U.S. EQUAL EMPLOYMENT OPPORTUNITY COMMISSION Office of Federal Sector P.O. Box 77960 Washington, DC 20013 Tasia C.,1 Complainant, v. Troy E. Meink, Secretary, Department of the Air Force, Agency. Appeal No. 2025000790 Agency No. 9X1M2303478 DECISION Complainant filed a timely appeal with the Equal Employment Opportunity Commission (EEOC or Commission) from a final decision (FAD) by the Agency dated October 7, 2024, finding that it was in compliance with the terms of the settlement agreement into which the parties entered. See 29 C.F.R. § 1614.402; 29 C.F.R. § 1614.504(b); and 29 C.F.R. § 1614.405. BACKGROUND At the time of events giving rise to this complaint, Complainant had worked as a Security Specialist, NH-0080-III at the Agency’s Air Force Life Cycle Management Center Security Directorate in Arlington, Virginia. Believing that the Agency subjected her to unlawful discrimination, Complainant contacted an Agency EEO Counselor to initiate the EEO complaint process. 1 This case has been randomly assigned a pseudonym which will replace Complainant’s name when the decision is published to non-parties and the Commission’s website.
2025000790 2 On April 3, 2024, Complainant and the Agency entered into a settlement agreement to resolve the matter. The settlement agreement provided, in pertinent part, that: (b) As soon as is practicable, but not later than forty-five (45) calendar days following the final signature on this Agreement, the Agency shall change Complainant’s SF-50 dated July 10, 2023, from a probationary termination to a resignation dated the effective date of settlement. Specifically, the Agency agrees to cancel the SF-50 dated July 10, 2023, and submit a new Request for Personnel Action, SF-52 and SF-50 to reflect Complainant’s reinstatement effective July 10, 2023. The Agency shall immediately place Complainant into a leave without pay (LWOP) status. The Agency shall also submit a new Request for Personnel Action, SF-52 and SF-50 to reflect Complainant’s resignation effective the same date as the effective date of this Agreement. The reason for the resignation, in the comments section of the SF-50, shall state, “to pursue other job opportunities.” The Agency shall remove the termination during probationary period SF-50 from Complainant’s electronic official personnel folder (eOPF). The Agency shall provide a copy of the reinstatement SF-50 and resignation SF-50 to Complainant and her representative via email within ten (10) calendar days after the SF-50 change. (c) As soon as is practicable, but not later than forty-five (45) calendar days following the final signature on this Agreement, the Agency shall submit a Customer Service Request (CSR) to the Consolidated Adjudication Services (CAS) providing supplemental information to the incident report that was submitted by the Agency against Complainant’s clearance. The CSR will reference the incident report submitted and that Complainant’s termination was converted to a resignation. The Agency will provide Complainant with a copy or screenshot of what was submitted to CAS within ten (10) calendar days after the Agency submits the CSR to CAS. (d) As soon as is practicable, but not later than forty-five (45) calendar days following the final signature on this Agreement, the Agency shall remove the letter about Complainant entered into JADE on or about July 11, 2023. The Agency will provide a copy of the audit log showing that the letter was deleted from JADE within ten (10) calendar days after the Agency deletes the letter from JADE.
2025000790 3 On September 11, 2024, Complainant learned that the Missile Defense Agency (MDA) decided to withdraw Complainant’s tentative job offer, informing Complainant that it was discovered that Complainant had been terminated from her last position with the Agency during her probationary period and that in light of the information presented in her termination letter, leadership was rescinding the offer. Complaint File at 39-40. By letter to the Agency dated September 12, 2024, Complainant, through counsel, alleged that the Agency was in breach of the settlement agreement, and requested that the Agency specifically implement its terms. Specifically, Complainant alleged that the Agency failed to remove Complainant’s termination letter from her personnel file and replace it with a SF-50 showing Complainant’s voluntary resignation. Complainant alleged that while the Agency had previously informed Complainant that it had complied with the terms described above, recent events established that the Agency did not effectuate the conditions properly, violating the terms of the Settlement Agreement. In its decision dated October 7, 2024, the Agency determined that it was in full compliance with all the terms in the settlement agreement. The decision found that regarding the actions in paragraph 2(b), the Agency provided documentation to support that the SF-50 was changed from a probationary termination to a resignation within the required timeline. The updated SF-50s were provided on May 15, 2024. Subsequently, Complainant, through counsel, requested changes two times, leading to the final version of the SF-50 resignation currently contained in Complainant’s eOPF. Regarding the actions in paragraph 2(d), the decision found that the Agency provided documentation to support that the termination was removed from the JADE system within the required timeline. The Agency’s decision stated that Complainant failed to provide documentation or a source showing that the conditions of the settlement agreement were violated. Complainant had provided an email from the Missile Defense Agency (MDA), informing Complainant that leadership had rescinded her employment offer due to her OF 306 showing the Agency had terminated Complainant’s employment. The Agency noted that the email from the MDA did not indicate how the MDA discovered Complainant had been terminated during her probationary period or how the MDA obtained a copy of Complainant’s termination letter. Therefore, there was insufficient evidence proving Complainant failed to meet its obligations in paragraph 2(b) and 2(d) of the settlement agreement.
