REDONDO CONSTRUCTION CORPORATION v. AUTORIDAD DE CARRETERAS DE PUERTO RICO et al

3:03-ap-00192Prb31 août 2009

Texte intégral

1
IN THE UNITED STATES BANKRUPTCY COURT
FOR THE DISTRICT OF PUERTO RICO
In re: 	:
:
REDONDO CONSTRUCTION CORPORATION, 	: 	Case No. 02-02887 (GAC)
:
Debtor 	: 	Chapter 11
___________________________________:
:
REDONDO CONSTRUCTION CORPORATION, 	:
:
Plaintiff, 	:
:
v. 	: 	Adv. No. 03-0192
: 	Adv. No. 03-0194
PUERTO RICO HIGHWAY AND 	: 	Adv. No. 03-0195
TRANSPORTATION AUTHORITY, 	:
:
Defendant 	:
___________________________________:
DECISION AND ORDER
On 	March 	19, 	2002, 	Redondo 	Construction 	Corporation 	(“RCC”)
filed a 	voluntary petition under Chapter 11 of the Bankruptcy Code.
On December 23, 2003, RCC filed three complaints against the Puerto
Rico 	Highway 	Authority 	(“PRHA”), 	claiming 	amounts 	due 	for
construction work performed in three projects: AC-005317 (“Desvío
Sur 	de 	Patillas”), 	Adversary 	No. 	03-0192; 	AC-20009 	(“PR 	2
Mayagüez”), 	Adversary 	No. 	03-0194; 	and 	AC-01657 	(“Dorado-Toa
Alta”), 	Adversary 	No. 	03-0195. 	On 	October 	5, 	2005, 	the 	Court
confirmed 	RCC’s 	plan 	of 	reorganization, 	as 	amended. 	(Docket 	No.
1207).
After significant discovery by the parties, the trial on these
adversaries 	was 	held 	on 	February 	12-16, 	26-28, 	and 	July 	2 	and 	6,
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 1 of 55
Pertains to the PR-2 Mayagüez project.1
2
2007. 	During the trial, RCC offered extensive documentary evidence
and 	the 	testimony 	of 	Arq. 	Miguel 	Redondo, 	Engs. 	Rodolfo 	Montero,
Raúl 	Bras, 	Angel 	Mercado, 	Humberto 	Reynolds, 	Luis 	García, 	Mr.
Andrew Civitello, and Rafael Pérez-Villarini, CPA.
PRHA had announced Dr. Sergio González, Engs. Fabián Delgado,
Víctor 	Pérez, 	Gonzalo 	Aponte, 	José 	Borges, 	and 	Messrs. 	Rubén 	del
Valle, Frank López, and Carlos Alamo, as its witnesses. (Pre-trial
Reports) (RCC’s EX 63 ) (Tr. of 2/27/07, pp. 1523-1530) (Docket No. 109).	1
Thereafter, PRHA informed that Dr. González was not going to be used
as 	a 	witness 	and 	consequently, 	RCC 	offered 	into 	evidence 	certain
portions 	of 	Dr. 	González’s 	deposition. 	During 	the 	hearing 	of
February 	16, 	2007, 	PRHA 	indicated 	that 	it 	would 	use 	all 	of 	its
witnesses and the case was scheduled to include July 2, 3, 6, 	and 9,
and if 	necessary, July 10, 2007. 	(Tr. of 2/16/07, pp. 1069-1079 ).
On 	February 	28, 	2007, 	PRHA 	offered 	the 	testimony 	of 	Eng.
Delgado. 	However, 	on 	July 	2, 	2007, 	PRHA 	announced 	that 	of 	the 	six
remaining 	witnesses, 	it 	was 	only 	going 	to 	use 	two, 	Engs. 	Pérez 	and
Aponte (Tr. of 7/2/07, pp. 93-94), and Miguel Díaz (“Díaz”), announced
by 	RCC 	as 	its 	witness, 	renounced 	as 	cumulative 	evidence, 	and 	made
available to PRHA. 	Eng. Pérez testified on July 2, 2007. 	However,
on 	July 	6, 	2007, 	PRHA 	announced 	that 	it 	was 	not 	going 	to 	use 	Eng.
Aponte either and submitted its case.
Since 	RCC 	had 	deposed 	the 	witnesses 	renounced 	by 	PRHA, 	during
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 2 of 55
Exs 62, 66 and 67 pertain to the PR-2 Mayagüez project.2
Joint EX 53 is common to the 3 projects.3
3
the 	hearing 	of 	July 	6, 	2007, 	RCC, 	without 	opposition 	from 	PRHA,
offered 	in 	evidence 	part 	of 	the 	transcripts 	of 	the 	following
depositions, 	admitted 	as 	RCC’s 	exhibits: 	Mr. 	Alamo’s 	(RCC’s EX 62),
Mr. López’ (RCC’s EX 66), and Eng. Del Valle’s (RCC’s EX 67). 2
At the conclusion of the trial, the Court directed the parties
to file simultaneous post-trial memoranda by August 31, 2007, which
was subsequently extended until November 9, 2007.
BACKGROUND
The Contracts
RCC is a corporation organized and authorized to do business
in 	accordance 	with 	the 	laws 	of 	the 	Commonwealth 	of 	Puerto 	Rico.
(Pretrial 	Report, 	Stipulated 	Facts). 	PRHA 	is 	a 	body, 	politic 	and
corporate, 	duly 	established 	and 	existing 	under 	the 	laws 	of 	the
Commonwealth of Puerto Rico. 	(Pretrial Report, Stipulated Facts).
On April 18, 1990, PRHA entered into a contract with RCC as to
the 	PR-2, 	Mayagüez 	project 	(Federal 	Aid 	Project 	No. 	HES-2-5(17)),
consisting 	of 	improvements 	and 	additional 	lanes 	at 	Road 	PR-2 	from
Mayagüez Terrace to PR-10. 	(Pretrial Report, Stipulated Facts; Joint
EXs 1, 2, 3, 7, 53 	; RCC’s EX 8) (Tr. of 2/12/07, pp. 93-95, 102-103,	3
105, 110-113).
On August 30, 1991, PRHA entered into a second contract with RCC
as to the Desvío Sur de Patillas project (Federal Aid Project PR-53
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 3 of 55
Exhibits pertain to the Desvío Sur de Patillas project.4
Exhibits pertain to the Dorado-Toa Alta project.5
4
Fed. 	F-53-1). 	(Pretrial 	Report, 	Stipulated 	Facts). 	This 	project
consisted mainly of a large bridge crossing the Patillas River, with
an approach road. 	It required pile driving to support the bridge bed
and 	lasted 	about 	three 	years. 	The 	original 	contract 	price 	was
$8,729,000.00, 	with 	an 	original 	540-day 	term 	and 	was 	substantially
completed on March 18, 1994. 	(Pretrial Report)(Joint EX 1; RCC’s EXs
3, 	4, 	5, 	6 	and 	9 	) 	(Tr. 	of 	2/12/07, 	pp. 	18, 	20, 	33, 	63-64; 	Tr. 	of	4
2/26/07, pp. 715-716, 725-728, 731-735, 743).
On June 7, 1993, PRHA awarded RCC a third contract, the Dorado-
Toa 	Alta 	project, 	consisting 	of 	the 	replacement 	of 	a 	bridge 	and
access 	roads 	between 	Dorado 	and 	Toa 	Alta, 	Puerto 	Rico, 	for
$2,657,000.00, known as Construction of Federal Aid Project BR-2165
(12), Replacement of Bridge No. 365, Highway PR 165R, Municipalities
of 	Dorado 	and 	Toa 	Alta, 	PR, 	also 	with 	a 	540-day 	term. 	(Pretrial
Report, Stipulated Facts). 	This project was completed on September 5,
2005. 	(Joint EX 1; RCC’s EXs 11, 12, 13, 14 )(Tr. of 2/12/07, pp. 19-20,	5
45).
The 	plans 	and 	specifications 	for 	all 	three 	projects 	were
prepared by PRHA. 	(Tr. 2/12/07, pp. 50-51). 	The three were unit-price
projects and had federal funds participation. 	(Tr. of 2/12/07, pp. 45-
46, 139-141; Tr. of /15/06, pp. 801-802, 878-882).
The master contract for each of the three projects is contained in
a 	contract 	book 	that 	incorporates 	the 	award, 	the 	bid 	documents, 	the
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 4 of 55
5
plans 	and 	specifications 	and 	general 	provisions, 	as 	an 	integral 	part
thereof. 	It 	also 	incorporates 	the 	Commonwealth 	of 	Puerto 	Rico
Department of Transportation and Public Works and Highway Authority’s
“Standard 	Specifications 	for 	Road 	and 	Bridge 	Construction 	of 	1989,”
known as the “Blue Book.” 	(Pretrial Reports, Stipulated Facts; Joint EXs
1 and 53 as to the 3 projects)(Tr. of 2/12/07, pp. 45, 102-103, 105, 109,
111-113, 117-121).
Blue Book Provisions
The pertinent parts of the Blue Book are as follows:
Section 104 of the Blue Book titled Scope of Work provides as to
the intent of the contract and the alterations of plans or character of
the proposed work:
104.01 	Intent of Contract — The intent of the Contract is
to 	provide 	for 	the 	construction 	and 	completion 	in 	every
detail of the work described. 	The Contractor shall furnish
all 	labor, 	materials, 	equipment, 	tools, 	transportation 	and
supplies required to complete the work in accordance with the
plans, specifications and terms of the contract.
104.02 	Alteration 	of 	Plans 	or 	Character 	of 	Proposed 	Work
—
a. 	The Authority reserves the right to make, at any
time 	during 	the 	progress 	of 	the 	work, 	such 	increases 	or
decreases in quantities and such alterations in the work as
necessary 	to 	satisfactorily 	complete 	the 	project. 	Such
increases or decreases and alterations shall not invalidate
the 	contract 	nor 	release 	the 	Surety, 	and 	the 	Contractor
agrees to perform the work as altered.
b. 	Unless such alterations and increases or decreases
materially change the character of the work to be performed
or the costs thereof, the altered work shall be paid for at
the 	same 	unit 	prices 	as 	other 	parts 	of 	the 	work. 	If,
however, the magnitude of the alterations is such as to alter
the 	scope 	of 	work 	specified 	in 	the 	contract 	by 	materially
changing either the character or the unit costs of the work
under 	the 	contract, 	whether 	or 	not 	changed 	by 	any 	such
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 5 of 55
6
alteration, an adjustment will be made to the contract. 	The
basis for the adjustment shall be agreed upon prior to the
performance of the work; if a basis cannot be agreed upon,
then 	the 	Authority 	reserves 	the 	right 	to 	require 	the
Contractor 	to 	perform 	the 	work 	by 	force 	account 	as 	per
Article 109.04, to eliminate the increased quantity from the
contract, or to perform the work in other manner.
c. 	If 	the 	altered 	or 	added 	work 	is 	of 	sufficient
magnitude to require additional time in which to complete the
project, such time adjustments may be made in accordance with
the provisions of Article 108.08.
As to the increased or decreased quantities of the work performed
under the contracts, Section 104.03 of the Blue Book recognizes that the
quantities in the proposal schedule are approximate only and the actual
quantities 	to 	be 	paid 	for 	are 	to 	be 	determined 	when 	the 	work 	is
performed 	and 	accepted. 	Increases 	or 	decreases 	in 	the 	proposed
scheduled 	quantities, 	other 	than 	as 	provided 	under 	Section 	104.02(b)
(see above), will be considered as normal overruns or underruns, and the
Contractor shall accept as payment in full, so far as contract items are
concerned, payment at the original contract unit prices for the accepted
quantities of work performed.
With respect to differing site conditions, the Blue Book at Section
104.05(a), 	provides 	that 	should 	the 	Contractor 	encounter 	during 	the
progress 	of 	the 	work 	subsurface 	or 	latent 	physical 	conditions 	at 	the
site 	differing 	materially 	from 	those 	indicated 	in 	the 	contract 	or
unknown physical conditions at the site, of an unusual nature, differing
materially from those ordinarily encountered and generally recognized
as inherent in the work of the character provided for in the contract,
the Contractor shall promptly notify the [Resident] Engineer in writing
of the specific differing conditions before they are disturbed or the
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 6 of 55
7
affected work is performed. 	Upon written notification, the [Resident]
Engineer will promptly investigate the conditions, and if the [Resident]
Engineer determines that they do materially differ and cause an increase
or decrease in the cost of, or the time required for the performance of
any part of the work under the contract, 	whether or not 	changed 	as 	a
result of the conditions, an equitable adjustment will be made and the
contract modified in writing accordingly.
Paragraph (b) of Section 104.5 provides that no contract adjustment
for the benefit of the Contractor shall be allowed unless the Contractor
has given the written notice required.
