Questione giuridica chiave
Whether the appeal could challenge the requested underground tunnel alignment at Visp and the Rotten
Decisione estratta
The request was inadmissible because the dispute in the planning-approval procedure is limited to the objections raised in the objection proceedings; the tunnel solution was raised only later.
Motivazione estratta
The subject matter cannot be expanded on appeal beyond the issues raised in the opposition stage.