Dakota Gasification Company v. Sure Steel, Inc.

1:18-cv-00226Ndd24 giu 2019

Testo completo

IN THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF NORTH DAKOTA
Dakota Gasification Company, 	)
)
Plaintiff, 	)
)
v. 	)
) 	ORDER
Sure Steel, Inc., 	)
)
Defendant, 	)
)
AND 	)
)
Sure Steel, Inc., 	)
)
Third-Party Plaintiff, 	)
)
v. 	)
Robertson-Ceco II Corporation, d/b/a 	) 	Case No. 1:18-cv-226
Garco Building Systems, Steel Concepts 	)
LLC, and Rice Lake Contracting Corp., 	)
d/b/a Rice Lake Construction Group, 	)
)
Third-Party Defendants. 	)
Before the court is a Joint Motion to Amend Scheduling Order filed by the parties on June
20, 2019. The motion (Doc. No. 41) is GRANTED and scheduling order is amended as follows:
1. 	The parties shall have until October 31, 2019 to complete fact discovery and to file
discovery motions.
2. 	Plaintiff shall serve its Rule 26(a)(2) disclosures on or before December 2, 2019.
3. 	Defendant shall serve its Rule 26(a)(2) disclosures on or before January 3, 2020.
4. 	Third Party Defendants shall serve their Rule 26(a)(2) disclosures on or before
February 3, 2020.
1
Case 1:18-cv-00226-PDW-CRH Document 46 Filed 06/24/19 Page 1 of 2
5. 	The parties shall have until March 13, 2020 to complete discovery depositions of
expert witnesses.
6 	The parties shall have until December 2, 2019 to file other nondispositive motions
(e.g., consolidation, bifurcation).
IT IS SO ORDERED.
Dated this 24th day of June, 2019.
/s/ Clare R. Hochhalter
Clare R. Hochhalter, Magistrate Judge
United States District Court
2
Case 1:18-cv-00226-PDW-CRH Document 46 Filed 06/24/19 Page 2 of 2