Order No. PSC-2024-0511-TRF-GU•Florida Public Service Commission native order document 10320-2024
Florida Public Service Commission native order document 10320-2024
Order No. PSC-2024-0511-TRF-GUFlapubserv
Testo completo
FILED 12/20/2024 DOCUMENT NO. 10320-2024 FPSC - COMMISSION CLERK BEFORE THE FLORIDA PUBLIC SERVICE COMMISSION In re: Petition for approval of 2023 true-up, projected 2024 true-up, and 2025 revenue requirements and surcharges associated with cast iron/bare steel pipe replacement rider, by Peo les Gas S stem, Inc. DOCKET NO. 20240133-GU ORDER NO. PSC-2024-0511-TRF-GU ISSUED: December 20, 2024 The following Commissioners participated in the disposition of this matter: BY THE COMMISSION: MIKE LA ROSA, Chairman ART GRAHAM GARY F. CLARK ANDREW GILES FAY GABRIELLA PASSIDOMO SMITH ORDER APPROVING TA RIFF Background On August 30, 2024, Peoples Gas System, Inc. (Peoples or utility) filed a petition fo r approval of its final 2023 true-up, projected 2024 true-up, and 2025 revenue requirement and surcharges associated with the cast iron/bare steel replacement rider (CT/BSR Rider or rider). The rider was originally ap proved by Order No. PSC-12-0476-TRF-GU (2012 Order) to recover the cost of accelerating the replacement of cast iron and bare steel pipes through a surcharge on customers' bills. 1 In the 20 12 Order, we found that, " replacement of these types of pipelines is in the public interest to improve the safety of Florida's natural gas infrastructure, and reduce the possibility of loss of li fe and destruction of property should an incident occur." Peoples' current surcharges were approved by Order No. PSC-2023-0363-TRF-GU. 2 In Order No. PSC-1 7-0066-AS-GU, we approved a comprehensive settlement agreement between Peoples and the Office of Public Co unse l. 3 The settlement agreement, in part, added problematic plastic pipe (PPP) in sta ll ed in the company's distribution system to e li gible replacements under the rider beginning in 2017 and continuing through 2028. PPP was 1 Order No. PSC-12-0476-TRF-GU, issued Sept ember 18, 2012, in Docket No. 20110320-GU, In re: Petition/or approval of Cast Iron/Bare Steel Pipe Replacement Rider (Rider CIIBSR), by Peoples Gas System. 2 Order No. PSC-2023-0363-TRF-GU, iss ued November 29, 2023, in Docket No. 20230098-GU, In re: Petition for approval of 2022 true-up, pr oject ed 2023 tru e- up, and 2024 revenue requirements and surcharges associated with cast iron/bare steel replacement rider, by Peoples Gas System. 3 Order No. PSC-17-0066-AS-GU, issued February 28, 2017, in Docket No. 20160 159-GU, In re: Petition for approval of settlement agreement pertaining to Peoples Gas System's 2016 depreciation study, environmental reserve account, problematic plastic pipe replacement, and authori::: ed ROE.