2025000790 4 Complainant filed the instant appeal. CONTENTIONS ON APPEAL On appeal, Complainant argues, through counsel, that the Agency breached the settlement agreement because the Agency failed to ensure destruction of the Complainant’s Notice of Termination in all relevant personnel files and in JADE, while replacing it with an SF-50 showing a voluntary resignation. Additionally, Complainant argues the Agency failed to ensure that it notified the Defense Counterintelligence Security Agency (DCSA) Adjudication and Vetting Services (AVS), previously known as CAS, of the full context of these changes through a Customer Service Request (CSR). Complainant argues that the Agency had an obligation to ensure that, to the fullest extent of its control, rescind the termination letter and remove it from all relevant systems of record. In response to the instant appeal, the Agency argues that it complied with the material terms of the agreement. The Agency provided affidavits from several MDA employees describing how the MDA learned of the probationary termination, which was not due to the Agency’s violation or failure to fulfill its obligations under the settlement agreement. Additionally, the Agency submitted various emails and documentation showing that it complied with the settlement agreement. ANALYSIS EEOC Regulation 29 C.F.R. § 1614.504(a) provides that any settlement agreement knowingly and voluntarily agreed to by the parties, reached at any stage of the complaint process, shall be binding on both parties. The Commission has held that a settlement agreement constitutes a contract between the employee and the Agency, to which ordinary rules of contract construction apply. See Herrington v. Dep’t of Def., EEOC Request No. 05960032 (December 9, 1996). The Commission has further held that it is the intent of the parties as expressed in the contract, not some unexpressed intention, that controls the contract’s construction. Eggleston v. Dep’t of Veterans Affairs, EEOC Request No. 05900795 (August 23, 1990).
2025000790 5 In ascertaining the intent of the parties with regard to the terms of a settlement agreement, the Commission has generally relied on the plain meaning rule. See Hyon O v. U.S. Postal Serv., EEOC Request No. 05910787 (December 2, 1991). This rule states that if the writing appears to be plain and unambiguous on its face, its meaning must be determined from the four corners of the instrument without resort to extrinsic evidence of any nature. See Montgomery Elevator Co. v. Building Eng’g Servs. Co., 730 F.2d 377 (5th Cir. 1984). In the instant case, regarding Provision 2(b), the Agency emailed Complainant’s counsel on May 15, 2024, attaching Complainant’s updated SF-50s, showing cancelation of the Termination During Probationary Period and Complainant’s resignation effective April 3, 2024, to pursue other job opportunities. Agency Brief in Opp. Of Appeal (corrected), Exh. C. Complainant’s counsel requested two changes to the SF-50 on June 27, 2024. That same day, the Agency emailed Complainant’s counsel with the updated the SF-50 addressing the requested changes. Agency Brief in Opp. Of Appeal (corrected), Exh. E. On July 8, 2024, Complainant’s counsel emailed the Agency, stating the SF-50 was not sufficient and requested several additional changes. On July 9, 2024, the Agency emailed Complainant’s counsel with an updated SF-50 reflecting the additional revisions. Agency Brief in Opp. Of Appeal (corrected), Exh. F. The Agency also submitted on appeal emails confirming that on July 9, 2024, the documents pertaining to the Probationary Termination were purged from Complainant’s eOPF. Agency Brief in Opp. Of Appeal (corrected), Exh. G. The Agency acknowledges there was a delay in purging documents related to the probationary termination from Complainant’s eOPF until around July 9, 2024, due to a misunderstanding of how removal of the SF-50 works between Agency counsel and Human Resources. Specifically, HR had to request to purge the documents from Complainant’s eOPF, which did not happen until July 8, 2024. However, it is clear from the record that the Agency was actively taking steps to remove the documents and issue a satisfactory SF-50. Additionally, Complainant alleged breach of settlement two months after the documents were removed. Previous Commission decisions have indicated that failure to satisfy a time frame specified in an agreement does not prevent a finding of substantial compliance, especially when all required actions were subsequently completed. See Ela O. V. U.S. Postal Serv., EEOC Appeal No. 2024003974 (Dec. 9, 2024); Lazarte v. Dep't of the Interior, EEOC Appeal No. 01954274 (Apr. 25, 1996); Owens v. Dep't of the Army, EEOC Appeal No. 01955828 (July 1, 1996).
