In the
United States Court of Appeals
For the Seventh Circuit
____________________
No. 22-1466
NATIONAL WILDLIFE FEDERATION, et al.,
Plaintiffs-Appellants,
v.
U NITED STATES A RMY CORPS OF ENGINEERS, et al.,
Defendants-Appellees.
____________________
Appeal from the United States District Court for the
Southern District of Illinois.
No. 3:20-cv-00443-DWD — David W. Dugan, Judge.
____________________
A RGUED MARCH 27, 2023 — D ECIDED A UGUST 1, 2023
____________________
Before HAMILTON, SCUDDER , and P RYOR , Circuit Judges.
HAMILTON, Circuit Judge. Since 1910, Congress has author-
ized the U.S. Army Corps of Engineers to construct “river
training structures” on what is known as the Middle Missis-
sippi River to keep the river navigable. The Middle Missis-
sippi is the 195-mile-long stretch of the river from just north
of St. Louis, Missouri, where the Missouri River flows into the
Mississippi, downstream to Cairo, Illinois, where the Ohio
River flows into the Mississippi and more than doubles its
-- 1 of 28 --
2 No. 22-1466
flow. The more-than-century-old project is known as the Reg-
ulating Works Project. In 2017, the Corps published a final
supplemental environmental impact statement assessing the
ongoing project. That statement was used to support the
Corps’ 2017 decision to continue the overall program of build-
ing river training structures to maintain the navigable channel
in the Middle Mississippi. Plaintiffs, a coalition of environ-
mental organizations, challenge the Corps’ decision to con-
tinue with the project. They argue that the supplemental en-
vironmental impact statement did not comply with the Water
Resources Development Act of 2007 (WRDA), Pub. L. No. 110-
114, 121 Stat. 1041 (2007), or the National Environmental Pol-
icy Act of 1969 (NEPA), 42 U.S.C. § 4321, et seq. The district
court granted summary judgment for defendants, and plain-
tiffs now appeal. We affirm.
I. Factual and Procedural History
The Mississippi River watershed drains 1,245,000 square
miles—approximately one-third of the continental United
States—and includes all or part of thirty-two states. The wa-
tershed supports large tracts of forest, wetlands, and aquatic
habitats and is home to more than 300 species of birds, 57 spe-
cies of mammals, 45 species of amphibians and reptiles, and
150 species of fish. The Mississippi River is also a vital artery
for commerce.
In the nineteenth century, some areas of the Middle Mis-
sissippi measured a depth of only three and a half feet, which
was not enough for commercial vessels. The Mississippi River
Commission established by Congress recommended in 1881
the construction of permanent structures to deepen the chan-
nel. Letter from Robert T. Lincoln, Secretary of War, Transmitting
a Progress Report of the Miss. River Comm’n, S. Exec. Doc. No.
-- 2 of 28 --
No. 22-1466 3
47-10, at 18-20 (1881). The Commission recommended that
these structures be supplemented with dredging as needed to
maintain a navigable channel. Id. at 19.
In the Rivers and Harbors Act of 1910, Congress adopted
the 1881 plan and authorized the Corps to construct perma-
nent river training structures and to perform supplemental
dredging to maintain a channel eight feet deep, sufficient for
commercial traffic. Pub. L. No. 61-264, 36 Stat. 630, 659 (1910).
In the Rivers and Harbors Act of 1927, Congress modified the
Middle Mississippi project by adopting recommendations
made by the Chief of Engineers in his letter to Congress dated
December 17, 1926. Pub. L. No. 69-560, 44 Stat. 1010, 1012
(1927). In that letter, the Chief recommended that the author-
ized navigation channel from St. Louis to the Ohio River be at
least nine feet deep and 300 feet wide. Letter from the Chief of
Eng’rs to Hon. S. Wallace Dempsey, Chairman Comm. on Rivers
and Harbors, H.R. Doc. No. 69-9, at 4 (1926). He also recom-
mended that dredging be minimized because it produced
only temporary results on the Middle Mississippi. Id.
Three years later, Congress authorized the Corps to main-
tain a nine-foot channel for the remainder of the Middle Mis-
sissippi, from St. Louis upstream to the mouth of the Missouri
River. Rivers and Harbors Act of 1930, Pub. L. No. 71-520, 46
Stat. 918, 927 (1930). Consistent with this authorization, the
Corps has for decades built and maintained structures—such
as dikes, jetties, and chevrons—along the Middle Mississippi
to ensure that the channel stays deep and wide enough for
commercial navigation.
In 1976, after passage of the National Environmental Pol-
icy Act, the Corps prepared an environmental impact state-
ment assessing the ecological impacts of the project. In 2013,
-- 3 of 28 --
4 No. 22-1466
the Corps decided to supplement its 1976 environmental im-
pact statement for the Middle Mississippi project. Although
the project had not changed substantially since the Corps had
issued its initial environmental impact statement, the Corps
determined that a supplement was warranted due to new cir-
cumstances, such as newly designated threatened and endan-
gered species, and new information on the effects of river
training structures and dredging on fish and wildlife. In 2017,
the Corps issued a 1,400-page final supplemental environ-
mental impact statement and a record of decision that
adopted recommendations made in the final supplemental
statement.
In that statement, the Corps identified the purpose of the
project as ensuring a navigation channel at least nine feet
deep and 300 feet wide through the construction of regulating
works and supplemental dredging. After considering several
alternatives to pursue that goal, the Corps chose the “Con-
tinue Construction Alternative” as its preferred course. The
Corps decided to continue building permanent river training
structures until the cost of building such structures is no
longer justified by the resulting reduction in dredging costs.