ORDER NO. PSC-2024-0511-TRF-GU DOCKET NO.20240133-GU PAGE2 manufactured before 1983 and has significant safety concerns. fn certain areas, the PPP is interspersed with , or connected to, the cast iron/bare steel pipe that is being replaced under the rider. As provided for in the settlement agreement, PPP replacements are included in the calculation of the 2024 rider surcharges. In December 2023, we approved Peoples' petition for rate increase, which contained two provisions that would impact the CI/BSR Rider. 4 First, Peoples moved its CI/BSR investments as of December 31, 2023, into rate base, as required by the 2012 Order approving the rider. 5 This provision had the effect of resetting the CI/BSR Rider rates to zero. Second, we approved Peoples' request for the Long Term Debt Cost Rate (LTDR) true- up mechanism. The LTOR true-up mechanism allowed Peoples to make a one-time adjustment to the estimated cost of long-tenn debt for the projected test year ending December 31, 2024. 6 The purpose of the LTDR true-up mechanism was to reflect the actual embedded costs of the utility's inaugural long-tem1 debt issuance in its revenue requirement and rates. 7 This provision was a result of Peoples being spun off from Tampa Electric Company, because Peoples no longer obtains long-term debt capital from Tampa Electric Company and instead issues its own debt as a separate entity. We fmther ordered that if the impact to the incremental revenue requirement was greater than $500,000 for the period between the implementation of the base rate increase and the implementation of the LTOR true-up mechanism , then the incremental revenue requirement would be recovered through the CI/BSR rider for 2025. 8 We approved the incremental revenue requirement of $874,085 associated with the LTDR true-up mechanism in May 2024.9 The total amount associated with the L TOR true-up mechanism to be recovered through the 2025 CI/BSR rider is $476,034, as shown in Exhibit B to the petition, page 2 of 4, line No. 9a. Currently, Peoples has an active petition for an expansion of the Cl/ BSR rider in Docket No. 20240107-GU. 10 Peoples has proposed to re name the Cl /BSR rider to the Safety of Facilities and Infrastructure Replacement Rider (SAFIR) and expand the categories of eligible replacements under the rider. If the SAF lR program is approved, projected capital expenditures would increase for 2025. In paragraph 16 of the in stant petition, Peoples stated that if the SA FIR petition remains pending on November 30, 2024, the utility would not seek approval of the revenue requirement and surcharge for the SAFIR modifications in the subject docket. We are still in the process of reviewing the SA FIR petition; therefore, the SA FIR modifications were not considered as part of our vote in this docket or this Order. 4 Order No. PSC-2023-0388-FOF-GU, issued December 27, 2023, in Docket No. 20230023-GU, In re . Petition/or rate increase by Peoples Gas System, Inc. 5 See page 3 of Order No. PSC-12-0476-TRF-GU. 6 See pages 10 7- 109 of Order No. PSC-2023-0388-FOF-GU. 7 l ei. 8 See page 108 of Order No. PSC-2023-0388-FOF-GU. 9 Order No. PSC-2024-0170-TRF-GU, issued May 23, 2024, in Docket No. 20240028-GU, In re: Petition to implement long-term debt cost true-up mechanism, by Peoples Gas System, In c. 10 In re: Petition for appr oval of modifications to cast iron/bare s1eel pipe replacement rider, by Peoples Gas System, In c.
ORDER NO. PSC-2024-0511-TRF-GU DOCKET NO. 20240133-GU PAGE3 Ow· staff issued a data request to the utility, for which responses were received on October 7 and October 9, 2024. By Order No. PSC-2024-0453-PCO-GU. issued October 17, 2024, the utility's petition was suspended to allow our staff a suflicient opportunity to gather and evaluate all pertinent infonnation related to the tariff proposals in order to present us with an informed recommendation. Attachment A, attached hereto, to this Order contains Table l, which consolidates actual and projected CI/BSR and PP P miles, replaced investment, and revenue requirements for each year of the replacement program. 11 Additionally, Peoples provided tables that display the replacement progress and forecasts for the CI/BSR Rider (Table 2) and for PPP (Table 3). 12 Attachment B, attached hereto, contains the proposed tariff. We have jurisdiction over this matter pursuant to Section 366.03, 366.04, 366.05, and 366.06, Florida Statutes (F.S.). Decision The CI/ BSR Rider charges have been in effect since January 2013 and were projected to be in effect for IO years with replacement projects completed by the end of 2022. In response to our staffs first data request, Peoples stated that the COVID-19 pandemic environment greatly contributed to replacement efforts going beyond the I 0-year period. 13 Contributing factors include construction contractor labor shortages, consulting firm availability, supply chain challenges, and extensive permitting challenges. Peoples stated that it expects to have 8.11 miles of CI/BSR replacement remaining entering 2025. In 2024, Peoples' cast iron/bare steel and PPP replacement activity focused in the areas of Miami, Tampa, St. Pete, Orlando, Eustis, Jacksonville, Lakeland, Daytona, Avon Park, and Ocala. In 2025, Peoples states it will focus on replacement projects in Miami, Tampa, St. Pete, Orlando, Eustis, Jacksonvi ll e, Lakeland, Daytona, Jupiter. Panama City, and Ocala. A detailed description of the projects, including their address, was provided in response to our staff's first data request. 