to this alleged conflict of interest — most notably when

Smith responded to B.C.’s Rule 56(h) motion.

¶ 75 Because Smith had to affirmatively raise this defense, it

waived this argument by first raising it in its JNOV motion. See

Hawg Tools, LLC v. Newsco Int’l Energy Servs., Inc., 2016 COA

176M, ¶ 43; see also Fid. Nat’l Title Co. v. First Am. Title Ins. Co.,

2013 COA 80, ¶ 51 (a defense raised for the first time in a post-trial

motion is not preserved for appellate review).

¶ 76 We therefore decline to review this contention on appeal.

B. The Indemnification Order was Proper

¶ 77 Smith next argues that the Indemnification Order was

improper because (1) Smith did not have adequate notice and an

opportunity to respond to Denver Water’s motion for summary

judgment or present its arguments before the Indemnification Order

was entered; (2) the district court erred by imposing an

indemnification duty on Smith when the PSJ Order did not address

causation; and (3) the Indemnification Order assumed that Smith

breached its duty of care while the PSJ Order did not address it,

32
and the jury impermissibly awarded damages for an unproven

breach.

¶ 78 As explained below, we disagree with each contention.

1. Smith Had Adequate Notice and an Opportunity to
Respond

¶ 79 According to Smith, the district court erred by relying on the

PSJ Order to grant summary judgment sua sponte in favor of B.C.

via the Indemnification Order, denying Smith a chance to present

contrary evidence. Smith contends it had insufficient notice and no

opportunity to respond. The record refutes this contention.

¶ 80 True, “[t]o protect the nonmoving party, the trial court must

provide an adequate opportunity to present legal argument and to

assert contested facts that would render summary judgment

inappropriate.” ISG, LLC v. Ark. Valley Ditch Ass’n, 120 P.3d 724,

730 (Colo. 2005). While Denver Water moved for summary

judgment against B.C., not Smith, it did so on the grounds that

B.C., via the Smith Report, breached the Prime Agreement. The

Report’s technical inaccuracy was Denver Water’s main argument

for partial summary judgment. Smith was a party, and Smith’s

counsel entered an appearance on May 6, 2021.

33
¶ 81 Smith also knew that the Subcontract required it to

“indemnify, defend and hold [B.C.] harmless” for all claims arising

out of a breach by Smith. Smith should have realized that if the

court held that B.C. breached the Prime Agreement because of the

Smith Report, Smith could readily be found in breach of the

Subcontract. And it has never been disputed that the Report was

inaccurate because it “missed” ACM areas.

¶ 82 Smith recognized the importance of the Report to its liability.

For example, in April 2022, Smith responded to Denver Water’s

motion for reconsideration concerning the district court’s refusal to

strike Smith’s expert’s report, arguing that Smith met the

applicable standards of care (rebutting Szynzkie’s report). Smith

wrote, “[W]hether Smith performed its work accurately is the fact in

issue in this litigation.” Smith also argued that it was “entitled to

defend” the allegation that Smith failed to accurately identify ACM

at the site, “regardless of the . . . relationships between the parties.”

And at a March 2022 discovery dispute conference, Smith’s counsel

announced that it intended to defend its conduct, noting, “I find it

very hard to believe that there wasn’t an expectation based on the

way things are pled . . . that Smith would certainly defend itself and

34
provide evidence to support that it was not negligent in the work

that it did, that it met its standard of care.” More importantly, in

June 2022, in the Duty to Defend Order, the district court found

that Smith was obligated to defend B.C.

¶ 83 Thus, Smith had months (from February 2022, when Denver

Water filed its motion for partial summary judgment, to December

2022 when the PSJ Order issued) to respond to Denver Water’s

summary judgment motion, especially after the court ruled that

Smith had an obligation to defend B.C. Yet Smith filed no

response. Instead, Smith waited until weeks before trial in January

2023 to take advantage of the PSJ Order’s ruling against B.C. to try

to absolve itself of its own liability. This shows that Smith made an

intentional choice — one that ignored its duty to defend B.C. no

less.

¶ 84 The district court did not grant B.C. summary judgment sua

sponte — it requested briefing on important legal issues ahead of

trial. And as the district court noted, the expedited briefing

schedule ahead of the Indemnification Order was necessary since

no party asked to continue the trial (scheduled to start February 6).

Smith had ample opportunity to respond to the district court’s

35
questions, and to respond to B.C.’s arguments, ahead of the

Indemnification Order.

¶ 85 The record refutes Smith’s contention that it had no adequate

opportunity to respond to Denver Water’s motion for summary

judgment or present its arguments before the Indemnification

Order. See ISG, 120 P.3d at 730 (“De novo review of the record in

summary judgment cases may reveal that the party against whom

summary judgment was entered was on notice of the matters of law

at issue and had an adequate opportunity to present legal

argument and evidence, despite technical irregularities.”). The

district court did not err.

2. The Indemnification Order Did Not Depend on the PSJ
Order Establishing Smith’s Breach

¶ 86 Next, Smith contends that the Indemnification Order ignored

the Subcontract’s indemnification language limiting Smith’s

responsibility for claims “arising out of” its acts or breaches of

contract, therefore, requiring causation. Because the PSJ Order did

not address causation, Smith contends that the Indemnification

Order erroneously concluded that Smith had to indemnify B.C.

before its liability was adjudicated.

36
¶ 87 According to Smith, the PSJ Order primarily determined that

B.C. breached the Prime Agreement because the Report was

inaccurate. It did not explicitly determine that Smith breached the

Subcontract or determine whether the Report’s inaccuracy caused

Denver Water’s damages, leaving the question of those damages for

trial. Smith argues that the PSJ Order did not address Smith’s

standard of care, whether the Report caused Denver Water’s

damages, or whether Smith breached the Subcontract. Thus, the

Indemnification Order could not have found, as it did, that the

necessary corollary of the PSJ and Duty to Defend Orders was that

Smith was obligated to indemnify B.C.