Because the exact locations and types of river training struc-
tures that may be needed in the future are unknown, the sup-
plemental statement studied the project’s environmental im-
pacts at a programmatic level, assessing the impacts that “can
reasonably be anticipated to occur going forward.” The state-
ment noted that the Corps would perform site-specific envi-
ronmental assessments before actually building additional
river training structures.
In 2020, plaintiffs sued the Corps alleging that the 2017 fi-
nal supplemental environmental impact statement violated
-- 4 of 28 --
No. 22-1466 5
several federal laws, including the 2007 Water Resources De-
velopment Act and the National Environmental Policy Act.
On cross-motions for summary judgment, the district court
granted summary judgment for defendants on all claims. Na-
tional Wildlife Fed’n v. U.S. Army Corps of Eng’rs, No. 20-cv-
00443-DWD, 2022 WL 195332 (S.D. Ill. Jan. 22, 2022).
II. Analysis
We review the district court’s grant of summary judgment
de novo. Sauk Prairie Conservation Alliance v. U.S. Dep’t of the
Interior, 944 F.3d 664, 669 (7th Cir. 2019). Under the Adminis-
trative Procedure Act, which governs here, we may set aside
agency action if it is “arbitrary, capricious, an abuse of discre-
tion, or otherwise not in accordance with law.” 5 U.S.C.
§ 706(2)(A). When assessing whether agency action is arbi-
trary and capricious, our review is “deferential,” and we may
not “substitute [our] own policy judgment for that of the
agency.” FCC v. Prometheus Radio Project, 141 S. Ct. 1150, 1158
(2021). A reviewing court “simply ensures that the agency has
acted within a zone of reasonableness and, in particular, has
reasonably considered the relevant issues and reasonably ex-
plained the decision.” Id.
A. Water Resources Development Act of 2007
Plaintiffs contend that the Corps violated a paragraph in
the Water Resources Development Act of 2007 by failing to
prepare a detailed mitigation plan when it selected the Con-
tinue Construction Alternative as described in its 2017 final
supplemental environmental impact statement. Section 2283
of Title 33 of the United States Code is plaintiffs’ focus. Section
2283 is found in the midst of a host of statutory provisions
dealing with water resources all over the United States.
-- 5 of 28 --
6 No. 22-1466
Section 2283 addresses mitigation measures for fish and wild-
life affected by water projects.
Subsection (d) has long addressed mitigation plans in pro-
ject proposals. Plaintiffs contend the Corps’ final supple-
mental environmental impact statement and record of deci-
sion violated § 2283(d)(1), as amended in 2007. The 2007 Wa-
ter Act amended § 2283(d)(1) by adding the following itali-
cized language: “After November 17, 1986, the Secretary shall
not submit any proposal for the authorization of any water
resources project to Congress in any report, and shall not select
a project alternative in any report, unless such report contains”
either a specific plan to mitigate ecological damage or a find-
ing by the Secretary that the project will have negligible ad-
verse impact on fish and wildlife. Pub. L. No. 110-114,
§ 2036(a)(1), codified at 33 U.S.C. § 2283(d)(1).
Plaintiffs argue that the supplemental environmental im-
pact statement counts as a “report” under § 2283(d)(1) and,
because the document selected a project alternative (the Con-
tinue Construction Alternative), the Corps was required to
prepare a detailed mitigation plan as part of the report. The
Corps, on the other hand, insists that “report” in § 2283(d)(1)
refers more narrowly to reports submitted to Congress. Be-
cause neither the record of decision nor the supplemental en-
vironmental impact statement was submitted to Congress, the
Corps argues, it was not required to develop a detailed miti-
gation plan.
Both sides have offered good arguments about the proper
scope of “report” in § 2283(d)(1). As we explain below, several
factors persuade us that the better understanding of “report”
in § 2283(d)(1) is that the term refers only to a report submit-
ted to Congress. Under that paragraph, the Corps is therefore
-- 6 of 28 --
No. 22-1466 7
required to develop a specific fish and wildlife mitigation
plan for projects with non-negligible environmental impact
only when it submits a project proposal or selects a project
alternative in a report submitted to Congress. The Corps did
not submit the supplemental statement in this case to Con-
gress. Plaintiffs, on the other hand, focus more narrowly on
the word “report.” That focus tends to support plaintiffs’
view that the term is broader than “reports to Congress” and
can include environmental impact statements like the one at
issue here on the Middle Mississippi River, as well as a host
of other types of reports. We agree with the Corps.
Statutory language “cannot be construed in a vacuum.”
Sturgeon v. Frost, 577 U.S. 424, 438 (2016), quoting Roberts v.
Sea-Land Servs., Inc., 566 U.S. 93, 101 (2012); see also 1 William
Blackstone, Commentaries on the Laws of England § 2, p. 43
(Wayne Morrison ed., 2001) (“The fairest and most rational
method to interpret the will of the legislator, is by exploring
his intentions at the time when the law was made, by signs the
most natural and probable. And these signs are either the
words, the context, the subject-matter, the effects and conse-
quences, or the spirit and reason of the law.”). Statutory inter-
pretation is a “holistic endeavor,” and a provision that “may
seem ambiguous in isolation is often clarified by the remain-
der of the statutory scheme—because the same terminology
is used elsewhere in a context that makes its meaning clear.”
United Savings Ass’n of Texas v. Timbers of Inwood Forest Assocs.,
Ltd., 484 U.S. 365, 371 (1988). We can also trace the evolution
of statutory language to get a better understanding of the final
language enacted into law, e.g., Russello v. United States, 464
U.S. 16, 23–24 (1983), and actual implementation of statutory
language can offer further guidance in interpreting the text.