2025000790 6 Regarding Provision 2(c), the Agency sent Complainant’s counsel an email on May 16, 2024, stating that the CSR was submitted to the DCSA AVS (previously known as the CAS), on May 16, 2024. The email stated the relevant case ID number and attached documentation showing the CSR-Provide Supplemental Information was submitted on May 16, 2024. The attachment shows the CSR details stating that Complainant’s termination of employment effective July 10, 2023, had been canceled and that Complainant resigned from the Agency effective April 3, 2024. The CSR also showed the supporting documentation that was attached for the change of personnel action in response to Complainant’s July 10, 2023, incident report. Agency Brief in Opp. Of Appeal (corrected), Exh. D. We find that the Agency complied with Provision 2(c) of the settlement agreement. Regarding Provision 2(d), the Agency’s appeal submission shows that on April 17, 2024, the Agency sent Complainant’s counsel an email attaching an audit log, stating that the termination letter had been deleted from JADE on August 17, 2024, satisfying Provision 2(d) of the Settlement Agreement. Agency Brief in Opp. Of Appeal (corrected), Exh. B. While the termination letter was deleted from JADE, the file history page of Complainant’s JADE showed a notice of termination had been deleted. However, the settlement agreement did not request for any reference of the letter to be scrubbed, just for the letter to be deleted. We find that the Agency complied with Provision 2(d) of the settlement agreement. Complainant alleges the MDA withdrew her temporary job offer due to the Agency’s failure to fulfill its obligations under the settlement agreement. However, a review of the record and submissions on appeal, show that it was not through the Agency’s failure to satisfy its obligations under the settlement agreement that caused the MDA to withdraw its job offer. CONCLUSION In this case, we find the Agency in substantial compliance with the agreement. Accordingly, we AFFIRM the Agency's decision.
2025000790 7 STATEMENT OF RIGHTS - ON APPEAL RECONSIDERATION (M1125) The Commission may, in its discretion, reconsider this appellate decision if Complainant or the Agency submits a written request that contains arguments or evidence that tend to establish that: 1. The appellate decision involved a clearly erroneous interpretation of material fact or law; or 2. The appellate decision will have a substantial impact on the policies, practices, or operations of the agency. Requests for reconsideration must be filed with EEOC’s Office of Federal Sector (OFS) within thirty (30) calendar days of receipt of this decision. If the party requesting reconsideration elects to file a statement or brief in support of the request, that statement or brief must be filed together with the request for reconsideration. A party shall have twenty (20) calendar days from receipt of another party’s request for reconsideration within which to submit a brief or statement in opposition. See 29 C.F.R. § 1614.405; Equal Employment Opportunity Management Directive for 29 C.F.R. Part 1614 (EEO MD-110), at Chap. 9 § VII.B (Aug. 5, 2015). Complainant should submit their request for reconsideration, and any statement or brief in support of their request, via the EEOC Public Portal, which can be found at https://publicportal.eeoc.gov/Portal/Login.aspx. Alternatively, Complainant can submit their request and arguments to the Director, Office of Federal Sector, Equal Employment Opportunity Commission, via regular mail addressed to P.O. Box 77960, Washington, DC 20013, or by certified mail addressed to 131 M Street, NE, Washington, DC 20507. In the absence of a legible postmark, a complainant’s request to reconsider shall be deemed timely filed if OFS receives it by mail within five days of the expiration of the applicable filing period. See 29 C.F.R. § 1614.604. An agency’s request for reconsideration must be submitted in digital format via the EEOC’s Federal Sector EEO Portal (FedSEP). See 29 C.F.R. § 1614.403(g). Either party’s request and/or statement or brief in opposition must also include proof of service on the other party, unless Complainant files their request via the EEOC Public Portal, in which case no proof of service is required.
2025000790 8 Failure to file within the 30-day time period will result in dismissal of the party’s request for reconsideration as untimely, unless extenuating circumstances prevented the timely filing of the request. Any supporting documentation must be submitted together with the request for reconsideration. The Commission will consider requests for reconsideration filed after the deadline only in very limited circumstances. See 29 C.F.R. § 1614.604(f). COMPLAINANT’S RIGHT TO FILE A CIVIL ACTION (S0124) You have the right to file a civil action in an appropriate United States District Court within ninety (90) calendar days from the date that you receive this decision. If you file a civil action, you must name as the defendant in the complaint the person who is the official Agency head or department head, identifying that person by their full name and official title. Failure to do so may result in the dismissal of your case in court. “Agency” or “department” means the national organization, and not the local office, facility or department in which you work. If you file a request to reconsider and also file a civil action, filing a civil action will terminate the administrative processing of your complaint. RIGHT TO REQUEST COUNSEL (Z0815) If you want to file a civil action but cannot pay the fees, costs, or security to do so, you may request permission from the court to proceed with the civil action without paying these fees or costs. Similarly, if you cannot afford an attorney to represent you in the civil action, you may request the court to appoint an attorney for you. You must submit the requests for waiver of court costs or appointment of an attorney directly to the court, not the Commission. The court has the sole discretion to grant or deny these types of requests.
2025000790 9 Such requests do not alter the time limits for filing a civil action (please read the paragraph titled Complainant’s Right to File a Civil Action for the specific time limits). FOR THE COMMISSION: T. Gimbrere _________ Acting Director's signature T. Gimbrere, Acting Director Office of Federal Sector September 23, 2026 Date
Ti chiedi come si applica questo testo alla tua situazione?
Consulenza gratuita, senza impegno
Descrivi la tua situazione. Il nostro team ti ricontatterà via e-mail per la tua consulenza.
Continua la tua ricerca in ChatGPT o Claude
Collega Omnilex per cercare nel corpus legale dal tuo assistente IA.