¶ 88 We conclude that the Indemnification Order’s outcome was a

logical conclusion given the PSJ Order’s findings concerning B.C.’s

breach of the Prime Agreement, and the resulting implications for

Smith’s liability. Indeed, there was no other possible result given

the plain language of the Prime Agreement and Subcontract. See E.

Ridge, 109 P.3d at 974; Boulder Plaza, 198 P.3d at 1221.

Consequently, the district court did not err by finding that the Duty

to Defend and PSJ Orders’ necessary implication was that Smith

37
breached the Subcontract and, thus, had to indemnify B.C. for

damages resulting from the Report’s deficiencies.

¶ 89 The Subcontract’s indemnification clause provided that Smith

“shall indemnify, defend and hold [B.C.] harmless,” against “all

claims . . . arising out of . . . [a] breach of contract” by Smith.

(Emphasis added.) Further, the Subcontract provided that B.C.’s

obligations to Denver Water “under the Prime Agreement, which are

applicable to [Smith’s] Scope of Services herein, shall in turn be

assumed by [Smith] to [B.C.]” Thus, Smith assumed any obligation

B.C. had to Denver Water related to Smith’s services, and Smith

agreed to defend and indemnify B.C. for any claims arising out of its

contractual breaches.

¶ 90 B.C.’s obligations to Denver Water included a “responsib[ility]

for the professional quality, technical accuracy, timely completion,

and coordination of all studies, reports and other Work performed

under this Agreement.” (Emphasis added.) Therefore, B.C. was

obligated to provide Denver Water an accurate report, and Smith, in

turn, was obligated to provide B.C. an accurate report under the

scope of its services. There is no dispute that the Report was

inaccurate by failing to highlight areas containing ACM.

38
¶ 91 Once the district court found that the Report was inaccurate,

and that B.C. breached the Prime Agreement, Smith had then

breached the same obligation it contractually assumed. That the

PSJ Order addressed B.C.’s and not Smith’s standard of care is

largely irrelevant on this point (though we address this point further

below) — the Report breached B.C.’s obligations, and Smith’s

assumed obligations, under the Prime Agreement. Thus, when the

jury determined the damages Denver Water incurred were because

of the Report, Smith was obligated to indemnify B.C.

¶ 92 The Indemnification Order found that the necessary corollary

of the Duty to Defend and PSJ Orders was that when B.C. breached

the Prime Agreement with the Smith Report, it “necessarily

followed” that Smith had breached the same obligation. The plain

language of the Prime Agreement and Subcontract support this

outcome. See E. Ridge, 109 P.3d at 974; Boulder Plaza, 198 P.3d at

1221. Because Smith was obligated to indemnify B.C. for the

resulting damages, the district court did not err.

39
3. Neither the Indemnification Order nor the Jury
Instructions Erroneously Assume Smith’s Breach of a
Standard of Care

¶ 93 Next, Smith contends that because the PSJ Order did not

address Smith’s standard of care, the resulting Indemnification

Order assumed an unproven breach of Smith’s standard of care.

Smith argues this resulted in jury instructions that improperly

informed the jury that it had breached its duty of care and allowed

the jury to award damages for either the Report’s inaccuracy or the

assumed breach of the standard of care. Smith argues this error

requires a new trial. We disagree.

¶ 94 “[T]he giving of an erroneous [jury] instruction constitutes

reversible error once prejudice is shown.” Walker v. Ford Motor Co.,

2017 CO 102, ¶ 21 (citation omitted). We “will deem an error

harmless, and thus will not reverse a judgment, unless the error

resulted in substantial prejudice to a party.” Id. “A court commits

error by giving an incorrect instruction ‘unless the error is cured by

the instructions as a whole.’” Brooktree Vill. Homeowners Ass’n v.

Brooktree Vill., LLC, 2020 COA 165, ¶ 51 (citation omitted). Smith

preserved this issue for appeal by tendering its own jury

instructions. See In re Estate of Chavez, 2022 COA 89M, ¶ 20.

40
¶ 95 Smith specifically highlights that B.C. agreed to conduct its

work “with the usual thoroughness and competence and in

accordance with generally accepted standards of care of [B.C.’s]

profession prevailing in Colorado and utilized by competent

engineering firms.” The Subcontract, in contrast, provides that

Smith’s standard of care was that it “shall perform its services with

the standard of care, diligence and skill ordinarily exercised by

firms providing similar services and in accordance with accepted

and sound professional practices and procedures.”

¶ 96 Arguing these standards are different, Smith posits that the

PSJ Order could not have found that Smith breached its duty of

care, and to the extent it did, it contradicted the plain language of

the Subcontract. While Smith assumed B.C.’s obligations related to

Smith’s scope of services, Smith argues that applying B.C.’s

standard of care for engineering firms to Smith would lead to an

absurd result by placing “a hazardous material assessment firm in

the role of an engineer” rendering its own standard of care under

the subcontract superfluous.

41
¶ 97 Smith points to Instructions 7 and 15 as evidence of the harm

this allegedly caused.4 Instruction 7 provided, in pertinent part,

The Court has found that [B.C.] breached its
contract with Denver Water in two respects:
(1) under the Agreement, [B.C.] is responsible
for the technical inaccuracy in the Smith
Report and has failed to take responsibility for
it; and (2) [B.C.] failed to meet the standard of
care required under the Agreement with
respect to the technical inaccuracy in the
Smith Report.

