23-1719•Nhc LLC v. CENTAUR CONSTRUCTION COMPANY INC., SPIRO TSAPARAS, and PETER ALEXOPOULOS
23-1719Court of Appeals for the Seventh Circuit24 de set. de 2025
United States Court of Appeals
For the Seventh Circuit
Chicago, Illinois 60604
Argued January 17, 2024
Decided September 24, 2025
Before
JOEL M. FLAUM, Circuit Judge*
FRANK H. EASTERBROOK, Circuit Judge
DORIS L. PRYOR, Circuit Judge
No. 23-1719
NHC LLC,
Plaintiff-Appellee,
v.
CENTAUR CONSTRUCTION
COMPANY INC., SPIRO TSAPARAS,
and PETER ALEXOPOULOS,
Defendants-Appellants.
Appeal from the United States District
Court for the Northern District of
Illinois, Eastern Division.
No. 19-cv-06332
Matthew F. Kennelly,
Judge.
O R D E R
In 2017, NHC LLC hired Centaur Construction Company, Inc. to design and
build the Nobu Hotel in Chicago’s West Loop neighborhood. NHC sued Centaur and
two of its officers, Spiro Tsaparas and Peter Alexopoulos, for fraud and breach of
contract. In particular, NHC alleged that Defendants falsely represented that they had
* Circuit Judge Flaum passed away on December 4, 2024, and did not participate in the decision
of this case, which is being resolved under 28 U.S.C. § 46(d) by a quorum of the panel.
NONPRECEDENTIAL DISPOSITION
To be cited only in accordance with Fed. R. App. P. 32.1
-- 1 of 8 --
No. 23-1719 Page 2
completed work for which they requested payment from NHC, failed to pay project
subcontractors, and failed to complete the project on time and within budget. The
district court found Defendants liable for breach of contract on summary judgment, and
a jury found Defendants liable for fraud and awarded NHC over $20 million in
damages. The district court denied Defendants’ motions for a new trial and judgment as
a matter of law. We affirm.
I. BACKGROUND
A. Factual Background
In 2017, NHC purchased the Chicago Nobu Hotel project, which was already
underway but had stalled under previous ownership. NHC then promoted Centaur
from its position as the project’s general contractor to the project’s lead designer and
builder. Centaur’s CEO, Spiro Tsaparas, and President, Peter Alexopoulos, were
responsible for negotiating the contract with NHC, which the parties called a design-
build agreement. Before signing the contract, one of NHC’s owners, Rodrigo Chapur,
told Tsaparas that NHC would not spend more than $49 million to build the hotel.
Tsaparas drafted a payment schedule in line with Chapur’s stipulation and told Chapur
that payment requests would be “for work performed.”
The parties signed the design-build agreement on April 16, 2018, which stated
that the total cost of the project would not exceed $48,257,000. Among other things, the
agreement required Centaur to substantially complete the project within 400 days after
beginning construction; submit “[a]pplications for [p]ayment”—i.e., invoices—for
completed portions of work; provide accurate reports of completion progress; and pay
subcontractors within seven days of receiving a payment from NHC for the work of the
subcontractor. Alexopoulos was responsible for signing the invoices on a monthly basis,
which were to align with the agreed-upon payment schedule between Tsaparas and
Chapur.
As the project progressed, Tsaparas repeatedly represented to NHC that the
project was under budget and on schedule. Yet, it was later revealed that the project
was over budget by millions, in part because Centaur had used NHC funds to pay
expenses unrelated to the project instead of paying subcontractors. For example,
Centaur used NHC’s progress payments to repay loans incurred prior to the
construction of the Nobu Hotel. It also transferred nearly $2 million directly to
Alexopoulos and Tsaparas. NHC spent roughly $20 million to cover subcontractor liens
and to hire another firm to finish construction.
-- 2 of 8 --
No. 23-1719 Page 3
Tsaparas eventually admitted the project was over budget and attempted to
repair the relationship with NHC. In July and August 2019, he told Chapur by text
message that he took “full responsibility for the contract overruns,” asked Chapur to
“wire [him] the funds to pay the trades” so he could “keep [his] world at bay and keep
the job going,” and acknowledged that “credibility ha[d] been lost.” And in a July 2019
email, he offered Chapur “a simple yet accurate update on the final cost to complete the
project.” He explained that Centaur’s outstanding financial responsibility at that time
exceeded $9 million.
