CourtListener 3152234•Pesall v. Montana Dakota Utilities, Co.
Texte intégral
#27324-a-SLZ
2015 S.D. 81
IN THE SUPREME COURT
OF THE
STATE OF SOUTH DAKOTA
****
GERALD PESALL, Intervener and Appellant,
v.
MONTANA DAKOTA UTILITIES, CO.,
OTTER TAIL POWER and
THE SOUTH DAKOTA PUBLIC
UTILITIES COMMISSION, Appellees,
and
SCHURING FARMS, INC. and
BRADLEY MOREHOUSE, Interveners.
****
APPEAL FROM THE CIRCUIT COURT OF
THE FIFTH JUDICIAL CIRCUIT
DAY COUNTY, SOUTH DAKOTA
****
THE HONORABLE SCOTT P. MYREN
Judge
****
N. BOB PESALL
Flandreau, South Dakota Attorney for intervener
and appellant.
****
CONSIDERED ON BRIEFS
ON AUGUST 31, 2015
OPINION FILED 11/04/15
THOMAS J. WELK
JASON R. SUTTON of
Boyce Law Firm, LLP
Sioux Falls, South Dakota Attorneys for appellees
Montana Dakota Utilities Co.
and Otter Tail Power.
MARTY J. JACKLEY
Attorney General
JOHN J. SMITH
KAREN E. CREMER
Special Assistant Attorneys General
South Dakota Public Utilities Commission
Pierre, South Dakota Attorneys for appellee the
South Dakota Public Utilities
Commission.
#27324
ZINTER, Justice
[¶1.] Montana Dakota Utilities Co. and Otter Tail Power Company
(Applicants) filed an application with the South Dakota Public Utilities Commission
(PUC or Commission) for a permit to construct a high-voltage electrical
transmission line. Appellant Gerald Pesall objected to the project because he was
concerned that excavating and moving soil to construct the project might unearth
and spread a crop parasite. The PUC granted the permit on conditions, including a
condition to identify and mitigate the potential parasite problem. The circuit court
affirmed. Pesall’s appeal raises two issues: whether the permit condition relating to
the parasites constituted an improper delegation of authority to a private party;
and, whether the PUC exceeded a twelve-month time limit for rendering complete
findings on the application. We affirm.
Facts and Procedural History
[¶2.] On August 23, 2013, Applicants applied for a permit to construct a
345-kilovolt transmission line that would start near Ellendale, North Dakota; would
run through Brown, Day, and Grant counties in South Dakota; and would terminate
near Big Stone City. The construction involved the suspension of high-voltage
electrical lines from steel monopole towers. Each tower would be approximately 120
to 155 feet in height. The towers were to be attached to cylindrical concrete
foundations, six to eleven feet in diameter and twenty-five to thirty feet deep.
Construction required the removal and disposal of approximately thirty cubic yards
of soil for each tower.
-1-
#27324
[¶3.] Applicants’ project would cross one part of Pesall’s farm. Pesall
intervened and was granted party status. 1 In a subsequent contested-case hearing,
Dr. Gregory Tylka, one of Pesall’s witnesses, testified about soybean cyst nematodes
(SCNs). He testified that SCNs are soil-born parasites that can decrease soybean
productivity in infected fields. SCNs may exist in soil at depths of six feet, and they
may remain dormant for ten years. SCNs have been found in three of the counties
through which the transmission line would traverse. SCNs can spread by any
activity that moves soil. There is no dispute that the construction necessary to
build the proposed line could spread the parasite. However, wind, water erosion,
burns, typical farming practices, and even people walking over infected soil can also
spread SCNs. Furthermore, there was no evidence that SCNs infected any soil
along the project route.
[¶4.] Before the evidentiary hearing, Applicants and PUC staff submitted a
proposed settlement stipulation that would subject the permit to thirty-three
conditions. One condition addressed SCN mitigation. Condition 17 provided:
“Applicant shall develop and implement a mitigation plan to minimize the spread of
[SCNs] . . . in consultation with a crop pest control expert.” Pesall objected to the
proposed condition at the evidentiary hearing.
[¶5.] Following the hearing, PUC staff and Applicants entered into an
amended settlement stipulation that further addressed SCN mitigation. Pesall also
objected to this proposal. He did not, however, propose an alternative mitigation
1. Other parties/landowners also intervened, but they are not parties in this
appeal.
-2-
#27324
plan. Instead, he requested that the PUC deny the permit on grounds relating to
SCN mitigation, require the Applicants to reapply within three years, and limit the
reconsideration to SCN mitigation. The PUC acknowledged Pesall’s concerns, but
denied his request. The PUC found that the risk of spreading SCNs from the
project was not a serious threat. Additionally, in rendering its final decision to
grant the permit, the PUC modified Condition 17 to require PUC oversight of any
required SCN mitigation. Modified Condition 17 provided:
After Applicants have finished the soil sample field assessment
in accordance with the specifications for such assessment
prepared in consultation with an expert in the proper
methodology for performing such a sampling survey, Applicants
shall submit to the Commission a summary report of the results
of the field assessment and Applicants’ specific mitigation plans
for minimizing the risk of the spread of soybean cyst nematode
from contaminated locations to uncontaminated locations. At
such time and throughout the construction period, one or more
Commissioners or Staff shall have the right to request of
Applicants confidential access to the survey results to enable
verification of the survey results, assess the appropriateness of
the mitigation measures to address such results, and monitor
the execution of the plan during construction.