. . . The Court has found that [Smith] breached
its Subcontract with [B.C.] due to the
technically inaccurate Smith Report and
[Smith] failed to meet the standard of care
under the Subcontract with respect to the
technical inaccuracy in the Smith Report.

¶ 98 Instruction 15, in turn, provided that

The Court has already determined that [Smith]
owes [B.C.] indemnification for any damages
awarded to Denver Water against [B.C.] which
arise out of or are in connection with [Smith’s]
breach of its contract with [B.C.] due to the
technical inaccuracy contained in the Smith
Report and failure to meet the standard of
care.

4 Smith also posits that, given the district court’s post-trial order, it

was plain error for the court to have given Instructions 7 and 15.
But plain error review in civil cases — particularly of jury
instructions, C.R.C.P. 51 — is necessarily “confined to the most
compelling cases,” and this is not such a case. Robinson v. City &
Cnty. of Denver, 30 P.3d 677, 684-85 (Colo. App. 2000).

42
¶ 99 Smith contends that these instructions show that the jury was

allowed to find that Smith breached some other standard of care in

the Subcontract.

¶ 100 To the extent that the Indemnification Order found that Smith

breached a standard of care, however, we discern no error. And,

regardless, any such error would have been harmless.

¶ 101 The PSJ Order addressed B.C.’s mirror argument on this point

concerning the reference to “competent engineering firms” in the

Prime Agreement. The Prime Agreement did not solely hold B.C. to

the standard of care applicable to professional engineers because

the Prime Agreement encompassed both engineering and non-

engineering work. The parties’ intent was that B.C.’s work would be

“performed in accordance with any generally accepted standards of

care (plural) of its profession.” (Emphasis added.) The plain

language of the Prime Agreement supports this interpretation. See

E. Ridge, 109 P.3d at 974; Boulder Plaza, 198 P.3d at 1221.

¶ 102 The PSJ Order next found that, particularly in light of Denver

Water’s unrebutted expert testimony, B.C. failed to meet the

standard of care “utilized by competent engineering firms

in Colorado” because of the Smith Report. Because Smith assumed

43
B.C.’s obligations vis-a-vis the Smith Report — obligations that did

not depend on a standard for professional engineers — when B.C.

breached its duty via the Report, so did Smith. And this is precisely

why the district court rejected this argument in the Indemnification

Order.

¶ 103 Even if this was error, it would be harmless because,

considering the jury instructions as a whole, Smith was not

substantially prejudiced. See Walker, ¶ 21; see also Brooktree,

¶ 51. The jury instructions overwhelmingly directed the jury’s

attention to the key breach Smith committed — producing the

inaccurate Report.

¶ 104 Instruction 7 explains that Smith breached the Subcontract

because of the “technically inaccurate Smith Report and [Smith]

failed to meet the standard of care under the Subcontract with

respect to the technical inaccuracy in the Smith Report.” (Emphasis

added.) And Instruction 15 adds that Smith must indemnify B.C.

for damages arising “out of or . . . in connection with [Smith’s]

breach of its contract with [B.C.] due to the technical inaccuracy

contained in the Smith Report and failure to meet the standard of

care.” (Emphasis added.) These instructions are not telling the

44
jury to find that Smith breached an alternative duty of care under

the Subcontract — the breach concerned only the Report’s

inaccuracy.

¶ 105 The instructions do indicate that a possible breach of Smith’s

standard of care is an alternative to a breach for the technical

inaccuracy (though, as detailed above, this is not error). For

example, Instruction 15 provides that if the jury found Denver

Water was entitled to general damages from B.C. it also had to

determine if (1) those damages arose from the technical inaccuracy

in the Smith Report, and (2) the damages were the “natural and

probable consequence” of the Report’s inaccuracy. If the jury found

both conditions proven, then it was required to award B.C. damages

“which arise out of or . . . in connection with [Smith’s] breach of its

contract with [B.C.] due to the technical inaccuracy contained in

the Smith Report or failure to meet the standard of care.”

(Emphasis added.)

¶ 106 But Instruction 15 required the jury to only award B.C.

general damages if it found by a preponderance of the evidence that

“the damages you have awarded to Denver Water against [B.C.]

45
arose out of or in connection with the technical inaccuracy

contained in the Smith Report.”

¶ 107 As a result, the only issues the jury decided concerned B.C.’s

and Smith’s breaches as a result of the Smith Report — not Smith’s

other breaches of the standard of care. Even if an error occurred

with the jury instructions, when read as a whole, the instructions

did not substantively prejudice Smith, and any error was harmless.

See Walker, ¶ 21; see also Brooktree, ¶ 51.

C. The District Court Erroneously Excluded Smith’s Proffered
Causation Evidence, but the Error Was Harmless

¶ 108 Smith next contends that the district court erred by excluding

proffered evidence that would have shown that the Smith Report

warned of transite at a specific location along the NW wall. Smith

argues that the excluded evidence would have refuted evidence that

the Report’s inaccuracy caused Denver Water’s damages. Although

we conclude the court erred by excluding the evidence, we affirm

because the error was harmless.

1. Additional Facts

¶ 109 The challenged ruling occurred during Smith’s cross-

examination of Robert Mahoney, Denver Water’s chief engineering

46
officer. Displaying the ACM Diagram, Smith’s counsel inquired as

to whether the ACM Diagram included a red box — identifying ACM

— around the reservoir’s NW wall. He then asked, “On the far left

of this drawing that’s within the red box, do you see up in the upper

left-hand corner where it says ‘[NW] wall?’” Directing Mahoney to

Section B, counsel asked if “the area on the far right that’s boxed in

red actually belongs in the drawing on the [NW] wall?” The

reproduced ACM Diagram is below with references to Section B

enlarged and relevant language highlighted.