Congress’s response to agency or judicial interpretations of
-- 7 of 28 --
8 No. 22-1466
statutes—of which Congress is presumed to be aware—can
offer further guidance in interpreting the text. E.g., Forest
Grove School Dist. v. T.A., 557 U.S. 230, 239–40 (2009).
All of these interpretive tools are useful here. Before div-
ing into the details, we pause to note the lawmaking and pol-
icymaking context. From the early days of the Republic, inter-
nal improvements to promote commerce, including river
management and flood control, have been a major focus of
federal spending and personnel, with Congress legislating
and appropriating many details of the improvements. The di-
alogue between the Corps of Engineers and Congress has now
gone on for more than two centuries. Courts have not been
the most important participants in the dialogue, but they are
occasionally called upon to referee disputes among the major
players or to enforce laws at the behest of other parties, such
as the environmental groups who brought this case.
In construing the term “report” in § 2283(d), we look first
to textual clues provided by other, nearby provisions of the
Water Act. Congress has frequently used the word “report” to
refer only to reports submitted to Congress, including in the
same 2007 Water Act. See, e.g., 33 U.S.C. § 2282a(f)(2) (requir-
ing that “a report of the Chief of Engineers for a water re-
sources project” be submitted to specified congressional com-
mittees) (added by § 2033 of 2007 Water Act); § 2282d(a) (re-
quiring the Secretary of the Army to develop and submit to
Senate and House committees a “Report to Congress on Fu-
ture Water Resources Development”); § 2282e(a) (requiring
the Corps to prepare and submit to Congress a “post-author-
ization change report” for water resources development pro-
jects); § 2283a(1) (requiring the Secretary to submit to speci-
fied congressional committees “a report on the status of
-- 8 of 28 --
No. 22-1466 9
construction of projects that require mitigation”) (added by
§ 2036 of 2007 Water Act). By comparison, another nearby
provision uses “report” to instruct the Corps to prepare cer-
tain reports that are submitted not to Congress but to “the
non-Federal interest” sponsoring a water resources project,
but it makes that broader meaning plain. § 2282(b)(5). And
that language was added in 2020, long after the 2007 legisla-
tion we focus on in this case. See Pub. L. No. 116-260, Div. AA,
§ 117.
The textual signs in favor of the Corps’ position include
the fact that Congress used “report” to refer to submissions to
Congress in the verb clause that immediately precedes the
disputed phrase in § 2283(d)(1) itself: the specific fish and
wildlife mitigation requirement applies to water resources
project proposals submitted “to Congress in any report….”
§ 2283(d)(1). It is not unreasonable to think that congressional
drafters saw no need to repeat “to Congress” in the very next
verb phrase. We generally assume, “[a]bsent evidence of Con-
gress’s intent to the contrary,” that “Congress intended the
same words used close together in a statute to have the same
meaning.” United States v. LaFaive, 618 F.3d 613, 617 (7th Cir.
2010). That principle supports the view that “report” in
§ 2283(d)(1) means a report submitted to Congress.
In deciding whether “report” in 33 U.S.C. § 2283(d)(1) in-
cludes environmental impact statements that are not submit-
ted to Congress, we note that elsewhere in the 2007 Water Re-
sources Development Act, Congress distinguished between
“reports” and associated environmental impact statements. In
§ 2043 of the 2007 Act, Congress defined “feasibility report”
as “each feasibility report, and any associated environmental
impact statement and mitigation plan” prepared by the Corps
-- 9 of 28 --
10 No. 22-1466
for a water resources project. Pub. L. No. 110-114, § 2043, cod-
ified at 33 U.S.C. § 2282(a)(4). Section 2041 similarly distin-
guishes between environmental impact statements and “re-
ports.” That section requires the Secretary to provide the Li-
brary of Congress with, among other things, a copy of each
“final environmental impact statement” and each “report to
Congress prepared by the Corps of Engineers.” Pub. L. No.
110-114, § 2041, codified at 33 U.S.C. § 2346(b)(1). If the term
“report” already encompassed environmental impact state-
ments that are not sent to Congress routinely, there would
have been no need for Congress to mention environmental
impact statements expressly in these provisions.
The weight of these textual clues favors the Corps’ view
here. Still, as plaintiffs point out, the key phrase in
§ 2283(d)(1) does not expressly limit “report” to reports sub-
mitted to Congress. If that is indeed what Congress meant, it
would have been easy to make that meaning unmistakably
clear. We therefore continue consideration of other indica-
tions of statutory meaning. We find important corroboration
of the Corps’ view in the history of the 2007 amendment. The
Senate first adopted a version of what became the 2007 Water
Resources Development Act with language that would have
amended § 2283(d)(1) to require the precise result plaintiffs
seek here. The Senate version would have provided that the
Secretary shall not submit any proposal for authorization and
“shall not select a project alternative in any final record of de-
cision, environmental impact statement, or environmental as-
sessment, unless the proposal, record of decision, environ-
mental impact statement, or environmental assessment” con-
tains a specific mitigation plan or a finding by the Secretary
that the project would have negligible adverse impact on fish
and wildlife. S. Rep. No. 110-58, at 103 (2007).
-- 10 of 28 --
No. 22-1466 11
The House version, by contrast, proposed no change to
§ 2283(d)(1). H.R. Rep. No. 110-80, at 20 (2007). In a conference
committee, the Senate proposal favoring these plaintiffs’ view
was rejected. In the language of congressional conference
committees, the conference substitute that was enacted into
law reflects a compromise reached in the conference commit-
tee: Congress limited § 2283(d)(1) to “reports,” but it ex-
panded its reach to cover any report to Congress that selects
a project alternative, not just those proposing new projects.
