Pennsylvania Act 2012-154 — PENNSYLVANIA MUNICIPALITIES PLANNING CODE - CONTENTS OF SUBDIVISION AND LAND DEVELOPMENT ORDINANCE, COMPLETION OF IMPROVEMENTS OR GUARANTEE THEREOF PREREQUISITE TO FINAL PLAT APPROVAL AND RELEASE FROM IMPROVEMENT BOND

act-2012-0-1542012 Pa. Act 154Law

Act text
PENNSYLVANIA MUNICIPALITIES PLANNING CODE - CONTENTS OF SUBDIVISION AND LAND DEVELOPMENT ORDINANCE, COMPLETION OF IMPROVEMENTS OR GUARANTEE THEREOF PREREQUISITE TO FINAL PLAT APPROVAL AND RELEASE FROM IMPROVEMENT BOND
Act of Oct. 24, 2012, P.L. 1258, No. 154Cl. 53

Session of 2012

No. 2012-154

HB 1718

AN ACT

Amending the act of July 31, 1968 (P.L.805, No.247), entitled, as amended, "An act to empower cities of the second class A, and third class, boroughs, incorporated towns, townships of the first and second classes including those within a county of the second class and counties of the second through eighth classes, individually or jointly, to plan their development and to govern the same by zoning, subdivision and land development ordinances, planned residential development and other ordinances, by official maps, by the reservation of certain land for future public purpose and by the acquisition of such land; to promote the conservation of energy through the use of planning practices and to promote the effective utilization of renewable energy sources; providing for the establishment of planning commissions, planning departments, planning committees and zoning hearing boards, authorizing them to charge fees, make inspections and hold public hearings; providing for mediation; providing for transferable development rights; providing for appropriations, appeals to courts and penalties for violations; and repealing acts and parts of acts," in subdivision and land development, further providing for contents of subdivision and land development ordinance, for completion of improvements or guarantee thereof prerequisite to final plat approval, and for release from improvement bond.

The General Assembly of the Commonwealth of Pennsylvania hereby enacts as follows:

Section 1. Section 503(1) of the act of July 31, 1968 (P.L.805, No.247), known as the Pennsylvania Municipalities Planning Code, amended November 30, 2004 (P.L.1613, No.206), is amended to read:

Section 503. Contents of Subdivision and Land Development Ordinance.--The subdivision and land development ordinance may include, but need not be limited to:

(1) Provisions for the submittal and processing of plats, including the charging of review fees, and specifications for such plats, including certification as to the accuracy of plats and provisions for preliminary and final approval and for processing of final approval by stages or sections of development. Such plats and surveys shall be prepared in accordance with the act of May 23, 1945 (P.L.913, No.367), known as the "Engineer, Land Surveyor and Geologist Registration Law," except that this requirement shall not preclude the preparation of a plat in accordance with the act of January 24, 1966 (1965 P.L.1527, No.535), known as the "Landscape Architects' Registration Law," when it is appropriate to prepare the plat using professional services as set forth in the definition of the "practice of landscape architecture" under section 2 of that act. Review fees may include reasonable and necessary charges by the municipality's professional consultants for review and report thereon to the municipality. Such review fees shall be based upon a schedule established by ordinance or resolution. Such review fees shall be reasonable and in accordance with the ordinary and customary charges for similar service in the community, but in no event shall the fees exceed the rate or cost charged by the professional consultant for comparable services to the municipality for services which are not reimbursed or otherwise imposed on applicants. Fees charged to the municipality relating to any appeal of a decision on an application shall not be considered review fees and may not be charged to an applicant.

(i) The governing body shall submit to the applicant an itemized bill showing work performed, identifying the person performing the services and the time and date spent for each task. Nothing in this subparagraph shall prohibit interim itemized billing or municipal escrow or other security requirements. In the event the applicant disputes the amount of any such review fees, the applicant shall, no later than [45] 100 days after the date of transmittal of the bill to the applicant, notify the municipality and the municipality's professional consultant that such fees are disputed and shall explain the basis of their objections to the fees charged, in which case the municipality shall not delay or disapprove a subdivision or land development application due to the applicant's dispute over fees. Failure of the applicant to dispute a bill within [45] 100 days shall be a waiver of the applicant's right to arbitration of that bill under section 510(g).

(ii) In the event that the municipality's professional consultant and the applicant cannot agree on the amount of review fees which are reasonable and necessary, then the applicant and the municipality shall follow the procedure for dispute resolution set forth in section 510(g), provided that the arbitrator resolving such dispute shall be of the same profession or discipline as the professional consultant whose fees are being disputed.

(iii) Subsequent to a decision on an application, the governing body shall submit to the applicant an itemized bill for review fees, specifically designated as a final bill. The final bill shall include all review fees incurred at least through the date of the decision on the application. If for any reason additional review is required subsequent to the decision, including inspections and other work to satisfy the conditions of the approval, the review fees shall be charged to the applicant as a supplement to the final bill.


Section 2. Section 509(j) and (k) of the act, reenacted and amended December 21, 1988 (P.L.1329, No.170), are amended to read:

Section 509. Completion of Improvements or Guarantee Thereof Prerequisite to Final Plat Approval.--* * *

(j) As the work of installing the required improvements proceeds, the party posting the financial security may request the governing body to release or authorize the release, from time to time, such portions of the financial security necessary for payment to the contractor or contractors performing the work. Any such requests shall be in writing addressed to the governing body, and the governing body shall have 45 days from receipt of such request within which to allow the municipal engineer to certify, in writing, to the governing body that such portion of the work upon the improvements has been completed in accordance with the approved plat. Upon such certification the governing body shall authorize release by the bonding company or lending institution of an amount as estimated by the municipal engineer fairly representing the value of the improvements completed or, if the governing body fails to act within said 45-day period, the governing body shall be deemed to have approved the release of funds as requested. The governing body may, prior to final release at the time of completion and certification by its engineer, [require retention of] retain 10% of the [estimated cost of] original amount of the posted financial security for the aforesaid improvements.