47
¶ 110 Denver Water objected. The court sustained the objection,

reasoning that the evidence went to liability, not damages or

causation, and that it “would prove the opposite of what Judge

[Myers] found, which was that there should have been a red box

there.”

2. Preservation and Standard of Review

¶ 111 B.C. argues that Smith did not preserve this argument. We

disagree. Without explaining its argument, B.C. contends that

Smith’s offer of proof did not specify the relevance and admissibility

of Mahoney’s testimony.5

¶ 112 To preserve an objection to excluded evidence, a party’s offer of

proof must show the evidence’s relevance and admissibility. Vu v.

Fouts, 924 P.2d 1129, 1131 (Colo. App. 1996). If a party raised “the

sum and substance of the argument it now makes on appeal,” the

argument is preserved. Madalena v. Zurich Am. Ins. Co., 2023 COA

32, ¶ 50 (citation omitted); see also CRE 103(a)(2).

5 B.C. cites the district court’s denial of Smith’s C.R.C.P. 59 motion

for a new trial, wherein the court found that “Smith never made a
factual proffer about testimony it would have elicited.” We need not
defer to this finding because we review preservation rulings de novo.
See In re Estate of Ramstetter, 2016 COA 81, ¶ 65.

48
¶ 113 Smith’s counsel first explained that the evidence “shows that

the area [where] they claim a spill occurred . . . is boxed in red to

warn them that there’s transite there . . . . [T]hey should have

known there was transite” in the spill area. Smith’s counsel further

argued that “[t]his [evidence] goes directly towards damages,” and

B.C.’s counsel added, “[I]t goes to causation, which is still open

game.”6 When the court asked how the evidence pertained to

causation, Smith’s counsel explained that “it proves that they

should have known if in fact it was true, [transite] was at the [NW]

wall,” and “it will absolutely prove that there is no causation.”

¶ 114 On appeal, Smith raises the same argument about damages

and causation. In addition to the above exchange, Smith moved for

a new trial, arguing that the court improperly excluded this

evidence. This is adequate preservation.

¶ 115 We review a district court’s exclusion of evidence for an abuse

of discretion. Wolven v. Velez, 2024 COA 8, ¶ 9. A district court

abuses its discretion when its decision is “manifestly arbitrary,

6 Despite siding with Smith at trial, B.C. changed its position on

appeal and now argues that the court properly excluded the
evidence.

49
unreasonable, or unfair.” Id. (citation omitted). We review de novo

whether an evidentiary ruling misapplied the law. Id. (citation

omitted). Finally, absent clear error, we defer to a district court’s

factual findings. French v. Centura Health Corp., 2022 CO 20, ¶ 24.

Clear error occurs if the finding “lacks support in the record” or

leaves us, “after a review of the entire evidence, with the firm and

definite conviction that a mistake has been made.” Briargate at

Seventeenth Ave. Owners Ass’n v. Nelson, 2021 COA 78M, ¶ 18 n.3

(citation omitted).

3. The Relevant Evidence Did Not Contradict the PSJ Order

a. Applicable Law

¶ 116 In Colorado, a plaintiff asserting breach of contract must prove

four elements by a preponderance of the evidence: (1) a valid

contract existed; (2) the plaintiff performed or justifiably failed to

perform under the contract; (3) the defendant failed to perform

under the contract; and (4) the defendant’s failure to perform

caused the plaintiff’s damages. Univ. of Denver v. Doe, 2024 CO 27,

¶ 46. We consider the fourth element, causation, here.

¶ 117 Although “proof of actual damages is not an essential element

of a claim for breach of contract,” Overland Dev. Co. v. Marston

50
Slopes Dev. Co., 773 P.2d 1112, 1114 (Colo. App. 1989), recovering

actual damages requires proof that the plaintiff “suffered a loss

resulting from the defendant’s actions,” Isaac v. Am. Heritage Bank

& Tr. Co., 675 P.2d 742, 745 (Colo. 1984) (emphasis added). The

plaintiff must offer “evidence of both the existence and the cause of

damages,” such that the damages are “traceable to and the direct

result of the wrong sought to be redressed.” City of Westminster v.

Centric-Jones Constructors, 100 P.3d 472, 477-78 (Colo. App. 2003)

(citation omitted).

¶ 118 Once a plaintiff establishes a prima facie breach of contract

case, a defendant may present evidence to rebut the plaintiff’s

claim. W. Distrib. Co. v. Diodosio, 841 P.2d 1053, 1058 (Colo.

1992). To be admissible, the rebuttal evidence must be relevant,

see CRE 402, meaning it “tends to prove or disprove a fact in issue,”

In re Marriage of Turilli, 2021 COA 151, ¶ 13.

b. Analysis

¶ 119 B.C. argues that Smith’s proffered evidence was inadmissible

because it did not pertain to disputed facts and contradicted the

PSJ Order. Granting partial summary judgment, the district court

found for Denver Water on the first three elements of its breach of

51
contract claim. On the third element, failure to perform, the court

held that the Smith Report’s technical inaccuracies constituted a

breach. Specifically, it found the Report technically inaccurate for

“includ[ing] an annotated construction drawing with red boxes that

depict areas containing assumed ACM when the same annotated

drawing fails to depict red boxes for equally identifiable areas with

assumed ACM.” The fourth element, “whether Denver Water was

damaged as a result of this breach . . . remain[ed] a contested issue

for trial.” (Emphasis added.)

