Questione giuridica chiave
Whether the cantonal court arbitrarily interpreted the March 18, 2004 agreement and judicial admissions regarding who had to restart the repair works.
Decisione estratta
No. The court could treat the agreement as incomplete and accept that the tenants were not required to contact the landlord again before ordering the remaining works.
Motivazione estratta
The minutes showed only a partial arrangement and the later conduct of the parties was compatible with the appeal court's reading. The tenants even exceeded their initial undertaking by advancing all costs.