The 	probabilities 	of 	differing 	site 	conditions 	is 	recognized 	in
Section 105.02(b) of the Blue Book, when it states:
The detail plans and specifications for the contract have
been prepared with care and are intended to show as clearly
as 	is 	practicable 	the 	work 	required 	to 	be 	done. 	The
Contractor must realize, however, that construction details
cannot 	always 	be 	accurately 	anticipated 	and 	that 	in
executing the work, field conditions may require reasonable
modifications 	in 	the 	details 	of 	plans 	and 	quantities 	of
work 	involved. 	Work 	under 	all 	the 	items 	in 	the 	contract
must be carried out to meet these field conditions to the
satisfaction of the [Resident] Engineer and in accordance
with his instructions and the contract specifications.
As 	to 	extra 	work, 	Section 	104.06(a) 	and 	(b) 	of 	the 	Blue 	Book
specifies that the Contractor shall perform unforeseen work, for which
there 	is 	no 	price 	included 	in 	the 	contract, 	whenever 	it 	is 	deemed
necessary or desirable by the [Resident] Engineer, in accordance with
the applicable specifications, standard plans, the contract documents,
and as directed by the [Resident] Engineer, and that payment for such
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 7 of 55
8
extra work shall be at the prices agreed upon between the Authority and
the Contractor as specified in the approved extra work order.
Under 	the 	contracts 	and 	as 	stated 	in 	Section 	104.06(c), 	if 	an
agreement on the prices for the extra work could not be reached, PRHA
could 	order 	in 	writing 	RCC 	to 	perform 	the 	required 	work 	on 	a 	force
account basis and RCC was then to execute the order. 	Payment for such
force 	account 	work 	is 	specified 	in 	Section 	109.04. 	PRHA 	could 	also
elect 	to 	have 	such 	work 	performed 	by 	the 	Commonwealth 	forces 	or 	by
separate contract.
Section 105.17(a) and (b) of the Blue Book provides:
a. 	When the Contractor deems that extra compensation
is due him for work or materials not clearly covered in the
contract or not ordered by the [Resident] Engineer as extra
work, 	as 	defined 	herein, 	the 	Contractor 	shall 	notify 	the
[Resident] Engineer in writing of his intention to make claim
for such extra compensation within one working day after he
begins 	the 	work 	on 	which 	he 	bases 	the 	claim. 	If 	such
notification is not given, and the [Resident] Engineer is not
afforded 	proper 	facilities 	by 	the 	Contractor 	for 	keeping
strict 	account 	of 	actual 	cost 	as 	required, 	then 	the
Contractor hereby agrees to waive any claim for such extra
compensation. 	Such notice by the Contractor, and the fact
that the [Resident] Engineer has kept account of the cost as
aforesaid, shall not in any way be construed as proving or
substantiating the validity of the claim.
b. 	If the claim, after consideration of the [Resident]
Engineer, is found to be just, it will be paid as extra work
as provided in Article 104.06.
The 	Blue 	Book, 	in 	Section 	108.08(a) 	and 	(b) 	addresses 	the
determination 	and 	extension 	of 	the 	contract 	time 	by 	stating 	that 	the
contract time will be the number of days allowed for completion of the
work as stated in the proposal and in the contract, and shall commence
on the date stipulated in the notice to proceed. 	When the contract time
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 8 of 55
9
is 	a 	calendar 	day 	basis, 	every 	calendar 	day 	after 	the 	date 	of
commencement 	will 	be 	counted 	until 	the 	project 	is 	substantially
completed.
Section 	108.08(e) 	states 	that 	the 	determination 	of 	whether 	a
project is substantially completed is at the discretion of PRHA and that
a project will normally be considered substantially completed when all
the contract work, except for a few minor details, has been completed,
the required final cleaning-up has been performed, and the project can
be fully and safely opened to traffic or used for the intended use.
Then, Section 108.08(f) provides for the extension of the time for
the performance of the contract work for reasons that include (1) when
the 	satisfactory 	fulfillment 	of 	the 	contract 	requires 	performance 	of
work 	in 	greater 	quantities 	than 	those 	set 	forth 	in 	the 	proposal, 	by
increasing the performance on a basis commensurate with the amount, cost
and difficulty of the added work; (2) if at the time a change order or
an extra work order is executed, a time extension is agreed upon and so
stipulated in the written order or supplemental agreement, in which case
the added cost of such work will not be considered for time extension.
If no time extension is stated, any added cost resulting therefrom is
to 	be 	considered 	for 	time 	extension 	as 	provided 	for 	in 	Section
108.08(f); 	and 	(3) 	causes 	beyond 	the 	control 	of 	the 	Contractor,
including causes not attributable thereto.
A particular provision of the Blue Book is Section 206-3.05 titled
Cofferdams and Sheet Piling, specifying that suitable and practically
watertight cofferdams are to be used whenever water-bearing strata are
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 9 of 55
10
encountered above the elevation of the bottom of the excavation. 	Then
Section 206-3.05 goes into the specifications for the construction of
cofferdams, followed by RCC in the Dorado-Toa Alta project.
In 	turn, 	Section 	206-4.04 	specifies 	that 	the 	concrete 	for
foundation 	seals 	is 	to 	be 	measured 	in 	specification 	601, 	structural
concrete, also followed by RCC in the Dorado-Toa Alta project, who is
entitled to be paid for the concrete used in the cofferdam in accordance
to Section 601-4 of the Blue Book.
DISCUSSION
Due to the problems encountered by RCC in the three projects, RCC
was 	given 	extra 	time 	by 	PRHA 	to 	complete 	the 	same, 	but 	was 	not
compensated 	financially 	for 	the 	costs 	incurred 	thereby 	due 	to
inefficiency 	and 	extended 	overhead, 	resulting 	from 	the 	required
extensions of time to complete the jobs due to delays and differing site
conditions. 	(Tr. of 2/12/07, pp. 76-77, 135-136; Tr. of 2/14/07, pp.
557-559).
But, 	by 	the 	granting 	of 	extra 	time, 	it 	was 	obvious 	that 	RCC’s
overhead would increase, since RCC had to keep engineers at the project,
as well as other personnel and equipment, and had to incur all the fixed
expenses, 	aside 	from 	the 	consequent 	increase 	in 	the 	main 	office
overhead. 	When RCC submitted its proposals or bids for the projects,
it did so on the basis of the contract time indicated by PRHA, 540 days
in 	all 	three 	cases. 	In 	demanding 	that 	RCC 	continue 	working 	without
being paid 	for the increase in overhead, 	due 	to 	the policy of PRHA’s
Executive Director, Dr. González, that overhead would be dealt with at
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 10 of 55
11
the end 	of 	the contracts, 	PRHA did 	not act in accordance 	thereto and
caused RCC’s resources to be depleted. 	(Tr. of 2/12/07, pp. 135-136).
For the quantification of its claim for overhead on the three
projects, RCC used the Eichlay Formula. 	(Tr. of 2/12/07, pp. 70-75,
152).
The 	problems 	encountered 	by 	RCC 	in 	the 	three 	projects 	were
brought to the attention of PRHA as the construction work went along.
Every 	time, 	a 	differing 	site 	condition 	arose, 	PRHA 	was 	informed
through its resident engineers, who being at the projects, were aware
of them. 	(Tr. of 2/12/06, p. 125; Tr. of 2/14/07, pp. 565, 638-640).
After 	the 	trial 	of 	these 	matters 	was 	held, 	in 	their 	post-trial
briefs, PRHA spent considerable time arguing that these matters are non-
core proceedings and that it does not consent to the entry of any final
orders 	or 	judgments 	by 	this 	Court. 	Notwithstanding, 	this 	Court
concludes 	that 	at 	a 	hearing, 	held 	on 	November 	18, 	2003, 	PRHA
specifically agreed to submit these matters to the bankruptcy court in
lieu of the arbitration proceedings provided for in the contracts (dkt.
#649 	in 	the 	legal 	case). 	Accordingly, 	the 	Court 	concludes 	that 	as
proceedings 	related 	to 	RCC’s 	bankruptcy 	case 	and 	based 	on 	PRHA’s
explicit consent, the Court has jurisdiction to enter final orders and
judgments in these proceedings.
AC-005317 (“Desvío Sur de Patillas”), Adversary No. 03-0192
This project consisted of the construction of 1.79 kilometers of
paved 	road, 	two 	lanes, 	3.65 	meters 	wide, 	an 	emergency 	lane 	three
meters 	wide, 	drains, 	lighting, 	signs, 	markers, 	a 	prefabricated
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 11 of 55
12
concrete beam of 13.30 meters 	wide and 1,219 meters long and other
miscellaneous work with a contract term of 540 calendar days, at an
original cost of $8,729,000.00. 	Some of the problems experienced by
RCC at the project consisted of an “under-run” in the installation of
piles, with the surveying, 	the elevations of the decks, and design
problems, 	such 	as 	the 	diaphragms 	and 	the 	beams. 	(RCC’s 	Ex 	2, 	Tr.
2/15/07, pp. 738-742). 	The design problems were:
a. 	Discrepancies in vertical and horizontal control points.
b. 	Change of axis in the batter piles.
c. 	Modification in the quantity of the rebar in the footings.
d. 	Vertical and horizontal axis alignment in the west access.
e. 	Modification on diaphragm width with respect to plan detail.
f. 	Location of wing wall piles.
g. 	Relocation of pump house.
h. 	Geometric improvements to the west access.
I. 	Backwall abutment elevation #1 and #2.
j. 	Width of OG bearing wall abutments.
k. 	Width of bridge overhand.
l. 	Modification of rings in diaphragm.
m. 	Addition of deck drains.
n. 	Width of ramp and earthwork on west access.
o. 	Modification in width of pavement lines.
p. 	Geometric improvements in east intersection.
q. 	Improvements in project signs.
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 12 of 55
13
r. 	Over width construction in east access.
s. 	Modification on bridge profile.
t. 	Wetland restoration.
u. 	Property line points on south side fence.
(RCC’s Exhibit 11).
At the trial of this matter, Arq. Miguel Redondo testified as to
the Desvío Sur de Patillas project and the Dorado-Toa Alta projects.
At the time of the Desvío Sur de Patillas project, Arq. Redondo was
RCC’s 	executive 	vice-president 	in 	charge 	of 	all 	field 	operations,
including 	that 	project, 	as 	to 	which 	Eng. 	Reynolds 	was 	the 	project
manager. 	(Tr. of 2/27/07, p. 1445). 	Arq. Redondo testified that the
Patillas 	project 	had 	a 	lot 	of 	defects 	as 	to 	the 	plans 	and
specifications, 	as 	summarized 	in 	the 	attachments 	to 	Exhibit 	11,
which reflect the problems encountered by RCC, resulting in twenty-
two extra work and fifteen change orders. 	(Tr. of 2/27/07, pp. 1446-
1448).
Eng. Reynolds also testified as to the Desvío Sur de Patillas
project. 	He reiterated the problems 	that affected the progress of
the work, i.e., under-run on the piles for the construction of the
bridge, 	modifications 	of 	design 	and 	to 	the 	structure 	itself, 	which
delayed 	the 	project. 	The 	under-run 	on 	the 	piles 	was 	due 	to 	the
actual 	conditions 	found 	when 	driving 	them, 	which 	resulted 	in 	a
reduction in their driving length. 	(Tr. of 2/26/07, pp. 1099-1100).
RCC 	became 	aware 	of 	this 	factor 	during 	the 	construction 	of 	the
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 13 of 55
14
project. 	The 	situation 	lasted 	throughout 	the 	installation 	of 	the
piles 	and 	was 	subject 	to 	final 	liquidation 	by 	PRHA. 	The 	final
assessment 	as 	to 	its 	impact 	had 	to 	be 	done 	when 	the 	activity 	was
finished. 	(Tr. 	of 2/26/07, pp. 1100; 1102; 1151-1152).
These 	problems 	affected 	the 	progress 	of 	the 	construction,
causing a loss of productivity and inefficiency in the work that had
been 	planned. 	They 	delayed 	the 	work 	and 	increased 	the 	construction
costs. 	(Tr. 	of 	2/15/07, 	pp. 	742-743). 	The 	estimate 	of 	the
quantities as to the piles shown in the contract were more than those
for 	the 	actual 	construction, 	causing 	under-runs. 	(Tr. 	of 	2/15/07,
pp. 738-739).