¶ 120 Before Denver Water was dismissed from this appeal by

stipulation, it cited the district court’s factual finding that the

Report did not include a red box highlighting “assumed ACM along

the [SW] wall. Other original construction drawings also show the

location of this transite, including along the [NW] wall. The location

of this transite was not specifically called out as assumed ACM

anywhere in the Smith Report.” Denver Water argued that Smith’s

attempt to offer evidence of a red box around Section B contradicted

the court’s conclusion that the Report failed to identify transite at

that wall. Smith responded that the court’s finding pertained only

52
to the SW wall and that it made no specific findings about the NW

wall or Section B.

¶ 121 For several reasons, we conclude that the court erroneously

excluded this evidence. First, while the above-cited language, in

isolation, suggests that the court was referring to missed transite at

the NW wall, in context that is less clear:

Mr. Keyes failed to specifically identify
additional transite . . . along the [SW] wall . . . .
[He] testified . . . that this reference to transite
is something that he “missed”. . . . [A] red box
was not added . . . to highlight this finding of
assumed ACM along the [SW] wall. Other
original construction drawings also show the
location of this transite, including along the
[NW] wall. The location of this transite was not
specifically called out . . . anywhere in the
Smith Report. . . . While the Smith Report did
not specifically identify this transite, [it] also
did not state that areas [without red boxes]
were free of ACM or suspected ACM.

(Emphases added.)

¶ 122 The court repeatedly referenced “this” transite without

clarifying exactly which transite it meant. Because the preceding

sentence explicitly called out the SW wall, it is at least plausible

that the court’s reference to “this transite” along the NW wall

referred to transite on the SW wall that abuts, but is not on, the NW

53
wall. It is similarly unclear whether the court’s reference to the NW

wall included Section B or only pertained to the ACM Diagram’s

larger image of the wall.

¶ 123 Further, the above-quoted portion of the court’s order is from

its factual findings. In the analysis section, the court ruled that the

Smith Report was technically inaccurate and therefore constituted a

breach, because it identified some assumed ACM and missed other

“equally identifiable areas with assumed ACM.” We understand the

court’s legal conclusion to be that the general failure to identify

some assumed ACM resulted in a breach, not that the damages

resulted from specific unidentified transite.

¶ 124 We hesitate to conclude that the PSJ Order explicitly found

the Report inaccurate for failing to identify suspected ACM on the

NW wall given the red box around Section B, clearly referencing the

NW wall. If the district court found that the Report failed to identify

possible ACM at the NW wall, that finding would lack record

support and is not entitled to deference. See French, ¶ 24.

54
¶ 125 Moreover, Smith did not offer the challenged evidence to

dispute the court’s ruling that the Report was inaccurate.7 Rather

than disputing the Report’s accuracy, Smith argued that the

Report, regardless of its inaccuracies, did not cause the asbestos

spill or Denver Water’s damages. Finally, the fact that the Report’s

mistakes established a contractual breach did not preclude

arguments at trial about those inaccuracies when a key remaining

issue was whether they caused Denver Water’s damages. Therefore,

Smith’s attempt to highlight the red box around the NW wall as

depicted in Section B did not directly contradict the PSJ Order.

¶ 126 Second, this evidence was relevant to “whether Denver Water

was damaged as a result of [the] breach,” which was “a contested

issue for trial.” The district court misapplied the law when it

reached a contrary conclusion. Specifically, the court found that

the proffered evidence “goes towards liability” rather than damages

7 In denying Smith’s Rule 59 motion, the court construed Smith’s

proffer as an attempt to argue that “the Smith Report was not
technically inaccurate because Denver Water should have known
that transite existed on the [NW] wall despite there not being a red
box calling it out.” We disagree. Smith attempted to show that,
regardless of other inaccuracies, there was a red box calling out
ACM at the NW wall.

55
and said, “It’s not a negligence claim,” in response to B.C. and

Smith’s argument that the evidence went to causation.

¶ 127 In so holding, the court conflated liability for breach with

liability for damages. Whether the Smith Report’s inaccuracies

constituted a contractual breach and whether they caused Denver

Water’s damages are different issues. See Overland, 773 P.2d at

1114 (finding a breach does not support an actual damages award

absent proof of causation). The court’s reference to negligence also

suggests that it did not view causation as a required element. To

recover more than nominal damages, Denver Water had to prove

that its loss resulted from the breach — i.e., the Report’s

inaccuracy. See Isaac, 675 P.2d at 745.

¶ 128 If the spill occurred at the NW wall, and if the Report warned

of ACM at that specific location, Smith’s evidence was relevant

because it tended to disprove the disputed causation. See Turilli,

¶ 13. Denver Water had to prove that the breach caused its

damages.8 See Centric-Jones Constructors, 100 P.3d at 478. Smith,

8 The jury instructions reflect this burden.
To award general (rather
than nominal) damages, the jury had to find that Denver Water’s
damages were “the natural and probable consequence of” the Smith
Report’s technical inaccuracy.

56
in turn, could seek to rebut causation. See Diodosio, 841 P.2d at

1058. The court’s ruling excluding this evidence rested on a

misinterpretation of the law and was therefore erroneous. See

Wolven, ¶ 9.

4. The Evidence was not Inadmissible under CRE 403

¶ 129 Relevant evidence is not automatically admissible. Instead,

otherwise relevant evidence may be excluded if “its probative value

is substantially outweighed by the danger of,” as pertinent here,

“confusion of the issues, or misleading the jury, . . . or needless

presentation of cumulative evidence.” CRE 403. However, because

the rules strongly favor admission, we afford evidence “its maximal

probative weight and its minimal prejudicial effect.” Murray v. Just

In Case Bus. Lighthouse, LLC, 2016 CO 47M, ¶ 19.