(k) Where the governing body accepts dedication of all or some of the required improvements following completion, the governing body may require the posting of financial security to secure structural integrity of said dedicated improvements as well as the functioning of said dedicated improvements in accordance with the design and specifications as depicted on the final plat for a term not to exceed 18 months from the date of acceptance of dedication. Said financial security shall be of the same type as otherwise required in this section with regard to installation of such improvements, and the amount of the financial security shall not exceed 15% of the actual cost of installation of said dedicated improvements.


Section 3. Section 510(g) of the act, amended November 30, 2004 (P.L.1613, No.206), is amended to read:

Section 510. Release from Improvement Bond.--* * *

(g) The municipality may prescribe that the applicant shall reimburse the municipality for the reasonable and necessary expense incurred in connection with the inspection of improvements. The applicant shall not be required to reimburse the governing body for any inspection which is duplicative of inspections conducted by other governmental agencies or public utilities. The burden of proving that any inspection is duplicative shall be upon the objecting applicant. Such reimbursement shall be based upon a schedule established by ordinance or resolution. Such expense shall be reasonable and in accordance with the ordinary and customary fees charged by the municipality's professional consultant for work performed for similar services in the community, but in no event shall the fees exceed the rate or cost charged by the professional consultant to the municipality for comparable services when fees are not reimbursed or otherwise imposed on applicants.

(1) The governing body shall submit to the applicant an itemized bill showing the work performed in connection with the inspection of improvements performed, identifying the person performing the services and the time and date spent for each task. In the event the applicant disputes the amount of any such expense in connection with the inspection of improvements, the applicant shall, no later than [30] 100 days after the date of transmittal of a bill for inspection services, notify the municipality and the municipality's professional consultant that such inspection expenses are disputed as unreasonable or unnecessary and shall explain the basis of their objections to the fees charged, in which case the municipality shall not delay or disapprove a request for release of financial security, a subdivision or land development application or any approval or permit related to development due to the applicant's dispute of inspection expenses. Failure of the applicant to dispute a bill within [30] 100 days shall be a waiver of the applicant's right to arbitration of that bill under this section.

(1.1) Subsequent to the final release of financial security for completion of improvements for a subdivision or land development or any phase thereof, the professional consultant shall submit to the governing body a bill for inspection services, specifically designated as a final bill , which the governing body shall submit to the applicant . The final bill shall include inspection fees incurred through the release of financial security.

(2) If the professional consultant and the applicant cannot agree on the amount of expenses which are reasonable and necessary, then the applicant shall have the right, within [45] 100 days of the transmittal of the final bill or supplement to the final bill to the applicant, to request the appointment of another professional consultant to serve as an arbitrator. The applicant and professional consultant whose fees are being challenged shall, by mutual agreement, appoint another professional consultant to review any bills the applicant has disputed and which remain unresolved and make a determination as to the amount thereof which is reasonable and necessary. The arbitrator shall be of the same profession as the professional consultant whose fees are being challenged.

(3) The arbitrator so appointed shall hear such evidence and review such documentation as the arbitrator in his or her sole opinion deems necessary and shall render a decision no later than 50 days after the date of appointment. Based on the decision of the arbitrator, the applicant or the professional consultant whose fees were challenged shall be required to pay any amounts necessary to implement the decision within 60 days. In the event the municipality has paid the professional consultant an amount in excess of the amount determined to be reasonable and necessary, the professional consultant shall within 60 days reimburse the excess payment.

(4) In the event that the municipality's professional consultant and applicant cannot agree upon the arbitrator to be appointed within 20 days of the request for appointment of an arbitrator, then, upon application of either party, the President Judge of the Court of Common Pleas of the judicial district in which the municipality is located (or if at the time there be no President Judge, then the senior active judge then sitting) shall appoint such arbitrator, who, in that case, shall be neither the municipality's professional consultant nor any professional consultant who has been retained by, or performed services for, the municipality or the applicant within the preceding five years.

(5) The fee of the arbitrator shall be paid by the applicant if the [review fee charged is sustained by the arbitrator; otherwise, it shall be divided equally between the parties. If the disputed fees are found to be excessive by more than $5,000, the arbitrator shall have the discretion to assess the arbitration fee in whole or in part against either the applicant or the professional consultant. The governing body and the consultant whose fees are the subject of the dispute shall be parties to the proceeding.] disputed fee is upheld by the arbitrator. The fee of the arbitrator shall be paid by the charging party if the disputed fee is $2,500 or greater than the payment decided by the arbitrator. The fee of the arbitrator shall be paid in an equal amount by the applicant and the charging party if the disputed fee is less than $2,500 of the payment decided by the arbitrator.

(6) In the event that the disputed fees have been paid and the arbitrator finds that the disputed fees are unreasonable or excessive by more than $10,000, the arbitrator shall:

(i) award the amount of the fees found to be unreasonable or excessive to the party that paid the disputed fee; and

(ii) impose a surcharge of 4% of the amount found as unreasonable or excessive to be paid to the party that paid the disputed fee.

(7) A municipality or an applicant shall have 100 days after paying a fee to dispute any fee charged as being unreasonable or excessive.

Section 4. This act shall take effect in 60 days.

APPROVED--The 24th day of October, A.D. 2012.

TOM CORBETT