H.R. Rep. No. 110-280, at 54 (2007) (Conf. Rep.); 33 U.S.C.
§ 2283(d)(1).1
Comparing the Senate version to the final statute as
enacted shows that if we were to adopt plaintiffs’
interpretation of “report,” we would read into the statute
language that Congress expressly rejected. We decline to do
so. Chickasaw Nation v. United States, 534 U.S. 84, 93 (2001),
quoting INS v. Cardoza-Fonseca, 480 U.S. 421, 443 (1987)
(Courts “ordinarily will not assume that Congress intended
‘to enact statutory language that it has earlier discarded in
favor of other language.’”); Victoria Nourse, Misreading Law,
Misreading Democracy 80 (2016) (explaining that when
interpreting legislative history, “[l]ater textual decisions
1 The 2007 conference committee report illustrates the level of detailed
congressional attention to water resources. The 369-page report includes
hundreds of provisions specific to particular rivers, harbors, and stretches
of rivers, including authorizing more than 100 new projects and adding
“project-related provisions” for 178 different projects, studies for 99 pro-
jects, and other provisions for more than 150 other projects. Similarly nu-
merous and detailed legislative provisions on water projects are common
in other omnibus water bills.
-- 11 of 28 --
12 No. 22-1466
trump earlier ones[,]” such that conference committee reports
changing relevant language can be especially helpful).
Finally, the Corps’ actual implementation of the 2007 Wa-
ter Act and congressional responses to that implementation
give further support to the narrower reading of “report” in
§ 2283(d)(1) that we adopt here. In 2009, the Corps issued im-
plementation guidance explaining that the 2007 Water Act
amended § 2283(d)(1) to require that “any report, submitted to
Congress for authorization, shall not select a project alternative
unless such report contains” a specific mitigation plan or a
determination that the project will have negligible adverse
impacts. U.S. Army Corps of Engineers, Memorandum for
Commanders: Implementation Guidance for Section 2036(a)
of the Water Resources Development Act of 2007 (WRDA
07)—Mitigation for Fish and Wildlife and Wetlands Losses
(Aug. 31, 2009), at 1(a) (emphasis added). If the Corps was
wrong in that interpretation, we have no evidence that Con-
gress has taken any action expressing disagreement. In fact,
in the fourteen years since the Corps issued that guidance,
Congress has passed several more Water Resources Develop-
ment Acts. It has not acted to amend the relevant language in
§ 2283(d)(1). See Water Resources Reform and Development
Act of 2014, Pub. L. No. 113-121, 128 Stat. 1193 (2014); Water
Resources Development Act of 2016, Pub. L. No. 114-322, 130
Stat. 1632 (2016); Water Resources Development Act of 2018,
Pub. L. No. 115-270, 132 Stat. 3768 (2018); Water Resources De-
velopment Act of 2020, Pub. L. No. 116-260, 134 Stat. 2615
(2020); Water Resources Development Act of 2022, Pub. L. No.
117-263, 136 Stat. 3691 (2022). This history provides strong ev-
idence that Congress approves the Corps’ interpretation. See
Forest Grove School Dist., 557 U.S. at 239–40, quoting Lorillard v.
Pons, 434 U.S. 575, 580 (1978) (“Congress is presumed to be
-- 12 of 28 --
No. 22-1466 13
aware of an administrative or judicial interpretation of a stat-
ute and to adopt that interpretation when it re-enacts a statute
without change.”). This reasoning from evidence of agency
implementation takes on special force in the context of federal
water projects and the close working relationship between
Congress and the Corps.
Plaintiffs insist, however, that construing “report” to mean
“reports submitted to Congress” would give no effect to the
2007 amendment. In their view, before 2007 the Corps was re-
quired to develop a specific mitigation plan for projects ex-
pected to cause more than negligible adverse environmental
impact whenever it selected a project alternative in a report
submitted to Congress. We agree with the general principle in
interpreting statutory amendments, but we disagree with the
proposed application to the 2007 amendment to § 2283(d)(1).
Before the 2007 amendment, § 2283(d)(1) applied only to
project proposals in reports submitted to Congress. See 33
U.S.C. § 2283(d)(1) (1986) (providing that “the Secretary shall
not submit any proposal for the authorization of any water re-
sources project to the Congress unless such report contains” a
specific mitigation plan or a determination of negligible ad-
verse impact on fish and wildlife) (emphasis added). The 2007
amendment thus broadened the provision’s reach to include
other reports submitted to Congress that select a project alter-
native, such as reevaluation reports submitted to Congress to
change an authorized project.
We recognize that the term “report” in the 2007 amend-
ment to § 2283(d)(1) does not contain the explicit limitation
the Corps advocates here. Taken in isolation, the English
word “report” is broad enough to cover the supplemental fi-
nal environmental impact statement. It was a report to the
-- 13 of 28 --
14 No. 22-1466
public assessing the environmental impact of the regulating
works project and different ways of moving forward with the
project. These other cues from associated statutory provi-
sions, the history of the statutory language at issue, and the
history of its implementation persuade us, however, to agree
with the Corps that the better reading is that Congress used
“report” in § 2283(d)(1) to refer to reports submitted to Con-
gress. Because neither the 2017 record of decision nor the final
supplemental environmental impact statement for the Middle
Mississippi River was such a report, the Corps was not re-
quired to develop a specific mitigation plan within the scope
of § 2283.2
B. National Environmental Policy Act
We turn next to plaintiffs’ arguments that the final supple-
mental environmental impact statement violated require-
ments of the National Environmental Policy Act. For all “ma-
jor Federal actions significantly affecting the quality of the hu-
man environment,” the Act requires agencies to develop a
“detailed” environmental impact statement. 42 U.S.C.