¶ 130 Here, B.C. argues that the excluded evidence was cumulative

of Smith’s other attempts to rebut causation. Smith refutes this

contention, arguing that it was unable to present any evidence

about Section B or that the Report specifically warned of transite at

the NW wall. The challenged evidence was not so needlessly

cumulative as to warrant exclusion under CRE 403. However,

because Smith had various opportunities to show that the Report

57
warned of possible ACM at or near the spill’s location, we conclude

that the evidence’s exclusion was harmless.

¶ 131 The record reflects confusion about the spill’s location. When

Smith questioned Mahoney about Denver Water initially reporting

the spill at the NE corner, Mahoney said, “[O]ne person calls it [NE]

corner and one calls it a [NW] corner, yet it doesn’t mean your

terminology is the same.” Similarly, Bowers testified that he and

his supervisor “had difficulty understanding the orientation of this

site. He was often confused of the locations,” and his supervisor

often “refer[red] to one side that was incorrect.” There was also

conflicting evidence about whether the spill occurred at the NW-NE

corner or the NW-SW corner.

¶ 132 While we do not weigh conflicting evidence, see Luster v.

Brinkman, 205 P.3d 410, 415 (Colo. App. 2008), this confusion

helps persuade us that the court’s error in excluding the evidence

was harmless. Given the discrepancies concerning whether the

spill occurred at the NE or NW walls, Smith’s original strategy was

to suggest that the Smith Report warned of transite at both

locations. After the court excluded the challenged evidence, Smith

pivoted to suggesting that (1) the spill occurred at the NE wall,

58
which was boxed in red; or (2) if the spill was at the NW wall, the

Report’s general warnings about suspected ACM challenged

causation.

¶ 133 Smith “presented considerable evidence . . . in its attempt to

convince the jury that the asbestos spill fell within one of the red

boxes.” Despite discrepancies about whether the spill occurred at

the NE wall or the Report warned of suspect ACM at the NW wall,

other evidence largely suggested that the spill was at the NW wall.

¶ 134 While the court did not allow Smith to offer evidence of a

specific warning of ACM at the NW wall, it allowed some evidence

that the Report generally warned of ACM at that wall. For example,

on cross-examination, Bowers confirmed that the Report noted “the

potential for additional suspect materials to also be present

underground.” Smith’s counsel then asked if this language

“indicated that there would be other areas of transite buried . . .

[including at] the [NW] wall?” After the court overruled Denver

Water’s objection, Smith’s counsel asked whether the Report’s

language meant that ACM could be anywhere at the project site,

including the NW wall, and Bowers agreed. The general warnings

were not necessarily cumulative of Section B’s specific warning, but

59
Smith was not entirely precluded from arguing that the Report

warned of ACM at the NW wall. Additionally, given the confusion

about the spill’s location, Smith offered an alternative argument

that the spill occurred within the red box at the NE wall.

¶ 135 Finally, the testimony Smith sought to elicit would not have

confused or misled the jury. See CRE 403. A limiting instruction

could mitigate any danger of misleading the jury about Smith’s

liability for failing to identify suspected ACM in the Report.9 That

Section B warned of ACM at the NW wall does not negate the

Report’s other inaccuracies. Denver Water could argue that the

Report’s failure to place a red box around all references to the NW

wall was an inaccuracy that caused its damages. The proffered

evidence also would not have been confusing, particularly

considering the evidence Denver Water presented. For example, on

redirect examination, Bowers answered “no” to each of the following

questions:

¶ 136 Q: “Is there a box around the [NW] wall?”

9 The instruction on damages and causation could clarify that

evidence disproving causation negates actual damages only, not
liability for the technical inaccuracies and breach.

60
¶ 137 Q: “Is there a red box around the areas where the potholes

indicated that transite had been disturbed?”

¶ 138 Q: “Do you have any reason to believe that transite was

disturbed within the red boxes?”

¶ 139 Similarly, Szynskie agreed that the Smith Report “fail[ed] to

identify transite at the footer of the [NW] wall” and that, if transite

had been disturbed there, asbestos “was not identified in any of the

materials provided by [B.C].” We do not see how evidence refuting

Bowers’s and Szynskie’s testimony would confuse the jury. See

Diodosio, 841 P.2d at 1058. Because Smith’s evidence was

probative of causation and any possible prejudice was slight,

exclusion under Rule 403 was not warranted. See Murray, ¶ 19.

Nevertheless, the fact that the challenged evidence was excluded

does not require reversal.

5. The Error Was Harmless

¶ 140 We reverse erroneous evidentiary rulings only if the error is

not harmless. Id. at ¶ 56. We cannot say that the district court’s

erroneous exclusion of Smith’s proffered evidence “substantially

influenced the outcome of the case.” Id. (citation omitted). As

noted, Smith was able to argue that the Report’s inaccuracies did

61
not cause Denver Water’s damages. And, even if Smith had

introduced testimony concerning the red box around Section B and

connected this to part of the NW wall, we cannot say that the jury

would have found a lack of causation.

¶ 141 First, because it is unclear which parts of the NW wall Section

B depicts, and because the evidence was unclear as to where

exactly the spill occurred, the red box may not have included the

part of the wall where the spill supposedly occurred. Second, there

was no red box around the largest and most obvious image of the

NW wall in the ACM Diagram. The jury heard evidence that there

was transite “going around the walls of the reservoir.” Thus, even if

the court had admitted Smith’s proffered evidence, the jury could

have found that failing to also place a red box around most of the

NW wall was an inaccuracy that caused Denver Water’s damages.