Shortly thereafter, NHC sued Centaur, Tsaparas, and Alexopoulos. Among other
things, NHC alleged that Tsaparas falsely represented that the project was just $750,000
over budget and behind schedule by “a month or two at the max”; that Alexopoulos
made false representations when signing invoices, including an invoice that falsely
stated Centaur had “earned” and “completed” construction work nearing $47 million;
and that NHC relied on these misrepresentations by continuing to make progress
payments to Centaur. It sought damages and attorneys’ fees as a result.
B. Procedural History
The parties cross-moved for summary judgment on the breach of contract claim.
Defendants moved for partial summary judgment on the fraud claim as well. The
district court granted in part NHC’s motion for summary judgment on the breach of
contract claim, concluding that Defendants breached several provisions of the design-
build agreement relating to schedule, budget, and subcontractor payments. It denied
Defendants summary judgment with respect to the fraud claim, which, along with the
question of damages for breach of contract, proceeded to trial.
NHC submitted its proposed witness list in anticipation of trial, which included
a project accountant, Manuel Nuñez, who had worked in Mexico for NHC’s parent
company, Corporación Inmobiliaria KTRC—also known as RCD. At a previously held
remote deposition, Nuñez testified that his role on the Nobu project was to obtain proof
that subcontractors had been paid. He recounted that in December 2018, he and Chapur
met with Tsaparas to obtain documentation showing the money Centaur had paid to
subcontractors. According to Nuñez, Tsaparas did not provide the supporting
documents Nuñez sought and could not explain why invoices were inaccurate.
NHC’s witness list indicated that Nuñez’s address was “[u]nknown,” and that
NHC expected to use the transcript of his deposition at trial. NHC reported that Nuñez
had resigned from RCD and clarified that Nuñez was never employed by NHC itself.
-- 3 of 8 --
No. 23-1719 Page 4
Defendants moved to compel Nuñez’s live testimony or for a missing witness
instruction. They asserted that the proposed jury instructions reflected new allegations
against Alexopoulos that they did not have the chance to question Nuñez about,
including that Alexopoulos “made false statements of material fact regarding the
project being on budget or … on schedule.” In Defendants’ view, that allegation
originally was imputed to Tsaparas. When asked to clarify their position, however,
Defendants admitted that the jury instructions did not list any newly-alleged
misrepresentations allegedly made by either Tsaparas or Alexopoulos; instead, they
noted differences in the “wording” that they viewed as “significant[].” The district court
denied the motion, observing that there was not “anything material that ha[d] …
changed since the [Nuñez] deposition that would make the deposition[] inadequate.”
Defendants also submitted several motions in limine. Relevant here, they sought
to exclude the July 2019 correspondence between Tsaparas and Chapur because it took
place before the lawsuit was filed and constituted “preemptory settlement discussions”
aimed at avoiding litigation. The district judge denied the motion because although
Tsaparas and Chapur discussed outstanding construction costs, the email did not show
a compromise offer within the meaning of Federal Rule of Evidence 408.
The case proceeded to trial. The jury found in favor of NHC on the fraud claim. It
also awarded NHC compensatory and punitive damages. Defendants moved for a new
trial or judgment as a matter of law on the breach of contract and fraud claims. The
district court denied the motions.
II. DISCUSSION
We considered all ten of Defendants’ questions presented and find that only two
merit discussion. First, whether the district court abused its discretion by admitting
evidence of settlement discussions. See FED. R. EVID. 408(a). Second, whether the district
court abused its discretion by denying Defendants’ request to issue a missing witness
instruction.
A. Admission of the July 2019 Email
We review the denial of motions in limine for an abuse of discretion. Stegall v.
Saul, 943 F.3d 1124, 1127 (7th Cir. 2019). “We will reverse only if no reasonable person
would agree with the trial court’s ruling and the error likely affected the outcome of the
trial.” Hernandez v. City of Peoria, 135 F.4th 517, 527 (7th Cir. 2025) (quoting Perry v. City
of Chicago, 733 F.3d 248, 252 (7th Cir. 2013)).
