United States of America for the use of J&L Paving LLC v. Rockford Corporation et al

3:18-cv-00156Akd3 mag 2019

Testo completo

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
UNITED STATES DISTRICT COURT
DISTRICT OF ALASKA
UNITED STATES OF AMERICA for )
the use of J&L PAVING LLC, )
)
Plaintiff, ) 3:18-CV-00156 JWS
)
vs. ) ORDER AND OPINION
)
) [Re: Motions at dockets 36, 37 & 46]
ROCKFORD CORPORATION and )
LIBERTY MUTUAL INSURANCE )
COMPANY, )
)
Defendants. )
)
I. MOTIONS PRESENTED
At docket 36 Plaintiff J&L Paving, LLC (J&L) moves for summary judgment on its
claims for payment under a subcontract against Defendants Rockford Corporation
(Rockford) and Liberty Mutual Insurance Company.1 Defendants respond at docket 38
and submit a cross-motion for summary judgment at docket 37. Plaintiff replies at
docket 41 and responds to the cross-motion at docket 40. Defendants reply to their
cross motion at docket 45. Oral argument was requested at docket 46, but argument
would not be of assistance to the court.
1Rockford obtained a payment bond from Liberty Mutual Insurance Company as required
by the Miller Act, 40 U.S.C. §§ 3131-3134.
-1-
Case 3:18-cv-00156-JWS Document 49 Filed 05/03/19 Page 1 of 11
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
II. BACKGROUND
This case is a payment dispute between a general contractor, Rockford, and its
subcontractor, J&L, for paving work J&L performed as part of a government contract
Rockford had with the United State Army Corps of Engineers to replace the existing
military fueling station at Tinker Air Force Base in Oklahoma (the Prime Contract).
Under Rockford's subcontract with J&L (the Subcontract), Rockford agreed to pay J&L
$274,620 to complete the paving work required under the Prime Contract.2 The work
required both the application of pre-asphalt bituminous coating and the laying of
asphalt. Rockford asserts that J&L materially breached the Subcontract in both its
application of the bituminous coating and in the laying of the asphalt, causing damages
to Rockford in amounts that almost equal the value of the Subcontract. Although
Rockford has received payment from the government pursuant to the Prime Contract for
completion of the fueling station project, including the paving work, it has not paid J&L.3
Rockford believes it is entitled to offset the damages it incurred against payments to
J&L under the Subcontract.
J&L moves for summary judgment on its contractual claims, arguing it is entitled
to be paid the full amount under the Subcontract. The issue it asks the court to resolve
as a matter of law, however, is not whether it breached the Subcontract, but rather
whether Rockford can withhold payment from J&L after applying for payment and being
paid by the government under the Prime Contract. J&L argues that regardless of any
breaches on its part, Rockford is required to pay the full Subcontract price because it
2The parties concede that a subsequent change order increased the Subcontract
amount by $4,679.62. Rockford contends that it immediately paid J&L the additional amount.
J&L admits that it received $4,679.62 from Rockford, although it points out that the record
remains unclear as to when Rockford made the payment and as to whether Rockford submitted
a payment request under the Prime Contract to cover this amount. In any event, the amount of
the Subcontract effectively remained $274,620 for the duration of the project and is the amount
listed on the contract documents and in Rockford's payment applications.
3The parties concede that J&L has not been paid apart from the initial payment of
$4,679.62.
-2-
Case 3:18-cv-00156-JWS Document 49 Filed 05/03/19 Page 2 of 11
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
certified to the government, pursuant to the Prompt Payment Act, that J&L would be
paid for its satisfactory work under the Subcontract. J&L asserts that Rockford's
certifications constitute a waiver of any right to claim and offset damages or at least bar
such a defense under the doctrine of quasi-estoppel.
In its response to Rockford's cross motion, J&L also asks that the court strike or
disregard the affidavit of Lonny Rhude, which Rockford included as evidence supporting
its motion. J&L argues that Rhude's affidavit is not based on his personal knowledge of
events and contains legal conclusions and impermissible characterizations of the
contents of business documents and communications attached to his affidavit. Rhude's
affidavit is admissible to authenticate the attached business records and to establish
certain facts that are within his knowledge. The court did not rely on any legal
conclusions or characterizations of evidence offered by Rhude.
III. STANDARD OF REVIEW
Summary judgment is appropriate where “there is no genuine dispute as to any
material fact and the movant is entitled to judgment as a matter of law.”4 The materiality
requirement ensures that “[o]nly disputes over facts that might affect the outcome of the
suit under the governing law will properly preclude the entry of summary judgment.”5
Ultimately, “summary judgment will not lie if the . . . evidence is such that a reasonable
jury could return a verdict for the nonmoving party.”6 However, summary judgment is
mandated “against a party who fails to make a showing sufficient to establish the
existence of an element essential to that party’s case, and on which that party will bear
the burden of proof at trial.”7
4Fed. R. Civ. P. 56(a).
5Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986).
6Id.
7Celotex Corp. v. Catrett, 477 U.S. 317, 322 (1986).
-3-
Case 3:18-cv-00156-JWS Document 49 Filed 05/03/19 Page 3 of 11
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
The moving party has the burden of showing that there is no genuine dispute as
to any material fact.8 Where the nonmoving party will bear the burden of proof at trial on
a dispositive issue, the moving party need not present evidence to show that summary
judgment is warranted; it need only point out the lack of any genuine dispute as to
material fact.9 Once the moving party has met this burden, the nonmoving party must
set forth evidence of specific facts showing the existence of a genuine issue for trial.10
All evidence presented by the non-movant must be believed for purposes of summary
judgment, and all justifiable inferences must be drawn in favor of the non-movant.11
However, the non-moving party may not rest upon mere allegations or denials but must
show that there is sufficient evidence supporting the claimed factual dispute to require a
fact-finder to resolve the parties’ differing versions of the truth at trial.12
IV. DISCUSSION
A. Prompt Payment Act
The Subcontract with J&L to perform a portion of work required under Rockford's
Prime Contract with the government was subject to the Prompt Payment Act13 and the
Act's implementing regulations. Pursuant to these statutes and regulations, when
requesting a progress payment from the government under a prime contract, the
contractor is required to itemize work performed by its subcontractors.14 The contractor
must make certain representations concerning its subcontractors' work—namely, that
8Id. at 323.
9Id. at 323-25.
10Anderson, 477 U.S. at 248-49.
11Id. at 255.
12Id. at 248-49.
1331 U.S.C. § 3901, et seq.
1448 C.F.R. § 52.232-5(b)(1).
-4-
Case 3:18-cv-00156-JWS Document 49 Filed 05/03/19 Page 4 of 11
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
the requested amount is for work performed in accordance with specifications of the
contract; that all payments due to subcontractors under previous payment requests
have been made and payments will be made to subcontractors for work itemized under
the current request; and that the payment request "does not include any amounts which
the prime contractor intends to withhold or retain from a subcontractor or supplier in
accordance with the terms and conditions of the subcontract."15 The contractor is also
allowed to assert that the certification "is not to be construed as final acceptance of a
subcontractor's performance."16
The contractor cannot request payment from the government for deficient work.17
If a contractor makes a payment request to the government certifying that no payments
have been withheld and receives payment for work completed by a subcontractor but
then discovers that the work is not in fact satisfactory, it must notify the subcontractor
and government and pay the government interest on the amount received from the
government but withheld.18
Rockford requested payment from the government for J&L's work on March 20,
2017, after J&L had finished the paving work. The total amount requested was
$234,882.70, which is about $40,000 less than the amount owed to J&L under the
Subcontract.19 Rockford contends that it deducted this amount from what was owed
J&L under the Subcontract through a change order and that it did so in order to cover
the costs it incurred to remediate an environmental hazard allegedly caused by J&L's
1531 U.S.C. § 3903(b)(1)(B); 48 C.F.R. § 52.232-5(c).
1648 C.F.R. § 52.232-5(c)(4).
1731 U.S.C. § 3905(h).
1831 U.S.C. § 3905(e); 48 C.F.R. § 52.232-5(d).
19Doc. 35-4 at p. 1.
-5-
Case 3:18-cv-00156-JWS Document 49 Filed 05/03/19 Page 5 of 11
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
application of pre-asphalt coating before a forecasted rain event.20 The record shows
that there had been communications between J&L and Rockford about the clean up and
that J&L knew that Rockford believed J&L was responsible for clean-up costs.21
One day after Rockford submitted its March payment application, government
engineers informed Rockford that J&L's work did not met project specifications. J&L
submitted a proposal as to how to correct the deficiencies in its work and eventually
completed the rework in early August of 2017.22
In October of 2017, Rockford submitted another payment application. This one
included a request for the balance of the J&L subcontract, which was about $40,000
(the amount they had not asked for in the previous application).23 As described above,
in order to obtain payment, Rockford had to itemize its subcontractors' work for which it
sought payment and certify that such work was completed according to the
specifications of the contract. It also had to certify that payments due to subcontractors
under previous payment requests had been made and that it did not intend to withhold
any payments. Despite this certification, Rockford had not yet paid J&L from the
proceeds of the prior payment request and intended to withhold the balance that it was
asking for in the current payment request.
The parties do not dispute that Rockford failed to comply with the required
withholding procedures and that its October certification was incorrect. Rockford,
however, asserts that its noncompliance is an issue between it and the government and
does not have any bearing on this contractual dispute between private entities.
20Doc. 35-8 at pp. 2, 3 7; doc. 35-8.
