Questione giuridica chiave
Whether the parties concluded a contract for planning and construction of the logistics center
Decisione estratta
No contract was proven, neither by oral agreement, conclusive conduct, nor by the 1 October 2002 letter.
Motivazione estratta
The appellant failed to show arbitrariness in the factual findings. The letter was conditional on successful negotiations with the investor, and the overall project structure excluded a direct contract between appellant and respondent.