-- 4 of 8 --
No. 23-1719 Page 5
Defendants argue the July 24, 2019, email from Tsaparas to Chapur constitutes
evidence of settlement negotiations, which are inadmissible under Federal Rule of
Evidence 408. In their view, Tsaparas’s email reflected an effort to avoid litigation,
which he knew was imminent. NHC responds that Rule 408 does not apply because the
email contains no offer to settle or proposed terms of settlement, mention of litigation,
or mention of any attorneys involved.
Federal Rule of Evidence 408 prohibits the admission of evidence of compromise
offers and statements made during compromise negotiations to prove “the validity or
amount of a disputed claim.” FED. R. EVID. 408(a); see also Zurich Am. Ins. Co. v. Watts
Indus., Inc., 417 F.3d 682, 688–89 (7th Cir. 2005). The party opposing admission must
“make a ‘substantial showing’” that the evidence was part of a settlement attempt.
Raybestos Prods. Co. v. Younger, 54 F.3d 1234, 1241 (7th Cir. 1995) (quoting New Burnham
Homes, Inc. v. Village of Burnham, 910 F.2d 1474, 1482 (7th Cir. 1990)). In reviewing the
evidence, we consider “the totality of the circumstances,” which include “the contents
of the [communication] and the timing of its delivery.” Id.
In Raybestos, a manufacturer of car parts sued a mechanic servicer and its
president for making defamatory statements about the manufacturer’s products. Id. at
1236–37. The plaintiff alleged the defendants launched a “deliberate campaign” by
publishing statements that the plaintiff’s products were defective. Id. at 1238. Eight
months before the litigation began, the defendants wrote a letter to the plaintiff with a
plan that would require the plaintiff to pay for research to identify problems with its
products and avoid litigation. Id. at 1240. The plaintiff sought to offer this letter as
evidence of intimidation tactics by the defendants, but the defendants argued the letter
was inadmissible evidence of settlement discussions. Id. at 1241. We affirmed the
district court’s decision to admit the letter, reasoning that “the record and the
atmosphere in which this letter was sent” reflected that settlement discussions had not
begun. Id. For instance, we observed that no such discussions had yet been initiated by
the plaintiff, and even assuming the defendant intended the letter to “avoid potential
litigation,” the timing and contents of the letter did not show that settlement
discussions had begun. Id. (emphasis in original).
So too, here. Tsaparas sent the July 24, 2019, email prior to this litigation. Even if
Tsaparas correctly predicted that litigation was forthcoming, that belief, without more,
is not proof that settlement discussions had begun. The email’s content similarly does
not help Defendants, as it made no mention of lawyers, compromise, or settlement; and
it did not reflect a dispute about whether any funds were owed or to whom. That
-- 5 of 8 --
No. 23-1719 Page 6
Tsaparas later sent Chapur text messages in August 2019 asking NHC not to file suit
does not change the result, as these messages post-date the July 24 email and, in any
event, do not reflect an effort by NHC to initiate or participate in settlement discussions.
“[T]he record and the atmosphere” surrounding the email was that of a worried
businessman attempting to placate his customer and avoid a lawsuit, not an attempt to
settle a dispute about funds he still owed. Id.
It is true that Tsaparas’s representation in his email that Centaur had outstanding
financial responsibilities as of July 24, 2019, could be used to help establish the validity
or amount of NHC’s claims. But Rule 408 does not prohibit using evidence for this
purpose where the evidence does not show the parties engaging in settlement
negotiations. See FED. R. EVID. 408. Because Defendants did not make a substantial
showing that the email was part of a settlement attempt, the district court did not abuse
its discretion in admitting the evidence at trial.
B. Missing Witness Instruction
Defendants also argue the district court erred by failing to issue a missing
witness instruction about Manuel Nuñez. District courts have broad discretion in
deciding whether to issue a missing witness instruction, and we review that decision for
abuse of discretion. United States v. Foster, 701 F.3d 1142, 1154 (7th Cir. 2012).