The 	project 	design 	included 	the 	installation 	of 	steel 	piles
manufactured in the United States on what is called a “mill length”
of 90 feet. 	For a 90-feet pile, a 40-feet and 50-feet pile would be
ordered, which required the use of a splice to weld the two pieces
together. 	A steel point would also be ordered to protect the end of
the pile during the installation. 	In preparation for the submission
of 	the 	bid 	for 	costs 	purposes, 	RCC 	considered 	the 	information
provided 	in 	the 	drawings 	by 	PRHA 	and 	made 	a 	calculation 	as 	to 	how
many steel points and splices would be needed based on the number of
piles and mill length. 	(Tr. of 2/15/07, pp. 744-746).
After that, a fixed cost was applied to the units specified in
the contract and distributed along the linear meters of the piles as
to the steel points and splices. 	However, when the pile to be driven
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 14 of 55
15
90 feet, the full length, goes into the ground only 60 feet, there is
an under-run, and the contractor does not recover the fixed cost of
the steel point and the splice on that pile, since what PRHA pays is
the linear feet of the pile driven into the ground. 	(Tr. of 2/15/07,
pp. 746-752).
This under-run of the piles, which is the foundation where the
piers or columns of the bridge shown in Exhibit 6 sits, happened in
the 	Desvío 	Sur 	de 	Patillas 	project 	as 	to 	all 	the 	piles. 	(Tr. 	of
2/15/07, 	pp. 	752-753). 	RCC 	identified 	the 	situation 	and 	requested
compensation for the cost caused by the 	under-run (Tr. of 2/15/07,
pp. 	754-755). 	On 	October 	19, 	1994, 	making 	reference 	to 	previous
correspondence, RCC submitted a revised claim to PRHA for $34,072.27
for the unrecovered expense during the driving of the piles (Ex 10;
Tr. 2/15/07, pp. 784-785).
As 	argued 	by 	PRHTA, 	the 	Court 	accepts 	that 	other 	courts 	have
consistently 	held 	that 	the 	differing 	site 	condition 	clause 	applies
only to conditions that already existed at the time of contracting.
See, 	Olympus 	Corp. 	v. 	US, 	98 	F. 	3d 	1314 	(Fed. 	Cir. 	1996) 	(holding
that a contractor was not entitled to an equitable adjustment for a
differing site conditions claim based on an event that occurred after
the contract was executed). 	And the Court concludes that RCC’s claim
based on differing site conditions was due to conditions that varied
materially from those indicated in the contract documents, that the
conditions 	were 	physical 	and 	that 	they 	clearly 	existed 	prior 	to
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 15 of 55
16
contract formation. 	RCC reasonably relied on the contract prepared
by PRHTA.
On February 21, 1995, RCC submitted its final claim, including
the under-run on the piles and the additional expenses incurred in
the 	construction 	of 	the 	Patillas 	project, 	resulting 	from 	the
alterations 	and 	modifications 	suffered 	thereby, 	which 	seriously
affected 	the 	original 	term 	of 	the 	contract, 	causing 	extraordinary
delays, 	and 	RCC’s 	direct 	administrative 	costs, 	as 	evidenced 	by 	the
fifteen 	change 	orders 	and 	the 	twenty-two 	extra 	work 	orders, 	which
caused an extended period of time to complete the job. 	RCC claims:
1. 	Office overhead 	$ 335,770.89
2. 	Credit office overhead 	($ 81,218.53)
3. 	Job overhead 	$ 359,864.49
4. 	Under-run piles/joints 	$ 	34,072.27
Total Cost 	$ 648,489.12
10% Profit 	$ 	64,848.91
Total 	$ 713,338.03
Interest 	would 	also 	have 	to 	be 	added 	to 	the 	claim 	at 	6.5% 	as 	of
February 27, 2007. 	(Joint Ex 12; RCC Ex 11; Tr. of 2/15/07, pp. 758-
762; Tr. of 2/27/05, pp. 1448-1450; 1457-1458).
Generally, the contractor is entitled to compensation if it can
prove 	that 	it 	did 	not 	concurrently 	cause 	the 	delay 	and 	if 	it 	can
quantify its damages with reasonable certainty. See Blinderman Const.
Co., Inc. V. U.S., 39 Fed. Cl. 529, 583 (1997), aff’d 178 F.3d 1307
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 16 of 55
17
(Fed. 	Cir. 	1998)(opining 	that 	the 	contractor 	as 	plaintiff 	has 	the
burden of proving "every essential element of a compensable delay").
When 	liability 	is 	established, 	the 	Contractor 	has 	to 	prove 	its
damages to a “reasonable certainty”. 	See Wunderlich Contracting Co.
v. U. S., 173 Ct. Cl. 180, 351 F.2d 956 (1965)("A claimant need not
prove his damages with absolute certainty or mathematical exactitude…
It is sufficient if he furnishes the court with a reasonable 	basis
for his computation …"); John E. Green Plumbing and Heating Co., Inc.
v. 	Turner 	Const. 	Co., 	742 	F.2d 	965, 	968 	(6th 	Cir. 	1984) 	("the 	law
does not require impossibilities when it comes to proof of damages,
but it does require whatever degree of certainty that the nature of
the 	case 	admits. 	A 	damage 	award 	must 	not 	be 	based 	on 	mere
speculation, guess or conjecture.").
In 	the 	present 	case, 	RCC 	has 	persuaded 	the 	Court 	that 	the
Authority 	had 	sole 	control 	over 	the 	activities 	that 	delayed 	the
project, 	entitling 	it 	to 	additional 	compensation 	for 	the 	delays 	in
the performance of the work. 	The extension of time suffered in the
Desvío 	Sur 	de 	Patillas 	project 	is 	not 	normal 	for 	this 	type 	of
project. 	(Tr. of 2/15/07, p. 761). 	The Court concludes that RCC has
demonstrated an entitlement to compensation for delay damages based
on 	the 	governing 	contractual 	provisions 	between 	the 	parties. 	The
delay was excusable, the delay was compensable and RCC demonstrated
the 	quantum 	of 	the 	resulting 	damages. 	PRHA 	also 	admitted 	in 	its
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 17 of 55
18
answer to the complaint that it owes RCC something for this project,
but did not specify what it owed.
RCC seeks compensation for extended overhead costs for a total
of 471 days of delay. 	RCC calculated this delay period by adding up
the number of days from March 1, 1993 (the original completion date)
to 	July, 	1994. 	However, 	the 	evidence 	showed 	that 	substantial
completion of the Project was achieved on March 18, 1994 (See Exhibit
No. 	9). 	Pursuant 	to 	the 	contract, 	the 	project 	is 	substantially
completed 	when 	all 	the 	contract 	work, 	except 	for 	few 	very 	minor
details, has been completed. 	See Blue Book § 108.08(e). 	After the
project 	was 	substantially 	completed 	there 	is 	no 	further 	delay
analysis 	because 	the 	only 	tasks 	to 	complete 	are 	the 	minor 	items,
punch 	list 	items 	or 	finishes 	which 	are 	not 	critical 	for 	the
completion of the project. 	Hence, the Court concludes that RCC is
unable to claim overhead expenses due to delay from March 18, 1994 to
July 1994, which represents a difference of 89 calendar days.
On February 	27, 1995, PRHA issued its final inspection report
(Joint 	Ex 	12) 	acknowledging 	that 	the 	contract 	was 	performed 	in
accordance 	to 	the 	requirements, 	thereof, 	within 	the 	time 	period
authorized, and recommending that the project be officially accepted.
(Tr. 	of 	2/15/07, 	pp. 	785-790). 	Also 	on 	February 	27, 	1995, 	PRHA’s
Director of Construction, Eng. Irving Ocasio, wrote to Eng. Reynolds
in 	relation 	to 	the 	extended 	job 	and 	main 	office 	overhead, 	stating
that 	such 	request 	had 	been 	referred 	to 	PRHA’s 	finance 	area 	for
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 18 of 55
19
auditing and that the claim for the “under-run” of the piles had been
referred 	to 	PRHA’s 	Sub-Regional 	Office, 	indicating 	that 	once 	the
recommendations were received, RCC would be called for a meeting to
discuss the same. 	That meeting never took place. 	(RCC’s Ex 13; Tr.
of 2/15/06, pp. 792-794). 	On April 7, 1995, Dr. González, referring
to the final inspection of April 14, 1994, stated that the project
was found in conformance with the conditions of the contract and as
such, 	accepted 	the 	same, 	conditioned 	to 	its 	final 	liquidation
pursuant to Section 109.09 of the General Conditions of the contract,
indicating 	March 	18, 	1994 	as 	the 	termination 	date. 	(RCC’s 	Ex 	14)
(Tr. of 2/15/06, pp. 795-796).
On 	that 	same 	date, 	Dr. 	González 	notified 	the 	Department 	of
Transportation of Puerto Rico that the Desvío Sur de Patillas project
had been completed in accordance to the plans and specifications and
requested 	that 	the 	project 	be 	included 	within 	the 	highway 	network
under 	conservation 	by 	the 	Department 	of 	Transportation. 	(RCC’s 	Ex
15; Tr. of 2/15/06, pp. 796-799). 	On August 16, 2001, Eng. Reynolds
wrote 	to 	PRHA’s 	Area 	Director 	of 	Construction, 	requesting 	a 	status
report on RCC’s claim, which was never answered. 	(RCC’s Ex 16; Tr.
of 2/15/06, pp. 800-801).
The Court rejects PRHTA’s allegation that RCC did not present it
claim 	to 	the 	Authority 	until 	over 	ten 	months 	after 	the 	final
completion. 	RCC notified PRHA of the problem, that its was affecting
RCC’s costs, based on the conditions of the site, which could not be
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 19 of 55
20
predetermined prior to performing the activity, that the construction
was being adversely impacted and that at the end of the activity or
the assessment, RCC would be submitting a request for payment. 	This
was 	done 	through 	letters, 	conversations, 	weekly 	meetings, 	and
discussions 	held 	at 	the 	project, 	in 	the 	normal 	course 	of 	the
construction. 	PRHA 	had 	resident 	engineers 	at 	the 	Desvío 	Sur 	de
Patillas project at all times. 	(Tr. of 2/26/07 p. 1151-1155). 	As a
matter 	of 	fact, 	the 	payment 	for 	the 	driving 	of 	the 	piles 	was 	made
according to the records 	of PRHA’s inspector. (Tr. of 2/26/07, pp.
1155-1156).
During the weekly construction meetings at both the Desvío Sur
de Patillas project and Dorado-Toa Alta projects, Eng. Reynolds was
present, 	with 	the 	project 	manager, 	the 	project 	engineers 	from 	RCC,
PRHA’s 	inspectors 	and 	its 	resident 	managers, 	and 	all 	the 	items
related 	to 	the 	projects 	were 	discussed. 	At 	those 	meetings, 	the
problems 	as 	to 	the 	two 	projects 	were 	brought 	to 	the 	attention 	of
PRHA. 	(Tr. 	of 	2/26/07, 	pp. 	1156-1157). 	In 	addition, 	special
meetings 	were 	held 	to 	discuss 	the 	problems. 	RCC 	would 	also 	call
extraordinary meetings to address them. 	(Tr. of 2/26/07, pp. 1157-
1158). 	Eng. Reynolds submitted a request for payment of the piles
and 	a 	formal 	claim, 	when 	he 	sent 	the 	letter 	requesting 	the
compensation. 	(RCC’s EXs 10 and 11; Tr. of 2/26/07, pp. 1165-1166).
PRHA 	has 	not 	made 	any 	payment 	to 	RCC 	as 	to 	its 	claim 	for 	the
Desvío Sur de Patillas project (Tr. of 2/27/07, p. 1482). 	The Court
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 20 of 55
21
concludes 	that 	RCC 	is 	entitled 	to 	office 	and 	job 	overhead 	of
$632,187.87, less the credit of $81,218.53, plus $34,072.27 for the
under-run of the piles and joints, for a total of $585,041.61, plus
10% 	profit 	of 	$58,504.16, 	for 	a 	total 	of 	$643,545.77, 	plus
prejudgment interest at 6.5% from February 27, 2007.
AC-20009 (“PR 2 Mayagüez”), Adversary No. 03-0194
PRHA 	awarded 	this 	project 	to 	RCC 	for 	the 	construction 	of
geometric 	improvements 	and 	additional 	lanes 	on 	7.23 	kilometers 	of
Road 	2 	from 	Mayagüez 	Terrace 	to 	PR 	100. 	The 	PR-2 	Mayagüez 	project
included the relocation of existing utilities such as pluvial, sewer and
electronic systems, and the installation of underground electric systems
for 	lighting 	in 	primary 	lanes 	and 	synchronized 	traffic 	lights 	at
seventeen intersections. 	(Tr. of 2/12/07, pp. 31-32, 45). 	The project
commenced 	on 	April 	30, 	1990, 	as 	provided 	for 	in 	PRHA’s 	order 	to
proceed 	dated 	April 	18, 	1990. 	The 	original 	completion 	date 	was
October 21, 1991, for an original contract price of $14,750,000.00,
and 	a 	contract 	time 	of 	540 	days. 	RCC 	substantially 	completed 	the
project on November 1, 1993, with an actual completion date of June
30, 1994. 	Nonetheless, RCC did additional work at the project until
May 31, 1995. 	While the construction work went on, the pavement was in
use at all times, at least partially. (Tr. of 2/14/07, p. 644).
