Whether the plaintiff has claims against the defendant under the Internet-System contract.
The plaintiff has no further claims against the defendant under the contract.
32 C 14969/07•Internet-System Contract Claims and Counterclaim
32 C 14969/07Tribunale di primo grado14 gen 2009Diritto civileParzialmente accolto
Estratto da Omnilex
The Düsseldorf Local Court set aside its document-reservation judgment of 10 September 2008, dismissed the plaintiff's claim, and granted the defendant's counterclaim. It declared that the plaintiff had no further claims against the defendant under the Internet-System contract dated 14 June 2007. The plaintiff was ordered to bear the litigation costs, except for the costs attributable to the defendant's default, which the defendant must bear. The judgment was declared provisionally enforceable, subject to security provisions.
Entscheidungsdatum: 2009-01-14
Aktenzeichen: 32 C 14969/07
ECLI: ECLI:DE:AGD:2009:0114.32C14969.07.00
Dokumenttyp: Schlussurteil
Spruchkörper: 32. Abteilung
hat das Amtsgericht Düsseldorf
auf die mündliche Verhandlung vom 11.12.2008
durch den Richter am Amtsgericht X
für Recht erkannt:
Das Urkundsvorbehaltsurteil vom 10.09.2008 wird aufgehoben. Die Klage wird abgewiesen. Auf die Widerklage wird festgestellt, dass der Klägerin gegen die Beklagte aus dem Internet-System-Vertrag vom 14.06.2007, Vertrags-Nr. xxxxx, keinerlei weiteren Ansprüche gegen die Beklagte zustehen.
Die Kosten des Rechtsstreits trägt die Klägerin mit Ausnahme der Kosten der Säumnis der Beklagten, die die Beklagte trägt.
Das Urteil ist vorläufig vollstreckbar. Die Klägerin darf die Vollstreckung durch Sicherheitsleistung in Höhe von 110 % des vollstreckbaren Betrages abwenden, wenn nicht die Beklagte vor Vollstreckung Sicherheit in Höhe von 110 % des zu vollstreckenden Betrages leistet.
Whether the plaintiff has claims against the defendant under the Internet-System contract.
The plaintiff has no further claims against the defendant under the contract.
The defendant's counterclaim seeking a declaration that no further contractual claims are owed.
It is established that the plaintiff has no further claims against the defendant under the contract.
Disposition of the prior document-reservation judgment.
The document-reservation judgment of 10 September 2008 is set aside.
Allocation of litigation costs.
The plaintiff bears the costs, except the costs of the defendant's default, which are borne by the defendant.
Consulenza gratuita, senza impegno
Descrivi la tua situazione. Il nostro team ti ricontatterà via e-mail per la tua consulenza.
Collega Omnilex per cercare nel corpus legale dal tuo assistente IA.