§ 4332(2)(C). This statement should describe the environmen-
tal impact of the proposed action and analyze potential alter-
natives. Id. Here, plaintiffs allege that the supplemental state-
ment’s purpose-and-need statement was inadequate, that the
Corps failed to explore reasonable alternatives, and that the
Corps did not meaningfully consider the studied alternatives.
We find no violation of the Act.
2 The final supplemental environmental impact statement does, how-
ever, include an appendix detailing the Corps’ plans to mitigate habitat
losses caused by the project. We do not decide here whether the appendix
would be sufficient to comply with the mitigation requirements of § 2283.
-- 14 of 28 --
No. 22-1466 15
1. Purpose-and-Need Statement
An environmental impact statement must “briefly specify
the underlying purpose and need to which the agency is re-
sponding in proposing the alternatives including the pro-
posed action.” 40 C.F.R. § 1502.13 (1978).3 We review an
agency’s purpose-and-need statement for reasonableness and
grant agencies “considerable discretion to define a project’s
purpose and need.” Alaska Survival v. Surface Transp. Bd., 705
F.3d 1073, 1084 (9th Cir. 2013). An agency may not, however,
“contrive a purpose so slender as to define competing ‘rea-
sonable alternatives’ out of consideration.” Simmons v. U.S.
Army Corps of Eng’rs, 120 F.3d 664, 666 (7th Cir. 1997). When
an agency acts “pursuant to a specific statute, the statutory
objectives of the project serve as a guide by which to deter-
mine the reasonableness of objectives outlined” in the envi-
ronmental impact statement. Westlands Water Dist. v. U.S.
Dep’t of the Interior, 376 F.3d 853, 866 (9th Cir. 2004).
Here, the supplemental statement identified the project’s
purpose as “obtaining and maintaining a navigation channel”
on the Middle Mississippi that is at least nine feet deep and
300 feet wide. The statement noted further that the “long-term
goal of the Project, as authorized by Congress, is to obtain and
maintain a navigable channel and reduce federal expendi-
tures by alleviating the amount of annual maintenance dredg-
ing through the construction of regulating works.” The pur-
pose of the supplemental environmental impact statement
3 The Council on Environmental Quality amended NEPA regulations
in 2020 and 2022. 85 Fed. Reg. 43,304 (July 16, 2020); 87 Fed. Reg. 23,453
(Apr. 20, 2022). Throughout this opinion, we cite the NEPA regulations in
effect in 2017 at the time of the challenged action.
-- 15 of 28 --
16 No. 22-1466
itself was to assess the project’s effects on the environment
and to update the 1976 environmental impact statement in
light of new information.
The Corps reasonably defined the purpose and need for
the project. Congress authorized the project in the Rivers and
Harbors Act of 1910. Pub. L. No. 61-264, 36 Stat. at 659. It later
modified the project in the Rivers and Harbors Act of 1927 “in
accordance with the recommendations submitted by the
Chief of Engineers” in his letter to Congress. Pub. L. No. 69-
560, 44 Stat. at 1012. In that letter, the Chief recommended a
channel at least nine feet deep and 300 feet wide, and he ad-
vised that this channel be maintained through the construc-
tion of permanent river training structures. Letter from the Chief
of Eng’rs, H.R. Doc. No. 69-9, at 4. Though he acknowledged
that some amount of dredging “will probably always be nec-
essary,” he recommended that it be “reduced to a minimum”
because it offered only temporary results. Id. The 2017 final
supplemental statement’s purpose-and-need statement tracks
this Congressional authorization. It identifies the purpose of
the project as maintaining a navigable channel in the Middle
Mississippi River at least nine feet deep and 300 feet wide
through the construction of permanent river training struc-
tures and minimal dredging. The Corps tailored the purpose
and need of its project to Congress’s specific instructions.
Plaintiffs argue, however, that the Corps ignored limits in
the project’s authorizing legislation. In their view, the Corps
was authorized to build structures only to narrow the river to
a certain width. Once the authorized width was obtained,
they insist, the Corps was required to maintain the channel
through dredging. Plaintiffs are mistaken. Though they cite
the Chief of Engineers’ letter in support of their position, they
-- 16 of 28 --
No. 22-1466 17
do not cite his recommendations. The Chief included pro-
posals from the Board of Engineers for Rivers and Harbors
and the District Engineer, Major John C. Gotwals, in his letter
to Congress. Letter from the Chief of Eng’rs, H.R. Doc. No. 69-9,
at 4–31. In their brief, plaintiffs cite the letter of the District
Engineer, who recommended that the channel be maintained
through dredging once the river is contracted to a certain
width. Congress, however, specifically adopted the recom-
mendations “submitted by the Chief of Engineers,” not those
of the District Engineer. Rivers and Harbors Act of 1927, Pub.
L. No. 69-560, 44 Stat. at 1012.
The plaintiffs’ remaining arguments are unpersuasive.
They argue that the purpose-and-need statement ignores
Congress’s other directives—found in the National Environ-
mental Policy Act, various Water Resources Development
Acts, and the Fish and Wildlife Coordination Act, 16 U.S.C.
§ 661 et seq.—to protect the environment and mitigate ecolog-
ical damage. None of these acts, however, modified the pro-
ject’s authorization or purpose. And, while agencies should
“always consider the views of Congress, expressed … in the
agency’s statutory authorization to act, as well as in other con-
gressional directives,” Citizens Against Burlington, Inc. v.