Throughout 	the 	project, 	RCC 	encountered 	(i) 	that 	the 	technical
plans and specifications prepared by PRHA were incomplete and contained
errors; 	(ii) 	that 	the 	technical 	information 	provided 	by 	PRHA 	was
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 21 of 55
22
insufficient to estimate and perform the necessary work; (iii) that the
original 	design 	by 	PRHA 	did 	not 	comply 	with 	the 	requirements 	and
regulations of public agencies of the Commonwealth of Puerto Rico and
was 	defective 	for 	the 	electrical 	work 	to 	be 	performed; 	(iv) 	the
existence 	of 	unidentified 	elements 	and 	structures 	in 	the 	contract
documents prepared by PRHA and of conditions in the terrain different
from those indicated by PRHA, including the deplorable condition of the
concrete slabs, and that due to the poor quality of the material below
the asphalt, it could not be used in other sections, as provided for in
the contract specifications. 	The material had to be discarded and other
material 	had 	to 	be 	brought 	in 	(borrowed) 	from 	other 	sources; 	(v)
numerous changes of sequence in the execution of the work all over the
seven 	kilometers 	of 	the 	project, 	causing 	inefficiency 	throughout 	the
time of the project, due to circumstances that could not be foreseen,
among others, different site conditions; (vi) undue delays by PRHA in
the resolution of the different problems and issues, such as design and
other 	technical 	aspects; 	and 	(vii) 	delays 	in 	the 	disbursement 	of
payments 	under 	the 	contract 	by 	PRHA, 	contrary 	to 	what 	was 	agreed 	to.
(Joint EXs 11, 19, 23, and 41; RCC’s EXs 4, 5, 6, 12, 13, 14, 15, 18,
20, 22, 24, 47 and 59) (Tr. of 2/12/07, pp. 129-130, 143-148, 179,
185-188, 	193-200, 	234-240, 	329; 	Tr. 	of 	2/13/07, 	pp. 	234-240, 	395-
398;Tr. 	of 	2/14/07, 	pp. 	513-514, 	520-530, 	553-554, 	596, 	604, 	632,
659-660; Tr. of 7/2/07, pp. 44-48).
As in the other projects, 	the Court rejects PRHA’s contention
that RCC has failed to establish a differing site conditions claim.
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 22 of 55
23
PRHA 	admits 	that 	Miguel 	Redondo 	personally 	performed 	a 	general
investigation of the road and its surroundings during one day, but
claims 	that 	it 	was 	insufficient 	as 	due 	diligence. 	In 	spite 	of
experience, RCC could have spent a number of days investigating and
not determined the poor quality of the material below the asphalt.
The required change orders and extra work orders were of such
magnitude 	that 	PRHA 	agreed 	to 	extensions 	of 	almost 	three 	times 	or
300% the original contract time. 	In Arq. Redondo’s more than thirty
years 	of 	experience 	in 	construction, 	he 	indicated 	that 	the 	PR-2
Mayagüez project was the first time where the term of a contract was
extended in such a fashion.
The project was designed in conjunction with Dr. González as to
the 	traffic 	signal 	system, 	who 	at 	the 	time 	was 	a 	professor 	at 	the
University 	of 	Puerto 	Rico’s 	Mayagüez 	Campus 	and 	later, 	during 	the
performance 	of 	the 	contract, 	became 	PRHA’s 	Executive 	Director,
remaining as such during the time Continental Lord, Inc. (“Lord”) did
electrical 	work 	at 	the 	project, 	as 	RCC’s 	electrical 	subcontractor,
until May 1994. 	(Tr. of 2/13/07, pp. 395-398; Tr. of 2/2/6/07, pp.
1188-1190).
Eng. 	Julio 	Feliciano 	(“Feliciano”), 	PRHA’s 	resident 	engineer,
acknowledged 	the 	deficiencies 	and 	problems 	that 	RCC 	and 	Lord 	were
encountering in the performance of their contracts. 	(EXs 11, 12, and
19) (Tr. of 2/12/07, pp. 201-205, 240-242; Tr. of 2/13/07, pp. 249-
252; 	Tr. 	of 	2/14/07, 	pp. 	584-585). 	Eng. 	Montero 	spoke 	about 	the
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 23 of 55
24
problems with PRHA’s resident engineers and thereafter, a letter was
addressed to PRHA. 	He also broached the issues during RCC’s weekly
meetings with PRHA. 	(Tr. of 2/14/07, pp. 587, 594-597).
PRHA was notified of RCC’s claims, as recognized by the change
orders and extra work orders 	issued by PRHA. 	Eng. Mercado, Lord’s
project 	manager, 	participated 	in 	the 	weekly 	meetings 	with 	PRHA,
during which RCC indicated to PRHA’s representatives its intention of
presenting its formal claim, which could not be presented until the
conclusion of Lord’s electrical work. 	(Tr. of 2/14/07, pp. 565-638-
640; Tr. of 2/26/07, p. 1263). 	Through a letter dated December 6,
2000, RCC presented its formal claim to PRHA. (Joint EXs 9, 25, 26,
27, 	28, 	30, 	37, 	38, 	and 	41; 	RCC’s 	EXs 	4, 	5, 	6, 	and 	12) 	(Tr. 	of
2/12/07, 	pp. 	77-79, 	127-129, 	135-136, 	141-142, 	150-152; 	Tr. 	of
2/13/07, pp. 388-391, Tr. of 2/14/07, pp. 513-514, 520-530, 553-554,
561, 581-582).
Lord 	was 	responsible 	for 	the 	installation 	of 	the 	lighting
systems 	at 	the 	project, 	including 	the 	installation 	of 	a 	thirteen
traffic signal system at intersections and new highway lighting along
the 	project. 	There 	were 	also 	some 	pedestrian 	amenities 	that 	had
electrical facilities to be done by Lord. 	Eng. Mercado, as Lord’s
project 	manager, 	coordinated 	with 	RCC 	the 	electrical 	work 	to 	be
performed. 	He 	participated 	in 	meetings 	with 	PRHA 	to 	coordinate
therewith, on behalf of RCC. 	Eng. Mercado was in contact with the
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 24 of 55
25
project on a day to day basis and visited the project twice or more
per week. 	(Tr. of 2/26/07, pp. 1182-1185, 1188).
Part 	of 	Lord’s 	job 	was 	to 	coordinate 	with 	the 	Puerto 	Rico
Electric 	Power 	Authority 	(“PREPA”) 	the 	construction 	of 	a 	new 	power
line that would align with the project in order for RCC to be able to
proceed 	with 	its 	work. 	(Tr. 	of 	2/26/07, 	pp. 	1186-1187). 	Lord
encountered 	hundreds 	of 	problems 	and 	major 	design 	issues. 	Lord’s
claim, RCC’s EX 68, prepared by Eng. Mercado, includes a discussion
of 	the 	problems 	faced 	by 	Lord 	in 	performing 	its 	contract 	and 	the
evidence in support thereof. 	(Tr. of 2/26/07, pp. 1191-1202, 1243-
1244, 1249; Tr. of 2/14/06, pp. 632, 658).
Due 	to 	errors 	in 	the 	design 	of 	the 	pull 	boxes, 	part 	of 	the
electrical system, and PRHA’s delay in correcting the errors, Lord’s
work was delayed approximately 453 calendar days. 	These are the days
that transpired from the time the problem was presented 	by Lord to
PRHA, until PRHA’s approval of the extra work order to correct it.
(Tr. of 2/26/07, pp. 1202-1203; 1205-1209, 1215; Tr. of 7/2/07, pp.
36-37).
The design of the master control room area, where the central
computer for the control power system is located, with an emergency
generator, for the power and data communication distribution to the
thirteen traffic signal system at intersections, was incomplete and
a 	redesigning 	was 	necessary 	since 	the 	designed 	location 	was
insufficient 	and 	existing 	utilities 	prevented 	RCC 	from 	doing 	its
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 25 of 55
The master control room area is located in the area designated as A-3.
6
26
work, 	in 	order 	for 	Lord 	to 	be 	able 	to 	do 	its 	own. 	PRHA 	took 	980
calendar days since Lord’s notification to do the required redesign.
PRHA was notified during the project meetings and in writing, even at
its central office, of this matter. 	(Tr. of 2/26/07, pp. 1209-1215).
The 	design 	for 	the 	electrical 	facilities 	for 	the 	pedestrian
amenities 	designated 	by 	PRHA 	in 	its 	drawings 	as 	A-1 	and 	A-3, 	which	6
included a fountain and some light poles, lacked the details necessary
for 	Lord 	to 	do 	the 	work. 	Lord 	requested 	that 	PRHA 	complete 	the
electrical design, since there was no electrical distribution for the
electrical 	devices. 	This 	was 	also 	brought 	to 	the 	attention 	of 	PRHA
during meetings with its representatives, as in the case of the other
problems. 	It took PRHA 668 calendar days to perform the required design
and issue the necessary extra work and change orders for the work to be
done. 	RCC’s EX 68) (Tr. of 2/26/07, pp. 1216-1221).
RCC’s EX 68 also describes the problems encountered by Lord as to
the power and communication distribution for the thirteen traffic signal
system, as to which Lord did not have a complete design to perform the
work, since the drawing provided by PRHA did not show how the circuits
were 	to 	be 	distributed 	along 	the 	thirteen 	intersections, 	nor 	the
communication cable. 	This was also communicated to PRHA. It took PRHA
277 calendar days to correct the deficiency and provide Lord with the
required information. 	(Tr. of 2/26/07, pp. 1221-1224).
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 26 of 55
27
The 	last 	major 	problem 	encountered 	by 	Lord 	had 	to 	do 	with 	the
traffic 	signal 	poles. 	When 	their 	installation 	commenced, 	trucks 	with
sugarcane started to smash the traffic lights and PRHA required Lord to
increase their height. 	As in the case of the other designs, these poles
were designed by the team headed by Dr. González. 	(RCC’s EX 68) (Tr.
of 	2/26/07, 	pp. 	1224-1225; 	Tr. 	of 	7/2/07, 	pp. 	36-37). 	In 	discussing
this problem with PRHA’s representatives, PRHA decided to increase the
height 	of 	the 	base 	of 	the 	poles, 	but 	Dr. 	González, 	by 	then 	PRHA’s
executive director, visited the project site, did not like the solution
due 	to 	the 	aesthetics 	and 	instructed 	the 	removal 	of 	the 	poles, 	the
demolition 	of 	the 	bases 	and 	the 	ordering 	of 	new, 	higher 	pole 	shafts.
It took 	PRHA 717 	calendar 	days 	to 	approve the 	final 	solution 	to 	this
last 	major 	problem. 	Lord 	was 	directed 	to 	stop 	its 	work 	as 	to 	this
activity when the problem arose until it was solved. 	(Tr. of 2/26/07,
pp. 	1225-1228, 1256).
The 	problems 	encountered 	by 	Lord 	impacted 	its 	original 	project
schedule by 940 days. 	(RCC’s EX 68) (Tr. of 2/26/07, pp. 1228-1229).
The 	sequence 	of 	Lord’s 	work 	was 	affected 	by 	these 	major 	problems,
forcing Lord to have to move from one location to another, which also
affected RCC, since RCC could not complete the work in particular areas
until Lord finished its work. 	(RCC’s EX 68) (Tr. of 2/26/07, pp. 1229-
1237).
The original completion date for Lord’s work was October 10, 1991,
and due to the delays caused by PRHA, Lord had to remain at the project
until 	May 	15, 	1994. 	(RCC’s 	EX 	68) 	(Tr. 	of 	2/26/07, 	pp. 	1238-1239).
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 27 of 55
28
RCC’s 	EX 	68 	contains 	the 	cost 	analysis 	of 	Lord’s 	claim 	done 	by 	Eng.
Mercado 	with 	the 	assistance 	of 	Lord’s 	comptroller, 	showing 	a 	claim
totaling 	$1,746,085.00. 	RCC’s 	EX 	68 	includes 	extended 	general 	home
office overhead, extended job overhead, additional labor costs due to
loss 	of 	productivity, 	extended 	overhead 	for 	miscellaneous 	tools 	and
expenses for inflation of miscellaneous materials, other expenses, and
a 	profit 	factor 	of 	15%. 	In 	computing 	the 	extended 	general 	and 	home
office overhead, Eng. Mercado also used the Eichleay formula. 	(Tr. of
2/26/07, pp. 1238-1242, 1266). 	As 	stated 	by 	Eng. Mercado, Lord had
never 	encountered, 	either 	before 	or 	after 	the 	Mayagüez 	project, 	the
amount 	of 	delays 	and 	problems 	it 	had 	to 	face 	in 	the 	PR-2 	Mayagüez
project. 	(Tr. of 2/26/07, p. 1243).