14 True-ups by Yea r Peoples' calculation for the 2025 revenue requirement and surcharges includes a final true-up for 2023, an actual/estimated true-up for 2024, and projected costs for 2025. Pursuant to the 2012 Order, the capital expenditures fo r 2024 and 2025 exclude the first $1 million of facility replacements each year because that amount is included in rate base. Peoples has included depreciation expense savings as discussed in the 2012 Order; however, the utility has not identified any operations and maintenance savings. Final True- up f or 2023 Exhibit A of the petition shows that the revenues collected for 2023 were $8,215.491 compared to a revenue requirement of $7,531,346, resu lting in an over-recovery of $684,145. 11 ON 09444-2024, response No. 8. 12 Id. 13 DN 09444-2024, response No. 4. 14 fd
ORDER NO. PSC-2024-0511-TRF-GU DOCKET NO. 20240133-GU PAGE4 The final 2022 under-recovery of $787,888, 2023 over-recovery of $684,145, and interest associated with any over- and under-recoveries, results in a final 2023 under-recovery of $102,499. Ac tual/Estimat ed 2024 Tr ue-up In Exhibit B of the petition, Peoples provided actual revenues for January through July and forecast revenues for August through December of 2024, totaling $883,056, compared to an actual/estimated revenue requirement of $576,693, resulting in an over-recovery of $306,363. Th e final 2023 under-recovery of $102,499, 2024 over-recovery of $306,363, 2024 LTOR true- up mechanism adjustment of $476,034, and interest associated with any over- and under- recoveries, resu lts in a total 2024 under-recovery of $276,028. Proj ected 2025 Costs Exhibit C. page 2 of 4, of the petition shows Peoples' project investments of $32,120,344 for the replacement of cast iron/bare steel infrastructure and PPP in 2025, exclud in g the $1 million adjustment to rate base. The return on investment, depreciation expense (less sav in gs), and property tax expense associated with that investment are $3,402,010. After ad ding the total 2024 under-recovery of $276,028, the total 2025 revenue requirement is $3,678,038. Table 1 displays the 2025 revenue requirement ca lculation. In response to our staffs first data request, Peoples provided updated investment and revenue requirement projections for Cl/BS R and PPP which is con tain ed in Table I of Attachment A, attached hereto. Table 1 2025 Reve nu e Rc ouiremcnt 2025 Projected Expenditures Return on Investment Depreciation Expense (less savings) Property Tax Expense 2025 Revenue Requirement Plus 2024 Under-recovery Total 2025 Revenue R equ irement Source: Page 2 of 4 in Exhibit C in petition (Docket No. 20240133-GU). Propo sed Surcharges $32,120,344 $2,767,833 $405,346 $228,830 $3,402,010 $276.028 $3,678,038 As established in the 2012 Order, the total 2025 revenue requirement is allocated to rate classes using the same methodology that was used for the allocation of mains and services in the cost of service study used in Peoples ' most recent approved rate case. After calculating the percentage of total plant costs attributed to each rate class, the respective percentages were multiplied by the 2025 revenue requirement resulting in the revenue requirement by rate class. Divid in g each rate class 's revenue requirement by projected therm sales provides the rider surcharge for each rate class. If approved, the proposed 2025 1ider surcharge for residential customers wou ld be $0.01391 per therm (compared to the current surcharge of $0.00322). The 2025 monthly bill impact would be $0.28 for a residential customer who uses 20 thenns.
ORDER NO. PSC-2024-0511-TRF-GU DOCKET NO. 20240133-GU PAGES Conclusion We have reviewed Peoples' filings and supporting documentation and find that the calculations are consistent with the methodology approved in the 2012 Order and are reasonable and accw-ate. Therefore, we hereby approve Peoples' proposed CI/BSR Rider surcharges to be effective for the first billing cycle of January through the last billing cycle of December 2025. Based on the foregoing, it is ORDERED by the Florida Public Service Commission that Peoples Gas System's proposed CI/BSR Rider surcharges to be effective for the first billing cycle of January through the last billing cycle of December 2025 is hereby approved. It is further ORDERED that if a protest is filed within 2 I days of issuance of the Order, the tariff shall remain in effect with any charges held subject to refund pending resolution of the protest. It is further ORDERED that if no timely protest is filed, this docket shall be closed upon the issuance of a Consummating Order. RPS By ORDER of the Florida Public Service Commission this 20th day of December, 2024. Florida Public Service Commission 2540 Shumard Oak Boulevard Tallahassee, Florida 32399 (850) 413-6770 www.floridapsc.com Copies furnished: A copy of this document is provided to the patt ies of record at the time of issuance and, if applicable, interested persons.