The PUC ultimately found that Applicants’ SCN mitigation plan, together with
modified Condition 17, would reasonably minimize the risk of spreading SCNs. The
PUC entered a written Final Decision and Order granting the permit subject to this
and other conditions.
[¶6.] Pesall appealed to the circuit court raising six issues. The circuit court
affirmed. Pesall now appeals to this Court raising two issues: (1) whether the PUC
improperly delegated its authority to a private party; and (2) whether the PUC
exceeded a statutory twelve-month time limit for issuing complete findings. Pesall’s
arguments raise questions of law and statutory interpretation. “[Q]uestions of law,
-3-
#27324
including statutory interpretation, are reviewed de novo.” In re Establishment of
Switched Access Rates for U.S. W. Commc’ns, Inc., 2000 S.D. 140, ¶ 13, 618 N.W.2d
847, 851.
Decision
[¶7.] A permit is required to construct the type of electrical transmission
line at issue in this case. See SDCL 49-41B-4. The Legislature conferred the
authority to grant or deny these permits on the PUC. Id.
[¶8.] Pesall first argues that the PUC should have rejected Applicants’
application because their mitigation proposal did not state with specificity what
Applicants would do to mitigate the spread of SCNs; what Applicants would do with
potentially contaminated soil; and how Applicants would prevent contaminated soil
from being transported by equipment from one field to another. Pesall argues that
the PUC should have required Applicants to correct these alleged defects and
reapply within three years. See SDCL 49-41B-22.1 (authorizing this procedure). 2
2. SDCL 49-41B-22.1 provides:
Nothing contained herein shall prohibit an applicant from
reapplying for a permit previously denied pursuant to § 49-41B-
24 or 49-41B-25 within three years from the date of the denial of
the original permit. Upon the first such reapplication, the
applicant shall have the burden of proof to establish only those
criteria upon which the original permit was denied, provided
that nothing in the reapplication materially changes the
information presented in the original application regarding
those criteria upon which the original permit was not denied.
However, nothing contained in this provision shall prohibit the
Public Utilities Commission from requiring such applicant to
meet its burden of proof as to any criteria, upon a specific
finding by the commission of a material change in the
circumstances regarding those criteria, but the Public Utilities
(continued . . .)
-4-
#27324
Although this was an alternative for the PUC, the PUC chose to grant the permit
subject to SCN mitigation conditions. The Legislature expressly authorized the
PUC’s choice, see SDCL 49-41B-24, 3 and we give “deference to PUC’s expertise and
special knowledge in the field of electric utilities,” Matter of N. States Power Co.,
489 N.W.2d 365, 370 (S.D. 1992). Pesall has not demonstrated an error of law or an
abuse of discretion in the PUC’s decision to grant a conditional permit rather than
requiring reapplication.
[¶9.] Pesall next argues that modified Condition 17 improperly delegated
the PUC’s authority to a private party. Pesall relies on In re Nebraska Power
District, 354 N.W.2d 713 (S.D. 1984).
[¶10.] In Nebraska Power District, the Nebraska Public Power District
(NPPD) applied for a permit to construct an electrical transmission facility. Id. at
715. Certain affected landowners had concerns about the soil handling procedures
to be used in the project. See id. at 716. In response, the PUC conditioned the
permit on a requirement that NPPD offer soil treatment options to the affected
landowners. Id. The options allowed the landowners to “require that NPPD utilize
________________________
(. . . continued)
Commission shall not, in any event, prepare or require the
preparation of an environmental impact statement.
3. SDCL 49-41B-24 provides:
Within twelve months of receipt of the initial application for a
permit for the construction of energy conversion facilities,
AC/DC conversion facilities, or transmission facilities, the
commission shall make complete findings in rendering a
decision regarding whether a permit should be granted, denied,
or granted upon such terms, conditions or modifications of the
construction, operation, or maintenance as the commission
deems appropriate.
-5-
#27324
other specified topsoil preservation procedures on their land.” Id. We concluded,
“SDCL 49-41B-24 dictates that the PUC is the only body which can impose terms
and conditions. Because no other statute expressly states that landowners can
dictate topsoil restoration conditions, the PUC had unlawfully delegated its
authority.” Id. at 719.