Eng. Díaz, the president of Remodelco, Inc. (“Remodelco”), RCC’s
subcontractor for special type concrete sidewalks and special purpose
recreational areas called “amenities,” work that was to be accomplished
as 	RCC 	was 	doing 	the 	construction 	of 	the 	road, 	submitted 	Remodelco’s
$85,000.00 	claim 	for 	extended 	overhead 	to 	RCC, 	resulting 	from 	the
delays, 	design 	errors, 	and 	delays 	in 	decision-making 	attributable 	to
PRHA, and the ensuing additional work that Remodelco had to do. 	(Tr.
of 7/2/07, pp. 12-15, 17-20).
The Court finds that PRHA was aware of the problems in the PR-2
Mayagüez project. 	The problems were brought to the attention of PRHA
throughout the project, area by area, by Eng. Montero to Eng. Feliciano.
In 	doing 	so, 	RCC 	reserved 	its 	right 	to 	claim 	indirect 	costs 	not
contemplated 	by 	the 	change 	orders 	and 	extra 	work 	orders 	initiated,
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 28 of 55
29
approved 	and 	authorized 	by 	PRHA, 	resulting 	from 	delays 	beyond 	RCC’s
control. 	Eng. Delgado, PRHA’s Regional Director for the Mayaguez Area
during 1999-2000 and supervisor of the PR-2 Mayaguez project since 2001,
referred to the project as complicated (Tr. of 2/28/07, pp. 6-7; 11-13;
69) and recognized the difficulties encountered by RCC. 	(Joint EXs 11,
19, and 23; RCC’s EXs 13, 14, 22, and 24) (Tr. of 2/12/07, pp. 201-205,
211-216, 240-242;Tr. of 2/13/07, pp. 225-234, 252-264, 393, 398; Tr. of
7/2/07, p. 40).
Since early in the PR-2 Mayagüez project, RCC apprised PRHA as to
its claim for extended overhead. 	(RCC’s EX 16). 	Mobilization costs of
getting into and out of the project, monthly expenses of the project,
project office, warehouse at site, and having an engineer at the project
are part of the job-site overhead. 	(Joint EX 41) (Tr. of 2/13/07, pp.
267-268).
On November 26, 2006, Eng. Bras met with Eng. Jorge Redondo and
Eng. 	Díaz 	Sáez, 	at 	the 	time 	PRHA’s 	Director 	of 	Construction. 	Engs.
Pérez 	and 	Delgado 	also 	participated. 	Eng. 	Pérez 	was 	by 	then 	PRHA’s
resident 	engineer 	in 	charge 	of 	liquidating 	the 	project. 	Eng. 	Pérez
substituted 	Eng. 	Feliciano 	for 	the 	PR-2 	Mayaguez 	project’s
administration. Eng. Delgado was Eng. Pérez’s supervisor. 	The purpose
of the meeting was for RCC to seek the payment of monies due for work
performed, pursue liquidation of the job and present its claims caused
by the delays and for extended overhead. 	(Tr. of 2/13/07, pp. 399-402;
Tr. of 7/2/07, pp. 25-27; Tr. of 	2/28/07, pp. 82-83).
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 29 of 55
30
At that time, with Eng. Pérez as the last administrator on behalf
of 	PRHA 	for 	the 	PR-2 	Mayagüez 	project, 	RCC’s, 	Lord’s 	and 	Remodelco’s
claims for inefficiency and extended overhead were again discussed and
one more time, PRHA stated that these were matters to be dealt with at
another 	level. 	It 	was 	not 	for 	Eng. 	Pérez, 	appointed 	to 	work 	on 	the
liquidation process, to enter into the matter due to PRHA’s policy of
dealing 	with 	those 	issues 	at 	another 	level, 	meaning 	PRHA’s 	Executive
Director 	or 	its 	Director 	of 	Construction 	Area. 	(RCC’s 	EXs 	35 	and
36)(Tr. of 7/2/07, pp. 25-27, 60-61, 69-73).
Upon 	receiving 	Joint 	EX 	41 	in 	the 	year 	2001, 	Eng. 	Pérez 	was
surprised that it had taken so much time to liquidate the PR-2 Mayagüez
project, 	recognizing 	that 	the 	claims 	raised 	by 	RCC 	were 	just. 	Eng.
Pérez was also surprised that at the time of the trial, the project had
still not been liquidated. 	Eng. Delgado also recognized Exhibit 41 as
RCC’s formal claim, with the basis therefor, and that RCC also submitted
another claim. 	Eng. Delgado admitted that his contract with the PR-2
Mayaguez 	project 	began 	in 	2001, 	approximately 	two 	years 	after 	PRHA’s
order to proceed and that he did not have personal knowledge as to what
happened during those two previous years. 	He also admitted that Eng.
Montero 	and 	Eng. 	Feliciano, 	as 	the 	resident 	agent 	for 	PRHA, 	had
differences in reference to the performance of the work and that there
was animosity between them. 	Eng. Delgado could deal with Eng. Montero,
whom 	he 	considered 	to 	be 	a 	professional 	and 	a 	very 	competent 	worker.
Eng. Feliciano was replaced by Eng. Pérez and contrary to the situation
with 	Eng. 	Feliciano, 	Eng. 	Montero 	and 	Eng. 	Pérez 	did 	not 	have 	any
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 30 of 55
31
problems. 	Eng. 	Delgado 	admitted 	that 	due 	to 	animosity 	between 	Engs.
Feliciano and Montero, the information as to the problems in the project
would flow mainly by correspondence, identifying one of the letters from
Eng. Montero setting forth the different problems and alerting PRHA as
to the consequential delay. 	Eng. Delgado also recognized that during
the 	meetings 	between 	RCC’s 	and 	PRHA’s 	representatives, 	the 	problems
related to the construction work were discussed. 	(Tr. of 7/2/07, pp.
31-33, 62-65, 78-82; Tr. of 2/28/07, pp. 11-13; 107-108; 115; 122-129;
125-127; 130).
In 	examining 	RCC’s 	Exhibit 	41, 	Eng. 	Delgado 	recognized 	that 	the
letter sets forth that the change orders, extra work orders and other
issues caused the time of performance of the contract to be increased
from the original contract term of 540 calendar days to 1,878 days. 	He
admitted that there was a significant extension of time granted by PRHA
to RCC. 	He recognized RCC as a reliable and efficient contractor and
that 	there 	were 	many 	change 	orders 	and 	extra 	work 	orders 	(Tr. 	of
2/28/07, pp. 135-136).
As evidenced by Joint EX 41, RCC’s final claim, which includes a
claim for extended overhead and inefficiency, there were multiple claims
against PRHA arising from the PR-2 Mayagüez project. 	Joint EX 41 was
prepared by Eng. Bras, RCC’s project manager, with the participation of
RCC’s claims consultant, Mr. Civitello, and Arq. Redondo, based on the
number of days granted by PRHA, without considering any specific date
as to the substantial completion of the project. 	The claim goes into
the specifics of the process that was followed in its preparation, has
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 31 of 55
32
a detailed analysis of the different items claimed, the basis therefore,
and 	the 	effects 	of 	the 	change 	orders 	thereon. 	According 	to 	Eng.
Montero, RCC’s project engineer, and Eng. Bras, the signatory, Joint EX
41 is an accurate portrayal of what transpired at the project. 	(Joint
EX 41) (Tr. of 2/12/07, pp. 372; Tr. of 2/13/07, pp. 	402-407; 	Tr. of
2/14/07, pp. 152, 562, 635, 639-640; Tr. of 2/16/07, pp. 950-964, 976-
977, 1002-1012, 1025-1035, 1044-1049).
Lord’s and Remodelco’s claims against RCC are included in Joint EX
41, in accordance with Section 109.04 of the Blue Book. 	They are the
only two subcontractors with claims. 	(EX 68) (Tr. of 2/14/07, pp. 658-
659, 	668-691; 	Tr. 	of 	7/02/07, 	pp. 	1242-1243). 	And 	while 	PRHA 	argues
that it had no contractual relationship with Lord and Remodelco, these
claims were direct costs of completing the project.
The PR-2 Mayagüez project had many disruptions. 	There were many
factors that delayed the job, which resulted in additional work, through
thirty-nine change orders for approximately $3M, and thirty-two extra
work orders for around $2M. 	The change orders, with the additives and
deductive items, included 196 activities. 	The extra work orders include
ninety 	activities 	not 	contemplated 	in 	the 	original 	plans 	and
specifications. 	The change orders and extra work orders did not occur
in 	an 	organized 	sequence 	from 	one 	point 	to 	the 	other. 	They 	skipped
around 	different 	areas 	of 	the 	project, 	causing 	inefficiency, 	which
affected the work to be performed under the contract by RCC. 	The entire
footprint of the project was affected by the change orders and the extra
work orders, causing the extension of the contract until the substantial
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 32 of 55
33
completion on November 1, 1994, which added to the 540 original term,
resulting in an additional 1,127 calendar days. 	Eng. Delgado recognized
that 	the 	additional 	work 	that 	RCC 	was 	required 	to 	perform 	under 	its
contract with PRHA was substantial. 	(Joint EX 41, RCC’s EX 59) (Tr. of
2/12/07, pp. 62-63, 132, 143-147, 177-178; Tr. of 2/13/07, pp. 393-395;
Tr. of 2/14/07, pp. 665-674; Tr. of 2/16/07, pp. 961-977, 1025-1035; Tr.
of 7/2/07, pp. 27-28; Tr. of 2/28/07, p. 123).
The change orders were paid on the basis of unitary prices, the
mechanism 	provided 	for 	in 	the 	contract 	by 	which 	line 	items 	are
adjudicated by actual quantities. 	The extra work orders consisted of
new 	items 	of 	work 	not 	contemplated 	within 	the 	scope 	of 	the 	contract.
The change orders and extra work orders, which were prepared, approved,
and 	executed 	by 	PRHA, 	resulted 	in 	a 	modification 	of 	the 	original
contract and in an increase in the contract price from $14,750,000.00
to $19,828,959.00. 	Of this amount, RCC has been paid $18,071,303.83 by
PRHA. 	(Tr. of 2/16/07, pp. 961-962, 976-977; Tr. of 7/2/07, p. 40).
The number of change orders and extra work orders is evidence of
the 	disruption 	caused 	by 	the 	deficient 	drawings, 	the 	problems 	with
utilities, 	different 	site 	conditions, 	as 	well 	as 	PRHA’s 	delays 	in
solving 	the 	problems. 	The 	degree 	of 	changes 	resulted 	in 	a 	different
concept from what the contract originally intended, which affected the
sequence of the work, causing inefficiency. 	(Joint EX 41; RCC’s EX 19)
(Tr. of 2/12/07, pp. 62-63; Tr. of 2/13/07, pp. 395-397; Tr. of 2/16/07,
pp. 979-1035).
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 33 of 55
34
Joint EX 41 establishes that the actual conditions at the project
were materially different from those anticipated by RCC when submitting
its proposal as part of the bidding process, which under the contract,
allowed RCC to revise the unit prices originally contemplated and modify
them 	to 	more 	equitably 	reflect 	the 	actual 	conditions 	which 	were
experienced. 	The change and extra work orders did not cover or 	take
into consideration their effect in the unitary prices and the original
costs of the contract, considered by RCC when submitting its proposal
back in 1990. 	As a result of the extension of time and the extra work
required to complete the project, RCC requested that PRHA pay extended
overhead for the 1,338 additional days. 	(Tr. of 2/12/07, pp. 143-152).
During his deposition, Dr. González acknowledged his involvement
in 	the 	project, 	that 	it 	was 	completed 	during 	his 	tenure 	as 	PRHA’s
Executive Director, that it took “twice” the contract time (actually,
more than three times), that the extensions were not common, and that
the time delays had monetary consequences in favor of RCC. 	Dr. González
was aware of RCC’s claim. 	(RCC’s EX 64) (Tr. of 2/12/07, pp. 37-39, 40-
41, 68-69).
While 	PRHA 	recognized 	the 	direct 	costs 	of 	the 	new 	items 	in 	the
extra 	work 	orders 	and 	the 	change 	orders, 	it 	did 	not 	recognize 	the
overhead 	expense 	resulting 	therefrom. 	PRHA 	only 	awarded 	time,
indicating that overhead would be dealt with at the end of the project,
in line with Dr. González’ policy. 	To date, PRHA has not liquidated the
project. 	(Tr. of 2/12/07, pp. 59, 136-139).