21Doc. 35 at ¶¶ 7-8; Doc. 35-3 at p.1.
22Doc. 35 at ¶¶ 11-13; doc. 35-5; doc. 39-5.
23Doc. 35 at ¶ 14; Doc. 35-6.
-6-
Case 3:18-cv-00156-JWS Document 49 Filed 05/03/19 Page 6 of 11
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
Rockford has since informed the government of its errors.24 While J&L concedes that it
cannot enforce the provisions of the Prompt Payment Act through this lawsuit, it
nonetheless argues that Rockford's false certifications and its failure to provide the
required notice affect the equities of this contractual dispute. J&L believes Rockford's
false representations and inconsistent positions as to J&L's performance and the
withholding now bar Rockford from denying full payment to J&L.
B. Waiver
J&L asserts that Rockford's actions amount to a waiver of its right to deny J&L
payment based on performance when it averred to the government that J&L's
performance met contractual standards and would not be subject to withholdings.
Waiver may "be implied from a party's conduct" if that conduct is "clear and
unambiguous."25 "An implied waiver arises where the course of conduct pursued
evidences an intention to waive a right, or is inconsistent with any other intention than a
waiver, or where neglect to insist upon the right results in prejudice to another party."26
Conduct that could be a result of a mistake, negligence, or incompetence does not
constitute an unequivocal waiver of a right.27
As for J&L's performance, Rockford's payment certifications did in fact indicate
that J&L's work met the specifications of the contract, but the certifications also made
clear that they were not to be construed as a final acceptance of the subcontractor's
work. Thus, the payment certifications did not clearly and unambiguously set out
Rockford's acceptance of J&L's performance or an abandonment of any claim for
damages. J&L does not provide evidence to show that it even received a copy of the
certifications; instead, the record shows that Rockford consistently communicated with
24Doc. 35-8.
25Powers v. United Servs. Auto. Ass'n, 6 P.3d 294, 298-99 (Alaska 2000).
26Milne v. Anderson, 576 P.2d 109, 112 (Alaska 1978).
27Airoulofski v. State, 922 P.2d 889, 895 (Alaska 1996).
-7-
Case 3:18-cv-00156-JWS Document 49 Filed 05/03/19 Page 7 of 11
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
J&L about its deficient performance. It informed J&L about the need to cure the defects
in the paving shortly after learning of the problems, and J&L knew that its work had to
be redone.28 The record also shows that Rockford informed J&L that it believed the
resulting delays caused damages for which J&L was liable.29 At best, Rockford's
conduct as a whole—looking at the government certifications and Rockford's
communication's with J&L—was ambiguous as to J&L's performance.
As for Rockford's intention to withhold payment to J&L to offset alleged damages,
the October 2017 certification indeed included a misrepresentation about its plans to
pay J&L. Again, this certification was made to the government and not J&L. The record
shows that Rockford communicated its belief that J&L was liable for damages as a
result of its performance and that it had used deductive change orders to the
Subcontract to reduce the amount owed to J&L in order to offset those damages.30
Given these communications by Rockford, along with the fact that Rockford continues to
withhold J&L's payment,31 this court is prevented from finding an unequivocal waiver
based on Rockford's submission of a contrary government certification—one that J&L
does not contend it even received or saw.
J&L also asserts that Rockford's failure to send the requisite withholding notices
under 31 U.S.C. § 3905(e) amounts to an intentional waiver of its right to withhold
disputed payments from J&L. However, as noted by Rockford in its reply brief, § 3905
cannot be used in this dispute to determine the parties' rights under the Subcontract:
28Docs. 35-5; 39-5; 35-9 at p.15; 39-7.
29Docs. 35-5; 35-8 at p. 42; 35-8 at pp. 43-47; 39-7.
30Docs. 35-3; 35-5; 35-8 at p. 5-10; 35-8 at pp. 37, 42, 43-47; 39-7.
31See Duenas-Rendon v. Wells Fargo Bank, N.A., 354 P.3d 1037, 1042 (Alaska 2015)
(affirming the superior court's ruling that mortgagee bank did not waive its right to foreclose by
accepting monthly payments after notice of mortgagor's default because the bank's conduct of
continuing the foreclosure after receiving the payments was consistent with exercising that
right).
-8-
Case 3:18-cv-00156-JWS Document 49 Filed 05/03/19 Page 8 of 11
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
[T]his section shall not limit or impair any contractual, administrative, or
judicial remedies otherwise available to a contractor or a subcontractor in
the event of a dispute involving late payment or nonpayment by a prime
contractor or deficient subcontract performance or nonperformance by a
subcontractor.32
Also, the failure to send formal notice cannot be considered in isolation. As noted
above, the record shows that J&L knew about its deficient performance. Indeed, it
proposed a cure and eventually fixed its original work.33 Rockford thereafter informed
J&L of its intention to assert a claim for damages because of the delayed
performance.34 There is no reasonable basis to conclude that the failure to send the
§ 3905 notices conveyed a message that Rockford was waiving its ability to assert a
claim for damages based on deficient performance.
