Questão jurídica principal
Whether the appeal against the mobile antenna permit was admissible and whether the permit had to be annulled or modified due to emission-limit issues.
Decisão extraída
The appeal was admissible but unfounded; the permit could stand because the planned installation complied with the federal emission limits.
Fundamentação extraída
The court held that the ORNI system already implements the precautionary approach. The new facts about a separate GSM-R antenna project could not be considered. The appellants did not show that the applicable installation limit of 6.0 V/m would be exceeded, so no stricter limitation was required.