Busey, 938 F.2d 190, 196 (D.C. Cir. 1991), the Corps was not
arbitrary or capricious when it defined the project’s goals ac-
cording to the project aims authorized by Congress.
Finally, plaintiffs contend that the purpose-and-need
statement is unduly narrow, because it assumes that only
river training structures can achieve the project’s purposes.
They argue that defining the project’s purpose and need in
this manner restricted the range of reasonable alternatives
that could be considered. While an agency may not
-- 17 of 28 --
18 No. 22-1466
“constrict[ ] the definition of the project’s purpose and
thereby exclude[ ] what truly are reasonable alternatives,”
Simmons, 120 F.3d at 666, that did not occur here. Congress
instructed the Corps to maintain the channel by using perma-
nent structures and by using supplemental dredging, but no
more than necessary and economical. The Corps, in turn, de-
veloped a statement of purpose and need that reflected these
instructions from Congress. It was not arbitrary and capri-
cious to do so.
2. Consideration of Reasonable Alternatives
Next, plaintiffs argue that the Corps failed to consider rea-
sonable alternatives in its supplemental impact statement. An
environmental impact statement must “[r]igorously explore
and objectively evaluate all reasonable alternatives” to the
proposed project, including “reasonable alternatives not
within the jurisdiction of the lead agency” and the alternative
of taking no action. 40 C.F.R. § 1502.14. A project’s purpose
determines the range of reasonable alternatives, and the
“broader the purpose, the wider the range of alternatives; and
vice versa.” Simmons, 120 F.3d at 666. “The existence of a via-
ble but unexamined alternative renders an environmental im-
pact statement inadequate.” Westlands Water Dist., 376 F.3d at
868, quoting Morongo Band of Mission Indians v. Fed. Aviation
Admin., 161 F.3d 569, 575 (9th Cir. 1998). Agencies, however,
need to evaluate only reasonable alternatives: they need not
consider alternatives that would be “impossible for the
agency to implement” or that would “frustrate the project’s
goals.” Protect Our Parks, Inc. v. Buttigieg, 39 F.4th 389, 400 (7th
Cir. 2022). We “owe and accord deference to the Corps” in de-
termining which alternatives are reasonable, considering the
project’s purposes. Simmons, 120 F.3d at 668–69.
-- 18 of 28 --
No. 22-1466 19
As discussed above, the supplemental impact statement
identified the Middle Mississippi project’s purpose as main-
taining a navigation channel that is nine feet deep and 300 feet
wide through the use of river training structures and minimal
supplemental dredging. The Corps evaluated several alterna-
tives before determining that only two warranted detailed
study.
In response to public comments, the Corps considered
conducting environmental restoration and enhancement
measures for fish and wildlife habitat as part of the project.
The Corps ultimately determined that this was not a reasona-
ble or feasible alternative because Congress had not author-
ized the Corps to undertake such measures without specific
funding and a cost-share partner. The Corps also considered,
in response to public comments, other ways to maintain the
Middle Mississippi channel, such as altering water releases
from the Upper Mississippi through locks and dams. That too
was determined to be an unreasonable alternative because the
locks and dams on the Upper Mississippi are maintained
through a different authorized project. That rationale has
more than a whiff of bureaucratic rigidity to it, but more sub-
stantively, the Corps also concluded that, while it was possi-
ble to alter some water control procedures to improve naviga-
tion on the Middle Mississippi, prior experience, especially
during the serious drought of 2012, indicated that these alter-
ations would not be substantial enough to accomplish the
purpose of the project and would not constitute a reasonable
alternative.
The Corps also revisited four alternatives studied in the
1976 environmental impact statement. The first, stopping all
construction and dredging activities on the Middle
-- 19 of 28 --
20 No. 22-1466
Mississippi, was determined to be unreasonable because it
would not satisfy the project’s purpose of maintaining a nav-
igable nine-foot channel. If the river were left to its own de-
vices, the navigable channel would soon be lost. The second
alternative, constructing locks and dams along the Middle
Mississippi, was also rejected because it went beyond the pur-
pose of the final supplemental statement, which was to up-
date the 1976 environmental impact statement, and because it
would require Congressional authorization and funding. The
third, seeking from Congress a change in authorization for the
project to include fish and wildlife habitat restoration as a pro-
ject purpose, was also determined to be unreasonable be-
cause, in the years since 1976, the Corps has incorporated en-
vironmental mitigation into the project and Congress has au-
thorized environmental restoration in other acts. Congress
has passed legislation permitting, but not requiring, ecologi-
cal restoration on the Middle Mississippi. Congress, however,
has not permitted the Corps to use construction funds for that
purpose, and any restoration project would require a cost-
share partner. This left the fourth alternative, which was
adopted in 1976: to continue construction of regulating works
and to supplement with as little dredging as possible.
The Corps then considered four additional alternatives,
each requiring different levels of construction and dredging.
Under the first, the “No New Construction Alternative,” the
Corps would maintain existing structures and dredge but
would build no new structures. The second alternative, re-
ducing dredging as much as possible by building new struc-
tures, was ultimately determined to yield the same outcome
as the third alternative, the most cost-effective mixture of new
construction and dredging. The Corps then considered a
fourth alternative, requested by natural resource agencies: to
-- 20 of 28 --
No. 22-1466 21
select a level of construction between the no new construction
option and the minimal dredging option that would avoid en-
vironmental impacts. The Corps thought it unreasonable to
select a “random dredge reduction amount” with a commen-
surate level of construction between these two options with-
out a scientific reason, but the Corps did incorporate the costs
of compensatory mitigation into the alternatives already iden-
tified. When compensatory mitigation costs were considered,
the final cost-effective level of dredging increased and the
level of construction decreased, which was precisely what the
natural resource agencies had proposed.