[¶11.] Nebraska Power District does not, however, apply in this case. In
Nebraska Power District, the private parties “could, if they desired, require that
NPPD utilize other specified topsoil preservation procedures on their land.” Id. at
716. We acknowledge that the PUC specified other procedures. Nevertheless, this
Court characterized the topsoil restoration program as a matter involving private
party “choice.” Id. at 720. In this case, the Applicants may not choose the
mitigation procedure because the PUC retained oversight authority to make the
ultimate decision. Consequently, Nebraska Power District is no support for the
proposition that the PUC delegated its authority to the Applicants. 4
[¶12.] On the contrary, the permit and the PUC’s modifications of Condition
17 reflect that the PUC retained its authority to make the ultimate decision
regarding SCN mitigation. There is no dispute that the PUC itself granted the
permit and imposed the mitigation conditions. Concededly, modified Condition 17
does not include a specific mitigation plan, but the condition requires Applicants to
4. Pesall also relies on two federal cases. See Ass’n of Am. R.Rs. v. U.S. Dep’t of
Transp., 721 F.3d 666 (D.C. Cir. 2013), vacated on other grounds sub nom.
Dep’t of Transp. v. Ass’n of Am. R.Rs., ___ U.S. ___, 135 S. Ct. 1225, 191 L.
Ed. 2d 153 (2015); and Carter v. Carter Coal Co., 298 U.S. 238, 269, 56 S. Ct.
855, 858, 80 L. Ed. 1160 (1936). These cases are inapposite because they
involved private actors exercising regulatory authority over other private
actors.
-6-
#27324
conduct a field assessment to determine if SCNs contaminate the soil. Additionally,
Applicants must consult an expert to ensure their field assessment follows a proper
methodology. Then, the permit condition requires Applicants to submit the field
assessment and a specific mitigation plan to the PUC for a sufficiency review.
Finally, under the permit condition, the PUC must verify the survey results, assess
the appropriateness of the mitigation measures, and monitor execution of the
mitigation plan during construction. Thus, although the PUC did not specify a
precise pre-construction mitigation plan, if SCNs are encountered during
construction, Applicants do not have the ultimate authority to choose the final
mitigation plan. Modified Condition 17 requires the PUC to oversee and determine
the actual mitigation requirements in light of the variables that will be encountered
in construction. 5 As the PUC indicated in its findings of fact, Condition 17 was
modified to provide “clarity concerning exactly what process [Applicants] would
follow in the SCN soil assessment[,] . . . mitigation plan development[,] [mitigation
plan] execution[,] and [the PUC’s] ability to verify and exercise its oversite authority
over the development and execution during construction.” (Emphasis added.) We
5. Applicants’ mitigation plan explained the dilemma:
Mitigating the spread of SCN from an existing affected field to a
non-SCN affected field, a variety of measures may be utilized,
which are dependent on soil conditions, weather conditions,
topography, distance traveled, equipment type, and cost.
Unfortunately, one mitigation measure alone is not a “catch-all”
and will be determined on a site-specific basis. Measures to
assist in the control of soils on equipment may include: cleaning
stations, utilizing clean crews for non-affected fields and a dirty
crew for affected fields, equipment mats, and weather-
dependent construction (i.e. frozen and dry soils). The measures
ultimately used will depend on the results of the sampling effort,
cost, resource availability, and contractor input.
-7-
#27324
conclude that modified Condition 17 did not delegate the PUC’s authority to the
Applicants. 6
[¶13.] Pesall also argues that the PUC did not issue complete findings on the
permit within twelve months as required by SDCL 49-41B-24. Pesall points out
that the PUC did not order a specific mitigation plan within a year after the
application was filed. Pesall contends that the PUC lacks authority to act after that
twelve-month deadline. The implication is that SDCL 49-41B-24 was violated
because the PUC made no specific finding on the ultimate mitigation plan that
would be implemented.
[¶14.] Applicants filed their application on August 23, 2013. On August 22,
2014, the PUC issued its Final Decision and Order. Detailed findings and modified
Condition 17 were included in the Final Decision and Order. Therefore, the PUC
timely rendered a decision granting the permit on conditions and included detailed
findings. We acknowledge Pesall’s point that specific mitigation plans are not
included: modified Condition 17 contemplates future action after the one-year
deadline. However, as previously noted, the future action involves PUC
enforcement of modified Condition 17. The fact that the PUC retained jurisdiction
to enforce its conditions does not mean they failed to render complete findings on
the permit. SDCL 49-41B-33 authorizes future enforcement of conditions: “A
permit may be revoked or suspended by [the PUC] for . . . [f]ailure to comply with
the terms or conditions of the permit[.]” See also In re Otter Tail Power Co. ex rel.
6. Pesall also advances three policy considerations for not allowing the PUC to
delegate its authority. We do not address those concerns because the PUC
did not unlawfully delegate authority to a private party.
-8-
#27324
Big Stone II, 2008 S.D. 5, ¶ 33, 744 N.W.2d 594, 604 (upholding a similar forward-
looking enforcement provision in a case where the permit required “that the
Applicants submit annual reviews of any regulations on CO2 emissions and their
efforts to comply with those regulations”). Enforcement of conditions is often
necessary in these types of cases. Pesall’s contrary suggestion is unsupported by
the nature of the project and the PUC’s statutory authority.
[¶15.] The PUC did not delegate its regulatory authority to Applicants, and
the PUC timely rendered complete findings on the permit application. We affirm.
[¶16.] GILBERTSON, Chief Justice, and SEVERSON, WILBUR, and KERN,
Justices, concur.
-9-