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 34 of 55
35
As testified by Eng. Bras in cross-examination, Joint EX 41 is a
recollection of 5 years of the hazards, delays and problems that were
job experienced. 	He explained how the document was prepared. 	(Tr. of
2/14/07, pp. 646-646, 654-658). 	As project manager, Eng. Bras knew what
was going on in the project and had daily contact with Eng. Montero. He
visited the project once or twice per week. 	(Tr. of 2/14/07, pp. 663,
665).
The Court concludes that RCC has proven the disruptions in the
work 	performed 	and 	therefore 	established 	an 	entitlement 	to
inefficiency 	claims 	against 	PRHA. 	There 	was 	a 	reduction 	in 	the
expected productivity of labor and equipment, which went well beyond
the normal range of disruption inherent in the construction process.
These 	delays 	were 	caused 	solely 	by 	compensable 	events 	within 	the
control of PRHA.
By the end of 1993, the project was not accepted by Dr. González
due 	to 	the 	fine-tuning 	of 	the 	traffic 	lighting 	system 	designed 	by
him. 	Dr. 	González 	required 	that 	RCC 	give 	up 	this 	part 	of 	the
contract, which was deducted as a line item, and then awarded to Dr.
González’s 	company, 	while 	he 	was 	still 	PRHA’s 	Executive 	Director.
The back charge to the contract for this item resulted in a reduction
in 	the 	contract 	price. 	After 	the 	work 	was 	completed 	by 	the 	other
company, 	Dr. 	González 	accepted 	the 	project 	as 	substantially
completed. 	(Joint EXs 25, 26, 27, and 30) (Tr. of 2/13/07, pp. 264-
273).
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 35 of 55
36
In accepting the PR-2 Mayagüez project, Dr. González found it to
be in compliance with the conditions of the contract, constructed in
accordance 	with 	the 	plans 	and 	specifications, 	and 	reflecting 	no
visible 	deficiencies. 	It 	was 	accepted, 	pending 	its 	final
liquidation, 	in 	accordance 	with 	Section 	109.08 	of 	the 	Blue 	Book,
liquidation 	which 	has 	not 	taken 	place, 	notwithstanding 	having 	been
recommended by Eng. Delgado, after the acceptance of the project and
its turning over to the Department of Transportation and Public Works
of Puerto Rico. 	(Joint EXs 30 and 38; RCC’s EXs 33 and 34) (Tr. of
2/13/07, pp. 275-276, 280-284, 307-309).
On October 	4, 2001, RCC’s prior counsel, Rebeca Barnés, Esq.,
wrote to Dr. Fernando Fagundo, then PRHA’s Executive Director, in an
attempt 	to 	obtain 	an 	answer 	regarding 	RCC’s 	claim 	and 	commence
arbitration. 	(Joint EX 41 and RCC’s EX 42) (Tr. of 2/13/07, pp. 309-
316). 	This effort was undertaken after Eng. Bras, on February 21, 2001,
wrote 	to 	Dr. 	Luis 	Lluch, 	at 	the 	time 	PRHA’s 	Executive 	Director,
requesting an answer to the December 6, 2000 claim. 	(RCC’s EX 43) (Tr.
of 2/13/07, p. 316). 	Thereafter on October 31, 2001, in referring to
RCC’s demands for indirect expenses, inefficiency and other claims,
PRHA repeated that RCC’s claims would be dealt with at another level,
while recognizing the problems. 	(RCC’s EX 34(a)) (Tr. of 2/13/07,
pp. 284-294).
Having received no response to Ms. Barnés’ letter, on February 6,
2002, RCC again requested arbitration in accordance with Section 109.08
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 36 of 55
37
of 	the 	Blue 	Book. 	(RCC’s 	EX 	44) 	(Tr. 	of 	2/13/07, 	pp. 	317-321). 	On
February 	21, 	2002, 	counsel 	for 	PRHA 	responded 	to 	the 	letter 	of
February 6, 2002, stating that RCC could invoke arbitration within 30
days 	of 	notice 	of 	PRHA’s 	final 	decision 	on 	RCC’s 	claim, 	obviously
accepting that PRHA had not decided the same, indicating that RCC’s
demand 	was 	being 	referred 	to 	investigation, 	more 	than 	seven 	years
after the substantial completion of the project. 	(Joint EX 45) (Tr.
of 	2/13/07, pp. 321-329).
RCC 	filed 	Case 	No. 	KAC 	2002-1428 	with 	the 	local 	courts,
requesting arbitration. 	In response, PRHA contested the request for
arbitration 	because 	PRHA 	had 	still 	not 	decided 	RCC’s 	claim 	under
Section 109.08 of the Blue Book. 	In its answer, PRHA recognized the
submittal of RCC’s claim (Joint EX 41) and sustained that RCC’s cause
of action arose from a contractual relationship as to which RCC had
a 	fifteen-year 	term 	for 	the 	filing 	of 	its 	claim. 	PRHA 	further
recognized 	that 	RCC’s 	claim 	(Joint 	EX 	41) 	complied 	with 	the 	first
requirement of Section 109.08 of the Blue Book, in order to proceed
with 	arbitration, 	but 	claimed 	that 	since, 	as 	of 	the 	date 	of 	its
answer, PRHA had not denied totally or partially, RCC’s claim, RCC’s
complaint 	was 	premature 	because 	the 	second 	requirement 	for
arbitration 	[the 	denial 	of 	the 	claim] 	had 	not 	been 	met. 	PRHA
indicated its intention of processing RCC’s December 6, 2000 claim.
(Joint 	EXs 	41, 	57 	and 	58)(Tr. 	of 	2/13/07, 	pp. 	336-350; 	Tr. 	of
2/14/07, pp. 510-512).
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 37 of 55
38
It 	was 	not 	until 	August 	27, 	1996, 	that 	the 	documents 	for 	the
liquidation 	of 	the 	PR-2 	Mayagüez 	project 	were 	turned 	over 	to 	Mr.
Alamo. 	(Joint EX 50)(Tr. of 2/12/07, pp. 92; Tr. of 7/2/07, pp. 58-
60; 	Tr. 	of 	7/2/07, 	p. 	60). 	Mr. 	Alamo 	admitted 	that 	all 	of 	RCC’s
claims to PRHA had been stayed and that he was aware of Joint EX 41.
Furthermore, 	he 	indicated 	that 	the 	documents 	that 	had 	been 	turned
over to him in August 27, 1996, by Eng. Pérez for the liquidation of
the project 	had been lost, that he had to commence the liquidation
process 	again 	in 	2006, 	and 	that 	as 	of 	October 	3, 	2006, 	the 	final
liquidation of the PR-2 Mayagüez project had not been finalized, in
order 	for 	it 	to 	be 	turned 	over 	to 	PRHA’s 	finance 	department. 	Mr.
Alamo 	testified 	that 	the 	computation 	he 	was 	in 	the 	process 	of
completing, did not include the extension of time factor, which was
to be done separately from the liquidation. 	As did Eng. Pérez, Mr.
Alamo acknowledged that what transpired as to the liquidation of the
PR-2 	Mayagüez 	project 	was 	not 	common 	or 	usual. 	He 	could 	not
recollect any other project that had not been liquidated in thirteen
years, nor any other in which the liquidation documents had been lost
and thirteen years later, had to be redone. 	(Joint EX 50; RCC’ EX
62) (Tr. of 7/2/07, pp. 41-44, 62-65, 78-82).
Mr. 	López, 	Director 	of 	PRHA’s 	Pre-Intervention 	Office,
acknowledged 	having 	in 	his 	records 	the 	letter 	as 	to 	the 	final
inspection and acceptance of the PR-2 Mayagüez project (Joint EX 30)
with a value of $19,041,517.09, of which $18,121,896.51 had been paid
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 38 of 55
39
as to work performed by RCC, and that for the final liquidation to
come to his office, it had to be processed by the Construction Area
with a final report, which had to go first to PRHA’s Treasurer. 	As
to the issue of extended overhead, Mr. López stated that his office
receives recommendations from the Construction Area and that he had
not seen them in the case of the PR-2 Mayagüez project. 	He stated
that 	they 	were 	still 	waiting 	for 	the 	package 	to 	come 	from 	the
Construction 	Area 	for 	the 	liquidation 	of 	the 	project. 	Mr. 	López
indicated that of all projects pending liquidation, PR-2 Mayagüez was
the only one in which he was yet to receive the final certification
from the Construction Area. 	(RCC’s EX 66).
Mr. Del Valle, PRHA’s Treasurer, testified 	that he remembered
seeing the final inspection and acceptance of the project letter in
the file (Joint EX 30), and explained the procedure for the liquidation
of the PR-2 Mayagüez project after its final acceptance, which is the
delivery 	of 	the 	liquidation 	documents 	to 	the 	Construction 	Area 	for 	a
Contract 	Final 	Report, 	which 	could 	not 	be 	found 	in 	the 	file, 	as 	he
discussed on August 21, 2006. 	The Contract Final Report is necessary
for Mr. Del Valle’s office to evaluate the same and refer it to the Pre-
Intervention 	Office 	for 	the 	liquidation 	of 	the 	contract 	and 	payment.
(RCC’s EX 67).
Eng. Delgado testified that the PR-2 Mayaguez project had still
not 	been 	liquidated 	on 	February 	28, 	2007 	(the 	day 	of 	the 	hearing)
that it had been over thirteen years since the substantial completion
of the project and that he had not been involved in any other project
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 39 of 55
40
which took over thirteen years 	to be liquidated. 	(Tr. of 2/28/07,
pp. 143-144). 	Eng. Delgado admitted that the granting of additional
time 	to 	a 	contractor 	means 	that 	the 	contractor 	is 	entitled 	to
compensation for those additional days and that a contractor incurs
additional overhead expenses if the contract time is extended beyond
the original contract date (Tr. of 2/28/07, pp. 149-152).
Notwithstanding RCC’s demands for the amounts owed to it and its
two 	subcontractors 	under 	the 	contract, 	PRHA 	to 	date, 	more 	than
fifteen 	years 	after 	the 	substantial 	completion 	of 	the 	project, 	has
not proceeded with its liquidation and as a consequence, has failed
to pay RCC the items claimed to be due under the contract. 	(RCC’s
EXs 33, 34, 34A, 35, 36, 42, 43, and 44; Joint Exs. 27, 28, 30, 31,
41, 45, 56, 57, and 58) (Tr. of 2/12/07, pp. 62-63).
The original amount claimed by RCC as set forth in Joint EX 41
were 	corrected 	by 	Mr. 	Civitello 	as 	to 	certain 	mathematical 	errors,
including the inefficiency factor, as reflected in RCC’s EX 41(b) and
EX 	59. 	(RCC’s 	EXs 	4, 	5, 	6, 	41-A, 	41(b), 	52, 	59, 	and 	69) 	(Tr. 	of
2/12/07, pp. 152-156, 157-168, 169-200, 359, 360-368; Tr. of 2/13/07,
pp. 	351-368; 	Tr. 	of 	2/14/07, 	pp. 	693-697; 	Tr. 	of 	2/16/07, 	pp. 	79-
1001, 1013-1022, 1025-1035, 1044-1047, 1057-1068).
The 	Court 	finds 	that 	between 	the 	original 	completion 	date 	of
October 21, 1991 and June 30, 1994, which the Court accepts as the
true substantial completion date, there were 1003 	days. 	The Court
also finds that RCC’s on site daily expenses were $1,882.06 and the
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 40 of 55
41
home 	office 	overhead 	was 	$1,071.16 	per 	day 	(Ex. 	41). 	While 	PRHA
argues 	that 	the 	elimination 	of 	the 	night 	shift, 	resulting 	in 	work
that was supposed to be performed in two shifts being performed 	in
only one, may have affected the contract time, PRHA has not presented
any evidence to prove the percentage by which the time was arguably
affected. 	The elimination of the night shift 	was approved by PRHA
and by the Federal Highway Administration. 	The evidence was that the
night shift was not productive and that the material being removed
from one part of the project was inadequate for use in another, which
caused 	the 	borrow 	material, 	which 	PRHA 	approved. 	The 	Court 	also
concludes 	that 	RCC 	did 	not 	concurrently 	cause 	the 	delays 	and 	has
proven its damages with reasonable certainty. 	Prejudgment interest
will 	accrue 	from 	June 	30, 	1996, 	when 	RCC 	indicated 	that 	the 	final
payment was due.