The Corps thus ultimately identified two alternatives that
warranted detailed study. Under the first, the “No New Con-
struction Alternative,” the Corps would not construct any ad-
ditional structures but would maintain the channel through
dredging and maintenance of existing structures. Under the
second, the “Continue Construction Alternative,” the Corps
would continue constructing river training structures until
the cost of building additional structures could not be justified
by the reduction in dredging costs. In determining what level
of construction is cost-effective, this alternative considers
costs of compensatory mitigation.
Plaintiffs challenge the Corps’ selection of reasonable al-
ternatives on several grounds. First, they criticize the Corps
for offering a “binary choice,” and they insist that more alter-
natives should have been studied. As illustrated above, how-
ever, the Corps considered many alternatives but offered sub-
stantial reasons for eliminating several from further consider-
ation because they would not satisfy the project’s purpose or
were otherwise unreasonable. As regulations require, the
-- 21 of 28 --
22 No. 22-1466
Corps “briefly discuss[ed] the reasons” for not studying these
alternatives in detail. 40 C.F.R. § 1502.14(a).
In any event, the “reasonableness of the analysis of project
alternatives … is resolved not by any particular number of al-
ternatives considered, but by the nature of the underlying
agency action.” Friends of Capital Crescent Trail v. Fed. Transit
Admin., 877 F.3d 1051, 1063 (D.C. Cir. 2017) (finding no viola-
tion of NEPA where the agency’s final environmental impact
statement studied only two alternatives); see also Citizens for
Smart Growth v. Sec’y of the Dep’t of Transp., 669 F.3d 1203, 1212
(11th Cir. 2012) (“NEPA does not impose any minimum num-
ber of alternatives that must be evaluated.”). Here, the pur-
pose of the project, as defined by Congress for generations,
was relatively narrow. Congress authorized the Corps to
maintain a navigation channel through construction of river
training structures with minimal supplemental dredging.
That narrow purpose appropriately limited the range of rea-
sonable alternatives that the Corps selected for detailed study.
Citizens Against Burlington, 938 F.2d at 195 (“The goals of an
action delimit the universe of the action’s reasonable alterna-
tives.”).
Plaintiffs next contend that the Corps ignored reasonable
alternatives, including those that would require the Corps to
seek Congressional authorization. Specifically, plaintiffs ar-
gue that the Corps should also have considered (1) an alter-
native that would remove or modify existing structures; (2) an
alternative that would maintain the navigation channel
through other means, including upstream water level man-
agement regimes, alternative dredging, and the development
of new, innovative techniques; and (3) an alternative that
-- 22 of 28 --
No. 22-1466 23
would propose ecological restoration and fish and wildlife
conservation as authorized project purposes.
As an initial matter, the Corps did consider some of these
alternatives, either individually or as part of studied alterna-
tives. The Corps has already removed or modified a number
of river training structures, such as those that are no longer
effective. It plans to continue to do so as a compensatory mit-
igation measure under the chosen Continue Construction Al-
ternative. The Corps will also continue to develop and imple-
ment innovative river training structures that are more envi-
ronmentally friendly than traditional structures. And, as part
of both studied alternatives, the Corps considered alternative
dredging techniques and beneficial uses of dredged material
that would minimize environmental harm.
Other alternatives suggested by plaintiffs were rejected, in
part, because they would require Congressional authoriza-
tion. As discussed above, the Corps considered and rejected
an alternative proposing ecological restoration as an author-
ized project purpose and an alternative that would use up-
stream water management techniques to maintain the naviga-
tion channel.
Courts have repeatedly said that an otherwise reasonable
alternative should not be eliminated solely because it would
require legislative action. Natural Resources Def. Council, Inc. v.
Morton, 458 F.2d 827, 837 (D.C. Cir. 1972) (“The mere fact that
an alternative requires legislative implementation does not
automatically establish it as beyond the domain of what is re-
quired for discussion,” but court did not “suppose Congress
intended an agency to devote itself to extended discussion of
the environmental impact of alternatives so remote from real-
ity as to depend on, say, the repeal of the antitrust laws.”);
-- 23 of 28 --
24 No. 22-1466
Environmental Def. Fund, Inc. v. Froehlke, 473 F.2d 346, 351 (8th
Cir. 1972) (disagreeing with Corps’ conclusion that it need not
study further an alternative that would require separate Con-
gressional authorization). An alternative requiring Congres-
sional authorization, however, will “qualify for inclusion in
an [environmental impact statement] only in very rare cir-
cumstances.” City of Sausalito v. O’Neill, 386 F.3d 1186, 1208
(9th Cir. 2004), quoting City of Angoon v. Hodel, 803 F.2d 1016,
1021 n.2 (9th Cir. 1986). The touchstone is reasonableness,
which can include assessment of political realities. Natural Re-
sources Def. Council, 458 F.2d at 837. Compare City of Sausalito,
386 F.3d at 1209–10 (reasonable for Park Service not to con-
sider alternative requiring Congressional funding for refur-
bishment project in light of previous indications from Con-
gress that funding would not be provided), with Muckleshoot
Indian Tribe v. U.S. Forest Serv., 177 F.3d 800, 814 (9th Cir. 1999)
(unreasonable for Forest Service not to consider alternative
because it would require additional funding when the alter-
native ultimately selected relied on “admittedly speculative
funds”).
Here, it was not unreasonable for the Corps to eliminate
from consideration certain alternatives that would require
Congressional action. The Corps’ rejection of an alternative
that would use upstream water level management techniques
to ensure a navigable channel was based not only on that fact
that Congress had authorized water control plans for the Up-
per Mississippi in a separate project but also the Corps’ as-
sessment that such an alternative could not guarantee a navi-
gable channel.