ORDER NO. PSC-2024-051 1-TRF-GU DOCKET NO. 20240133-GU PAGE6 NOTICE OF FURTHER PROCEEDINGS The Florida Public Service Commission is required by Section 120.569(1), Florida Statutes, to noti fy parties of any administrative hearing or judicial review of Commission orders that is available under Sections 120.57 or 120.68. Florida Statutes, as well as the procedures and time limits that apply. This notice should not be construed to mean all requests for an administrative hearing or judicial review will be granted or result in the relief sought. Mediation may be available on a case-by-case basis. lf mediation is conducted, it does not affect a substantially interested person's right to a hearing. The Commission's decision on this tariff is interim in nature and will become final , unless a person whose substantial interests are affected by the proposed action files a petition for a forma l proceeding, in the form provided by Rule 28-106.201, Florida Administrative Code. This petition must be received by the Office of Commission Clerk, 2540 Shumard Oak Boulevard, Tallahassee, Florida 32399-0850, by the close of business on January I 0, 2025. In the absence of such a petition, this Order shall become final and effective upon the issuance of a Consummating Order. Any objection or protest filed in this docket before the issuance date of this order is considered abandoned unless it satisfies the foregoing conditions and is renewed within the spec ified protest period.
ORDER NO. PSC-2024-05 11-TRF-G U DOCKET NO. 20240133-GU PAGE 7 Table 1 P I ' CI/BSR R I t P P eo1:> es ep acemen rogram Year CI/BS PPP Miles CVBS PPP Miles Replaced a Investment ln vestmentb Replaced 2017 51 - $ 17,588,366 $308,227 20 18 62 56 $27,035.678 $ I 8, l 13 , 104 2019 52 42 $35.82 1, 371 $15,349.847 2020 55 43 $32.317, 184 $9,209,668 2021 14 38 $23,726,642 $2 1,051 ,938 2022 10.4 29 $13,079,280 $6, 109,870 2023 2.3 44 $5,815,954 $26,827,191 2024* 5 31 $4,698,860 $ 14 ,646,431 2025* 5 65 $2,906,616 $29,2 13,728 2026* 2 75 $ 1, 104,945 $32, 951 ,727 2027* Jc 90 $874,752 $35,028,300 202 8* I 54 $1,08 I, 1001 $20, l 39,38Y *Projected a CVBS Investment includes remo val of initial $ 1M through 2025. Attachment A Pagel of 3 rogress Cl/BS PPP Revenue Revenue Requirement Requirement $6,868,302 $74,02 1 $8,510,823 $848,201 $11 ,075,229 $2,706, 161 $ 14 ,8 17 ,804 $4,358,010 $1,347,321 $( I 60,452) $3 , 154,597 $1,921,940 $3,927,032 $3,604,313 $2 17,94& $366,77& $760,428 $2,721,026 $1,043,083 $6,227,488 $1 , 151 ,720 $10, 103 ,2 81 $1,246,217 $13,34 1,632 b PPP Investment includ es removal of initial $1 M each year start in g in 2026. c 5-year construction moratoriums in effect in the City of Miami preventing completion before 2027. d2028 investment includes rollover costs to occur in 2029. eRevenue requirement based on current year investment only as investment for prior years rolled into rate base pursuant to the 2023 Rate Case.