Accordingly, PRHA owes RCC the following amounts as to the PR-2
Mayagüez project:
Construction Inefficiency (Contract + COs) 	$1,767,742.33
Equitable Adjustment for Extra Work Orders
Due to Inefficiency 	$ 	991,080.53
Extra Work Orders: 	$ 	306,594.79
Miscellaneous Items 	$126,594.79
Type X Sidewalks 	$180,000.00
Extended Time of Performance Overhead: 	$2,962,079.66
On-site Costs 	$1,887,706.18
Home Office 	$1,074,373.48
Claims of Subcontractors: 	$1,831,085.00
Lord 	$1,746,085.00
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 41 of 55
42
Remodelco 	$ 	85,000.00
Total Equitable Adjustment 	$7,858,582.31
Profit 10% 	$ 	785,858.23
Payment due on original Contract 	$1,757,659.12
TOTAL 	$10,402,099.66
AC-01657 (“Dorado-Toa Alta”), Adversary No. 03-0195
On 	September 	23, 	1998, 	the 	contract 	for 	the 	Dorado-Toa 	Alta
project 	was 	executed 	between 	RCC 	and 	PRHA. 	(RCC’s 	EX. 	1) 	(Tr. 	of
2/15/06, pp. 801-802). 	The contract included plans for a bridge to
be 	constructed 	across 	La 	Plata 	River 	and 	had 	four 	piers 	and 	two
abutments. 	RCC had to build a bridge on a short approach connecting
Road 165 from Toa Alta to Dorado, PR. 	(Tr. of 2/15/06, pp. 802-03).
Eng. 	Reynolds 	was 	in 	charge 	of 	this 	project. 	He 	was 	the 	project
manager for RCC and was also directly involved in the field. 	(Tr. of
2/15/06, p. 804).
On September 23, 1993, PRHA issued to RCC the notice to proceed
with the project by no later than October 4, 1993, with a total term
of 	540 	calendar 	days 	and 	an 	original 	completion 	date 	of 	March 	27,
1995. 	(RCC’s EX. 11) (Tr. of 2/15/06, pp. 804-805). 	On October 4,
1993, RCC commenced the project.
On 	May 	31, 	2001, 	PRHA 	issued 	the 	final 	report 	for 	the 	final
inspection 	as 	to 	the 	Dorado-Toa 	Alta 	project, 	with 	the 	original
amount 	of 	the 	contract 	as 	$2657,000.00, 	and 	a 	final 	value 	of
$3,063,042.54. 	The 	report 	indicated 	that 	the 	final 	inspection 	was
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 42 of 55
43
undertaken 	on 	October 	26, 	1995, 	and 	that 	the 	project 	was 	found
according 	to 	specifications 	with 	a 	completion 	date 	of 	September 	5,
1995. 	(RCC’s EX. 12)(Joint Ex. 14) (Tr. of 2/15/06, pp. 805-809).
Also 	on 	May 	31, 	2001, 	PRHA 	notified 	the 	Department 	of
Transportation of Puerto Rico that the project had been completed and
inspected, 	and 	that 	it 	should 	be 	included 	in 	the 	Department 	of
Transportation’s 	network 	for 	maintenance 	purposes. 	(RCC’s 	EX 	13)
(Tr. of 2/15/06, pp. 806-807).
During 	the 	construction 	of 	the 	project, 	RCC 	found 	several
problems that altered the character of the work that RCC anticipated.
At the beginning, rock excavation was found instead of 	the regular
excavation that was expected. 	During the construction of Pier 3, RCC
had to build a foundation that included pile driving because RCC had
a major de-watering problem in building the pier at the site. 	(Tr.
of 2/15/06, pp. 810-811). 	The problem impacted the project in terms
of 	costs 	and 	time, 	increasing 	both. 	None 	of 	the 	problems 	were
attributable to RCC (Tr. of 2/15/06, p. 811). 	They were considered
differing site conditions, attributable to the owner, PRHA. 	(Tr. of
2/15/06, p. 811). 	As of November 1994, there was zero completion of
work 	at 	Pier 	3 	because 	of 	the 	water 	problem. 	(Tr. 	of 	2/15/06, 	p.
817). 	In its answer 	to the adversary complaint, PRHA alleges that
RCC 	is 	not 	entitled 	to 	any 	damages 	for 	delays, 	if 	any, 	since
government caused delay was foreseeable and due to RCC’s experience
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 43 of 55
44
in 	the 	industry, 	its 	effects 	should 	have 	been 	included 	in 	the
contract price.
In referring to the cost report for the Dorado-Toa Alta project,
Eng. 	Reynolds 	indicated 	that 	through 	it, 	all 	costs 	related 	to 	the
project, as to each item, are tracked. 	The de-watering problem as to
Pier 	3 	is 	reflected 	in 	the 	cost 	report 	by 	the 	costs 	incurred 	in
reference to Pier 3. 	The cost report relates to RCC’s EX 16. 	This
exhibit 	tracks 	time 	and 	the 	cost 	report, 	the 	costs. 	RCC’s 	EX 	16
shows the delay (RCC’s EX 2) (Tr. of 2/15/06, pp. 822-831). 	RCC’s EX
10 shows a loss for the excavation of Pier 3 of $122,802.55 and as to
problems with the excavation of Pier 3, $334,752.56. 	(RCC’s EX 10)
(Tr. of 2/15/06, pp. 834-837).
Eng. Reynolds explained how, by the use of tremi-seal, which is
like a plug, the application of a concrete layer of two or three feet
of 	concrete, 	when 	there 	is 	a 	lot 	of 	water, 	is 	used 	in 	order 	to 	be
able 	to 	de-water 	and 	build 	the 	footing 	and 	the 	columns, 	and 	other
items. 	(Tr. of 2/15/06, pp. 851-852). 	In view of the water problem
at Pier 3, it was decided to change the elevation of the footing, for
which leave from the Corps of Engineers had to be obtained, due to
its flood control program. 	(RCC’s EX. 20) (Tr. of 2/15/06, pp. 853-
857). 	On March 13, 2005, Eng. Reynolds wrote to Eng. Gonzalo Aponte
(“Aponte”), 	supervisor 	for 	PRHA, 	Manatí 	Region, 	submitting 	the 	re-
design 	of 	Pier 	3 	to 	get 	approval 	therefore, 	which 	was 	obtained.
(RCC’s 	EX. 	22) 	(Tr. 	of 	2/15/06, 	pp. 	857-861). 	On 	March 	20, 	1995,
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 44 of 55
45
Eng. Reynolds wrote to Eng. Aponte requesting payment for the tremi-
seal concrete placed at the bottom of the footing installed at Pier
3, referring to four different sections of the contract that justify
the payment, totaling $30,229.00. 	This amount has not been paid to
RCC. 	(RCC’s EX. 26) (Tr. of 2/15/06, pp. 865-867).
Eng. 	Reynolds 	wrote 	to 	RCC’s 	consultant, 	Mr. 	Gale 	Green, 	who
helped 	RCC 	deal 	with 	the 	Corps 	of 	Engineers 	providing 	him 	with
information as to the problems encountered as to Pier 3. 	(RCC’s EX.
25) (Tr. of 2/15/06, pp. 854-855, 867-870). 	On March 31, 2005, Eng.
Reynolds wrote to Eng. Víctor Pellicier, attaching the acceptance of
the Corps of Engineers to the concept proposed for the solution to
the problem at Pier 3. 	It was sent to Eng. Pellicier in his capacity
as engineer of record. 	(RCC’s EX. 27) (Tr. of 2/15/06, pp. 87-876).
Through 	the 	correspondence 	of 	March 	31, 	1995 	(RCC’s 	EX. 	27), 	Eng.
Reynolds sent to Eng. Pellicier the acknowledgment of 	the Corps of
Engineers, that it had no problem with the modifications proposed by
RCC 	to 	Pier 	3, 	relative 	to 	the 	adjustment 	in 	elevation, 	which 	was
necessary for RCC to do the work. 	(Tr. of 2/15/06, p. 876).
On May 10, 1995, Eng. Héctor Ortega, resident engineer for PRHA,
wrote 	to 	Eng. 	Reynolds 	requesting 	that 	he 	provide 	the 	revised
construction schedule to complete the activities for the construction
of 	the 	project 	and 	for 	RCC 	to 	request 	additional 	time 	due 	to 	the
problems and the changes required at Pier 3. 	(RCC’s EX. 28) (Tr. of
2/15/06, 	pp. 	876-878). 	Because 	the 	Dorado-Toa 	Alta 	project 	was 	a
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 45 of 55
46
federally-funded project, the approval for the changes in elevation
of 	the 	footing 	at 	Pier 	3 	also 	had 	to 	be 	obtained 	from 	the 	Federal
Highway Authority. 	(RCC’s EX. 29) (Tr. of 2/15/06, pp. 878-882).
On May 22, 1995, Eng. Reynolds wrote to Eng. Aponte, regional
supervisor 	of 	the 	Dorado-Toa 	Alta 	project, 	submitting 	as 	an
attachment the impacted schedule to complete the work that was left,
as 	requested 	by 	PRHA, 	reflecting 	the 	actual 	conditions 	as 	of 	that
date. 	The 	same 	involved 	and 	included 	the 	impact 	caused 	to 	the
project by the different site conditions at Pier 3. 	The faxed letter
refers 	to 	de-watering, 	the 	sheet 	piling, 	the 	re-design 	of 	the
footing, 	the 	construction 	of 	Pier 	3, 	and 	the 	impacted 	schedule,
included 	as 	an 	attachment, 	reflects 	the 	incorporation 	of 	all 	the
revised dates and elements as to what happened in relation to Pier 3,
showing an extended date of September 12, 1995. 	(RCC’s EX. 30) (Tr.
of 2/15/06, pp. 886-889).
An internal document of PRHA dated May 24, 2005, signed by Eng.
Ocasio and Eng. José Hernández, PRHA’s director of design, consisting
of 	a 	memorandum, 	attaches 	the 	letter 	from 	the 	Federal 	Highway
Authority. 	(RCC’s 	EXs 	29 	and 	31) 	(Tr. 	of 	2/15/06, 	pp. 	889-890).
Eng. Reynolds was involved with the Dorado-Toa Alta project since the
bidding process. 	He was the full time project manager and became the
project engineer of the Dorado-Toa 	Alta project for the purpose of
solving 	the 	problems 	that 	RCC 	encountered. 	(Tr. 	2/26/07, 	pp. 	1104-
1105). 	Eng. 	Reynolds 	had 	a 	lot 	of 	experience 	in 	building 	bridges
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 46 of 55
47
over river beds. 	He was involved in the construction of the largest
bridge 	in 	Puerto 	Rico 	on 	PR-22 	Highway 	between 	Barceloneta 	and
Manatí. 	(Tr. 	of 	2/26/07, 	pp. 	1104-1105; 	1157-1159). 	After
explaining 	the 	method 	of 	construction 	and 	the 	determination 	of 	the
equipment 	to 	be 	used 	in 	a 	project 	of 	the 	nature 	of 	the 	Dorado-Toa
Alta project, Eng. Reynolds concluded that this project consisted of
a very basic bridge design. 	(Tr. of 2/26/07, pp. 1106-1107).
Eng. Reynolds described the type of protection to the excavation
which is used when working close to a river, indicating that a coffer
dam 	would 	normally 	be 	used 	and 	that 	some 	box 	protection 	could 	be
utilized. RCC considered using two large steel boxes to protect the
excavation from caving in when doing the installation of the piles.
(Tr. of 2/26/07, p. 1108). 	Being a standard bridge, RCC expected to
find 	some 	water 	in 	the 	river 	area. 	(Tr. 	of 	2/26/07, 	p. 	1109).
However, 	RCC 	found 	conditions 	different 	from 	those 	under 	which 	it
submitted its proposal. 	RCC expected to build a metal coffer dam to
protect 	the 	excavation 	from 	cave-ins 	and 	had 	a 	water 	control 	pump
available 	to 	take 	care 	of 	casual 	water, 	rain 	water 	or 	some 	minor
water that would come into the excavation. 	Nevertheless, what RCC
found at Pier 3 was basically an underground river plunging into the
excavation. 	(Tr. of 2/26/07, p. 1110). RCC’s EXs 33A, 33 B and 33E
when 	compared 	with 	RCC’s 	EX 	33C, 	illustrate 	the 	dry 	conditions 	of
Pier 1, 2 and 4, when compared with the water table found at Pier 3.
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 47 of 55
48
RCC’s EX 33D shows RCC’s involvement in the project and the extensive
equipment that was required.
The 	condition 	found 	at 	Pier 	3 	caused 	a 	change 	in 	the
construction method, since a tremi concrete seal had to be applied to
the 	bottom 	of 	the 	excavation 	in 	the 	coffer 	dam 	after 	driving 	the
piles at Pier 3, in order to try to seal the bottom of the excavation
so 	that 	the 	water 	would 	not 	come 	in 	from 	the 	bottom. 	RCC 	was
required to drain the piles from the water, apply the concrete seal,
use 	drain 	pumps 	to 	take 	the 	water 	out 	and 	build 	Pier 	3. 	(Tr. 	of
2/26/07, pp. 1111-1113).