Rockford's certification to the government regarding performance and withholding
and its failure to provide formal notice under the Prompt Payment Act could very likely
be the product of something other than intentional waiver of a claim for damages, such
as negligence or incompetence in reading and filling out the government's form for
payment and understanding the requirements of the Prompt Payment Act submissions.
Given these other possible explanations for Rockford's Prompt Payment Act missteps,
the court cannot conclude that through these actions Rockford clearly intended to
abandon its claim for damages stemming from J&L's delayed performance and its
intention to offset those damages.
C. Quasi-Estoppel
J&L also argues that the doctrine of quasi-estoppel bars Rockford from denying
J&L payment for its work under the Subcontract. "Quasi-estoppel . . . appeals to the
conscience of the court to prevent injustice by precluding a party from asserting a right
3231 U.S.C. § 3905(j).
33Docs. 35-5; 39-5; 35-9 at p.15; 39-7.
34Docs. 35-5; 35-8 at p. 42; 39-7.
-9-
Case 3:18-cv-00156-JWS Document 49 Filed 05/03/19 Page 9 of 11
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
inconsistent with a position previously taken by him . . . ."35 "The essence of the
doctrine of quasi-estoppel is the existence of facts and circumstances making the
assertion of an inconsistent position unconscionable."36 Unlike estoppel, quasi-estoppel
does not require a showing of reliance as an essential element; however, reliance is
one factor for the court to consider.37 Other factors include
whether the party asserting the inconsistent position has gained an
advantage or produced some disadvantage through the first position;
whether the inconsistency was of such significance as to make the
present assertion unconscionable; and, whether the first assertion was
based on full knowledge of the facts.38
Given the equitable nature of the doctrine, the issue is one that is appropriately decided
by the court.39
The court is not persuaded that Rockford's erroneous certifications to the
government provide a basis for J&L to assert quasi-estoppel in this contract dispute
between the parties. As noted by Rockford in its briefing, J&L is not the aggrieved party
in relation to the misrepresentations made in Rockford's request to be paid pursuant to
the Prime Contract. The government is. J&L does not assert, and the record does not
show, that J&L was privy to these payment applications. Rather, as discussed above,
the record shows that Rockford took a consistent position with J&L concerning its
performance and the issue of damages. Therefore, the false certification has little
significance to the parties' current contract dispute. Also diminishing the significant of
Rockford's inconsistency is the fact that there is no evidence of bad faith in the record;
that is, Rockford's false certification could be a result of negligence or incompetence.
35Jamison v. Consol. Utils., Inc., 576 P.2d 97, 102 (Alaska 1978).
36Id.
37Id. at 102-03.
38Id. at 103.
39See Alaska Interstate Constr., LLC v. Pac. Diversified Inv., Inc., 279 P.3d 1156, 1179,
1180 (Alaska 2012).
-10-
Case 3:18-cv-00156-JWS Document 49 Filed 05/03/19 Page 10 of 11
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
The fact that Rockford may have improperly benefitted from not disclosing its
withholding—by avoiding interest payments or other penalties under the applicable
federal statutes—or may have violated the False Claims Act is a matter for the
government to address. It does not make Rockford's long-standing claim for damages
against J&L in this contract dispute unconscionable.
Similarly, Rockford's failure to send the requisite notice under 31 U.S.C.
§ 3905(e) does not amount to unconscionable conduct justifying the application of
quasi-estoppel. Aside from the fact that § 3905(j) prevents the issue from limiting
Rockford's contractual rights, Rockford, as noted above, took a consistent position with
J&L. J&L knew what was needed to cure its paving work and did so and knew that the
issue of damages stemming from delays remained unsettled. The court is hard pressed
to see how any unconscionable situation arose from the lack of a § 3905(e) notice.
V. CONCLUSION
Plaintiff's motion at docket 36 is DENIED. Defendants' cross-motion at docket 37
is GRANTED—Rockford is not barred by virtue of its payment applications to the
government or failure to send notices under 31 U.S.C. § 3905(e) from arguing that J&L
breached the Subcontract, thereby entitling it to offset any resulting damages against
J&L's payment. The motion for oral argument at docket 46 is DENIED.
DATED this 3rd day of May 2019.
/s/ JOHN W. SEDWICK
SENIOR JUDGE, UNITED STATES DISTRICT COURT
-11-
Case 3:18-cv-00156-JWS Document 49 Filed 05/03/19 Page 11 of 11

Continua la tua ricerca in ChatGPT o Claude

Collega Omnilex per cercare nel corpus legale dal tuo assistente IA.