ORDER NO. PSC-2024-0511-TRF-GU DOCKET NO. 20240133- GU PAGE8 p eop es Table 2 ' CI/BSR R I ep acement p roqress Year Ma in Replacements Replaced Replaced Remaining Remaining Total Cast Iron Bare Cast Iron Bare Steel Miles (miles) Steel at Year at Year Remaining (miles) End End ofCI/BS (miles) (miles) Mains 2012 - - 100 354 454 2013 13 38 87 316 403 2014 2 15 85 298 383 2015 26 60 59 238 297 2016 15 35 44 203 247 2017 15 36 29 178 207 2018 10 52 18 126 144 2019 8 44 10 8)' 93 2020 4 5 1 6 3S1 41 2021 3.5 10.5 2 24 26 2022 l.3 9.1 0.9 14.61 15 .5 2023 0.3 2.0 0.6 12.4' 12.4 2024* <O 5 0.5 8.& 8.11 *Projected a Additional miles of pipe added after reclassification of pipe type. Attachment A Page 2 of 3 Service Line Reola cements Nwnber Number of of Bare Remaining Steel Bare Steel Service Service Lines Lines Replaced - 14,978 907 14,071 7,964 6,107 1,019 5,088 1,050 6,963 1,135 4,279 1,970 2,309 649 1,660 423 l ,237 191 998 74 941 40 931 63 799
ORDER NO. PSC-2024-0511-TRF-GU DOCKET NO. 20240133-GU PAGE9 Table 3 Peoples' PPP Replacement p Attachment A Page 3 of3 ro ,~ram Pro~ress Year Replaced PPP Total Remaining Replaced Total Number of (Mi les) PPP Mains (Mi le s) 2016 - 551 2017 - 509 2018 56 461 2019 42 418 2020 43 370 2021 38 337 2022 29 306 2023 44 28 Ja 2024* 31 284' 2025* 65 219 2026* 75 144 2027* 90 54 2028* 54 - *Projected nAdditional service Iine s reclassified during the year. bTh is will be determined during the replacement yea r. Number of PPP Remaining PPP Service Lines Service Lines - 28,237 1,396 26,841 3,941 24,741 2,349 20,420 1,702 18 ,7 18 882 17 ,683 837 17 ,229 883 16 ,34& 500 b b b b b b b b b
ORDER NO. PSC-2024-0511-TRF-GU DOCKET NO. 20240133-GU Attachment B Page I of l PAGE 10 Peopl es Gas System , Inc. Original Volume No. 3 F8~rteentl'I Fifteenth Revised Sheet No. 7.806 Can cels Thirteenll'I Fourteenth Rev ised Sheet No. 7.806 CAST IRON/BARE STEEL REPLACEMENT RIDER RIDER CI/BSR The monthly bi ll for Gas SeMce in any Billing Period shall be increased by the CI/BSR Surcharge determined In accordance wrth this Rider CI/BSR Surcharges approved by the Comm ission for bills rendered for meter readings taken on or after January 1 ~~ are as follows with respect to Customers rece iving Gas Service under the following rate schedules: Rate Schedule ReSJdent1aVResidential Standby Generator I Residential Gas Heat Pump Service Small General Service General Service - 1/ Commercial standby Generator Service / Commercial Gas Heat Pump Service General Service - 2 General Service - 3 General Service - 4 General Service - 5 Commercial Street Lighti ng 'Mlolesale Small lnterrupbble Service Interruptible Service Interruptible Servi ce - Large Volume Cl/BSR Surctiarqe $ Q..003~ per therm S ~ per therm S 0.00.1440 00516 per t herm $ ~ per therm S ~ 00468 per therm $ ~ 00333 per therm S 0-000000 00228 per therm S 0-00i040~ per therm S ~ 00269 per t herm S c..oooSQO 00 127 per therm $ ~ 00030 per therm S O00000 per therm The CI/BSR Surcharges set forth above shall remain in effect until changed pursuarrt to an order of the Commission. CI/BSR Surcharges shall be determined 1n accordance with the provisions of th is Rider set forth below Definitions For purposes of this Rider · E11a1ble Replacements· means the foll01.V1ng Company plant investments that (1) do not increase revenues by directly connecting new customers to the plant asset, (11) are in service and used and useful In providing ublrty service and (iii) were not incl uded In the Company's rate base for purposes of determining the Company's base rates in its most recent general base rate proceeding Mains and service lines, as replacements for existing matenals recognized/identified by the PIpehne Safety and Hazardous Materials Administration as being obsolete and that present a potential safety threat to operations and the general public, including cast iron, wrought iron , bare steel, and specff1c polyethylene/plastic fac1 lrt1es, and regulators and other pipeline system components the installation of which 1s required as a consequence of the replacement of the aforesaid facilities. "CI/BSR Revenues· means the revenues produced through CIIBSR Surcharges, exclus111e of revenues from all other rates and charges. Issued Bv: Helen J. Weslev. President & CEO Effective : Januarv 1. ~2025
Ti chiedi come si applica questo testo alla tua situazione?
Consulenza gratuita, senza impegno
Descrivi la tua situazione. Il nostro team ti ricontatterà via e-mail per la tua consulenza.
Continua la tua ricerca in ChatGPT o Claude
Collega Omnilex per cercare nel corpus legale dal tuo assistente IA.