¶ 142 We also note that no party has appealed the judgment against

B.C. in favor of Denver Water. That judgment obligated B.C. to pay

for any damages found to be attributable to the Smith Report,

regardless of any separate argument Smith might have made about

causation on its own behalf.

62
¶ 143 Although the district court erred by excluding the proffered

evidence, we affirm because the error was harmless.

D. The Amended Duty to Defend Judgment was Proper

¶ 144 Smith’s final challenge is that that the district court erred

when it amended the duty to defend judgment to add a “new

category of damages.” Following trial, as relevant here, the district

court issued an indemnification judgment in B.C.’s favor on March

2, 2023, and a duty to defend judgment on April 28, 2023.

¶ 145 B.C. asked, pursuant to C.R.C.P. 59(a), that the court amend

the April 28 judgment to include the costs awarded to Denver Water

against B.C. Despite Smith’s opposition, the court amended that

judgment to include $323,010.07 of the costs it had awarded to

Denver Water. Smith now challenges that award.

¶ 146 According to Smith, Rule 59 — whose purpose is to give the

court an opportunity to correct its own mistakes — is not the

appropriate vehicle for the court to entertain B.C.’s untimely

request for a new category of damages (related to Smith’s

indemnification duties), especially when B.C. had ample

opportunity to request those damages earlier in the case. B.C.

disagrees with Smith’s characterization of its request and urges us

63
to conclude that the district court acted entirely within its

discretion in amending the April 28 duty to defend judgment.

1. Standard of Review and Legal Framework

¶ 147 We review a district court’s decision to amend findings under

Rule 59 for abuse of discretion. Skyland Metro. Dist. v. Mountain W.

Enter., LLC, 184 P.3d 106, 115 (Colo. App. 2007).

¶ 148 A party seeking relief under Rule 59(a) must file a timely

request for that relief. Schuster v. Zwicker, 659 P.2d 687, 689

(Colo. 1983) (recognizing that a court may not enlarge the time to

file if the request is not filed within the period specified in the rule);

accord Przekurat v. Torres, 2016 COA 177, ¶ 52, aff’d, 2018 CO 69.

2. Denver Water’s Fees and Costs

¶ 149 The April 28 duty to defend judgment consisted of B.C.’s

attorney fees and costs incurred in defending against Denver

Water’s claims (totaling $942,717.94). B.C. promptly requested an

extension of time to address the April 28 duty to defend judgment

(which the court granted) and then timely requested, from Smith,

64
$323,010.37 of the costs the court had awarded to Denver Water

(from B.C.) on April 6, 2023.10

¶ 150 The court later issued an order, dated May 23, 2023,

amending the March 2 and April 28 judgments as follows:

Judgment Date Damage Category Amount
March 2 Jury verdict $999,352.86
March 2 Prejudgment interest $262,559.20
March 2 Postjudgment interest $276.58/day
April 28 Attorney fees & costs $942,717.94
April 28 Prejudgment interest $69,143.02
April 28 Postjudgment interest $292.57/day
April 28 Denver Water’s costs $323,010.37

¶ 151 According to Smith, per Rule 59(a)(4), B.C. could not ask the

district court to amend the March 2 duty to indemnify judgment

after March 16, 2023, and B.C. had until May 2, 2023, to seek any

amendment to the April 28 duty to defend judgment. But until the

court awarded costs to Denver Water (on April 6), B.C. could not

request a specific amount from Smith as covered by the

10 B.C. calculated its “proportionate share” of Denver Water’s costs

to be $323,010.37, presumably to reflect that the jury allocated
some responsibility to B.C., given the difference in the verdict
against B.C. versus the verdict against Smith. Denver Water
requested and was awarded $403,762.97. Of that total,
$330,647.17 was for Denver Water’s experts.

65
Subcontract’s indemnity clause (admittedly, B.C. could have

requested the category of damages with the amount to be later

determined).

¶ 152 In any event, B.C. was granted until May 12, 2023, to file its

Rule 59 motion, and B.C. met the court’s extended deadline. All

three parties filed a flurry of post-trial motions soon after the

verdict was entered, and the district court did an admirable job in

addressing the various claims of error and damage adjustments.11

Because the district court had broad discretion to grant the

requested extension, see Schuster, 659 P.2d at 689, we cannot say

its amendments were improper.

11 Had Smith timely assumed the duty to defend (with or without a

reservation of rights), it could have assumed control over the course
of the litigation and availed itself, as it later suggested B.C. should
have done, of exploring a reasonable settlement before all parties
expended the enormous resources they did. See, e.g., Advanced
Ground Sys. Eng’g, Inc. v. RTW Indus., Inc., 388 F.3d 1036, 1041
(7th Cir. 2004) (recognizing that an indemnitor has the choice of
defending under a reservation of rights or staying “out of the
lawsuit,” thus gambling “that its interpretation of the scope of the
indemnity clause” will prevail; and, if it loses the gamble, it is
responsible not only for the defense costs, but also for the sums the
indemnitee must pay). The duty to defend serves, in part, to avoid,
or at least minimize, liability before it is established. See Certain
Underwriters at Lloyd’s of London v. Superior Ct., 16 P.3d 94, 101
(Cal. 2001); Nitto v. Fairbrother, No. 20-CV-6660-MJP, 2023 WL
2142146, at *14 (W.D.N.Y. Feb. 21, 2023) (unpublished order).

66
E. B.C.’s Cross-Appeal

¶ 153 B.C.’s cross-appeal argues that the district court erred in

allowing the jury — not the court — to decide its indemnification

claim against Smith. B.C. argues that the district court should

have entered judgment as a matter of law that B.C. is entitled to

damages against Smith equaling the full amount of damages that

were awarded to Denver Water and that it is entitled to 100% of the

costs and interests awarded to Denver Water (rather than a

proportionate share as detailed above in Part V.D).

