Questão jurídica principal
Whether the second construction stage was based on a revised lump-sum contract price or a non-contractual claim
Decisão extraída
The prior finding that the parties agreed on a revised general contractor price remained binding in this appeal.
Fundamentação extraída
The defendant lacked standing to challenge an issue already decided in his favor at an earlier stage, and the claimant had consistently relied on a contractual basis.