It was also reasonable for the Corps to reject an alternative
that would propose ecological restoration as an authorized
-- 24 of 28 --
No. 22-1466 25
project purpose. An alternative that would require Congress
to alter a project’s purpose is substantially different from one
that would require Congress to provide additional funding,
see Muckleshoot, 117 F.3d at 814, or to acquire land, see Froeh-
lke, 473 F.2d at 351. Moreover, given the history of the Middle
Mississippi project, it was not unreasonable for the Corps to
conclude that Congress was unlikely to approve a change in
project purpose. Since 1910, Congress has directed the Corps
to maintain a navigation channel on the Middle Mississippi.
While Congress has, in other acts, authorized the Corps to en-
gage in environmental protection and restoration, it has never
altered the Middle Mississippi project’s purpose to include
ecological restoration, even after the Corps sought authoriza-
tion to that effect as part of its 1976 environmental impact
statement. The Corps was not arbitrary and capricious in re-
jecting this alternative, especially given the purpose of the
supplemental statement itself, which was to update the 1976
environmental impact statement in light of new circum-
stances and information.
3. Informed Consideration of Alternatives
Finally, plaintiffs argue that the Corps failed to provide in-
formed consideration of the alternatives it did study. They ar-
gue that the final supplemental statement does not explain
what criteria will trigger future dredging, revetment, or con-
struction of river training structures. Plaintiffs further com-
plain that the supplemental statement does not specify where
future dredging and construction will take place, nor does it
assess the economic cost and environmental impact of the
studied alternatives. Last, plaintiffs fault the supplemental
statement for not identifying which river training structures
will be built under the Continue Construction Alternative.
-- 25 of 28 --
26 No. 22-1466
We disagree with these criticisms. First, the supplemental
statement does explain how the Corps decides where and
when to dredge, as well as how it determines whether and
where to build river training structures. Plaintiffs’ other ob-
jections are, at core, objections to the fact that the supple-
mental statement is a programmatic analysis rather than an
analysis of specific proposed structures.
Due to the Middle Mississippi’s changing flows and sedi-
ment levels, the Corps cannot know in advance just where fu-
ture construction, revetment, and dredging will be needed. In
light of these unknowns, the supplemental statement assesses
the programmatic impacts that “can reasonably be antici-
pated to occur,” while providing that the Corps will conduct
site-specific environmental assessments before it builds spe-
cific additional river training structures.
“Tiering” environmental studies in this manner is permit-
ted and in fact encouraged by NEPA regulations. 40 C.F.R.
§ 1502.20 (“Agencies are encouraged to tier their environmen-
tal impact statements to eliminate repetitive discussions of the
same issues and to focus on the actual issues ripe for decision
at each level of environmental review.”); see also Environmen-
tal Law & Policy Center v. U.S. Nuclear Reg. Comm’n, 470 F.3d
676, 684 (7th Cir. 2006), quoting County of Suffolk v. Sec’y of the
Interior, 562 F.2d 1368, 1378 (2d Cir. 1977) (“Courts have per-
mitted agencies to defer certain issues in an [environmental
impact statement] for a multistage project when detailed use-
ful information on a given topic is not ‘meaningfully possible’
to obtain, and the unavailable information is not essential to
determination at the earlier stage.”). Corps regulations ex-
plain that when using tiered environmental analyses, the “in-
itial broad or programmatic [environmental impact
-- 26 of 28 --
No. 22-1466 27
statement] must present sufficient information regarding
overall impacts of the proposed action so that the decision-
makers can make a reasoned judgment on the merits of the
action at the present stage of planning.” 33 C.F.R. § 230.13(c).
Given the necessary and permissible limits of a program-
matic study, we are satisfied that the Corps took the “hard
look” required by the National Environmental Policy Act.
Highway J Citizens Grp. v. Mineta, 349 F.3d 938, 953 (7th Cir.
2003), quoting Kleppe v. Sierra Club, 427 U.S. 390, 410 n.21
(1976). The supplemental statement discusses the types of
river training structures the Corps would likely build under
the Continue Construction Alternative, including their vari-
ous effects on channel flow, sediment levels, and river habi-
tats. The supplemental statement also assesses the environ-
mental impact of each studied alternative, including antici-
pated effects on side channel habitats, water quality, air qual-
ity, fishery resources, threatened and endangered species,
and human resources.
As for economic cost, the supplemental statement em-
ploys an admittedly simplified economic analysis to estimate
the amount of construction under the Continue Construction
Alternative that would be cost effective considering the costs
of construction, dredging, and compensatory mitigation. The
statement explains, however, that due to constraints on an-
nual funding and the Corps’ inability to predict where future
construction and dredging will be required, it was not practi-
cable to produce detailed economic analyses in the program-
matic statement, but that such analyses would be provided in
future site-specific environmental assessments. Considering
both the purpose of the supplemental statement, which was
to update the Corps’ analysis of the project’s environmental
-- 27 of 28 --
28 No. 22-1466
impacts, and its programmatic nature, the Corps did not act
unreasonably in declining to provide more detailed economic
analyses.
We conclude that the Corps’ final supplemental environ-
mental impact statement satisfied the National Environmen-
tal Policy Act. The Corps reasonably articulated the purpose
and need for the project, identified reasonable alternatives
that warranted detailed study, and provided meaningful con-
sideration of those alternatives, given the programmatic na-
ture of the supplemental statement.
The judgment of the district court is AFFIRMED.
-- 28 of 28 --