PUBLIC UTILITY CODE (66 PA.C.S.) - OMNIBUS AMENDMENTS
Act of Jul. 2, 1996, P.L. 542, No. 94 Cl. 66
Session of 1996
No. 1996-94
HB 2446
AN ACT
Amending Title 66 (Public Utilities) of the Pennsylvania
Consolidated Statutes, affirming the opportunity for an
electric public utility to restructure, buy down or buy out a
nonutility generation contract from which such utility has an
obligation to purchase electricity and affirming rate
recovery of certain electric utility payments for such
purposes.
The General Assembly makes the following findings:
(1) Electric public utilities in Pennsylvania have
entered into contracts with various nonutility project
developers for the purchase of electric capacity or energy,
or both, from nonutility projects, some of which are in
operation and some of which have not yet been completed. Some
of these contracts have been entered into voluntarily by such
utilities. Others have been entered into pursuant to orders
of the Pennsylvania Public Utility Commission. Such contracts
were predicated, in each case, on avoiding the estimated
costs the utility would have incurred but for the nonutility
project. The utilities' payments under such contracts are and
should continue to be recoverable from customers, as well as
the utilities' payments pursuant to other arrangements which
are negotiated, as provided for herein.
(2) Some nonutility generation projects have provided
benefits to utilities, consumers and the economy.
(3) Some of the existing contracts for nonutility
projects not yet completed may no longer be needed or
justified based on present cost estimates. This is due to
unanticipated and unforeseeable changes in economic factors
as a result of which either the utility no longer needs the
contract's electric capacity or energy or there are less
expensive alternatives by which the utility could obtain such
needed electric capacity or energy.
(4) From time to time it may be in the mutual interest
of a nonutility project developer, or owner of an operating
nonutility project, and a public utility to voluntarily
negotiate reasonable arrangements to buy down, buy out and
terminate or otherwise restructure existing contracts.
(5) Negotiated arrangements to buy down, buy out and
terminate or otherwise restructure contracts with operating
nonutility projects and contracts for unfinished projects may
be in the public interest.
(6) The costs prudently incurred by utilities under a
buy out, buy down or other restructuring arrangement should
be recoverable from customers.
The General Assembly of the Commonwealth of Pennsylvania
hereby enacts as follows:
Section 1. Section 527 of Title 66 of the Pennsylvania
Consolidated Statutes is amended to read:
§ 527. Cogeneration rules and regulations.
(a) Availability.--The commission shall promulgate rules and
regulations concerning the rates, terms, conditions and
availability of cogeneration in this Commonwealth. The
commission shall require that utility rates to the public
reflect the costs and savings to the utility from
cogeneration[.], including, but not limited to, the costs
incurred by utilities under contracts with nonutility generating
unit project developers for the purchase of electric capacity or
energy, or both; the costs recoverable under subsection (b) to
buy out and cancel unfinished nonutility generating unit
projects by mutual agreement of the project developer and the
public utility; and the costs prudently incurred by utilities
under a voluntary buy out, buy down or other restructured
arrangement which are just and reasonable and which reduce the
cost to customers of nonutility generating unit projects.
(b) Recovery of cancellation costs of nonutility generating
unit projects.--A nonutility generating unit project is a
generating unit project that is not owned by a public utility.
If the construction of a nonutility generating unit project for
which a public utility has a contract, whether entered into
voluntarily or pursuant to commission order, to purchase project
energy or project capacity and energy is canceled by mutual
agreement of the project developer and the public utility prior
to the unit's completion and operation, the public utility may
recover all costs to be paid to the project developer and all
costs directly related thereto which are prudently incurred as a
result of such cancellation. The burden of proof to show that
any costs claimed were prudently incurred shall be on the public
utility. In reviewing a claim for such costs:
(1) the commission shall not disallow any portion solely
on the basis that it constitutes an amount greater than
actual development expenditures and all costs related
thereto; and
(2) the commission shall consider the amount of the
claim compared to the utility's total estimated costs of
obligations under the contract.
Section 2. Nothing in this act shall be construed as:
(1) requiring an electric utility or a nonutility
generating unit project to enter into an arrangement to buy
down, buy out and terminate or otherwise restructure a
contract; or
(2) authorizing the Pennsylvania Public Utility
Commission to require regulated utility to pursue such an
arrangement with a nonutility generating unit project.
Section 3. This act shall take effect immediately.
APPROVED--The 2nd day of July, A. D. 1996.
THOMAS J. RIDGE