A missing witness instruction allows the jury to infer the missing witness’s
testimony would have been unfavorable to the party that arguably should have, but
failed to, make the witness available for trial. United States v. DiSantis, 565 F.3d 354, 364
(7th Cir. 2009). The instruction is “generally disfavored” and warranted only when the
proponent of the instruction shows that (1) the witness was “peculiarly” within the
opponent’s “power to produce” and (2) the witness’s “testimony would have elucidated
issues in the case and would not merely have been cumulative.” Id. (quoting United
States v. Gant, 396 F.3d 906, 910 (7th Cir. 2005)). We find neither prong satisfied here.
1. Power to Produce
“A witness is peculiarly within the [opponent’s] power to produce when the
witness is physically available only to the [opponent], or where the witness’s
relationship with the [opponent] makes his testimony, in pragmatic terms, available
only to the [opponent].” United States v. Christ, 513 F.3d 762, 773 (7th Cir. 2008).
Defendants contend that Nuñez was within only NHC’s power to produce because he
lived in Mexico and worked for NHC. We disagree.
-- 6 of 8 --
No. 23-1719 Page 7
First, Defendants have not shown that Nuñez was physically available to NHC.
A missing witness instruction is not warranted when, “through neither party’s fault[,]
the witness was physically unavailable to both parties.” United States v. Pizarro, 717 F.2d
336, 346 (7th Cir. 1983) (emphasis in original). Under Federal Rule of Civil Procedure
32(a)(4)(B), a witness is unavailable when “the witness is … outside the United States,
unless it appears that the witness’s absence was procured by the party offering the
deposition.” Here, Nuñez lived in Mexico, and Defendants’ speculation as to
“gamesmanship” by NHC does not reflect that NHC procured his absence
intentionally.
Second, Nuñez was not pragmatically available to NHC. While pragmatic
availability can be based on the opponent’s employment of a witness, Christ, 513 F.3d at
773, the record does not reflect that NHC employed Nuñez. Nuñez testified at his
deposition that he worked for RCD and did not report to NHC. NHC’s lawyers likewise
represented that Nuñez was never an NHC employee. And although Nuñez had a
limited role on the Nobu project as part of his employment with RCD, he quit his job
before trial and there is no evidence that he ever had a personal interest in the success of
NHC at trial. See id. at 772–74 (affirming denial of a missing witness instruction when,
despite the absent witness’s employment by a party, he did not have a personal stake in
the outcome of the case). Moreover, Nuñez’s willingness to provide deposition
testimony when called by Defendants further undermines Defendants’ position, as a
missing witness instruction requires the evidence to “reflect the [proponent’s] inability
to present that same testimony.” Pizarro, 717 F.2d at 346.
2. Cumulativeness
Defendants also do not show that Nuñez’s testimony would have elucidated
issues in the case as opposed to merely being cumulative. Foster, 701 F.3d at 1154. Recall
the proposed jury instructions, submitted after Nuñez was deposed, alleged that both
Tsaparas and Alexopoulos misrepresented the project’s budget and schedule.
Defendants argued to the district court that the operative complaint did not contain
such allegations with respect to Alexopoulos and that Nuñez’s live testimony was
therefore critical to exploring the new allegations. Yet, Defendants then admitted to the
district court that nothing “brand new” had been added to the jury instructions that
was absent from the complaint. And Defendants do not otherwise show that Nuñez’s
live testimony would have elucidated issues involving Alexopoulos, particularly given
that Defendants represented to the district court that they had already asked Nuñez
about his meetings with Centaur representatives.
-- 7 of 8 --
No. 23-1719 Page 8
In sum, Nuñez was not peculiarly within NHC’s power to produce, and his live
testimony would not have elucidated the issues in the case. Therefore, the district court
did not abuse its discretion in declining to provide the missing witness instruction.
III. CONCLUSION
The district court did not abuse its discretion in admitting an email that did not
contain evidence of settlement discussions, nor in declining to issue a missing witness
instruction. Defendants’ remaining arguments are also unavailing and do not merit
discussion. Accordingly, we AFFIRM the judgment of the district court.
-- 8 of 8 --
Conecte o Omnilex para pesquisar o corpus jurídico pelo seu assistente de IA.