For the construction of the coffer dam, RCC used two systems:
a 	box 	built 	out 	of 	steel 	beams, 	steel 	sheets 	and 	one–quarter-inch
plys 	of 	steel 	welded 	together, 	setting 	it 	with 	a 	crane, 	and 	in
addition, 	RCC 	placed 	sheet 	piles 	around 	the 	box, 	which 	are 	the
elements in RCC’s EX 33C around the box, creating a double system for
the 	excavation. 	The 	sheet 	piles 	were 	driven 	with 	a 	crane 	and 	a
vibratory 	hammer. 	This 	is 	illustrated 	in 	RCC’s 	EXs 	33J 	and 	33K,
which 	also 	show 	the 	coffer 	dam. 	The 	frame 	is 	the 	top 	of 	the 	box.
RCC’s EX 33G shows the frame and skin with the steel structure (Tr.
of 2/26/07, pp.1124-1133; 1159-1160). 	RCC’s EXs 33L and 33N show the
change in the sequence and logistics of the work that was necessary
due 	to 	the 	different 	site 	condition 	found 	at 	Pier 	3. 	These
photographs 	were 	taken 	between 	July 	and 	August 	1994. 	(Tr. 	of
2/26/07, p. 1171).
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 48 of 55
49
The condition found at Pier 3 was not contemplated. 	Once the
situation was under control, RCC forwarded 	RCC’s EX. 19 on January
19, 1995, to PRHA as to RCC’s intention to file a claim. 	Before the
letter, there were a number of conversations about the water problem
with 	PRHA’s 	representatives. 	(RCC’s 	EX 	19, 	22, 	25, 	26, 	30 	and 	39)
(Tr. of 2/26/07, pp. 1134-1135). 	Because there were several notices
of the problem to PRHA, the Court rejects its contention that it was
presented with RCC’s original claim approximately two years and three
months after the commencement of the project.
PRHA was aware of the problem (RCC’s EX 28, 30, 31, 34, 35 and
39). 	Eng. 	Reynolds 	participated 	in 	the 	analysis 	of 	the 	claim 	with
Arq. 	Redondo. 	The 	claim 	was 	prepared 	after 	the 	notices 	to 	PRHA.
(Tr. of 2/21/07, pp. 1144-1145). 	RCC’s EX 26 is a letter dated March
20, 1995, which is part of the claim for the tremi concrete. 	There
were also the additional costs incurred in the construction of Pier
3. 	(Tr. of 2/26/07, pp.1145-1146).
RCC’s 	EX 	16, 	the 	progress 	schedule 	for 	the 	Dorado-Toa 	Alta
project, shows that the water problem commenced around July 26, 1994,
and concluded on August 16, 1994. (Tr. of 2/26/07, pp. 1114-1117).
RCC’s EX 33C is a photograph of Pier 3, in which on the left corner,
one 	of 	the 	pumps 	can 	be 	seen. 	The 	pumps 	were 	under 	water. 	The
photograph 	shows 	water 	and 	was 	taken 	before 	the 	pump 	system 	was
installed. 	(Tr. of 2/26/07, pp. 1117-1119).
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 49 of 55
50
PRHA provided the information as to the Dorado-Toa Alta project.
(Tr. of 2/26/07, p. 1162). 	And to be competitive, RCC relied on the
information 	provided 	by 	PRHA. 	As 	stated 	by 	Eng. 	Reynolds,
construction projects are live projects. 	When there is a problem,
the owner is notified, but at that point the contractor does not know
whether 	there 	is 	a 	claim 	yet. 	Therefore, 	during 	the 	construction
meetings, the owner, PRHA, was notified, made aware of the problems
that RCC was facing during the construction of the project. 	(Tr. of
2/26/07, pp. 1163-1164; 1172).
Eng. Reynolds met with Eng. García, from GeoCim, Inc., and gave
him the information about the water problem, the plans and probably
some photographs. 	(Tr. of 2/26/07, p. 1148). 	The problems were not
reflected 	in 	the 	change 	orders 	or 	extra 	work 	orders. 	(Tr. 	of
2/26/07, p. 1149). 	Eng. García, Geotechnical Engineer, testified as
principal 	of 	GeoCim, 	Inc., 	which 	provides 	geotechnical 	engineering
services, 	including 	engineering, 	testing 	and 	subsoil 	exploration.
Geotechnical services is the branch of civil engineering in the area
that has to do with the ground, earth, or rocks and the engineering
problems 	related 	to 	this 	aspect 	of 	the 	natural 	soil 	and 	earth
materials. 	(Tr. of 2/26/07, pp. 1317-1329).
Eng. García was engaged by RCC for the Dorado-Toa Alta project
as a consultant to evaluate the situation which RCC encountered. 	RCC
asked Eng. García to evaluate what he could estimate in terms of de-
watering requirements, based on the information that was available at
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 50 of 55
51
the time of the bidding on the project, as opposed to what RCC was
experiencing. 	(Tr. of 2/26/07, pp.1330-1333).
Eng. 	García 	was 	provided 	with 	construction 	drawings, 	a
geotechnical 	report 	by 	Suelos, 	Inc., 	prepared 	for 	the 	firm 	that
designed 	the 	bridge 	for 	PRHA, 	photographs 	to 	illustrate 	conditions
during construction at the site, sketches of the coffer dam built by
RCC, information as to the pumps used by RCC and reports from field
inspectors 	that 	documented 	the 	use 	of 	pumps 	at 	the 	time. 	(Tr. 	of
2/26/07, 	pp. 	1337-1348; 	1352; 	1354; 	1396-1398). 	He 	concluded 	that
what 	was 	experienced 	by 	RCC 	as 	to 	the 	flow 	of 	water 	at 	Pier 	3 	was
three and a quarter times more than what was to be expected. 	(RCC’s
EX. 37, Tr. of 2/26/07, pp. 1348). 	Among other things, Eng. García
used the daily reports for the project during the construction work
at Pier 3 generated by an inspector for PRHA. 	These were the reports
that indicated the number of pumps in use during that time. 	(RCC’s
EX. 39, Tr. of 2/26/07, pp.1396-1398).
Eng. 	García’s 	opined 	that 	he 	would 	have 	estimated 	170,000 	to
230,000 	gallons 	of 	water 	per 	hour 	for 	the 	lowering 	of 	the 	ground
water 	level 	inside 	the 	coffer 	dam 	to 	maintain 	it 	fairly 	dry 	for
construction of Pier 3. 	The actual volume of water found by RCC at
Pier 	3 	was 	655,000 	gallons 	per 	hour. 	That 	is 	approximately 	3.27
times 	more 	than 	Eng. 	García’s 	estimate. 	(RCC’s 	Ex. 	37, 	Tr. 	of
2/26/07, 	pp. 	1352-1353). 	Eng. 	García 	concluded 	that 	it 	was 	not
reasonable 	for 	a 	contractor 	to 	have 	three 	times 	the 	flow 	of 	water
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 51 of 55
52
expected 	to 	be 	found 	in 	the 	Dorado-Toa 	Alta 	project 	at 	Pier 	3.
(RCC’s EX. 37, Tr. of 2/26/07, pp. 1418-1419).
As to the Dorado-Toa Alta project, Arq. Redondo was in charge of
the 	bid 	and 	as 	part 	of 	his 	regular 	duties 	went 	to 	the 	project 	at
least once a week. 	(Tr. of 2/26/07, p. 1483). 	As indicated by Eng.
Reynolds, RCC encountered one main problem, that of Pier 3, where a
differing site condition was found, due to the amount of water that
came from the ground. 	It was of such quantity that it could not be
controlled, until RCC poured concrete Class A, with the water inside
the coffer dam, as provided for in the contract if they encountered
that type of situation, that is, making a concrete mat to stop the
leakage 	of 	water 	from 	below 	the 	foundation. 	This 	is 	a 	concrete
foundation seal (tremi-seal). 	(RCC’s EX. 22, Tr. 2/26/07, pp. 1483-
1484). 	Once the tremi-seal was in place, RCC was able to handle the
amount of water (Tr. 2/26/07, p.1518).
The Blue Book specifies the use of a coffer dam and that type of
seal, as well as the method of payment of concrete Class A, as set
forth in Sections 206.04 and 601.315. 	(Tr. of 2/26/07, p. 1484).
RCC had seven pumps in a simultaneous 24-hour operation at the
project to control the water seepage and even with the seven pumps
RCC was not able to lower the water level until the tremi-seal was
installed. 	(Tr. of 2/26/07, pp. 114-117; 1486).
RCC was eventually able to complete the Dorado-Toa Alta project
and 	has 	a 	claim 	in 	reference 	thereto, 	due 	to 	the 	differing 	site
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 52 of 55
53
condition, which disrupted the entire project. 	(Tr. of 2/26/07, pp.
1484-1486). 	In 	RCC’s 	EX 	41, 	PRHA 	acknowledges 	that 	RCC 	had 	been
unable to empty the excavation at Pier 3, “a fact that should worry
not 	only 	the 	contractor 	but 	us 	at 	the 	agency.” 	(Tr. 	of 	2/26/07,
pp.1510-1511).
The Court concludes that the water problem encountered by RCC at
Pier 	3 	existed 	at 	the 	time 	of 	contracting 	and 	was 	materially
different 	from 	the 	conditions 	expected 	or 	reasonably 	anticipated.
Based 	on 	the 	testimony, 	the 	conditions 	encountered 	were 	reasonably
unforeseeable and caused RCC’s damages. 	Only one of the four piers
had 	the 	water 	problem, 	which 	required 	elevation 	of 	footing, 	tremi
seal concrete, approval of government agencies for the modifications
and pumps to drain the water. 	As admitted by PRHA, public contracts
expressly establish a different site conditions clause, which allows
for 	equitable 	adjustment 	of 	time 	and 	money 	for 	contract 	conditions
encountered at a site that vary materially from those indicated in
the 	contract 	documents. 	Likewise, 	a 	contractor 	can 	be 	compensated
for conditions that vary materially from those ordinarily encountered
on a project site.
As 	to 	RCC’s 	claim 	for 	the 	Dorado-Toa 	Alta 	project, 	the 	Court
will allow:
Extended main office overhead 	$ 23,814.00
Extended job site overhead 	$125,064.00
Total Extended overhead 	$148,878.00
Cost of additional work (Inefficiency) 	$596,233.44
Final Progress payment 	$ 15,092.24
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 53 of 55
54
Liquidated damages 	$ 33,600.00
Sub-Total 	$793,803.68
Profit factor 15% 	$119,070.55
TOTAL 	$912,874.23
The Court will also allow interest at 6.5% per annum from October 26,
1995 until judgment. 	(RCC’s EXs 3; 36; 46; 47, Tr. of 2/26/07, pp.
1488-1492; 1493-149; 1504-1505; 1507; Tr. of 2/28/07, pp. 1277-1278;
1281-1294; 	1297-1298). 	The 	Court 	will 	not 	allow 	the 	$32,483.41
sought by RCC for the payment of insurance and bonds, as RCC failed
to offer into evidence a copy of the insurance endorsement or proof
of payment.
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 54 of 55
55
ORDER
WHEREFORE IT IS ORDERED that in 	Adv. 03-0192, the Puerto Rico
Highway 	and 	Transportation 	Authority 	is 	liable 	to 	Redondo
Construction 	Corporation 	in 	the 	amount 	of 	$713,338.03, 	plus
prejudgment interest at 6.5% from February 27, 2007.
IT 	IS 	FURTHER 	ORDERED 	that 	in 	Adv. 	03-0194, 	the 	Puerto 	Rico
Highway 	and 	Transportation 	Authority 	is 	liable 	to 	Redondo
Construction 	Corporation 	in 	the 	amount 	of 	$10,402,099.66, 	plus
prejudgment interest at 6.5% from June 30, 1996.
IT 	IS 	FURTHER 	ORDERED 	that 	in 	Adv. 	03-0195, 	the 	Puerto 	Rico
Highway 	and 	Transportation 	Authority 	is 	liable 	to 	Redondo
Construction 	Corporation 	in 	the 	amount 	of 	$912,874.23, 	plus
prejudgment interest at 6.5% from October 26, 1995.
Each party shall bear their own costs and expenses.
Judgment will enter accordingly.
SO ORDERED.
San Juan, Puerto Rico, this 31st day of August, 2009.
BY THE COURT:
s/ Gerardo A. Carlo
_______________________
GERARDO A. CARLO
U.S. Bankruptcy Judge
Case:03-00192-ESL Doc#:159 Filed:08/31/09 Entered:08/31/09 15:34:29 Desc: Main
Document Page 55 of 55