¶ 154 Smith counters that Denver Water reserved its right to pursue

additional breaches by B.C. And, because the jury heard evidence

of, and reached a verdict concerning, B.C.’s additional breaches,

Denver Water was entitled to all its proven damages.

¶ 155 It is true that at various points in the case, including at the

very beginning of trial, Denver Water unequivocally expressed its

intent to proceed on its theory that B.C. committed “other breaches”

not included in the PSJ Order. But Denver Water later affirmatively

gave notice that it was only advancing the breach for the technical

inaccuracy of the Report that was the subject of the PSJ Order.

Denver Water repeated its position in the verdict form it and B.C.

67
submitted jointly, “Denver Water no longer intends to seek[] a

finding of liability from the jury on the alleged additional breaches

of contract.” Rather, Denver Water and B.C. agreed that any

arguments on other breaches would relate only to causation. The

joint proposed verdict form read as follows:

To the Jury: You are instructed to answer the
following questions. You must apply the law
in the instructions that the Court gave you to
the facts that were proved by the evidence.
You must all agree on your answer to each
question and you must all sign the completed
form on the signature lines.

We, the jury, present our Answers to the
following Questions submitted by the Court, to
which we have all agreed:

I. Denver Water’s Claim Against [B.C.]

QUESTION NO. 1: State the total amount
of damages you decide should be
awarded to Denver Water for its claim
against [B.C.]:

AMOUNT: ______________________

II. [B.C.]’s Claim Against [Smith]

QUESTION NO. 2: State the total amount
of damages you decide should be
awarded to [B.C.] for its claim against
[Smith]:

AMOUNT: ______________________

68
¶ 156 While the jury awarded more damages against B.C. than

against Smith, the parties created the opportunity for the jury to do

so based on the evidence they presented and their closing

arguments. Their supposedly “simplified” (and stipulated) verdict

form confused the jury about how to reconcile the different lines for

damages against B.C. and against Smith, given the language of

Instruction 7.

¶ 157 That instruction informed the jury that B.C. had breached its

contract with Denver Water in two respects: (1) B.C. was

“responsible for the technical inaccuracy of the Smith Report and

has failed to take responsibility for it,” and (2) B.C. failed to “meet

the standard of care under the Agreement with respect to the

technical inaccuracy in the Smith Report.” The jury also learned

that Smith breached its subcontract with B.C. due to the

“technically inaccurate” Report and by failing to “meet the standard

of care” with respect to the inaccuracy.

¶ 158 During trial, Denver Water argued that B.C. had opportunities

to correct Smith’s error, including as part of its quality control

obligation. In closing argument, Denver Water and Smith argued

69
about B.C.’s other breaches.12 But the jury was never asked, as a

prior draft jury instruction (later withdrawn) did — to specify

whether B.C. committed other breaches vis-a-vis Denver Water. To

be sure, Denver Water’s concession simplified the trial and the

jury’s duty. But after Denver Water’s strategic choice and B.C.’s

acquiescence in that choice, the district court cannot be faulted for

not requiring the jury to more clearly delineate who caused which of

the damages Denver Water requested.

¶ 159 Having stipulated to the final jury instructions and verdict

forms, B.C. cannot now ask this court to untangle the jury’s

verdicts. See Morales v. Golston, 141 P.3d 901, 904-05 (Colo. App.

2005) (the failure to object to an alleged inconsistency in the jury’s

verdict before the jury was dismissed waived a subsequent

challenge). The parties’ closing arguments are, perhaps, the best

indication of what the jury was asked to do. For example, B.C.

12 Denver Water’s opening statement identified other ways in which

B.C. failed to meet its obligations to it, including by, in preparing for
ACM abatement, failing to exercise the agreed-upon quality control
obligations and by disregarding the project management plan. Of
course, opening statements do not equal evidence, and Denver
Water later withdrew its original request to have the jury instructed
on B.C.’s “other breaches.”

70
urged the jury to look at Denver Water’s own conduct (e.g., the

delay in notifying B.C. and not allowing B.C. to help with the

remediation). Smith suggested to the jury that B.C.’s contribution

to the demolition plan (without Smith’s involvement) presented it

with an opportunity to course correct. Given this record, the jury

very well could have heeded these suggestions. See Rodriguez v.

Morgan Cnty. R.E.A., Inc., 878 P.2d 77, 82 (Colo. App. 1994) (a jury

verdict will not be reversed for inconsistency if a reading of record

reveals any basis for the verdict).

F. Attorney Fees

¶ 160 B.C. invokes C.A.R. 39.1 and section VIII of the Subontract as

the basis for its attorney fees request. Where a contract allows

attorney fees and the requesting party explains the legal and factual

basis for the award, we may award appellate attorney fees. See

Saturn Sys., Inc. v. Militare, 252 P.3d 516, 530 (Colo. App. 2011).

Because the district court recognized, and this court affirmed,

Smith’s duties to defend and to indemnify, B.C. is entitled to the

fees it incurred in defending Smith’s appeal. See C.A.R. 39(a)(2).

We exercise our discretion pursuant to C.A.R. 39.1 and remand the

71
case to the district court to determine an award of reasonable

appellate attorney fees.

VI. Disposition

¶ 161 The district court’s judgment is affirmed. We remand the case

so the district court may determine an appropriate award of

reasonable appellate attorney fees in accordance with this opinion.

JUDGE SCHOCK and JUDGE BERNARD concur.

72

Poursuivez vos recherches dans ChatGPT ou Claude

Connectez Omnilex pour rechercher dans le corpus juridique depuis votre assistant IA.